HN-MECH-31 Progress Report PDF
HN-MECH-31 Progress Report PDF
HN-MECH-31 Progress Report PDF
Headers Plant room 03-09-20 22-09-20 7 7 100% Chiller and Pumps completed
Pipe work Plant room 07-09-20 03-09-20 100% Complete HVAC system completed
Roof top pipe Routes Roof top 20-07-20 27-08-20 3 3 100% completed
Cladding work Roof top piping Roof top 15-08-20 30-09-20 3 3 100% completed
Make up water tank and make up lines complete Roof top 29-09-20 29-09-20 1 1 100% completed
plant room and Pipe
Hydro testing of the HVAC system 06-10-20 11-10-20 5 5 100% completed
Routes
pressure, temp Gauges, flow switches, drain cocks plant room 07-10-20 11-10-20 98% completed
Plant room insulation cladding plant room 20-10-20 29-10-20 100% completed
Duct MS Supports Roof top 01-12-20 02-12-20 100% Duct MS Supports han been installed where as required.
ALL CPM Material including DDC Controlers, Motorized Valves, Sensors and cabling has been delived at Site by 08-12-2020
Daisy Chain Cable for Ahus has been installed in PVC Ducts.
Chiller CPM instruments i.e Temp. Pressure Transmitters Has been installed
Temperature and Humidity Sensors have been Installed on supply and return Ducts
Electrical Engineer
Mechanical Fixers
Project Manager
Project Engineer
Cladding team,
Ducting Team
Fabricators
Welder
Labor
we have a site meeting with team Highnoon regarding Ahus Scren play and Grapics this evening
Pending Work
1 1 8 3 1 2 2 6 1
Description OF Issues Holding Progress
Instructions to customer :
Test(s) Conducted :
Project Engineer
Name : Engr. Zeshan Haydar
Signature :