Construction Management of EVH & UVH Transmission Lines A Practical Guide
Construction Management of EVH & UVH Transmission Lines A Practical Guide
Construction Management of EVH & UVH Transmission Lines A Practical Guide
ISSN No:-2456-2165
Construction Management of
EVH & UVH Transmission Lines
A Practical Guide
Biswanath Sahu
B.Sc. Engg. PGDM (HRM), PGDM ( E&E), Gmpe(Iim-I)
Country:- India
Abstract:- Generation projects are generally located in Keywords:- The key words in this paper are Right of Way
areas nearer to availability of inputs required for power (ROW); Crop, Tree and land compensation; clearances;
generation such as water, coal, approach roads and Government stipulations; commercial issues, Farmer
having rail transport facilities. The load centers are at issues; soil conditions; Forest, Highways, Rly ways
different locations depending its own convenience load approvals etc.
requirement. Hence there is necessity of transmission of
bulk power from generation sites to load or consumer I. INTRODUCTION
points.
Power supply has become essential for day to day life
Hence the utility of power transmission through sustenance in a society.
EHV/UHV transmission lines. Further for transmission Global climatic developments demand supply of
of bulk power from one region of country to another reliable and quality power at minimum cost having
region also warrants establishment of Transmission minimum impact on environment.
lines. The technical as well as social and commercial It is s a tough challenge to maintain balance among
criteria are very important while construction and mutually opposing issues such as reliability in bulk
erection of EHV and UHV transmission lines. These power transmission, maintenance of environmental
issues are of public as well as organization importance sustainability with economic efficiency.
and hence efforts have been made in this presentation to The above tricky Situations can be tackled by focusing
elaborate in detail. our action in the following areas.
TOWERSPOTTING&TOWERSCHEDULE
Fig 1
Fig 3
Fig 2
CLEARANCE DETAILS
• As per I E Rule -77 the Ground clearances are:
• 132 KV-6.10 mtrs,
• 220 KV-7.00mtrs
• 400KV-8.84mtrs
• 800KV-12.40 mtrs
OTHERCLERANCES
• Minimum Clearance between Conductor & Tree
• 400KV-5.5mtr
• ,500KV-7.4mtr,
• 765 KV-9.0mtr
• 800KV-10.6 mtrs
• 1200KV-13.0mtr
• Clearance Between Lowest cross arm and Traction
Mast:
• 400KV-9.71mtrs
• 500KV-11.45mtrs
• 800KV-16.67 mtrs
OTHER CRITERIAS
• To meet ground clearance tower with extension or Fig 5
reduced span whichever is economical is to be used.
• Span should be as close to as design span. • Stub setting is done with stub template.
• Power line crossings double suspension and tension • Stub and other accessories required along with
Insulators used. concreting materials are to be made available at site.
• River crossings:
• Non-Navigated- clearance 3mtrs from High Flood
Level.
• Navigated-approval from authority is required.
• Road crossings: NH & Major SH- span 250mtrs(double
tension & suspension insulators for clearance & ODC
consignment.
SPAN &SAG
• Normal span-Design span
• Wind Span-On either side of a tower 50% spans
• Weight span- Tower either side lowest conductor point
distance.
• Max Sag =(l square d q)/8f where l=length of
conductor=W/A (weight/mtr of conductor, A-area of cross
section) q=Loading factor=01 for still wind. F= Stress
on conductor cross section.
• Sag at basic span/ sag at any span= Basic Span
square/Span Square
• From profile Location wise tower schedule that is no of
different towers and extensions are prepared. Fig 6
PAYMENT OF COMPENSATION
• After route is finalised ownership of land and crop and
trees affected or going to be affected during foundation,
tower erection & stringing need to be got certified by
revenue officials (Patwari , Tahsildar)
• Notices need to be issued to the owners that they are to
be suitably compensated as assessed, certified and
approved by revenuedept.
• Statement for Damaged crops & trees to be submitted to
revenue/Horticulture/forest dept. for finalisation of
amount.
• For crop &tree as many times these are damaged to be
compensated.
• For land for tower & overhead conductor as decided by Fig 7
collector to be compensated.
• Foundations are classified as: Methods of Tower erection:
• For Normal soil-Dry, Wet, Partially submersed, Fully • 1 Built up method or piece method by Deric & Gi pole(
submerged. widely used)
• This is the most difficult part of Execution in • Section wise by crane.
Transmission line works. • Ground assembly and total tower lifting by crane-Rarely
used, for small height towers feasible.
SOIL CLASSIFICATION • It is a very specialized and skilled job can be done by
• SOIL at tower location is classified as: experienced gangs.
• Normal soil-(If the soil is no other types given below)
• Black Cotton
• Fissured Rock
• Hard Rock
• Sandy soil
FOUNDATION CLASSIFICATION
• Dry- soil is normal, water is not met up to bottom of pit
at 3.0 mtr in worst season.
• Wet-Soil is normal, water met on surface like paddy field
after that no water up to 1.5 mtr from GL.
• PS-Soil normal, water met with in 0.75 to 1.5 mtr from
GL
• FS-Soil normal, water met with in GL to 0.75 mtr
• WBC-soil is Black cotton (at least 1.0 mtr from bottom
of pit)
Fig 8
• FR-If soil is Fissured rock, marram (at least 1.0 mtr
from bottom of foundation. If water within 1.5 mtr from
• Proper supervision to ensure safety of people on job is
GL special foundation.
essential.
• HR- Soil HR at least 1.0mtr from bottom. Sandy soil-
• Tack welding at least up to bottom cross arm & applying
special.
cold galvanized paint is required.
Fig 9
Fig 10
• Up to 220 KV Tractors used for pulleying, 400Kv- • Tension is calculated on equivalent span=Sqroot of(
Tensioner& pullers. sigmaL3/sigmaL)
• Rough sagging done first with winch,4way ( L is individual spans) Tension is given from Sag
pulley/Equalizing pulley& dynamometer. Tension chart and sag is checked in last span.
Fig 12