Nothing Special   »   [go: up one dir, main page]

BoQ Covalima Tanki

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 36

MINISTÉRIO

DIRRECÇÃO NACIONAL DE GESTÃO DEZASTRE NATURAIS

BILL OF QUANTITY

PROJECT OWNER : MINISTRY SOLIDARITY SOCIAL


PROJECT TITTLE : NEW CONSTRUCTION OF EVACUATION CENTRE
LOCATION : SUAI VILLA, COVALIMA DISTRICT - TIMOR LESTE

NO DISCRIPTIONS WORKS UNIT QUANTITY UNIT PRICE AMOUNT


(USD) (USD)
1 2 3 4 5 6
I Pekerjaan Persiapan
1 Pembersihan Lokasi Ls 1.00 $ 500.00 $ 500.00
2 Mobilisasi Ls 1.00 $ 1,000.00 $ 1,000.00
3 Direksi dan Kitt Ls 1.00 $ 500.00 $ 500.00
4 Dokumentasi Ls 1.00 $ 500.00 $ 500.00
5 Papan Nama LS 1.00 $ 250.00 $ 250.00
Sub total $ 2,750.00
II Pekerjaan catcement
1 Pekerjaan Galian Urugan Pasir
1.1 Pekerjaan tanah Fondasi cu.m 7.30 $ 3.75 $ 27.38
1.2 Urugan Pasir cu.m 1.20 $ 16.50 $ 19.80
Sub total $ 47.18
2 Pasangan Batu
2.1 Pasangan Batu Kali (1:4) cu.m 10.30 $ 90.15 $ 928.55
Sub total $ 928.55
3 Pekerjaan Lantai
3.1 Urugan Pasir dibawah lantai cu.m 18.50 $ 16.50 $ 305.25
3.2 Rabat Beton Untuk Lantai (1:2:3) cu.m 11.30 $ 510.61 $ 5,769.89
3.3 Pasangan Blok keliling Dengan Tinggi 20 cm m2 7.20 $ 18.25 $ 131.40
3.4 Plester (1:4) m2 14.00 $ 5.25 $ 73.50
Sub total $ 6,280.04
III Pekerjaan Bak Penampung $ -
1 Galian Tanah dan Urugan Pasir
1.1 Galian cu.m 65.20 $ 3.75 $ 244.50
1.2 Urugan Pasir dibawah dinding plat cu.m 0.71 $ 16.50 $ 11.72
Sub total $ 256.22
2 Pekerjaan Beton
2.1 Plat Beton Dibawah Dinding/Plain Concrete (1:2:3) cu.m 0.54 $ 461.72 $ 249.33
2.2 Dinding Beton Bertulang/Reinforce Concrete (1:2:3) cu.m 14.40 $ 461.72 $ 6,648.77
2.3 Lantai Rabat Beton/Plain Concrete (1:2:3) cu.m 1.90 $ 461.72 $ 877.27
2.4 Plat Atas (Penutup)/Reinforce Concrete (1:2:3) cu.m 2.10 $ 461.72 $ 969.61
Sub total $ 8,744.98
3 Instalasi PVC Pipe
3.1 Pipa PVC 2'' Unit 1.00 $ 20.00 $ 20.00
3.2 L BOW PVC 2'' Unit 6.00 $ 15.00 $ 90.00
Sub total $ 110.00
4 FINISHING
4.1 Finishing Ls 1.00 $ 500.88 $ 500.88
Sub total $ 500.88
VI Total A $ 19,617.83
1 Tax Fee 2% From Total A = B $ 392.36
2 Profit Company 10% From Total A = C $ 1,961.78
GRAND TOTAL $ 21,971.97

Prepared by: Approved by:

Shilton C. C. Gonçalves, ST Norman


PARATRIZEL ENGINEER Director PARATRIZEL
MINISTÉRIO DA SOLIDARIEDADE SOCIAL
DIRRECÇÃO NACIONAL DE GESTÃO DEZASTRE NATURAIS

SUMMARY

PROJECT OWNER : MINISTRY SOLIDARITY SOCIAL


PROJECT TITTLE : NEW CONSTRUCTION OF EVACUATION CENTRE
LOCATION : SUAI VILLA, COVALIMA DISTRICT - TIMOR LESTE

NO DESCRIPTIONS OF WORKS AMOUNT (USD)


1 Pekerjaan Persiapan $ 2,750.00
2 Pekerjaan catcement $ 47.18
3 Pasangan Batu $ 6,280.04
4 Pekerjaan Bak Penampung #NAME?
5 Instalasi PVC Pipe #NAME?
6 FINISHING #NAME?
7 Total A $ -
8 0 $ -
9 0 $ -
10 0 $ -
A TOTAL COST IN USD$ #NAME?
B CONTRACTOR FEE (10%) #NAME?
C TAX 4% #NAME?
D GRAND TOTAL COST (A + B + C) #NAME?

Prepared by: Checked by: Approved by:

Laurindo Barros Alves Zitu Fernandes Alvaro Silva de Jesus


Technic MSS BSRP - National Project Manager Director DNGD
UNIT PRICES ANALYSIS
Unit Prices Analysis
TIMOR LESTE STANDARD METHOD OF MEASUREMENT (TL - SMM)
EARTH WORKS
Project Tittle : NEW CONSTRUCTION Works item no. 1.00
Location : Suai, Covalima District Unit M³

Works Item : 1 M³ Soil Compaction (per 20 cm)

No Code Cost Component Unit Coefficient Unit Prices ($) Amount ($)
A LABOR
1 Labor Day 0.5000 $ 5.00 $ 2.50
2 Foreman Day 0.0500 $ 12.00 $ 0.60
Sub total $ 3.10
B MATERIAL
$ -
Sub total $ -
C EQUIPMENT
$ -
Sub total $ -
D Sum of Labor, Material & Equipment (A + B + C) $ 3.10

Unit Prices Analysis


TIMOR LESTE STANDAR METHOD OF MEASUREMENT (TL - SMM)
EARTH WORKS
Project Tittle : NEW CONSTRUCTION Works item no. 2.00
Location : Suai, Covalima District Unit M³

Works Item : 1 M³ Sand Filling

No Code Cost Component Unit Coefficient Unit Prices ($) Amount ($)
A LABOR
1 Labor Oh 0.3023 $ 5.00 $ 1.51
2 Foreman Oh 0.0127 $ 12.00 $ 0.15
Sub total $ 1.66
B MATERIAL
1 Filled sand M³ 1.2000 $ 15.00 $ 18.00
Sub total $ 18.00
C EQUIPMENT
$ -
Sub total $ -
D Sum of Labor, Material & Equipment (A + B + C) $ 19.66

Unit Prices Analysis


TIMOR LESTE STANDAR METHOD OF MEASUREMENT (TL - SMM)
EARTH WORKS
Project Tittle : NEW CONSTRUCTION OFFICE OF MSS Works item no. 3.00
Location : Suai, Covalima District Unit M³
1 M³ Construction of Stone Masonry Foundation (1 Pc :
Works Item :
4 sand)
No Code Cost Component Unit Coefficient Unit Prices ($) Amount ($)
A LABOR
1 Unskill labor Day 1.8313 $ 5.00 $ 9.16
2 Stonemason Day 0.8404 $ 8.00 $ 6.72
3 Skilled head Day 0.0991 $ 10.00 $ 0.99
4 Foreman Day 0.0750 $ 12.00 $ 0.90
Sub total $ 17.77
B MATERIAL
1 Stone masonry 15/20 cm M³ 1.2000 $ 25.00 $ 30.00
2 Portland Cement Kg 163.0000 $ 0.15 $ 24.45
3 Sand M³ 0.5348 $ 25.00 $ 13.37
Sub total $ 67.82
C EQUIPMENT
$ -
Sub total $ -
D Sum of Labor, Material & Equipment (A + B + C) $ 85.59

Unit Prices Analysis


TIMOR LESTE STANDAR METHOD OF MEASUREMENT (TL - SMM)
EARTH WORKS
Project Tittle : NEW CONSTRUCTION OFFICE OF MSS Works item no. 4.00
Location : Suai, Covalima District Unit M²

Works Item : 1 M² Pavement works 25x20x6 cm

No Code Cost Component Unit Coefficient Unit Prices ($) Amount ($)
A LABOR
1 Unskill labor Day 0.3210 $ 5.00 $ 1.61
2 Stonemason Day 0.4370 $ 8.00 $ 3.50
3 Skilled head Day 0.2200 $ 10.00 $ 2.20
4 Foreman Day 0.0175 $ 12.00 $ 0.21
Sub total $ 7.51
B MATERIAL
1 Pavemnt stone Bh 20.6000 $ 1.00 $ 20.60
2 Portland Cement Kg 8.3200 $ 0.15 $ 1.25
3 Sand M³ 0.0380 $ 25.00 $ 0.95
Sub total $ 22.80
C EQUIPMENT
$ -
Sub total $ -
D Sum of Labor, Material & Equipment (A + B + C) $ 30.31

Unit Prices Analysis


TIMOR LESTE STANDAR METHOD OF MEASUREMENT (TL - SMM)
Masonry Works
Project Tittle : NEW CONSTRUCTION OFFICE OF MSS Works item no. 5.00
Location : Suai, Covalima District Unit M²

Works Item : 1 M² Concrete block 40x20x10 cm, (1Pc : 4sand)

No Code Cost Component Unit Coefficient Unit Prices ($) Amount ($)
A LABOR
1 Unskill labor Day 0.3518 $ 5.00 $ 1.76
2 Stonemason Day 0.1131 $ 8.00 $ 0.90
3 Skilled head Day 0.0193 $ 10.00 $ 0.19
4 Foreman Day 0.0288 $ 12.00 $ 0.35
Sub total $ 3.20
B MATERIAL
1 Concrete block Bh 12.5000 $ 1.00 $ 12.50
2 Portland cement Kg 12.0000 $ 0.15 $ 1.80
3 Sand M³ 0.0380 $ 25.00 $ 0.95
Sub total $ 15.25
C EQUIPMENT
$ -
Sub total $ -
D Sum of Labor, Material & Equipment (A + B + C) $ 18.45
Unit Prices Analysis
TIMOR LESTE STANDAR METHOD OF MEASUREMENT (TL - SMM)
Masonry Works
Project Tittle : NEW CONSTRUCTION OFFICE OF MSS Works item no. 6.00
Location : Suai, Covalima District Unit M²

Works Item : 1 M² Plestering 1Pc : 4 sans, 15 mm thick

No Code Cost Component Unit Coefficient Unit Prices ($) Amount ($)
A LABOR
1 Unskill labor Day 0.2559 $ 5.00 $ 1.28
2 Stonemason Day 0.1500 $ 8.00 $ 1.20
3 Skilled head Day 0.0167 $ 10.00 $ 0.17
4 Foreman Day 0.0167 $ 12.00 $ 0.20
Sub total $ 2.85
B MATERIAL
1 Portland cement Kg 6.2400 $ 0.15 $ 0.94
2 Sand M³ 0.0214 $ 25.00 $ 0.54
Sub total $ 1.47
C EQUIPMENT
$ -
Sub total $ -
D Sum of Labor, Material & Equipment (A + B + C) $ 4.32

Unit Prices Analysis


TIMOR LESTE STANDAR METHOD OF MEASUREMENT (TL - SMM)
Concrete Works
Project Tittle : NEW CONSTRUCTION OFFICE OF MSS Works item no. 7.00
Location : Suai, Covalima District Unit M³

Works Item : 1 M³ Concrete f*c = 7.4 MPa (K 100)

No Code Cost Component Unit Coefficient Unit Prices ($) Amount ($)
A LABOR
1 Unskills labor Day 1.6500 $ 5.00 $ 8.25
2 Stonemason Day 0.2890 $ 8.00 $ 2.31
3 Skilled head Day 0.0290 $ 10.00 $ 0.29
4 Foerman Day 0.0200 $ 12.00 $ 0.24
Sub total $ 11.09
B MATERIAL
1 Portland cement Kg 254.0000 $ 0.15 $ 38.10
2 Gravel M³ 0.8197 $ 100.00 $ 81.97
3 Concrete sand M³ 0.6200 $ 30.00 $ 18.60
Sub total $ 138.67
C EQUIPMENT
$ -
Sub total $ -
D Sum of Labor, Material & Equipment (A + B + C) $ 149.76

Unit Prices Analysis


TIMOR LESTE STANDAR METHOD OF MEASUREMENT (TL - SMM)
Concrete Works
Project Tittle : NEW CONSTRUCTION OFFICE OF MSS Works item no. 8.00
Location : Suai, Covalima District Unit M³

Works Item : 1 M³ Concrete f*c = 14.5 MPa (K 175)

No Code Cost Component Unit Coefficient Unit Prices ($) Amount ($)
A LABOR
1 Unskill labor Day 1.6500 $ 5.00 $ 8.25
2 Stonemason Day 0.2675 $ 8.00 $ 2.14
3 Skilled head Day 0.0267 $ 10.00 $ 0.27
4 Foreman Day 0.0200 $ 12.00 $ 0.24
Sub total $ 10.90
B MATERIAL
1 Portland cement Kg 323.0000 $ 0.15 $ 48.45
2 Gravel M³ 0.7800 $ 100.00 $ 78.00
3 Concrete sand M³ 0.5200 $ 30.00 $ 15.60
Sub total $ 142.05
C EQEUIPMENT
$ -
Sub total $ -
D Sum of Labor, Material & Equipment (A + B + C) $ 152.95

Unit Prices Analysis


TIMOR LESTE STANDAR METHOD OF MEASUREMENT (TL - SMM)
Concrete Works
Project Tittle : NEW CONSTRUCTION OFFICE OF MSS Works item no. 9.00
Location : Suai, Covalima District Unit KG

Works Item : Steel reinforcecement (Polos/Ulir)

No Code Cost Component Unit Coefficient Unit Prices ($) Amount ($)
A LABOR
1 Unskill labor Day 0.0949 $ 5.00 $ 0.47
2 Blacksmith Day 0.0757 $ 8.00 $ 0.61
3 Skilled head Day 0.0109 $ 10.00 $ 0.11
4 Foreman Day 0.0223 $ 12.00 $ 0.27
Sub total $ 1.46
B MATERIAL
1 Steel reinforeced Kg 1.0500 $ 0.25 $ 0.26
2 Concrete wire Kg 0.1500 $ 2.00 $ 0.30
Sub total $ 0.56
C EQUIPMENT
$ -
Sub total $ -
D Sum of Labor, Material & Equipment (A + B + C) $ 2.02

Unit Prices Analysis


TIMOR LESTE STANDAR METHOD OF MEASUREMENT (TL - SMM)
Concrete Works
Project Tittle : NEW CONSTRUCTION OFFICE OF MSS Works item no. 10.00
Location : Suai, Covalima District Unit M²

Works Item : 1 M² Form works for Beams

No Code Cost Component Unit Coefficient Unit Prices ($) Amount ($)
A LABOR
1 Unskill labor Day 0.6600 $ 5.00 $ 3.30
2 Carpenter Day 0.3300 $ 8.00 $ 2.64
3 Skilled head Day 0.0330 $ 10.00 $ 0.33
4 Foreman Day 0.0330 $ 12.00 $ 0.40
Sub total $ 6.67
B MATERIAL
1 Wooden class III M³ 0.0400 $ 325.00 $ 13.00
2 Nail 5' - 12' Kg 0.4000 $ 1.75 $ 0.70
3 Formwork Oil Ltr 0.0536 $ 2.50 $ 0.13
4 Wooden beams Class II M³ 0.0360 $ 350.00 $ 12.60
5 9 mm thick plywood Sheet 0.3500 $ 15.00 $ 5.25
6 Dolken wood 8" - 12" / 4 m Piece 2.0000 $ 7.00 $ 14.00
Sub total $ 45.68
C EQUIPMENT
$ -
Sub total $ -
D Sum of Labor, Material & Equipment (A + B + C) $ 52.35
Unit Prices Analysis
TIMOR LESTE STANDAR METHOD OF MEASUREMENT (TL - SMM)
Finishing Works
Project Tittle : NEW CONSTRUCTION OFFICE OF MSS Works item no. 11.00
Location : Suai, Covalima District Unit M²

Works Item : 1 M² Render

No Code Cost Component Unit Coefficient Unit Prices ($) Amount ($)
A LABOR
1 Unskill labor Day 0.1753 $ 5.00 $ 0.88
2 Stonemason Day 0.1057 $ 8.00 $ 0.85
3 Skilled head Day 0.0146 $ 10.00 $ 0.15
4 Foreman Day 0.0146 $ 12.00 $ 0.18
Sub total $ 2.04
B MATERIAL
1 Portland cement Kg 3.4988 $ 0.21 $ 0.74
Sub total $ 0.74
C EQUIPMENT
$ -
Sub total $ -
D Sum of Labor, Material & Equipment (A + B + C) $ 2.79

Unit Prices Analysis


TIMOR LESTE STANDAR METHOD OF MEASUREMENT (TL - SMM)
Floor Works
Project Tittle : NEW CONSTRUCTION OFFICE OF MSS Works item no. 12.00
Location : Suai, Covalima District Unit M²

Works Item : Install 1 m² of Ceramics Floor Tile Size (60 x 60 cm)

No Code Cost Component Unit Coefficient Unit Prices ($) Amount ($)
A LABOR
1 Unskill labor Day 0.7000 $ 5.00 $ 3.50
2 Stonemason Day 0.3500 $ 8.00 $ 2.80
3 Skilled head Day 0.0350 $ 10.00 $ 0.35
4 Foreman Day 0.0350 $ 12.00 $ 0.42
Sub total $ 7.07
B MATERIAL
1 Ceramics Piece 3.0000 $ 9.00 $ 27.00
2 Portland cement Kg 8.0000 $ 0.21 $ 1.70
3 Sand M³ 0.0450 $ 30.00 $ 1.35
4 Cement color Kg 0.9321 $ 0.21 $ 0.20
Sub total $ 30.25
C EQUIPMENT
$ -
Sub total $ -
D Sum of Labor, Material & Equipment (A + B + C) $ 37.32

Unit Prices Analysis


TIMOR LESTE STANDAR METHOD OF MEASUREMENT (TL - SMM)
Ceiling Works
Project Tittle : NEW CONSTRUCTION OFFICE OF MSS Works item no. 13.00
Location : Suai, Covalima District Unit M²

Works Item : Intall 1 m² plywood ceiling

No Code Cost Component Unit Coefficient Unit Prices ($) Amount ($)
A LABOR
1 Unskill labor Day 0.1000 $ 5.00 $ 0.50
2 Carpenter Day 0.1000 $ 8.00 $ 0.80
3 Skilled head Day 0.0100 $ 10.00 $ 0.10
4 Foreman Day 0.0050 $ 12.00 $ 0.06
Sub total $ 1.46
B MATERIAL
1 Plywood Sheet 0.3750 $ 15.00 $ 5.63
2 Nails 1/2'' - 1'' Kg 0.0300 $ 1.75 $ 0.05
Sub total $ 5.68
C EQUIPMENT
$ -
Sub total $ -
D Sum of Labor, Material & Equipment (A + B + C) $ 7.14

Unit Prices Analysis


TIMOR LESTE STANDAR METHOD OF MEASUREMENT (TL - SMM)
Ceiling Works
Project Tittle : NEW CONSTRUCTION OFFICE OF MSS Works item no. 14.00
Location : Suai, Covalima District Unit M'

Works Item : Install 1 m' wooden trim profile for ceiling

No Code Cost Component Unit Coefficient Unit Prices ($) Amount ($)
A LABOR
1 Unskill labor Day 0.0500 $ 5.00 $ 0.25
2 Carpenter Day 0.0500 $ 8.00 $ 0.40
3 Skilled head Day 0.0050 $ 10.00 $ 0.05
4 Foreman Day 0.0030 $ 12.00 $ 0.04
Sub total $ 0.74
B MATERIAL
1 Wood trim profile M' 1.0500 $ 2.50 $ 2.63
2 Nail trim Kg 0.0329 $ 1.75 $ 0.06
Sub total $ 2.68
C EQUIPMENT
$ -
Sub total $ -
D Sum of Labor, Material & Equipment (A + B + C) $ 3.42

Unit Prices Analysis


TIMOR LESTE STANDAR METHOD OF MEASUREMENT (TL - SMM)
Painting works
Project Tittle : NEW CONSTRUCTION OFFICE OF MSS Works item no. 15.00
Location : Suai, Covalima District Unit M²
1 m² Old wall painting, (1 layer of primer, two coact
Works Item : cover)
No Code Cost Component Unit Coefficient Unit Prices ($) Amount ($)
A LABOR
1 Unskill labor Day 0.0362 $ 5.00 $ 0.18
2 Painter Day 0.0630 $ 8.00 $ 0.50
3 Skilled head Day 0.0064 $ 10.00 $ 0.06
4 Foreman Day 0.0064 $ 12.00 $ 0.08
Sub total $ 0.83
B MATERIAL
1 Priming Kg 0.1200 $ 12.00 $ 1.44
2 Cover paint (2 times) Kg 0.1839 $ 12.00 $ 2.21
3 Brush Piece 0.0294 $ 2.00 $ 0.06
Sub total $ 3.71
C EQUIPMENT
$ -
Sub total $ -
D Sum of Labor, Material & Equipment (A + B + C) $ 4.53
PRICE LIST OF LABOR AND MATERIALS

NO. DESCRIPTION UNT PRICE (USD) REMARKS

LABOUR
1 Foreman day $ 12.00
2 Chief mason day $ 10.00
3 Chief carpenter day $ 10.00
4 Chief blacksmith day $ 10.00
5 Chief painter day $ 10.00
6 Chief electrician day $ 10.00
7 Worker pipe day $ 8.00
8 mason day $ 8.00
9 carpenter day $ 8.00
10 blacksmith day $ 8.00
11 painter day $ 8.00
13 Unskill labour day $ 5.00
MATERIALS
1 Soil fill m3 $ 25.00
2 Sand fill m3 $ 25.00
3 Sand tide m3 $ 25.00
4 Sand for concrete m3 $ 10.00
5 Stone 15/20 cm m3 $ 10.00
6 Gravel break machine 2/3 cm m3 $ 50.00
7 River stone for disfution m3 $ 10.00
8 Portland Cement 40 kg kg $ 0.21
9 Cement colour for ceramic line (nat) kg $ 0.15
10 Concrete block 40x10x20 grade A2 pc $ 1.00
11 Hollow block 40x15x20 grade 1 pc $ 1.00
12 Beendrat (kawat ikat) kg $ 1.00
14 Round bar Ø 16mm kg $ 2.00
15 Round bar Ø D 12mm kg $ 1.75
16 Round bar Ø 10mm kg $ 1.50
17 Round bar Ø 8mm kg $ 1.25
19 Steel plate 3 mm kg $ 2.00
20 Steel plate 8 mm kg $ 5.00
26 Plate Nipper Rufter pcs $ 3.00
28 Nail kg $ 5.00
30 Steel Strip kg $ 0.25
33 Board 2/20 m' $ 4.50
34 Timber/wooden balk class III m3 $ 275.00
35 Scaffolding wood m3 $ 300.00
41 Wooden cornice profile, 3/4 cm m' $ 2.50
43 Ceramik 60 x 60 cm Pcs $ 1.75
48 Roof tile pc $ -
50 Glass 5 mm (ryban) m2 $ 15.00
51 Painting wall ex Jotun kg $ 12.50
52 Painting wood kg $ 2.50
53 Painting steel kg $ 2.50
54 Alkaly sealer wall (Plamir) kg $ 5.00
55 Alkaly sealer wood (Plamir) kg $ 5.00
56 Priming wood (Meni) kg $ 1.50
57 Priming steel (Meni) kg $ 1.50
58 Wooden varnish ltr $ 5.50
59 Oil paint (thiner) A lt $ 2.60
60 Paper rub sheet $ 0.50
61 Rollbrush pc $ 3.00
69 Hand locking door panyl (Good quality) unt $ 35.00
70 Hand locking door PVC (Good quality) unt $ 7.00
71 Hand locking door steel (Good quality) pc $ 30.00
72 Hinges door (Good quality) pc $ 5.00
73 Hinges doors steel (Good quality) pc $ 15.00
74 Hinges window & Boven (Good quality) pc $ 3.00
75 Grendel door panyl (Good quality) pc $ 3.00
76 Grendel window & bovenlight (Good quality pc $ 2.00
77 Right wind window & bovenlight (Good quali pc $ 4.00
78 Sead closed ex TOTO unt $ 210.00
80 Wastafel ex TOTO unt $ 50.00
81 Zinc basin for kitchen unt $ 25.00
82 Faucet wall Ø 1/2" pc $ 10.00
83 Pipe drain Ø 1/2" pc $ 2.00
84 Floor drain (Good quality) pc $ 6.50
88 Pipe PVC Ø 1" merk MASPION m' $ 1.00
90 Pipe PVC Ø 2" merk MASPION m' $ 1.88
92 Pipe PVC Ø 3" merk MASPION m' $ 2.50
93 Galvanis pipe Ø 1/2" m' $ 4.25
93 Galvanis pipe Ø 3/4" m' $ 5.25
94 Elbow PVC Ø 1/2" merk MASPION pc $ 0.35
96 Elbow PVC Ø 2" merk MASPION pc $ 1.25
97 Elbow PVC Ø 4" merk MASPION pc $ 2.00
98 Tee PVC Ø 1/2" merk MASPION pc $ 0.35
99 Tee PVC Ø 3/4" merk MASPION pc $ 0.50
100 Tee PVC Ø 2" merk MASPION pc $ 1.25
102 Embodous pc $ 0.10
103 PVC door for toilet merk Trilliun pc $ 60.00
104 Reducing socket PVC Ø 3/4"→1/2" merk M pc $ 1.00
105 Socket PVC Ø 3/4" merk MASPION pc $ 1.00
Faucet Socket PVC with metal insert Ø 3/4"
106 MASPION pc $ 1.00
110 Cable NYY 3 X 2.5mm merk SUPREME m' $ 1.10
112 Flourescent 2 x 38 wt ex Philip (completed) unt $ 30.00
113 Essential lamp 20 wt ex Philip (completed) unt $ 10.00
114 Single switch merk BROCCO pc $ 2.25
115 Double switch merk BROCCO pc $ 2.50
116 Power outlet merk BROCCO pc $ 2.50
115 Ceiling fitting pc $ 2.00
116 Garden Fitting pc $ 6.00
117 Ceilling fan (good quality) unt $ 30.00
118 Aluminium jamb m' $ 15.00
119 Aluminium windows frame m' $ 15.00
120 Aluminium doors frame m' $ 15.00
121 sealan rubber m' $ 2.50
122 Sealan glue kg $ 3.00
124 Paving stone thc 6 cm pc $ 0.80
125 Kerbstone m' $ 6.00
PERHITUNGAN VOLUME PEKERJAAN

NO URAIAN PEKERJAAN

OFFICE BUILDING + TOILET


I PEKERJAAN TANAH
A BOWPLANK
a Bowplank
Panjang
Lebar

B GALIAN TANAH PONDASI


Galian Tanah
Keliling
Lebar
Tinggi

C PASIR URUG DI BAWAH PONDASI


a Pasir Urug 1
Keliling
Lebar
Tinggi

D URUGAN PASIR DI BAWAH LANTAI


a Urugan Pasir Bawah Lantai
Panjang
Lebar
Tinggi

E URUGAN TANAH BEKAS GALIAN

25% dari pemasangan


pondasi batu kali/gunung

II PEKERJAAN PASANGAN
A PONDASI BATU BELAH/GUNUNG
1 Pasangan Pondasi
Panjang keliling pondasi
Lebar Atas
Lebar Bawah
Tinggi
Volume

B PASANGAN BATAKO
a Pasangan Batako
Luas total tembok
Luas pintu+Jendela+Ventilasi
jadi tot. luas pas. Tembok = Luas tot.tembok dikurangai luas
Pintu+jdnl+ven.

C PLESTERAN
Jumlah

D ACIAN
Jumlah

E LANTAI KERAMIK
a Ruangan Dalam 60 x 60 cm
Panjang
Lebar

b Koridor Depan 60 x 60 cm
Panjang
Lebar
Jadi total keramik 60x60 cm

e Lantai Keramik Kamar Mandi 20 x 20 cm


Panjang
Lebar
Jumlah

f Dinding Keramik Kamar Mandi 20 x 25 cm


Panjang
Tinggi
Jumlah Sisi
Luas
Jumlah Kamar Mandi

Dinding Keramik Kamar Mandi 20 x 25 cm


Panjang
Tinggi
Jumlah Sisi
Luas
Jumlah Kamar Mandi

Volume dinding keramik total

III PEKERJAAN BETON


1 Sloof
a Sloof 25/25

Keliling
b
h
Jumlah

b Sloof 15/25
Keliling
b
h
Jumlah
2 Kolom
a Kolom 25/25 cm
b
h
t
Jumlah kolom
Total volume kolom

b Kolom 15/15 cm
b
h
t
Jumlah
Total volume kolom

c Kolom 15/25 cm
b
h
t
Jumlah
Total volume kolom

d Kolom(15/15) cm
b
h
t
Jumlah

3 Ring balok
a Ring Balok 25/25

Keliling
b
h
Jumlah

b Ring Balok 15/25


Keliling
b
h
Jumlah

c Beam 15/15
Keliling
b
h
Jumlah

d Canopy 15/15
Keliling
b
h
Jumlah

e Reinforced chair
Keliling
b
h
Jumlah
4 Pekerjaan Rabat beton untuk Lantai
a Rabat Beton

Panjang
Lebar
Tebal
Jumlah

b Rabat Beton tangga, type 1


Area
Lebar
Jumlah

c Rabat Beton tangga, type 2


Panjang
Lebar
Tebal
Jumlah
Total rabat beton utk tangga = (type1 + type2)

IV PEKERJAAN ATAP
A Rangka kuda - kuda Canal C

Panjang Rangka 1 bh kuda-kuda


Jumlah kuda-kuda
Jumlah
B Gording Canal C

Panjang gording
Jumlah
C Penutup atap Zinclorbond

Sisi miring Depan


Panjang
Jumlah
Sisi miring Belakang
Panjang
Jumlah
Total penutup atap Zincolorbond

V PEKERJAAN PLAFOND
1 Rangka Plafond gypsum 9 mm
Panjang
Lebar
Jumlah

2 Penutup Plafond
List plafond
Panjang

VI PEKERJAAN PENGECETAN
1 Pengecetan Dinding
panjang Dinding bagian dalam
tinggi
Jumlah

panjang Dinding bagian Luar


Tinggi
Jumlah

2 Pengecetan Ceilling
Panjang
Lebar
Jumlah

3 Pengecetan foundation
Panjang
Lebar
Jumlah
EKERJAAN
PERHITUNGAN
TOTAL Volume SATUAN
Volume Satuan

80.00 m'
26.00 m
14.00 m

100.82 m³
141.00 m
1.10 m
0.65 m

14.10 m³
141.00 m
1.00 m
0.10 m

72.00 m³
24.00 m
12.00 m
0.25 m

- m³
22.03 m³
22.03 m
m
m
88.13 m³
141.00 m
0.35 m
0.90 m
1.00 m
88.13

365.15
439.06 m
73.92 m

365.15 m'

365.15 730.30 m²
2.00 Sisi

730.30 m²
2.00 Sisi

205 m²
20.50 m
10.00 m

48 m²
24.00 m
2.00 m
253 m2

35.00 m²
10.00 m
3.50 m
35.00 Bh

5.00 m
1.50 m
4.00 Sisi
30.00 m²
2.00 Bh 60

2.00 m
1.75 m
4.00 Sisi
14.00 m²
6.00 Bh 84

144.00 m²

6.00 m³
96.00 m
0.25 m
0.25 m
6.00

1.13 m³
30.00 m
0.15 m
0.25 m
1.13

11.59 m³
0.25 m
0.25 m
5.30 m
35.00 bh
11.59 bh

0.60 m³
0.15 m
0.15 m
5.30 m
5.00 bh
0.60 bh

1.19 m³
0.15 m
0.25 m
5.30 m
6.00 bh
1.19

1.35 m³
0.15 m
0.15 m
5.00 m
12.00 bh

6.00 m³
96.00 m
0.25 m
0.25 m
6.00

1.13 m³
30.00 m
0.15 m
0.25 m
1.13

1.19 m³
52.70 m
0.15 m
0.15 m
1.19

8.40 m 0.25 m3
0.10 m
0.30 m
0.25 m3

25.20 0.91 m3
0.12
0.30
0.91

34.56 m³
24.00 m
12.00 m
0.12 m
34.56 bh

1.96 m³
1.96 m2
1.00 m
1.96 m3

3.44 m³
11.25 m
1.53 m
0.20 m
3.44 m3
5.40

29.82 m 506.94 m'


17.00 bh
506.94 bh
702.00 m'
26.00 m
27.00 bh

8.50 m 221.00 m2
26.00 m
221.00 m2
6.52 m 169.52 m2
26.00 m
169.52 m2
390.52 m2

26.00 m 364.00 m2
14.00 m
364.00 m2

214.00 m²
214.00 m

638.73 m2
152.08 m2
4.20
638.73

56.08 235.53 m2
4.20
235.53

24.00 m 288.00 m2
12.00 m
288.00 m2

72.00 m 57.60 m2
0.80 m
57.60 m2

You might also like