ESTIMATED SCHEDULE FOR BIDDING
The projects listed below refer to projects with a total estimated investment
scheduled in the five-year investment plan that is expected to be developed for
implementation periods 2016 and 2017.
All these projects are emblematic for the current administration of President Juan
Carlos Varela, due to its high social impact for the country, helping to improve the
quality of life of thousands of Panamanians and to the economic development in
different areas of the country.
IMPROVING AND
EXTENSION OF VIA
BRUJAS AND BLVD.
ANDREWS (PANAMA
PACIFIC
AVE.)REHABILITATION
AND EXTENSION OF
BRUJAS AVENUE AND
ANDREWS BLVD.
(PANAMA PACIFIC
AVENUE) B/. 5,118,075.00 B/. 9,392,000.00
CONSTRUCTION OF
FIRST PHASE OF THE
NEW WASTEWATER
TREATMENT PLANT
AND REHABILITATION
OF PUMPING STATIONS B/. 1,800,000.00 B/. 5,100,000.00
CONSTRUCTION OF THE
MAIN LINE OF DRIVING
AND DRINKING WATER
AND STORAGE TANK
FOR THE TOWN CENTER
OF THE AREA B/. 3,435,402.00 B/. 3,435,402.00
REHABILITATION AND EXTENSION OF THE BRUJAS AVENUE AND ANDREWS BLVD. (PANAMA
PACIFIC AVENUE)
PROJECT TYPE
ROAD
PROJECT COST
PROJECT STRUCTURE
Project Summary
It involves the rehabilitation and expansion to four lanes of about 5 km from the
Brujas Avenue and Andrews Boulevard, to provide a high capacity access to the
Panama Pacifico Area due to the traffic increase projected by the Master
Development Plan because of all the housing and commercial projects in the area,
connecting it with Pan-American Highway, between Panama-Arraijan at the
North, and Veracruz route to the South. The project consists of 4 stages to be
developed in the next four years, starting in 2016. After, there will be a 5th stage
where it will be extended to six lanes from the entrance of the Pan-American
Highway to the entrance of the Andrews Boulevard.
PROJECT TYPE
PROJECT COST
PROJECT STUCTURE
Construction Bidding.
Project Summary
Construction of the first phase of expansion of the Wastewater Treatment Plant
for the management of wastewater from the Panama Pacific Area. It includes the
suitability of the site, civil works, improvement to existing pumping stations,
equipment and piping. This will timely meet the estimated demands of the
proposed development of the Master Development Plan. The capacity of the
existing wastewater treatment plant of Panama Pacifico Special Economic Area is
1.5 MOG; by building a new treatment plant of the "Intermittent SBR reactors"
type and improving the existing pumping stations; it is expected to attend on time
the estimated and designed demand according to the Master Development Plan,
expanding its capacity to about 5 MDG management.
Scheduled Dates:
Projected Bidding Date: March, 2017.
PROJECT TYPE
PROJECT COST
PROJECT STRUCTURE
Construction Bidding.
Project Summary
Expansion of the Drinking water System for the Panama Pacific area, in order to
timely attend the estimated demand of the Master Development Plan. The current
system has a water demand of approximately 2.8 MOG per day. It is estimated that
at completion of the project the demand will increase as the development of the
Area grows. As well it has to provide an alternative to guarantee the water supply
to the area of Veracruz, the coast of Palo Seco, Playa Bonita Resort and Farfan
Residential, which are connected to the system crossing through the Special
Economic Area. Therefore, it is necessary to ensure thecontinuous supply and the
quality of water required for the development of the Panama Pacific Area.
Scheduled Dates:
Projected Bidding Date: March, 2016.