Activity centers Costs (in pesos) Cost Drivers

Utilities 900,000 60,000 Machine hours used


Scheduling and setup 500,000 2,000 Numbers of set ups
Materials handling 1,300,000 2,500,000 Pounds of materials

Product A Product B Product C


Prime costs 650,000 522,000 354,000
Machine hours 30,000 20,000 10,000
Number of setups 725 695 580
Pounds of materials 1,125,000 800,000 575,000
Units produced 100,000 70,000 95,000
Direct labor hours 67,500 82,000 55,000

Activity based overhead


Activity Centers rate (in PHP)
Utilities 900,000/60,000 = P 15
Scheduling and setup 500,000/2,000 = P 250
Materials handling 1,300,000/2,500,000 = P 0.52

Product A Product B Product C

Utilities:
A (30,000 x 15) P 450,000
B (20,000 x 15) P 300,000
C (10,000 x 15) P 150,000

Scheduling and setup:


A (725 x 250) 181,250
B (695 x 250) 173,750
C (580 x 250) 145,000

Materials handling:
A (1,125,000 x 0.52) 585,000
B (800,000 x 0.52) 416,000
C (575,000 x 0.52) 299,000

TOTAL P 1,216,250 P 889,750 P 594,000


Total

P 900,000

500,000

1,300,000
P 2,700,000