1.

SCOPE OF WORK

The scope of work shall be covered fabrication, installation Inspection and


Painting of Tie in pipe spool with valve in the existing 10” CWS & CWR lines.

2. PURPOSE
Purpose of this Tie-in is to supply water to the new 3" Cooling water Supply
and Return line for the COOLER IN THE DISCHARGE PRODUCT
LUBRICATION LINE OF PUMP 141-G-0002 A/B.

3. PROCEDURE

 As per drawing site measurement’s to be done.


 Pre fabrication to be start at shop as per site verification.
 Fit up and welding joints inspection will be as per approved ITP
 NDT testing, and painting of prefabricated spool will be done at shop as per
approved IFC drawings.
 Notify the Operations department for Isolation.
 After obtaining necessary work permits field crew will be mobilized for
performing the site activities.
 Barricading the work area with warning tapes for safe working environment
to avoid accidents.
 Scaffolding activities will start one week prior to starting of job.
 Prefabricated spool is transported to site after completion of NDT and Final
inspection.
 Proper isolation and draining to be done before starting of activities
 Prepare cutting and welding activity work permit and get approval
from concerned department.
 Cutting of hole for 10"x3" weldolet fit-up.
 Fit-up of 10"x3" weldolet and fit-up inspection by Al Amara with Third party
inspection team.
 Root welding of weldolet and DPT inspection after that Fill up and final
welding.
 Fit-up of prefabricated flange spool (final inspection and NDT completed) with
weldolet.
 Fit-up inspection by Al Amara & Third party inspection team.
 Welding of 3" pipe to weldolet joint and final weld visual and DPT inspection
of two joints.
 100% Radiography for the welding joints to be done.
 Installation of 3" isolation valves, make sure all the flange faces has been
cleaned and inspect all the gaskets and bolt nuts before installation ,Final bolt
torqueing to be done as per the SATORP Standards.
 Final paint touch up in welding joints and housekeeping.
 Project completion documents preparation.
 Housekeeping and Demobilization.