Project Quality Plan: Document No: BK91-1312-INF-829-QAC-PLN-0001
Project Quality Plan: Document No: BK91-1312-INF-829-QAC-PLN-0001
Project Quality Plan: Document No: BK91-1312-INF-829-QAC-PLN-0001
BK91-1312-INF-829-QAC-
PLN-0001
Approval Code
Remarks
Here
Code 1 √ Approved
PROJECT QUALITY PLAN These comments do not relieve the Contractor/ Vendor and/ or their
Sub‐contractors of their responsibilities to meet the requirements of
the Contract.
RE-ISSUED
C FOR 17-05-2021 M. A. M. A. M. A. A. H.
APPROVAL
RE-ISSUED
B FOR 09-05-2021 M. A. M. A. M. A. A. H.
APPROVAL
Contents
REFERENCE DOCUMENTS ................................................................................................ 7
GENERAL ............................................................................................................................. 7
SCOPE ................................................................................................................................ 10
RESPONSIBILITIES ........................................................................................................... 10
6.1.1 General…………………………...………………………………………….…………........21
6.1.2 Kick Off Meeting……………………………………………………………………………..21
6.1.3 Contract Review……………………………………………………………………………..21
6.1.4 Project Schedule…………………………………………………………………………….22
6.5.1 General……………………………………………………………………………………….40
6.5.2 Identification and Traceability during Vendor Item Fabrication…………………………40
6.5.3 Identification and Traceability during Construction Phase………………………………41
REFERENCE DOCUMENTS
This document is based on the following Project documents, ISO 9001 standards, and Contractor’s
Project Specific Procedures and general corporate Quality Control procedures.
Contract Documents:
Section 4.0 SCOPE OF WORK – Clause 7.0 Quality Assurance & Quality Control
CONTROL OF NON-CONFORMANCE PROCEDURE
B Vend or Inspection and Guideline Handbook
Project Document B
BK91-1312-INF-000-QAC-NCR-0001: Control of Non-Conformance Procedure
BK91-1312-INF-000-QAC-AUD-0001: Project Audit Procedure
BK91-1312-INF-000-QAC-CAR-0001: CORRECTIVE ACTION AND PREVENTIVE ACTION
PROCEDURE
GENERAL B
This Project Quality Plan (hereinafter referred to as “PQP” describes how A.B. Co. Ltd. (hereinafter
referred to as “Contractor”) will apply his Quality Management System, which will established and
development in accordance with the requirements of the International Standard (ISO 9001:2015), to
meet the specific requirements of the “Engineering, Procurement and Construction for Security Defence
& Check points for Block 9 Phase 1 Projects “(hereinafter referred to as “Project”).
Purpose
This PQP establishes the Project Quality Management System and describes the detailed procedural
requirements to assure the reliability in quality of products and services for the Project in compliance
with the contract between Kuwait Energy Company (hereinafter called as “Company”) and the
Contractor.
The particular procedures of the Quality Management System which are applicable to each discipline of
this Project organization are referred to in each section of this PQP.
This PQP and revision thereto shall be submitted to Company for review and acceptance prior to
implementation. All changes should be reviewed for impact and adequacy by the same authorized
function, which conducted the review of the original PQP.
SCOPE B
Project QA/QC Manager is responsible for the preparation, issue and distribution of the PQP including
subsequent revisions.
The PQP shall apply to the activities of Contractor to ensure that all works, supplies and services for the
Project are carried out in a planned and systematic manner based on the guideline of this PQP.
The PQP and supporting control documents shall be under constant review and shall be amended,
added to or deleted from, as it is appropriate, following the experience gained as the Project progresses.
This document is the reference documents for the following purposes:
To inform all key personnel involved in the project about the essential quality requirements of
the project;
To define the project organization, and in particular the inter-relationships, responsibilities and
authorities;
To keep informed the Company about method used by Contractor to carry out and control the
project activities.
To serve as a basis for quality audits.
The PQP shall be distributed to all key personnel involved in the project.
Any conflict between this Quality Plan and Contracts shall be brought to the Company Representative
for resolution.
RESPONSIBILITIES
Management Commitment
Contractor Management will provide evidence of its commitment to the development and implementation
of the Quality Management System and continual improving its effectiveness and efficiency by:
communicating internally the importance of meeting the Contract as well as statutory and
regulatory requirements,
establishing the Quality Policy,
B
ensuring that quality objectives, schedule objectives, cost objectives and safety objectives are
established
conducting management reviews and ensuring availability of resources
Customer Focus
Contractor Management will ensure that Company requirements including legal obligations are
determined and will be met with the aim of enhancing Company satisfaction.
The Project Manager shall focus on reviewing contract requirements, quality management systems and
procedures for compatibility and submit the modifications as appropriate.
He will allocate trained and qualified staff resources to perform Project tasks. Training of personnel will
be undertaken as required.
The Project Manager will also perform management reviews and internal quality review. The Project
Manager will establish a program for problem identification, resolution and problem prevention and
maintain the data control system and records of the Project activities.
All the feedback from Company will be taken into account and reviewed to measure Company
satisfaction.
Contractor shall evaluate Company satisfaction through quarterly questionnaire survey and submitted to
Company.
Planning
4.3.1 Project Quality Objectives
Aiming the continual improvement, Contractor Management will continually plan, improve, review and
document the Project Management System in order to address the following objects:
Timely Submission of Quality System Deliverables
Acceptance rate of Company Inspection for Procurement Equipment and materials
B
Equipment/Materials delivered to Site: No Major Defect
Site Final Inspection Acceptance Rate
Utilization of Previous Lessons Learned: Zero Repeat
All related data including weekly reports of each discipline including Site, feedback data, the results of
Project quality audit and other related data will be reviewed and monitored through the Weekly/Monthly
Project Meeting.
President
President is the highest-ranking individual in CONTRACTOR.
He is responsible for the overall success of a business entity or other organization and for making top-
level managerial decisions the duties, responsibilities, and job description of president include:
Communicating, on behalf of the company, with shareholders, government entities, and the
public
Leading the development of the company’s short- and long-term strategy
Creating and implementing the company or organization’s vision and mission
Evaluating the work of other executive leaders within the company, including directors, vice
presidents, and presidents
Maintaining awareness of the competitive market landscape, expansion opportunities,
industry developments, etc.
Ensuring that the company maintains high social responsibility wherever it does business
Assessing risks to the company and ensuring they are monitored and minimized
Setting strategic goals and making sure they are measurable and describable
Managing Director
Managing Directors oversee a company's business operations, drive strategic company
growth, and are responsible for the overall performance of the business.
The duties, responsibilities, and job description of Managing Director include:
Developing and executing business strategies to achieve short and long-term goals
Reporting to the board, providing market insights and strategic advice
Developing and implementing business plans to improve cost-efficiency
Maintaining positive and trust-based relations with business partners, shareholders, and
authorities
Overseeing the company's business operations, financial performance, investments, and
ventures
Supervising, guiding, and delegating executives in their duties
Ensuring company policies and legal guidelines are clearly communicated
Project Manager
He will be responsible for ensuring that the construction plans including Project IT,
Interface Coordination, Vendor Quality control and Project procedures duly implemented for the Project.
His objective is to ensure that the project construction activities are completed to
customer’s satisfaction, consistent with all quality, safety, schedule and other contractual requirements.
His responsibility covers the entire project development, from the start of the project, up to its close-up.
On behalf of Contractor, he represents the operative counterpart towards Company and
all contractual matters shall therefore be reported to him for his solution with Company
as Contractor Representative
Construction Manager
He reports to the Project Manager and is responsible for the overall construction
management, coordination and administration of the Site activities, including
QA/QC Manager
He works and reports functionally to Construction Manager having dual function for Site Manager. He is
responsible for control all quality matters at Site except Project audit, which will be responsible for
performing by Audit Team organized by CONTRACTOR’s QA/QC Manager, in accordance with the
approved Project Quality Plan and its related procedures and plans in compliance with the requirements
of Contract.
He maintains contacts with the Company’s representative on site to discuss all quality
matter.
He is assisted by the Quality Control Supervisors and Inspectors for the inspections and controls to be
made during the development of the work, to provide inspection coordination between different
disciplines and for the issue and collection of quality records, as requested by the contract and by ITPs.
Safety Supervisors and Security Supervisors will be assigned under HSE Manager and
are responsible to carry out the following:
Conduct safety and health training including safety induction, emergency evacuation drills,
and joint safety inspection with subcontractor
Project Interfaces
4.5.1 Project Quality Meetings
The project quality meetings will be held weekly/monthly to present weekly/monthly or as the Company
representatives deems necessary.
The Contractor will prepare minutes of all formal meetings between Company and the Contractor.
The minutes will be forwarded to Company for approval prior to formal issue by the Contractor.
Internal meeting shall be held weekly to check the Project progress and to identify any quality matters
including problems during the week. Actions established during the meeting shall be documented on the
MOM.
A collection of the issued MOM shall be maintained and reviewed by the interested departments, in order
to ensure a proper follow-up of the established actions.
RESOURCE MANAGEMENT
Provision of Resources
Contractor shall identify, determine and mobilize resources as appropriate to provide products and
services as required in the Project Contract and allocate/assign the mobilized resources in a timely
manner. The mobilization of appropriate resources shall ensure that implementation, maintenance and
continual improvement of the Quality Management System will be achieved.
Human Resources
The Project Manager will ensure that adequate human resources with necessary expertise are available
to enable the efficient execution of the Project. In this respect, he will ensure that any required specialist
skill not available within organization is identified at an early stage and appropriate arrangements are
made to engage qualified personnel or subcontractors with relevant experience.
Necessary training for the personnel who performing work affecting quality shall be provided for the
training needs identified. Personnel competencies are based on appropriate education, training, skills
and experience.
The Project Manager is responsible to review the Contract requirements to determine for competent
level of personnel assigned to the Project and ensure assignment of personnel, including those of
subcontractors that meet the requirements. Contractor will maintain a record for quality personnel for
Company review that document the qualifications of Contractor quality personnel.
Each team manager ensures that the personnel within his scope are aware of the relevance and
importance of their activities and how they contribute to the achievement of the quality objectives.
The Project QA/QC Manager, Inspection Coordinators, Vendor Inspectors, Construction QC Supervisors,
Construction QC Inspectors and other necessary Project QA/QC staffs shall be appointed in compliance
with the requirements of Contract.
Quality inspectors shall be suitably qualified with knowledge, a minimum of 3 years of experience and
properly certified for special processes such as NDT, welding, coating, electrical tasks and instrument
installation activities.
Contractor will verify and provide resumes and all associated certifications in legible format of all
Contractor and subcontractor Quality personnel to Company for review and approval prior to the start of
work for each individual. Company shall have the right to interview and/or test assigned inspectors.
Contractor will subcontract inspection services, subject to Company’s review and approval. However,
this does not relieve Contractor of its contractual quality responsibilities.
Contractor’s Quality personnel shall be dedicated to perform quality functions and shall perform no other
function on this Contract.
Contractor’s quality personnel shall have sufficient and well defined responsibilities, qualifications,
authority, and organizational freedom to identify quality problems and areas of non-conformance and to
initiate, recommend and substantiate corrective actions. .
Contractor shall make quality personnel changes required due to vacations, illness, temporary
assignments, emergency leave, resignations or other reasons as necessary to maintain required Quality
coverage. Contractor shall advise the Company Representative of such personnel and quality coverage
at least thirty (30) calendar days in advance of scheduled absences or changes. All other changes such
as illness and emergency leaves shall be notified within 24 hours.
Contractor shall implement an on-going training program to introduce and familiarize all Contractor and
Subcontractor personnel with the project quality requirements for their area of responsibility.
All Project related documentation shall be transmitted via the COMPANY’S Document Management
System under the cover of a transmittal note and controlled in accordance with the Contractor
Documentation Control Procedure (Doc. BK91-1312-INF-000-DCC-PCD-0001) and format as required
by the COMPANY in accordance with the Engineering Document numbering procedure (Doc. ITD-GEN-
000-DCC-PCD-0002_0).
Documents and Records pertaining to all QA/QC are controlled by ALAA BAGHDAD CO. central
Document control.
B
CONTRACTOR will control, retain and preserve the quality document and records created during shop
inspection and site work for the project.
For each shop visit CONTRACTOR’s inspector shall review all records of inspection and test items
carried out between the current shop visit and the previous shop visit. Vendor shall prepare inspection
and test records timely.
Vendor’s welding procedures, specifications, and qualification records shall be reviewed and approved
by CONTRACTOR’s inspector prior to start of fabrication.
Procurement manager shall ensure that records of inspection are completed at the time of inspection
and proper authorizations are obtained.
Procurement manager shall compile all quality records and submit it after delivery of equipment to
worksite. Prior to turnover of quality documents to COMPANY, positive evidence that CONTRACTOR
has reviewed its Vendor/Subcontractor’s documents shall be indicated on the cover of the document.
For non-inspectable materials and equipment and for orders on which inspection has been waived,
CONTRACTOR shall obtain copies of mill test certificates or test data reports for COMPANY’s records
when required.
All quality records shall be in the English language and legible, readily identifiable and retrievable.
ITRs (Inspection and Test Records) shall as a minimum, identify.
All fabrication and manufacturing data dossiers/reports containing mill certificates, machinery test
certificates and all other relevant inspection data are compiled and submitted to COMPANY after delivery
of equipment to worksite.
For the control, retainment and preservation of the quality dossier and records, CONTRACTOR will use
Excel Sheets to capture day to day issued AFI and its status and use programmed Excel Sheets to
capture the daily welding status and NDT status.
Likewise, CONTRACTOR can prepare Excel based logs for tracking / control 3rd party tests, ITP records
and Subcontractor submittals etc.
CONTRACTOR will arrive hard copies filing system and scanned copies (PDF) stored by preparing file
folders in this hierarchy like each discipline / system / sub-system.
PROJECT REALIZATION
Planning of Project
6.1.1 General
The Project Manager shall plan and develop Project processes needed for Project realization covering
design, procurement, construction, and pre-commissioning activities in accordance with this
requirements, Contract requirements and other specified regulatory requirements. In planning Project
Realization, the Project Manager shall determine the following, as appropriate;
Project Quality Policy, Objectives and requirements for the Project
Contingency Planning
Processes, documents and resources needed for the Project
Verification, validation, monitoring, inspection and testing activities needed relating to quality
aspects of the Project
Records needed to provide evidence that the processes of Project Realization have met
requirements
The Project Manager is responsible to establish and implement the Project Execution Plan (Doc. BK91-
1312-INF-000-PMT-PLN-0001) including necessary resources, schedule, methods and procedures by
identifying appropriate work processes in accordance with Project specification as soon as the Project
awarded.
- Contract requirements differing from previously expressed are resolve, and Contractor has the
ability to meet the defined requirements.
The review results of Contract shall be documented by each discipline and transmitted to the
Project Manager.
When any incomplete, ambiguous and conflicting items are found, the items shall be separately
recorded and be notified to the Project Manager.
The Project Manager shall collect and summarize all incomplete, ambiguous and conflicting
items from each discipline which shall be clarified by written correspondence document or official
meeting.
All the clarification results shall be notified to the manager of each discipline of the Project.
Based on contract review, the Project Manager will prepare instruction that contains necessary
information to start the work and draw up the Project Control Procedure.
6.2.2.2. The Project Design Manager shall control design interface by defining
responsibility of design work.
B
6.2.2.3. The Engineering Coordinator of each design discipline shall establish the Design
Plan and control for his scope of engineering work to determine
the design stages
the review, verification that are appropriate to each design stage
the responsibilities and authorities for design
All design input requirements will be identified, documented and reviewed for adequacy. These inputs
include;
Functional and performance requirements
Applicable statutory and regulatory requirements
HSE requirements
Reliability, availability and maintenance requirements etc.
Company specified requirements
Process design package and technical information from the Engineering subcontractor shall be reviewed
for adequacy of details.
Incomplete, ambiguous or conflicting requirements shall be clarified and resolved with relevant engineers
and organizations in writing.
Specifications
B
BK91-1101-GEN-999-CIV-SPC-0001 Specification for Concrete Works
BK91-1101-GEN-999-CIV-SPC-0009 Specification for Fence and Gate
On the basis of design inputs and design experiences, an assigned Engineering Coordinator of Project
Engineering Team shall prepare design outputs, such as data sheets, drawings, etc.
Engineering output documents shall meet design-input requirements and reference acceptance criteria
and specify the characteristics that are essential for its safe and proper functioning of the product.
The outputs shall be provided in a form that will enable verification against the design inputs.
Engineering documents prepared by discipline engineers shall be reviewed and checked by LE and
approved by the Project Design Manager prior to release to confirm compliance with Contract
specifications and applicable codes, standards and procedures.
Each discipline engineer shall control their design activities and verify their design output and products
based on the TDR.
Control of Procurement
Procurement shall be performed in accordance with the Procurement Management Plan (Doc. BK91-
1312-INF-000-PUR-PLN-0001)
Issue of Inquiry
Inquiries shall be issued to vendors in accordance with the Vendor list approved by COMPANY.
The Contractor will inquire to a minimum of three (3) vendors selected from the above Vendor List.
The Buyer will be responsible for preparation of standard Inquiry documents, including;
Project name and location
Inquiry number
Needed delivery date
Destination port
Delivery condition
Date required for submittal of design calculations and data, where applicable
Request for complete spare parts list, recommended spare parts or special tools where
applicable
Inspection instructions
Number of copies of operating and/or maintenance manuals required, if applicable
Packing and Marking Instructions
The Inquiry documents will also instruct the Bidders:
To submit bids by the specified date
To state any deviations from the inquiry basis in the format included in MR
To specify delivery dates and commercial terms
To advise of point of origin
If applicable, to submit the following:
a. A detailed explanation of vendor’s organization and capability to provide technical
assistance and service engineers for normal and emergency situations after plant
commissioning
b. A detailed explanation of vendor’s procedure for the handling of repairs, including:
- Parts which vendor normally carries in stock and where located.
- Delivery time for normal and emergency requirements in respect of spare parts.
- Commercial terms for furnishing technical field assistance for installation and start-
up including proposal schedule.
Any technical deviations from Project Specifications shall be approved prior to award of the purchase
order.
Where it deems necessary, the Project Document Controller shall send them to relevant engineers for
squad check.
All Subcontractors and Vendors deliverables including Quality Records and certificates shall be reviewed
by the Project Procurement Inspector and approved by Project Procurement Manager. Also, shall ensure
that each Subcontractor or Vendor compiles a Quality dossier in accordance with the Certification(s) and
Final Documentation requirements of the Contract.
Expediting
For confirmation of vendor’s schedule and expediting, schedule meeting shall be held with Subcontractor
at his shop when Contractor requires. In this meeting, any problems related to vendor’s progress
schedule, inspection schedule, delivery and document issue schedule are discussed and necessary
expediting shall be carried out.
Expeditor shall carry out periodic expediting work by telecommunication with letter, facsimile, and
telephone, etc. and by shop visiting.
Expediting shall be conducted based on the equipment criticality level rating.
Inspection Personnel
Qualified QC Supervisor and inspector(s) shall be selected for the Project on the basis of prior
experiences and specialty from the QA/QC Team and/or Company approved third party inspector in
compliance with the Contract requirements.
Vendor and sub-vendor personnel for Positive Material Identification and welding shall be qualified as
specified by Company’s Standards. Contractor shall review and approve such qualifications prior to the
start of manufacturing.
Inspection Level
“Inspection Level” shall be decided after Criticality Rating Assessment.
Witness by Company
Witness points of Company will be confirmed in accordance with the Contract requirements
requirements to be witnessed and cover the minimum extent of inspection and test activities to
be performed by the Contractor and/or the Company.
Shop Inspection shall be performed in accordance with approved ITP (or shop inspection
procedure) to verify the compliance of products to the Project specifications.
For package units that include various disciplines (mechanical, welding, electrical and
instrumentations), Contractor shall assign additional discipline Inspectors during applicable
work activities for mechanical, welding, electrical, instrumentation and refractory inspections
Vendor will be required to submit manufacturing and test reports. The Contractor and company shall
review and indicate its acceptance of these inspection records prior to issuing the inspection (or shipping)
release. A copy shall be provided to Company with the Inspection Disposition Report.
Vendor Inspection Report will be issued by Inspector after each inspection visit or weekly in case of
continuous inspection. Vendor inspection reports shall include as a minimum the following information:
Narrative details about the inspection performed
ITP inspection points covered during the inspection
Brief material fabrication status
Punch list/outstanding work list (when applicable)
The vendor inspection report will be submitted to the Company within 10 days following inspection visit.
Inspection Release Note (IRN)
An Inspection Release Note (IRN) shall be issued for all equipment and materials at time of final
inspection. The IRN shall indicate all outstanding work items. Contractor shall ensure the IRN is available
with the equipment and materials at time of receipt at job site. Copies of IRN shall be submitted to
Company within 48 hours of issue.
Inspection Disposition Report
Within two weeks of acceptance of material or equipment, Contractor shall prepare and issue to the
Company Representative an Inspection Disposition Report. This report shall be based upon Contractor's
review of the inspection file and include as a minimum:
Narrative details of Quality activities performed during manufacturing and fabrication of the
equipment or material.
Copies of Company approved waivers to Company’s requirements.
All Contractor Inspection Reports.
Copies of supplier quality records.
Copies of all NCR's with final dispositions and resolutions.
Outstanding punch list items from pre-shipment inspections.
Inspection/Shipping Release (IRN).
In cases where the supplier is responsible for export packing, the final disposition report shall be
prepared after export packing has been inspected and accepted by Contractor.
Inspection Waiver
Contractor shall not basically waive the requirements of the any PQP and ITP previously accepted by
Company. In charge of Quality Controller for the Procurement will maintain a log detailing all waivers
obtained during all work phases. This log shall indicate the status of the waiver, a brief description and
details of the applicable purchase order.
Control of Construction
6.4.1 Construction Planning
Construction Manager has responsibility to establish Project Execution Plan (BK91-1312-INF-000-PMT-
PLN-0001) in accordance with relevant Contractor’s Standards and shall issue control procedures
covering field control elements before opening the site.
Prior to actual start of construction activities, Contractor shall develop and submit for review and approval
a detailed Construction Inspection and Test Plan along with related procedures/work instructions / work
method statements for all construction processes to be executed or subcontractors one month prior to
the start of the applicable work. Contractor shall review the quality requirements in all applicable
Company standards and procedures and include appropriate Quality requirements in each ITP. Each
ITP shall detail all review, witness, and hold points for Company, Contractor and subcontractors as
specified in this Contract. It shall also include the methods, extent and timing for examinations,
measurements or tests.
As a minimum, each ITP shall include the following information:
Process description
Quality control requirements
Notification requirements
Responsibilities
Applicable procedures
Acceptance criteria
Percentage of tests to be done (including increased inspection levels when performance
requirements are not met.)
Verifying documents
Review, Witness and Hold points
Contractor shall not waive the requirements of any Contractor Quality Plan and ITP previously accepted
by the Company Representative without the express written consent of the Company Representative.
The construction schedule shall be reviewed and monitored by the Project Control Manager /
Construction Manager and/or the Project Planning/Scheduling Engineer, in order to highlight possible
areas that may affect the overall Project schedule and completion.
Contractor shall submit each week a two-week look-ahead schedule of all planned quality activities to
the Company Representative during construction and pre-commissioning.
The schedule shall be sent electronically in a format acceptable to Company.
Contractor shall be fully responsible for the performance of its Subcontractors and their sub-suppliers.
Contractor shall control its construction processes and ensure its subcontractor(s) construction
processes including welding and NDT activities are controlled.
Inspection and test shall be performed in accordance with the approved ITP. Where the ITP identifies
tests and inspections to be performed by Subcontractors/Third Party including NDT activities, Contractor
shall review and approve results of such tests and inspections performed.
Inspection Personnel
Inspector for field inspection and test shall be qualified in accordance with the Contract requirements.
Inspection and Test report
The result of the inspection shall be recorded in proper forms included in the applicable Inspection
Procedures.
Contractor shall submit its test reports and its subcontractors test reports to the Company Representative
as specified by the applicable Company standards. The Contractor shall review its subcontractor’s test
reports prior to submittal.
For all other test reports/validation records whether performed by Contractor or subcontractor, test
reports/validation records shall be maintained current and available at Contractor site office for Company
review.
Contractor shall submit Hydrostatic Test Packages prior to conducting hydrostatic tests of piping,
pipeline, and equipment for Company review and approval.
Inspection & Tests status
The inspection and test status shall be kept under control and maintained as defined in the QC Inspection
Status Report.
The status report shall identify all Contractor and subcontractor required inspection and tests for each
system, when it is scheduled, when it was completed, and any non-conformances discovered during the
test or inspection. The QC Inspection Status Reports shall be kept current and shall be available for
Company’s review at all times.
6.4.7 Control of Pre-commissioning
It shall be the responsibility of Pre-commissioning Manager to develop Pre-commissioning Procedure
and Mechanical Completion Procedure (Includes Quality Data Base and Construction Management
System) covering organization, planning and implementation.
Pre-commissioning Manager shall establish the Pre-commissioning organization in which Pre-
commissioning staff group including Process Engineer, Operation Supervisors, Vendor’s Specialists and
quality personnel shall be designated.
The Contractor is operating and maintenance personnel shall be involved in this under Contractor’s
supervision and direction.
6.4.8 Commissioning
Another significant task of the commissioning team is to verify that construction is proceeding as
necessary to start up the plant. Any deficiencies will be documented on a punch list and then
distributed to the construction team for rectification. While conducting the walkthrough, the
commissioning engineer will not just be looking for loose bolts or missing valves. They will also be
evaluating the system from an all-important operator’s perspective. This includes checking for safety
issues around the work area, making sure that all valves and platforms are accessible to operators,
and that the system can be operated safely.
Vendor’s inspection & test reports, including material test certificates and NDE reports, etc. shall be
checked by QA/QC Manager or his representative.
When witnessing the inspections, Contractor inspectors shall verify, based on identification indications
and records that the Vendors have implemented or are implementing the required traceability for the
products being witnessed-inspected.
Customer Property
Contractor shall exercise care with customer property including while it is under Contractor’s control or
being used.
Customer shall identify, verify, protect and safeguard customer property provided for use or incorporation
into the product.
If any customer property is lost, damaged or otherwise found to be unsuitable for use, this shall be
reported to the customer and records are maintained.
Details for control of Customer Property shall be in accordance with the Customer Property Control
Procedure.
Preservation
Contractor will include procedures and requirements for handling, storage, and preservation of material
as specified in all applicable specifications, manufacturer recommendations and Company’s standards
in Field Material Control Procedure and the applicable work procedure or instructions. The procedure
shall list all inspection schedules for maintaining the quality of the material or equipment as well as
provide for documentation that the required activities have been performed.
Instruction or procedure for special handling, storage and preservation will be developed and
implemented. Individuals responsible for special handling, storage and preservation shall be fully
qualified to do so and supplied with predetermined work and inspection instructions.
Data concerning handling, storage and preservation shall be included on the Monthly Materials
Procurement Status Report and shall be available at site at time of material/equipment receiving.
Customer Satisfaction
The Project Control Manager shall monitor information relating to Customer perception as to whether
Contractor has met Company requirements through evaluation of Company assessment, Non-
conformance Reports (NCR) and Inspection Log entries and other Company complaints during
communication and meetings between the Contractor and the Company.
The Project Control Manager and Project QA/QC Manager shall also conduct Customer Satisfaction
Survey by using Customer Satisfaction Survey Questionnaire which will be developed by the Project
Control Manager quarterly.
The Project Control Manager shall develop the quarterly Customer Satisfaction Report on basis of the
evaluation results and the results of Customer Satisfaction Survey.
These reports shall be used for Project Management Review.
Waivers
Contractor shall not waive the requirements of any Contractor Project Quality Plan or Inspection and
Test Plan previously accepted by the Company Representative without the express written consent of
the Company Representative.
Contractor shall also maintain a log detailing all waivers to Company standards obtained during all
phases, including those initiated by Company (during or prior to the start of work) or Contractor. This log
must indicate the status of the waiver, a brief description and details of the applicable purchase order
and equipment or construction process.
Analysis of Data
The Project QA/QC Manager will prepare and submit a Monthly Quality Management Report in a format
acceptable to Company to demonstrate effective implementation of the Contractor's Quality System. The
report shall include the following items, as a minimum:
Listing and disposition of all defective or rejected material or equipment received at jobsite by
Contractor and subcontractor(s)
Welding rejection rate
Continual Improvement
7.7.1 Continual Improvement
Project Manager shall review and utilize the followings to continually improve the effectiveness of the
Quality Management System implemented for the Project. The continual improvement is an
established objective for the QMS and it is pursued by mean of:
Customer satisfaction
Internal and external audits
Internal and external Non-conformities
Repeat violations
Process performance measures
Data analysis
Corrective and Preventive Actions
Customer Satisfaction
Management Review
The Project QA/QC Manager shall request related discipline manager in charge to issue a Corrective
Action Request (CAR).
The discipline manager or related vendor shall be responsible for taking any corrective or preventive
action necessary, as a result of a reported. The conditions, their cause and the corrective action taken
shall be documented on the Corrective Action Request (CAR).
The Project QA/QC Manager is also responsible for the relevant follow-up in order to ensure that
corrective/preventive action has been taken and that it is effective.
ATTACHMENTS LIST
Attachment 1 – Project Organization Chart
Attachment 4: MDR
Approval Code
Approval Code
Approval Code
Approval Code
Approval Code
Planned
Planned
Planned
Planned
Planned
Date
Date
Date
Date
Date
Sr. System Document
Project Phase Project Code Unit Code Discipline Doc Type Document No. Document Title Actual Actual Actual Actual Actual Remarks
No Code Class
CNS
1 BK91 1 1312 INF 829 CNS CMM BK91-1312-INF-829-CNS-CMM-0001 Method of Statement for Earth Works 1
2 BK91 1 1312 INF 829 CNS CMM BK91-1312-INF-829-CNS-CMM-0002 Method of Statement for Geotechnical Investigation 1
3 BK91 1 1312 INF 829 CNS CMM BK91-1312-INF-829-CNS-CMM-0003 Method statement for topographic survey 1
4 BK91 1 1312 INF 829 CNS CMM BK91-1312-INF-829-CNS-CMM-0004 Method Statement for Concrete Works 1
5 BK91 1 1312 INF 829 CNS CMM BK91-1312-INF-829-CNS-CMM-0005 Method statement for Subbase Paving, Asphalt Paving and Sidewalk Paving 1
6 BK91 1 1312 INF 829 CNS CMM BK91-1312-INF-829-CNS-CMM-0006 Method Statement for Installation of Chain Link Fence and Gate 1
7 BK91 1 1312 INF 829 CNS CMM BK91-1312-INF-829-CNS-CMM-0007 Method of Statement for Piping Fabrication and Installation Construction 1
8 BK91 1 1312 INF 829 CNS CMM BK91-1312-INF-829-CNS-CMM-0008 Method of Statement for Steel Structure Prefabrication and Installation 1
9 BK91 1 1312 INF 829 CNS CMM BK91-1312-INF-829-CNS-CMM-0009 Method of Statement for Surface Preparation and Painting 1
10 BK91 1 1312 INF 829 CNS CMM BK91-1312-INF-829-CNS-CMM-0010 Method of Statement for Rotating Equipment Installation 1
11 BK91 1 1312 INF 829 CNS CMM BK91-1312-INF-829-CNS-CMM-0011 Method of Statement for Static Equipment Installation 1
12 BK91 1 1312 INF 829 CNS CMM BK91-1312-INF-829-CNS-CMM-0012 Method of Statement for Instrument Installation 1
13 BK91 1 1312 INF 829 CNS CMM BK91-1312-INF-829-CNS-CMM-0013 Method of Statement for Electrical Installation 1
14 BK91 1 1312 INF 829 CNS CMM BK91-1312-INF-829-CNS-CMM-0014 Method of Statement for Telecom Installation 1
15 BK91 1 1312 INF 829 CNS CMM BK91-1312-INF-829-CNS-CMM-0015 Method of Statement for Tank Installation 1
16 BK91 1 1312 INF 829 CNS CMM BK91-1312-INF-829-CNS-CMM-0016 Method of Statement for Leak Test 1
17 BK91 1 1312 INF 829 CNS CMM BK91-1312-INF-829-CNS-CMM-0017 Method of Statement for Loop Test 1
18 BK91 1 1312 INF 829 CNS CMM BK91-1312-INF-829-CNS-CMM-0018 Method of Statement for Telecom/Security System Site Integration 1
19 BK91 1 1312 INF 829 CNS CMM BK91-1312-INF-829-CNS-CMM-0019 Method of Statement for HVAC Installation 1
20 BK91 1 1312 INF 829 CNS CMM BK91-1312-INF-829-CNS-CMM-0020 Method of Statement for Security Defence (Included CCTV, LAN, PAGA, Fire Alarm System, Access Hydrostatic Test Procedure) 1
PMT
1 BK91 1 1312 INF 829 PMT ORG BK91-1312-INF-829-PMT-ORG-0001 ALAA-BAGHDAD Project organization chart and CVs 1
2 BK91 1 1312 INF 829 PMT PLN BK91-1312-INF-829-PMT-PLN-0001 Project Execution Plan 1
4 BK91 1 1312 INF 829 PMT PCD BK91-1312-INF-829-PMT-PCD-0001 Cost Control, Invoicing and Payment Procedure 1
5 BK91 1 1312 INF 829 PMT PLN BK91-1312-INF-829-PMT-PLN-0003 Engineering Execution Plan 1
6 BK91 1 1312 INF 829 PMT PLN BK91-1312-INF-829-PMT-PLN-0004 Logistic Management Plan 1
7 BK91 1 1312 INF 829 PMT PLN BK91-1312-INF-829-PMT-PLN-0005 Risk Management Plan 1
8 BK91 1 1312 INF 829 PMT PCD BK91-1312-INF-829-PMT-PCD-0002 Change Order Procedure 1
HSSE
1 BK91 1 1312 INF 829 HSE PCD BK91-1312-INF-829-HSE-PCD-0001 Work at height Procedure 1
2 BK91 1 1312 INF 829 HSE PCD BK91-1312-INF-829-HSE-PCD-0002 Hazard Identification and risk assessment procedure 1
3 BK91 1 1312 INF 829 HSE PCD BK91-1312-INF-829-HSE-PCD-0003 HSE Signs ,Barricade Procedure 1
4 BK91 1 1312 INF 829 HSE PCD BK91-1312-INF-829-HSE-PCD-0004 Work Permit Management Procedure 1
8 BK91 1 1312 INF 829 HSE PLN BK91-1312-INF-829-HSE-PLN-0002 Environment Protection Plan 1
9 BK91 1 1312 INF 829 HSE PLN BK91-1312-INF-829-HSE-PLN-0003 Traffic Management Plan 1
10 BK91 1 1312 INF 829 HSE PLN BK91-1312-INF-829-HSE-PLN-0004 Waste mangement procedure 1
11 BK91 1 1312 INF 829 HSE PLN BK91-1312-INF-829-HSE-PLN-0005 HSE Training Plan 1
12 BK91 1 1312 INF 829 HSE ERP BK91-1312-INF-829-HSE-ERP-0001 Emergency Response and Evacuation Plan 1
14 BK91 1 1312 INF 829 HSE PCD BK91-1312-INF-829-CNS-PCD-0008 Security Management Procedure 1
PRC
1 BK91 1 1312 INF 829 PRC SCH BK91-1312-INF-829-PRC-SCH-0001 Project Baseline Schedule 1
2 BK91 1 1312 INF 829 PRC SCH BK91-1312-INF-829-PRC-SCH-0002 Project Forecast Schedule 1
3 BK91 1 1312 INF 829 PRC PMS BK91-1312-INF-829-PRC-RPT-0001 Progress measurement System Report 1
PUR
1 BK91 1 1312 INF 829 PUR PLN BK91-1312-INF-829-PUR-PLN-0001 Procurement Management Plan 1
3 BK91 1 1312 INF 829 PUR VDL BK91-1312-INF-829-PUR-VDL-0002 Engineering Subcontractor List 1
4 BK91 1 1312 INF 829 PUR VED BK91-1312-INF-829-PUR-VED-0001 Geomark for geomatics engineering 1
5 BK91 1 1312 INF 829 PUR VED BK91-1312-INF-829-PUR-VED-0002 PIMPro Engineering Consultations Projects Managements 1
6 BK91 1 1312 INF 829 PUR VED BK91-1312-INF-829-PUR-VED-0003 AL-MAMAAS ENGINEERING LABORATORY 1
Page 1 of 2
"EPC SECURITY DEFENCE & CHECK POINTS FOR BLOCK9"
MANAGEMENT DOCUMENT REGISTER (MDR)
Approval Code
Approval Code
Approval Code
Approval Code
Approval Code
Planned
Planned
Planned
Planned
Planned
Date
Date
Date
Date
Date
Sr. System Document
Project Phase Project Code Unit Code Discipline Doc Type Document No. Document Title Actual Actual Actual Actual Actual Remarks
No Code Class
QAC
1 BK91 1 1312 INF 829 QAC PLN BK91-1312-INF-829-QAC-PLN-0001 Project Quality Plan 1
2 BK91 1 1312 INF 829 QAC PCD BK91-1312-INF-829-QAC-PCD-0001 Corrective and Preventive Action Procedure 1
3 BK91 1 1312 INF 829 QAC PCD BK91-1312-INF-829-QAC-PCD-0002 Non-Conformity Management and Cotrol Procedure 1
4 BK91 1 1312 INF 829 QAC PCD BK91-1312-INF-829-QAC-PCD-0003 Project Audit Procedure 1
5 BK91 1 1312 INF 829 QAC PCD BK91-1312-INF-829-QAC-PCD-0004 Inspection,Test and Measuring Equipment Calibration and Control Procedure 1
6 BK91 1 1312 INF 829 QAC PCD BK91-1312-INF-829-QAC-PCD-0005 Piping Hydrostatic Test Procedure 1
7 BK91 1 1312 INF 829 QAC PCD BK91-1312-INF-829-QAC-PCD-0006 Welding and Qualification Procedure 1
BK91 1 1312 INF 829 QAC PCD BK91-1312-INF-829-QAC-ITP-0001 Standard ITP and Checklist for Civil work 1
9 BK91 1 1312 INF 829 QAC ITP BK91-1312-INF-829-QAC-ITP-0002 ITP for Concrete Works & Grout 1
10 BK91 1 1312 INF 829 QAC ITP BK91-1312-INF-829-QAC-ITP-0003 ITP for Excavation, Backfill and Compaction 1
8 BK91 1 1312 INF 829 QAC ITP BK91-1312-INF-829-QAC-ITP-0004 ITP for Fence and Gate 1
11 BK91 1 1312 INF 829 QAC ITP BK91-1312-INF-829-QAC-ITP-0005 ITP for Asphalt Road 1
BK91 1 1312 INF 829 QAC ITP BK91-1312-INF-829-QAC-ITP-0013 ITP of Pre-Fabbrication Building 1
DCC
1 BK91 1 1312 INF 829 DCC MDR BK91-1312-INF-829-DCC-MDR-0001 Management Documentation Register (MDR) 1
2 BK91 1 1312 INF 829 DCC IDX BK91-1312-INF-829-DCC-IDX-0001 Table of Content-Final Documentation Handover 1
3 BK91 1 1312 INF 829 DCC PCD BK91-1312-INF-829-DCC-PCD-0001 Document and Data Management Procedure 1
4 BK91 1 1312 INF 829 DCC TMP BK91-1312-INF-829-DCC-TMP-0001 Drawing Template (Included A1, A2, A3) 1
5 BK91 1 1312 INF 829 DCC TMP BK91-1312-INF-829-DCC-TMP-0002 Template for Procedure 1
6 BK91 1 1312 INF 829 DCC PLN BK91-1312-INF-829-DCC-PLN-0001 Vendor Documentation Management Plan 1
7 BK91 1 1312 INF 829 DCC PCD BK91-1312-INF-829-DCC-PCD-0002 Final Document Hand Over Procedure 1
8 BK91 1 1312 INF 829 DCC TDR BK91-1312-INF-829-DCC-TDR-0001 Technical Documentation Register (TDR) 1
1 BK91 1 1312 INF 829 CMS PCD BK91-1312-INF-829-CMS-PCD-0001 Mechanical Completion, Provisional Acceptance and Handover Procedure 1
2 BK91 1 1312 INF 829 CMS PCD BK91-1312-INF-829-CMS-PCD-0002 Pre-Commissioning & Commissioning Procedure 1
Page 2 of 2