Dt. 09.09.2019 Boiler Commissioning Inputes Required From Molindo
Dt. 09.09.2019 Boiler Commissioning Inputes Required From Molindo
Dt. 09.09.2019 Boiler Commissioning Inputes Required From Molindo
2019
4. Passivation
a) Raw Water required for DM Plant Operation
b) Required Fire Wood
c) Required Coal
d) Required Boiler Chemical
1) Hydrogen peroxide - 60 kg
2) Ammonia - 10 kg
e) Manpower required for Chemical shifting / mixing / feeding to Steam drum
manhole
f) DM Makeup water required (whenever drum level getting down)
g) Manpower required for fire wood shifting and feeding the furnace
h) Diesel for initial light-up (5 Ltr)
i) DCS Operators required 24 Hrs up to completion of alkali boil-out
j) Boiler attender required to maintain furnace firing
k) Laboratory person required for take sample from boiler blow down every two
hours (to analyse the following parameters from Boiler Blow down water)
1) Hydrazine
2) PH
5. Steam blowing
a) Raw Water required for DM Plant Operation
b) Required Fire Wood
c) Required Coal
d) HP & LP Dosing Chemical
e) DM Makeup water required (whenever drum level getting down)
f) Manpower required for fire wood shifting and feeding the furnace
g) Diesel for initial light-up (5 Ltr)
h) DCS Operators required 24 Hrs up to completion of steam blowing
i) Boiler attender required to maintain furnace firing
j) Required lime powder for Bag filter
Note:
Parallely arrange the fire fighting system, street light and access road for
overall plant also required chemical for future smooth operation of DM
plant.
Housekeeping manpower required from 1st stage of alkali boil-out.
Maintenance team required from the 1st stage of alkali boil-out.
Truck required for Ash disposal from SMBC (Wet ash) discharge and Fly
ash silo discharge areas from the refractory dry out.
Apart from the above points if any additional requirements we will
update.