MINOR MATERIALS
No. Material Unit Qty Rate Amount / Rs.
Internal Transportation
10 3 Cube Tippers - 5 Nos Day 1800 6,500 11,700,000
11 Farm Tractors - 3 Nos Day 1800 2,500 4,500,000
12 Small Lorries - 3 Nos Day 1800 2,000 3,600,000
Contractors Office
No Item Duration Rate Amount
1 Office - Rent 12 40,000.00 480,000.00
2 Telephone 12 20,000.00 240,000.00
3 Water 12 5,000.00 60,000.00
4 Electricity 12 12,000.00 144,000.00
5 Furniture 1 400,000.00 400,000.00
6 Computer with Printer 5 75,000.00 375,000.00
7 Fax Machine 1 25,000.00 25,000.00
8 Cammara. 1 20,000.00 20,000.00 1,744,000
Site Laboratory
1 Building - Rent 12 25,000.00 300,000.00
3 Water 12 5,000.00 60,000.00
4 Electricity 12 15,000.00 180,000.00
5 Lab Equipment - rental 1 year 1 500,000.00 500,000.00
6 Computer with Printer 1 75,000.00 75,000.00 1,115,000
Food for Workers @ 125 Rs/Day -Average 125 45,000 125.00 5,625,000.00 5,625,000