Risk Assessment For Chilled Water Cladding

Download as pdf or txt
Download as pdf or txt
You are on page 1of 2

PROJECT: Title: PR 10057115 - REFURBISHMENT OF CHILLED WATER LINES

INSULATION AND CLADDING IN ALL EXTERNAL AREA IN DUBAI MARINA MALL.


RISK ASSESSMENT CONDUCTED BY: HAMID DATE CONDUCTED: 10.06.2019

Risk after Additional


Conditions that develop the Current Risk rating
No Task Personnelexposed Current Control Measure in place Additional Control measures REQUIRED to minimize the risk to acceptable level control measures Responsible Person
hazard (Food allergy etc.)
L S R L S R
1.Site Engineers / Foreman to assess and ensure tools used are
Hazards: 1. Use right and suitable tools for the task you are performing ,
Workers/Assistant fit to purpose.
1 Unsafe condition of tools. 4 3 12 M 4 1 4L HAMID
1. Electric Shock Technicians 2.Any unfit tools to be immediately removed from site. 2. Tools needs to be Inspected and tagged to ensure the safe condition .
2.Injury to Workers 3. Check for tags prior to the usage ( GREEN - SAFE TO USE , RED - UNSAFE TO USE )
1.Site Engineers / Foreman to assess and ensure power sources
Hazards: 1. Al workers to keep minimum distance of 1 mtr from the live Source .
are isolated prior to commencement of works.
Working near to the live Workers/Assistant
2 2.Any descripency found at site with reagrd to power source to 4 5 20 H 2. To carry out tool box training prior start of work or any new activity and understand the HAMID
source 1. Electric Shock Technicians
be recitified immediately and area isolated until further notice. hazards
2.Injury to Workers
Hazards: 1.Identify track for movement 1. Maintain proper House Keeping ,Do not use slippery footwear's.
2. Do not keep any rolling materials above the platform it can fall over the system and cause
1. Slip / trip & fall
any accidents which can lead to massive explosions .
Workers/Assistant
3 Movement on scaffoldings 4 3 12 M 3. Lay PVC floor protection sheet for movement of workforce 4 1 4L HAMID
Technicians
4. Cleaning and make surface dry by using wipers and vacuum cleaners
5. Above and below ground services must be located prior to work commencing
Hazards: 1.Identify track for movement 1. Do not work on the wet surface .
1.Slip and Falls 2. Use rubber mate in front for the panel
Workers/Assistant
4 Wet surface 4 5 20 H 3. Lay PVC floor protection sheet for movement of workforce if required 4 1 4L HAMID
Technicians
4. Cleaning and make surface dry by using wipers and vacuum cleaners
5. Above and below ground services must be located prior to work commencing
1.All machines should be operated by qualified and certified
Hazards: 1.Tool box talk for task to be given to team involved.
operators only.
2.Employees to be made aware of heat stress by means of
Men –machine interference 2. Required PPE to be worn all time during works.
toolbox talk.
Fall from height 3.Sufficient cool drinking water to be available on site.
4.Shaded rest areas to be provided.
5.Safe handling of load manually.
Inspection and preparation Workers/Assistant
5 6.Unauthorized people must be prohibited entry. 4 2 8M 4 1 4L HAMID
of area Technicians
7.Installation of guard rails at platforms.
8.Housekeeping on platforms. Cables to be tied to prevent
tripping.
9.Access and egress to be safe and clean.
10.Ladders to be in good condition and well fixed.
11.Protection from starter bars
Wear P.P.E to the rating and hearing protection ( rated rubber gloves, flash proof clothing,
Hazards: 1.All personnel to wear PPE at all times as per requirement flash proof helmet and face shield , rated rubber floor mats to be included for high voltage
installations )
Workers/Assistant 2.All necessary permits to be in place and compliance ensured Ensure all necessary permits and suitable sipervision is available at site and all condition
7 Disregard of PPE 1.Personnel injury 3 4 12 M 1 4 4L HAMID
Technicians without fail mentioned in work permit to be followed
2.Hazard to site operations 3.Emergency response plan & first aid kit in place.
3. Slip / trip & fall 4. Proper and suitably applicable PPE to be used.
5. Ensure Proper housekeeping at all times.
1.All activities should be ceased immediately in case of
Hazards: 1.Follow all instruction verbal and Permit at site.
emergency.
1.Fire/Electric shock 2.Follow emergency response procedure. 2.Emergency Exit
2.Physical Injury 3.Fire extinguisher should be kept on standby. 3.First Aid Box
3. Biological hazards 4.Emergency response plan & first aider in place 4.Emergency contact details in Place at site.
Workers/Assistant
8 Emergency situations 4.Oil spill from hydraulic system of 4 3 12 M 4 1 4L HAMID
Technicians 5.Emergency response exercise to be done.
the equipment.
6.Secondary means of access / egress must be provided every
5.Heat stress
50 M or as per available exits of mall.
7. Availability of Electrical Shock/heat stress management plan
and

Hazards 1.Identify track for movement 1. Lay PVC floor protection sheet for movement of workforce if required
Movement of Workers & Workers/Assistant
9 1.Slip and Falls 2. Follow logistic plan as agreed with Emaar representative. 4 3 12 M 2. Cleaning and make surface dry by using wipers and vacuum cleaners 4 1 4L RASHID
Logistics Technicians

2.Access control Page 1 of 2 3. Above and below ground services must be located prior to work commencing
PROJECT: Title: PR 10057115 - REFURBISHMENT OF CHILLED WATER LINES
INSULATION AND CLADDING IN ALL EXTERNAL AREA IN DUBAI MARINA MALL.
RISK ASSESSMENT CONDUCTED BY: HAMID DATE CONDUCTED: 10.06.2019

1.Site Engineers / Foreman to assess and ensure competant


Hazards: 1. Only trained competent personnel to be involved ,
manpower is employed for any particular works.
Workers/Assistant 2.Any under performing workers to be immediately taken out 2. Management are to ensure that all personnel on the Unit are competent in their respective
10 Incompetent staff 1. Electric Shock 4 3 12 M 4 1 4L HAMID
Technicians of jb site. trades,
3. Engineer to ensure qulaity of works is not compromised
2.Injury to Workers 3. A comprehensive Induction Training to be given on the arrival of the UNIT
under any circumstances.
3. Delay in works & quality issues
1.All workers/ Technicians working at job site should be 1. All the panels generate heat or produces sparks , so no materials should be placed where
Hazards:
competent and trained to execute works. this could lead to the uncontrolled ignition.
2.Thorough visual inspections of the electrical equipment to be
1.Electric Shock 2.Use of Cable detector to ensure no cable within proposed demolition work is Live.
carried out prior to task
3.Good cable management to be maintained, off the ground 3. .Electrical safety gloves are required to be worn at all times when operating the concrete
2.Fire
Workers/Assistant and out of wet areas saw/core cutting machine
11 Spark 4 5 20 H 1 4 4L RASHID
Technicians
4.Employees to wear mandatory PPE (safety shoes, hard hat
4.Damage to eyes and high visibility vest) at all times and task specific PPE as and
when required (Dust mask, ear defenders, goggles and gloves)

6.Lighting to be suitable and sufficient for the task and


5.Cut Injury
surrounding area
Damaged or loose conduit, trucking of cabling to be identified if any , Preventive, corrective
1.Gloves to be used when activities are carried out that may
Hazards: actions to be explicitly evidenced.
result in injury to the hands.
1.Hand injuries resulting from loose 2. Works/Material to be inspected to ensure that there are no
conduits ad trunking of cables risks present that have not been identified
Damage, loose conduit, Workers/Assistant
12 3. All works areas to have proper access. 4 4 16 H 1 4 4L RASHID
trucking of Cables Technicians
4. Materials to be placed in specific lay down areas dedicated
for these items

info@wulargroup.com : ‫ البريد اإللكتروني‬+971 4 580 8352 :‫ الفاكس‬+971 4 243 8889 :‫ الهاتف‬- ‫ دبي اإلمارالعربـية المـتـحدة‬392145 - ‫ ب‬.‫ص‬
P. O. Box: 392145 Dubai, United Arab Emirates T: +971 4 2438889 F: +971 4 580 8352 Email: info@wulargroup.com

Page 2 of 2