DAILY HVAC PROJECT PROGRESS REPORT

Report No. : HN-MECH-125


Date : 31-12-20 customer name : HIGHNOON LAB
Zone :
Project . : Welkin File No. : 100A Activity : HVAC
Form No. : 001 building type :
Discipline: ARCH CVL QTY SRVY location : LAHORE
ELC MECH MED
INSTALLED
Work Description ZONE START DATE FINISH DATE T/QTY Actual % Notes/Attachment Ref.
QTY
All Assemblies work Plant room 01-09-20 22-09-20 15 15 98% Chiller, Pumps, AHUs and Heat Exchanger completed

Headers Plant room 03-09-20 22-09-20 7 7 100% Chiller and Pumps completed

Pipe work Plant room 07-09-20 03-09-20 100% Complete HVAC system completed

Cooling tower Plant room 19-09-20 30-09-20 1 1 100% completed

Hot water Generator Roof top 19-09-20 10-09-20 1 1 98% completed

Air Separator Roof top 20-09-20 03-09-20 1 1 98% completed

Roof top pipe Routes Roof top 20-07-20 27-08-20 3 3 100% completed

Cladding work Roof top piping Roof top 15-08-20 30-09-20 3 3 100% completed

Electrical work Plant room 22-09-20 20-10-20 10 10 100% completed

Make up water tank and make up lines complete Roof top 29-09-20 29-09-20 1 1 100% completed
plant room and Pipe
Hydro testing of the HVAC system 06-10-20 11-10-20 5 5 100% completed
Routes
pressure, temp Gauges, flow switches, drain cocks plant room 07-10-20 11-10-20 98% completed

Plant room insulation cladding plant room 20-10-20 29-10-20 100% completed

plant room and Pipe


chemical water circulation and flushing 13-10-20 25-10-20 100% completed
Routes
Chiller Test Run Plant Room 04-11-20 04-11-20 1 1 100% Successfully done

Ahu # 23 Installation Roof top 06-11-20 09-11-20 1 1 100% completed

Ahu # 18 Installation Roof top 07-11-20 10-11-20 1 1 100% completed

Ahu # 17 Installation Roof top 01-12-20 02-12-20 1 1 100% completed

Ahu # 10 Installation Roof top 01-12-20 02-12-20 1 1 100% completed

Ahu # 14 Installation Roof top 02-12-20 1


Installation Schedule of 2 Ahus are still pending at
Highnoon end.
Ahu # 16 Installation Roof top 03-12-20 1

Duct MS Supports Roof top 01-12-20 02-12-20 100% Duct MS Supports han been installed where as required.

CPM is in Testing and Commessioning Phase now. 1st


Chiller Plant Management (CPM) Plantroom+ rooftop 05-12-20 31-12-20 1 80%
Ahu's logics testing is in progress. Pictuers are atached.

Progress Note WELKIN SOLUTIONS (PVT.) Ltd. MANPOWER

ALL CPM Material including DDC Controlers, Motorized Valves, Sensors and cabling has been delived at Site by 08-12-2020

Daisy Chain Cable for Ahus has been installed in PVC Ducts.

Motorized Valves for Chiller and Ahus have been installed.

Chiller CPM instruments i.e Temp. Pressure Transmitters Has been installed

Temperature and Humidity Sensors have been Installed on supply and return Ducts
Electrical Engineer

Mechanical Fixers
Project Manager

Project Engineer

Cladding team,
Ducting Team

40" LED Make SONY has been delivered at site.


Store & HSE

Fabricators
Welder

Labor

Cable Termination work is in progress.

Chiller Remote control unit cables termination has been completed.

5 Ahus Cables Termination work completed.

we have a site meeting with team Highnoon regarding Ahus Scren play and Grapics this evening

Tags have been fixed in plantroom Pipelines.

Project Dossier Documents will be submitted by tomorrow.

Pending Work

1 1 8 3 1 2 2 6 1
Description OF Issues Holding Progress

Connections for Remaining 2 Ahus are Pending at Team Highnoon end.


Accident Report : NILL

Instructions to customer :

Delivered Material : In Process

Test(s) Conducted :

Project Engineer
Name : Engr. Zeshan Haydar

Signature :