PROJECT PROPOSAL FOR INNOVATION

IN SCHOOL OPERATIONS AND LEARNING ENVIRONMENT

Name of Proponent: LAWRENCE C. ABADILLA

Project Title: Concreting of Pavement in front of BRO Building and Sulong Ilagan
Building

Project Time Frame: April-June 2021

I. Project Contact:

EMERITA M. BURGOS, PhD.


Principal IV
09176071171
emerita.burgos001@deped.gov.ph

LAWRENCE C. ABADILLA
BE Coordinator, JHS
09268114464
lawrence.abadilla@deped.gov.ph

MAHALINDO PREZA
School Facility Coordinator
09569214945
mahalindo.preza@deped.gov.ph

II. Project Summary

The target area for pavement concreting is located in front of the BRO Building and
Sulong PA Ilagan Building. The ease that the project will give the ISATians will help in
improving the learning environment and also for beautification purposes.
Concreting of the pavement will also lift passersby particularly the learners, faculty and
staff of ISAT going to SHS building from the danger brought by the usual muddy and slippery
condition of the road.
The project is a maximized collaboration in school planning design through consultative
planning, design and project implementation involving a wide spectrum of representatives from
the different stakeholders of the school.
The estimated project time-frame is from April to June 2021 with an estimated total cost
of P598,108.00
III. Project Background

Flooding is the nation’s most common natural disaster. School ground may be subject to
erosion and scour, with the possible loss of soil and damaged to paved areas, including access
roads.
The primary function of educational facilities is to provide the proper school environment
that is most conducive to effective teaching and learning. It shall be responsive to changes in
teaching methods and school organization taking into consideration the changes in educational
process which has become more active, interrelated, and has become an integral part of the wider
community.
Through the comprehensive planning of the school’s administration with the stakeholders
and constant evaluation of educational facilities and school grounds the project needs to be
implemented to avoid future accident that may happen due to muddy and slippery sidewalks. It
will also serve as the parking area of the school.

IV. Project Objective

The project will surely enhance the learning capabilities of the students for the maximum
development of their potential, skills and talents.
Concrete pavements are durable and safe. They are considerably less prone to wear and
potholes that can cause future accident.
It is also a good area in case of emergencies that will require students to immediately
evacuate from their classrooms (such as in case of fire or earthquake).
This project will also serves as parking area.

V. Project Methodology

A. Work Breakdown and Task Time Estimates

Activities Date Persons Involved


Conduct of Area/Project Assessment April, 2021 TVE Boys ISAT
Planning with the School Admin and School Head
other stakeholders
Preparation and approval of Project April, 2021 Project Proponent
Proposal/Program of Work School Admin
Other Stakeholders
Preparation and approval of other April, 2021 Project Proponent
necessary documents and materials School Admin
Project implementation TVE Boys ISAT
a. Procurement Period April-May 2021 School Admin

b. Laying of Stine Masonry


c. Pavement Concreting

B. Project Deliverables
All the materials and consumables are delivered upon purchasing in the hardware
store.

C. Project Risk Management


The project will be done observing the IATF protocol

VI. Project Costs

ITEM DESCRIPTION UNIT QTY UNIT COST TOTAL COST GRAND


NO MATERIAL LABOR MATERIAL LABOR TOTAL
CONCRETING
DRIVEWAY 14
SPANS
EXCAVATION CUBIC 125.00 800.00 0.00 100,000.00 100,000.00
C-PURLINS SIZE PCS 4.00. 900.00 270.00 3,600.00 1,080.00 4680.00
6”
CEMENT PCS 1,157.00 230.00 69.00 266,110.00 79,833.00 345,943.00
REINFORCING PCS 454.00 150.00 45.00 68,100.00 20,430.00 88,530.00
BAR 10 MM
TIE WIRE KILO 20.00 80.00 24.00 1,600.00 480.00 2,080.00
GRAVEL CUBIC 125.00 350.00 105.00 43,750.00 13,125.00 56,875.00

SUB-TOTAL 598,108.00

MATERIALS 383,160.00
LABOR 214,948.00
TOTAL COST 598,108.00
(I+II)

A. Sources
The project will be funded through the Brigada donations of the school.

I. Monitoring and Evaluation


Day-to-day monitoring will be done throughout the duration of the project.