BILL OF QUANTITY
SUMMARY
No Code Cost Component Unit Coefficient Unit Prices ($) Amount ($)
A LABOR
1 Labor Day 0.5000 $ 5.00 $ 2.50
2 Foreman Day 0.0500 $ 12.00 $ 0.60
Sub total $ 3.10
B MATERIAL
$ -
Sub total $ -
C EQUIPMENT
$ -
Sub total $ -
D Sum of Labor, Material & Equipment (A + B + C) $ 3.10
No Code Cost Component Unit Coefficient Unit Prices ($) Amount ($)
A LABOR
1 Labor Oh 0.3023 $ 5.00 $ 1.51
2 Foreman Oh 0.0127 $ 12.00 $ 0.15
Sub total $ 1.66
B MATERIAL
1 Filled sand M³ 1.2000 $ 15.00 $ 18.00
Sub total $ 18.00
C EQUIPMENT
$ -
Sub total $ -
D Sum of Labor, Material & Equipment (A + B + C) $ 19.66
No Code Cost Component Unit Coefficient Unit Prices ($) Amount ($)
A LABOR
1 Unskill labor Day 0.3210 $ 5.00 $ 1.61
2 Stonemason Day 0.4370 $ 8.00 $ 3.50
3 Skilled head Day 0.2200 $ 10.00 $ 2.20
4 Foreman Day 0.0175 $ 12.00 $ 0.21
Sub total $ 7.51
B MATERIAL
1 Pavemnt stone Bh 20.6000 $ 1.00 $ 20.60
2 Portland Cement Kg 8.3200 $ 0.15 $ 1.25
3 Sand M³ 0.0380 $ 25.00 $ 0.95
Sub total $ 22.80
C EQUIPMENT
$ -
Sub total $ -
D Sum of Labor, Material & Equipment (A + B + C) $ 30.31
No Code Cost Component Unit Coefficient Unit Prices ($) Amount ($)
A LABOR
1 Unskill labor Day 0.3518 $ 5.00 $ 1.76
2 Stonemason Day 0.1131 $ 8.00 $ 0.90
3 Skilled head Day 0.0193 $ 10.00 $ 0.19
4 Foreman Day 0.0288 $ 12.00 $ 0.35
Sub total $ 3.20
B MATERIAL
1 Concrete block Bh 12.5000 $ 1.00 $ 12.50
2 Portland cement Kg 12.0000 $ 0.15 $ 1.80
3 Sand M³ 0.0380 $ 25.00 $ 0.95
Sub total $ 15.25
C EQUIPMENT
$ -
Sub total $ -
D Sum of Labor, Material & Equipment (A + B + C) $ 18.45
Unit Prices Analysis
TIMOR LESTE STANDAR METHOD OF MEASUREMENT (TL - SMM)
Masonry Works
Project Tittle : NEW CONSTRUCTION OFFICE OF MSS Works item no. 6.00
Location : Suai, Covalima District Unit M²
No Code Cost Component Unit Coefficient Unit Prices ($) Amount ($)
A LABOR
1 Unskill labor Day 0.2559 $ 5.00 $ 1.28
2 Stonemason Day 0.1500 $ 8.00 $ 1.20
3 Skilled head Day 0.0167 $ 10.00 $ 0.17
4 Foreman Day 0.0167 $ 12.00 $ 0.20
Sub total $ 2.85
B MATERIAL
1 Portland cement Kg 6.2400 $ 0.15 $ 0.94
2 Sand M³ 0.0214 $ 25.00 $ 0.54
Sub total $ 1.47
C EQUIPMENT
$ -
Sub total $ -
D Sum of Labor, Material & Equipment (A + B + C) $ 4.32
No Code Cost Component Unit Coefficient Unit Prices ($) Amount ($)
A LABOR
1 Unskills labor Day 1.6500 $ 5.00 $ 8.25
2 Stonemason Day 0.2890 $ 8.00 $ 2.31
3 Skilled head Day 0.0290 $ 10.00 $ 0.29
4 Foerman Day 0.0200 $ 12.00 $ 0.24
Sub total $ 11.09
B MATERIAL
1 Portland cement Kg 254.0000 $ 0.15 $ 38.10
2 Gravel M³ 0.8197 $ 100.00 $ 81.97
3 Concrete sand M³ 0.6200 $ 30.00 $ 18.60
Sub total $ 138.67
C EQUIPMENT
$ -
Sub total $ -
D Sum of Labor, Material & Equipment (A + B + C) $ 149.76
No Code Cost Component Unit Coefficient Unit Prices ($) Amount ($)
A LABOR
1 Unskill labor Day 1.6500 $ 5.00 $ 8.25
2 Stonemason Day 0.2675 $ 8.00 $ 2.14
3 Skilled head Day 0.0267 $ 10.00 $ 0.27
4 Foreman Day 0.0200 $ 12.00 $ 0.24
Sub total $ 10.90
B MATERIAL
1 Portland cement Kg 323.0000 $ 0.15 $ 48.45
2 Gravel M³ 0.7800 $ 100.00 $ 78.00
3 Concrete sand M³ 0.5200 $ 30.00 $ 15.60
Sub total $ 142.05
C EQEUIPMENT
$ -
Sub total $ -
D Sum of Labor, Material & Equipment (A + B + C) $ 152.95
No Code Cost Component Unit Coefficient Unit Prices ($) Amount ($)
A LABOR
1 Unskill labor Day 0.0949 $ 5.00 $ 0.47
2 Blacksmith Day 0.0757 $ 8.00 $ 0.61
3 Skilled head Day 0.0109 $ 10.00 $ 0.11
4 Foreman Day 0.0223 $ 12.00 $ 0.27
Sub total $ 1.46
B MATERIAL
1 Steel reinforeced Kg 1.0500 $ 0.25 $ 0.26
2 Concrete wire Kg 0.1500 $ 2.00 $ 0.30
Sub total $ 0.56
C EQUIPMENT
$ -
Sub total $ -
D Sum of Labor, Material & Equipment (A + B + C) $ 2.02
No Code Cost Component Unit Coefficient Unit Prices ($) Amount ($)
A LABOR
1 Unskill labor Day 0.6600 $ 5.00 $ 3.30
2 Carpenter Day 0.3300 $ 8.00 $ 2.64
3 Skilled head Day 0.0330 $ 10.00 $ 0.33
4 Foreman Day 0.0330 $ 12.00 $ 0.40
Sub total $ 6.67
B MATERIAL
1 Wooden class III M³ 0.0400 $ 325.00 $ 13.00
2 Nail 5' - 12' Kg 0.4000 $ 1.75 $ 0.70
3 Formwork Oil Ltr 0.0536 $ 2.50 $ 0.13
4 Wooden beams Class II M³ 0.0360 $ 350.00 $ 12.60
5 9 mm thick plywood Sheet 0.3500 $ 15.00 $ 5.25
6 Dolken wood 8" - 12" / 4 m Piece 2.0000 $ 7.00 $ 14.00
Sub total $ 45.68
C EQUIPMENT
$ -
Sub total $ -
D Sum of Labor, Material & Equipment (A + B + C) $ 52.35
Unit Prices Analysis
TIMOR LESTE STANDAR METHOD OF MEASUREMENT (TL - SMM)
Finishing Works
Project Tittle : NEW CONSTRUCTION OFFICE OF MSS Works item no. 11.00
Location : Suai, Covalima District Unit M²
No Code Cost Component Unit Coefficient Unit Prices ($) Amount ($)
A LABOR
1 Unskill labor Day 0.1753 $ 5.00 $ 0.88
2 Stonemason Day 0.1057 $ 8.00 $ 0.85
3 Skilled head Day 0.0146 $ 10.00 $ 0.15
4 Foreman Day 0.0146 $ 12.00 $ 0.18
Sub total $ 2.04
B MATERIAL
1 Portland cement Kg 3.4988 $ 0.21 $ 0.74
Sub total $ 0.74
C EQUIPMENT
$ -
Sub total $ -
D Sum of Labor, Material & Equipment (A + B + C) $ 2.79
No Code Cost Component Unit Coefficient Unit Prices ($) Amount ($)
A LABOR
1 Unskill labor Day 0.7000 $ 5.00 $ 3.50
2 Stonemason Day 0.3500 $ 8.00 $ 2.80
3 Skilled head Day 0.0350 $ 10.00 $ 0.35
4 Foreman Day 0.0350 $ 12.00 $ 0.42
Sub total $ 7.07
B MATERIAL
1 Ceramics Piece 3.0000 $ 9.00 $ 27.00
2 Portland cement Kg 8.0000 $ 0.21 $ 1.70
3 Sand M³ 0.0450 $ 30.00 $ 1.35
4 Cement color Kg 0.9321 $ 0.21 $ 0.20
Sub total $ 30.25
C EQUIPMENT
$ -
Sub total $ -
D Sum of Labor, Material & Equipment (A + B + C) $ 37.32
No Code Cost Component Unit Coefficient Unit Prices ($) Amount ($)
A LABOR
1 Unskill labor Day 0.1000 $ 5.00 $ 0.50
2 Carpenter Day 0.1000 $ 8.00 $ 0.80
3 Skilled head Day 0.0100 $ 10.00 $ 0.10
4 Foreman Day 0.0050 $ 12.00 $ 0.06
Sub total $ 1.46
B MATERIAL
1 Plywood Sheet 0.3750 $ 15.00 $ 5.63
2 Nails 1/2'' - 1'' Kg 0.0300 $ 1.75 $ 0.05
Sub total $ 5.68
C EQUIPMENT
$ -
Sub total $ -
D Sum of Labor, Material & Equipment (A + B + C) $ 7.14
No Code Cost Component Unit Coefficient Unit Prices ($) Amount ($)
A LABOR
1 Unskill labor Day 0.0500 $ 5.00 $ 0.25
2 Carpenter Day 0.0500 $ 8.00 $ 0.40
3 Skilled head Day 0.0050 $ 10.00 $ 0.05
4 Foreman Day 0.0030 $ 12.00 $ 0.04
Sub total $ 0.74
B MATERIAL
1 Wood trim profile M' 1.0500 $ 2.50 $ 2.63
2 Nail trim Kg 0.0329 $ 1.75 $ 0.06
Sub total $ 2.68
C EQUIPMENT
$ -
Sub total $ -
D Sum of Labor, Material & Equipment (A + B + C) $ 3.42
LABOUR
1 Foreman day $ 12.00
2 Chief mason day $ 10.00
3 Chief carpenter day $ 10.00
4 Chief blacksmith day $ 10.00
5 Chief painter day $ 10.00
6 Chief electrician day $ 10.00
7 Worker pipe day $ 8.00
8 mason day $ 8.00
9 carpenter day $ 8.00
10 blacksmith day $ 8.00
11 painter day $ 8.00
13 Unskill labour day $ 5.00
MATERIALS
1 Soil fill m3 $ 25.00
2 Sand fill m3 $ 25.00
3 Sand tide m3 $ 25.00
4 Sand for concrete m3 $ 10.00
5 Stone 15/20 cm m3 $ 10.00
6 Gravel break machine 2/3 cm m3 $ 50.00
7 River stone for disfution m3 $ 10.00
8 Portland Cement 40 kg kg $ 0.21
9 Cement colour for ceramic line (nat) kg $ 0.15
10 Concrete block 40x10x20 grade A2 pc $ 1.00
11 Hollow block 40x15x20 grade 1 pc $ 1.00
12 Beendrat (kawat ikat) kg $ 1.00
14 Round bar Ø 16mm kg $ 2.00
15 Round bar Ø D 12mm kg $ 1.75
16 Round bar Ø 10mm kg $ 1.50
17 Round bar Ø 8mm kg $ 1.25
19 Steel plate 3 mm kg $ 2.00
20 Steel plate 8 mm kg $ 5.00
26 Plate Nipper Rufter pcs $ 3.00
28 Nail kg $ 5.00
30 Steel Strip kg $ 0.25
33 Board 2/20 m' $ 4.50
34 Timber/wooden balk class III m3 $ 275.00
35 Scaffolding wood m3 $ 300.00
41 Wooden cornice profile, 3/4 cm m' $ 2.50
43 Ceramik 60 x 60 cm Pcs $ 1.75
48 Roof tile pc $ -
50 Glass 5 mm (ryban) m2 $ 15.00
51 Painting wall ex Jotun kg $ 12.50
52 Painting wood kg $ 2.50
53 Painting steel kg $ 2.50
54 Alkaly sealer wall (Plamir) kg $ 5.00
55 Alkaly sealer wood (Plamir) kg $ 5.00
56 Priming wood (Meni) kg $ 1.50
57 Priming steel (Meni) kg $ 1.50
58 Wooden varnish ltr $ 5.50
59 Oil paint (thiner) A lt $ 2.60
60 Paper rub sheet $ 0.50
61 Rollbrush pc $ 3.00
69 Hand locking door panyl (Good quality) unt $ 35.00
70 Hand locking door PVC (Good quality) unt $ 7.00
71 Hand locking door steel (Good quality) pc $ 30.00
72 Hinges door (Good quality) pc $ 5.00
73 Hinges doors steel (Good quality) pc $ 15.00
74 Hinges window & Boven (Good quality) pc $ 3.00
75 Grendel door panyl (Good quality) pc $ 3.00
76 Grendel window & bovenlight (Good quality pc $ 2.00
77 Right wind window & bovenlight (Good quali pc $ 4.00
78 Sead closed ex TOTO unt $ 210.00
80 Wastafel ex TOTO unt $ 50.00
81 Zinc basin for kitchen unt $ 25.00
82 Faucet wall Ø 1/2" pc $ 10.00
83 Pipe drain Ø 1/2" pc $ 2.00
84 Floor drain (Good quality) pc $ 6.50
88 Pipe PVC Ø 1" merk MASPION m' $ 1.00
90 Pipe PVC Ø 2" merk MASPION m' $ 1.88
92 Pipe PVC Ø 3" merk MASPION m' $ 2.50
93 Galvanis pipe Ø 1/2" m' $ 4.25
93 Galvanis pipe Ø 3/4" m' $ 5.25
94 Elbow PVC Ø 1/2" merk MASPION pc $ 0.35
96 Elbow PVC Ø 2" merk MASPION pc $ 1.25
97 Elbow PVC Ø 4" merk MASPION pc $ 2.00
98 Tee PVC Ø 1/2" merk MASPION pc $ 0.35
99 Tee PVC Ø 3/4" merk MASPION pc $ 0.50
100 Tee PVC Ø 2" merk MASPION pc $ 1.25
102 Embodous pc $ 0.10
103 PVC door for toilet merk Trilliun pc $ 60.00
104 Reducing socket PVC Ø 3/4"→1/2" merk M pc $ 1.00
105 Socket PVC Ø 3/4" merk MASPION pc $ 1.00
Faucet Socket PVC with metal insert Ø 3/4"
106 MASPION pc $ 1.00
110 Cable NYY 3 X 2.5mm merk SUPREME m' $ 1.10
112 Flourescent 2 x 38 wt ex Philip (completed) unt $ 30.00
113 Essential lamp 20 wt ex Philip (completed) unt $ 10.00
114 Single switch merk BROCCO pc $ 2.25
115 Double switch merk BROCCO pc $ 2.50
116 Power outlet merk BROCCO pc $ 2.50
115 Ceiling fitting pc $ 2.00
116 Garden Fitting pc $ 6.00
117 Ceilling fan (good quality) unt $ 30.00
118 Aluminium jamb m' $ 15.00
119 Aluminium windows frame m' $ 15.00
120 Aluminium doors frame m' $ 15.00
121 sealan rubber m' $ 2.50
122 Sealan glue kg $ 3.00
124 Paving stone thc 6 cm pc $ 0.80
125 Kerbstone m' $ 6.00
PERHITUNGAN VOLUME PEKERJAAN
NO URAIAN PEKERJAAN
II PEKERJAAN PASANGAN
A PONDASI BATU BELAH/GUNUNG
1 Pasangan Pondasi
Panjang keliling pondasi
Lebar Atas
Lebar Bawah
Tinggi
Volume
B PASANGAN BATAKO
a Pasangan Batako
Luas total tembok
Luas pintu+Jendela+Ventilasi
jadi tot. luas pas. Tembok = Luas tot.tembok dikurangai luas
Pintu+jdnl+ven.
C PLESTERAN
Jumlah
D ACIAN
Jumlah
E LANTAI KERAMIK
a Ruangan Dalam 60 x 60 cm
Panjang
Lebar
b Koridor Depan 60 x 60 cm
Panjang
Lebar
Jadi total keramik 60x60 cm
Keliling
b
h
Jumlah
b Sloof 15/25
Keliling
b
h
Jumlah
2 Kolom
a Kolom 25/25 cm
b
h
t
Jumlah kolom
Total volume kolom
b Kolom 15/15 cm
b
h
t
Jumlah
Total volume kolom
c Kolom 15/25 cm
b
h
t
Jumlah
Total volume kolom
d Kolom(15/15) cm
b
h
t
Jumlah
3 Ring balok
a Ring Balok 25/25
Keliling
b
h
Jumlah
c Beam 15/15
Keliling
b
h
Jumlah
d Canopy 15/15
Keliling
b
h
Jumlah
e Reinforced chair
Keliling
b
h
Jumlah
4 Pekerjaan Rabat beton untuk Lantai
a Rabat Beton
Panjang
Lebar
Tebal
Jumlah
IV PEKERJAAN ATAP
A Rangka kuda - kuda Canal C
Panjang gording
Jumlah
C Penutup atap Zinclorbond
V PEKERJAAN PLAFOND
1 Rangka Plafond gypsum 9 mm
Panjang
Lebar
Jumlah
2 Penutup Plafond
List plafond
Panjang
VI PEKERJAAN PENGECETAN
1 Pengecetan Dinding
panjang Dinding bagian dalam
tinggi
Jumlah
2 Pengecetan Ceilling
Panjang
Lebar
Jumlah
3 Pengecetan foundation
Panjang
Lebar
Jumlah
EKERJAAN
PERHITUNGAN
TOTAL Volume SATUAN
Volume Satuan
80.00 m'
26.00 m
14.00 m
100.82 m³
141.00 m
1.10 m
0.65 m
14.10 m³
141.00 m
1.00 m
0.10 m
72.00 m³
24.00 m
12.00 m
0.25 m
- m³
22.03 m³
22.03 m
m
m
88.13 m³
141.00 m
0.35 m
0.90 m
1.00 m
88.13
365.15
439.06 m
73.92 m
365.15 m'
365.15 730.30 m²
2.00 Sisi
730.30 m²
2.00 Sisi
205 m²
20.50 m
10.00 m
48 m²
24.00 m
2.00 m
253 m2
35.00 m²
10.00 m
3.50 m
35.00 Bh
5.00 m
1.50 m
4.00 Sisi
30.00 m²
2.00 Bh 60
2.00 m
1.75 m
4.00 Sisi
14.00 m²
6.00 Bh 84
144.00 m²
6.00 m³
96.00 m
0.25 m
0.25 m
6.00
1.13 m³
30.00 m
0.15 m
0.25 m
1.13
11.59 m³
0.25 m
0.25 m
5.30 m
35.00 bh
11.59 bh
0.60 m³
0.15 m
0.15 m
5.30 m
5.00 bh
0.60 bh
1.19 m³
0.15 m
0.25 m
5.30 m
6.00 bh
1.19
1.35 m³
0.15 m
0.15 m
5.00 m
12.00 bh
6.00 m³
96.00 m
0.25 m
0.25 m
6.00
1.13 m³
30.00 m
0.15 m
0.25 m
1.13
1.19 m³
52.70 m
0.15 m
0.15 m
1.19
8.40 m 0.25 m3
0.10 m
0.30 m
0.25 m3
25.20 0.91 m3
0.12
0.30
0.91
34.56 m³
24.00 m
12.00 m
0.12 m
34.56 bh
1.96 m³
1.96 m2
1.00 m
1.96 m3
3.44 m³
11.25 m
1.53 m
0.20 m
3.44 m3
5.40
8.50 m 221.00 m2
26.00 m
221.00 m2
6.52 m 169.52 m2
26.00 m
169.52 m2
390.52 m2
26.00 m 364.00 m2
14.00 m
364.00 m2
214.00 m²
214.00 m
638.73 m2
152.08 m2
4.20
638.73
56.08 235.53 m2
4.20
235.53
24.00 m 288.00 m2
12.00 m
288.00 m2
72.00 m 57.60 m2
0.80 m
57.60 m2