RCD 2 Load Distribution 1
RCD 2 Load Distribution 1
RCD 2 Load Distribution 1
Load Distribution
Combination of Loads
Design Loads
Load Distribution
1. Office Ceiling
Ceiling - Suspended Metal Lath & Gypsum
Plaster
- Suspended Steel Channel System Floor Finish
- Acoustic Fiber Board - Ceramic or Quarry Tile (20mm) on
Floor Finish 13mm Mortar Bed
- Wood Block (76mm) on 13mm 3. Stockroom
- Mortar Base Ceiling
2. Toilet - Suspended Steel Channel System
Reinforced Concrete Design 2: REVIEW TO STRUCTURAL ANALYSIS
Prepared by: ENGR BIR
Exterior Walls
- 19.6kN/m3, Full Grout, 150mm thk, both sides are plastered
Interior Walls
- 19.6kN/m3, Full Grout, 100mm, both sides are plastered