Summary of Pipe Culvert Quanities 31+798.84: Description Unit Quantity Remark Pay Item No
Summary of Pipe Culvert Quanities 31+798.84: Description Unit Quantity Remark Pay Item No
Summary of Pipe Culvert Quanities 31+798.84: Description Unit Quantity Remark Pay Item No
Cross
Culvert
Des. Description sectional Length Volume Remark
Station
Area
V0 Cut off wall (Left) 0.33 2.92 0.97
V1 Grouted Stone Pitching (Left) 0.02 3.29 0.07
V2 Head Wall (Left) 1.65 5.22 8.62
31+798.84 V3 Pipe 43.60 2.42 105.51
V4 Head Wall (Right) 4.13 7.71 31.84
V5 Grouted Stone Pitching (Right) 1.47 2.32 3.41
V6 Cut off wall (Right) 6.11 1.22 7.46
Total 157.88
V3 V3
V4
V2 V2 Length
V1
2.0:1 Left
2.0:1 Right
Top of Backfill
0.30
V4
V1 V1 V2 Bedding
V5
0.45 . 0.45
0.30
0.30
V6
V3 V1
V1 V3
Deductions
Cross Gross
Culvert Length/ G.Stone Net Volume
Description sectional No Total Concrete Pipe
Station Thickness Pitching of Backfill
Area Volume (Cu.m.) (Cu.m.)
(Cu.m.)
V1 (Left) 0.120 3.35 1 0.40 0.40
V1 (Right) 0.260 6.71 1 1.74 1.74
V2 (Left) 3.230 0.5 2 3.23 3.23
V2 (Right) 1.670 0.5 2 1.67 1.67
31+798.84 V3 (Left) 0.310 3.35 2 2.08 2.08
V3 (Right) 0.280 6.71 2 3.76 3.76
V4 (Left) 1.1 3.35 1 3.69 0.51 3.18
V4(Right) 1.81 6.71 1 12.15 0.80 11.35
V5 (Left) 0.310 3.35 1 1.04 1.04
V5 (Right) 0.280 6.71 1 1.88 1.88
V6 34.580 1.42 1 49.10 49.10
TotalVolume 79.42
CONTRACTOR CONSULTANT CONSULTANT
Prepared By:__________________ Checked By:__________________ Approved By:_________________
Date :__________________ Date :__________________ Date :_________________
Project :-YALO-ABALA ROAD PROJECT LOT I YALO-NEHILE
GROUTED STONE PITCHING Employer :- Federal Democratic Republic of Ethiopia
QUANTITY Ethiopian Roads Authority
OF PIPE CULVERTS Consultant :- ICT Intercontinental Consultants & Technocrats
Contractor :-BRIDGE CONSTURCTION
31+798.84
5
0.5
0.5
5
.
.
1.32 .
L= 1.60 m.
A= (0.55+1.32+0.55)X1.6
A = 3.87 sq. m.
L= 2.60 m.
A= (0.55+1.32+0.55)X2.6
A = 6.29 sq. m.
AT = 3.87 + 6.29
= 10.16 sq. m.
5
0.5
0.5
5
.
.
1.32 .
L= 1.60 m.
A= (0.55+1.32+0.55)X1.6
###
###
Area
S
Masonry Volume Inlet (I) Masonry Volume Outlet (O) t
W1= 1.23 W1= 0.60 a
t
W2= 0.30 W2= 0.30 i
o
H = 2.33 H = 2.41 n
L = 6.71 L = 3.29 Diameter o
Gross Total Volume Gross Total Volume Side Slope l
Vi= (W1+W2)X 0.5X H X L Vi (W1+W2)X 0.5X H X L Side Slope R
= (1.23+0.3) X 0.5 X 2.33 X 6.71 (1.23+0.3)
= X 0.5 X 2.33 X 6.71 Flow Direct
= 11.96 Cu.m. = 3.57 Cu.m.
Deductions Deductions
Lp= 0.70 Lp= 0.70
A= 1.58 A= 1.58
Vp= A X Lp Vp= A X Lp
= 0.7 X 1.58 = 0.7 X 1.58
= 1.11 Cu.m. = 1.11 Cu.m.
Lp= Average Length of Pipe Within Masonry
A= Area of Pipe
Net Head wall Volume Net Head wall Volume
Vn= Vi - Vp Vn= Vi - Vp
= 11.96 - 1.11 = 11.96 - 1.11
= 10.85 Cu.m. = 10.85 Cu.m.
Cut off Wall Cut off Wall
W= 1.42 W= 1.42
H= 1.00 H= 1.00
V= 1.42 X 1 V= 1.42 X 1
V= 1.42 Cu.m. V= 1.42 Cu.m.
Total Masonry Volume (I + O)= 24.54 Cu.m.
###
###
Area
S
Masonry Volume Inlet (I) Masonry Volume Outlet (O) t
W1= 1.23 W1= 0.60 a
t
W2= 0.30 W2= 0.30 i
o
H = 2.33 H = 2.41 n
Date :__________________ Date :__________________ Date :_________________
Project :-YALO-ABALA ROAD PROJECT LOT I YALO-NEHILE
CONCRETE BLINDING Employer :- Federal Democratic Republic of Ethiopia
QUANTITY Ethiopian Roads Authority
OF PIPE CULVERTS Consultant :- ICT Intercontinental Consultants & Technocrats
Contractor :-BRIDGE CONSTURCTION
31+798.84
W= 1.45 m.
L= 5.88 m.
T= 0.10 m.
V= W X L X T
V= 0.85 Cu. m.
W= 1.45 m.
L= 5.88 m.
T= 0.10 m.
V= W X L X T
V= 0.85 Cu. m.
VT = 0.85 + 0.85
= 1.71 Cu. m.
W= 1.45 m.
L= 5.88 m.
31+798.84
5.420 1.5
4.420
.5
1
H Average
H Average
1
1.000
:
###
1
3.0
2.
3.
0:
0:
0:
2.
1
1
1.420 1.420
Quantity of Channel Excavation Left Side Quantity of Channel Excavation Right Side
L = 10.00 m. L = 20.00 m.
B1 = 1.42 m. B1 = 1.42 m.
B2 = 5.42 m. B2 = 4.42 m.
H = 1.00 m. H = 0.50 m.
Station
Total Volume=63.40Cu.m. Dia. Of Pipe