Project: Breeza Palms Subject: Aliya 6 Units Townhouse Construction (Structural) Contractor: VAPS 3 Builders Inc
Project: Breeza Palms Subject: Aliya 6 Units Townhouse Construction (Structural) Contractor: VAPS 3 Builders Inc
Project: Breeza Palms Subject: Aliya 6 Units Townhouse Construction (Structural) Contractor: VAPS 3 Builders Inc
MANPOWER DISTRIBUTION
SCOPE OF WORKS DAYS
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
I. GROUND FLOOR (1st 3 Units)
Rebar Works : Ground Floor Walls 2 4 4
Formworks: Hauling of EFCO Metal Forms (Walls) 3 4 4 4
Formworks: Hauling of EFCO Shoring Supports (for Decking) 3 3 3 3
Formworks: Ground Floor Walls & Suspended Slabs 4 9 9 9 9
Rebarworks: Suspended Slabs 3 6 6 6
Plumbing : Rough-Ins 2 2 2
Electrical : Rough-Ins 2 3 3
BUHOS (Concrete Pouring) 1 12
Formworks : Stripping of EFCO Metal Forms ( Walls) 2 7 7
II. GROUND FLOOR (2nd 3 Units)
Rebar Works : Ground Floor Walls 2 4 4
Formworks: Hauling of EFCO Metal Forms (Walls) 3 4 4 4
Formworks: Hauling of EFCO Shoring Supports (for Decking) 3 3 3 3
Formworks: Ground Floor Walls & Suspended Slabs 4 9 9 9 9
Rebarworks: Suspended Slabs 3 6 6 6
Plumbing : Rough-Ins 2 2 2
Electrical : Rough-Ins 2 3 3
BUHOS (Concrete Pouring) 1 12
Formworks : Stripping of EFCO Metal Forms ( Walls) 2 7 7
III. SECOND FLOOR ( 1st 3 Units)
Rebar Works : Second Floor Walls 3 3 3 3
Electrical : Rough-Ins & Auxiliares 2 3 3
Plumbing : Rough-Ins, VSTR 2 2 2
Formworks: Hauling of EFCO Metal Forms (Walls) 3 7 7 7
Formworks: Seond Floor Walls 5 8 8 8 8 8
BUHOS (Concrete Pouring) 1 10
Formworks : Stripping of EFCO Metal Forms ( Walls) 2 7 7
IV. SECOND FLOOR ( 2nd 3 Units)
Rebar Works : Second Floor Walls 3 3 3 3
Electrical : Rough-Ins & Auxiliares 2 3 3
Plumbing : Rough-Ins, VSTR 2 2 2
Formworks: Hauling of EFCO Metal Forms (Walls) 3 5 5 5
Formworks: Seond Floor Walls 4 6 6 6 6
BUHOS (Concrete Pouring) 1 10
Formworks : Stripping of EFCO Metal Forms ( Walls) 3 7 7 7
TOTAL 80 20 16 22 20 23 11 27 22 27 32 15 30 18 15 8 18 7 15 19 14 11 6 17 7 7