Material Management by Using SAP in Real Estate Construction Sector
Material Management by Using SAP in Real Estate Construction Sector
Material Management by Using SAP in Real Estate Construction Sector
---------------------------------------------------------------------***---------------------------------------------------------------------
Abstract – Material management play an important role Planning,
in construction industry. As far as real estate sector is Procurement,
consider construction material may constitute more than Logistic
60% cost of the total project cost. Material management is a Inventory.
scientific technique, concerned with planning, organizing
and control of flow of materials, from their initial purchase Material management (MM) module of SAP is the best
to destination. System Application and Product (SAP) can solution for material management in construction
help organization to reduce operating costs, generate more industry. By using SAP a 100 % data related to material
accurate forecasts of material, manage and maintain the management is centrally stored/saved on the server. SAP
inventories of material, accelerate procurement, and streamlines all the business functionalities and gives
enhance the delivery-storage-consumption of material at desired result in a single click. An SAP system can help to
right time. To implement an integrated system of materials improve the communication within an organization. SAP is
management, there must be a central database wherein user friendly i.e. information will be obtained as and when
anyone in the company can find out all information about required.
any material passing through the plant. SAP streamlines all
the business functionalities and gives desired result in one 1.1 Objectives of Material Management
click. An SAP system can help to improve the
communication within an organization. SAP is user friendly Efficient material planning.
i.e. information will be obtained as and when required. By Buying or purchasing.
using SAP (Materials Management-Module) for real estate Procuring and receiving.
construction industry, the product can be ordered and Storing and inventory control.
received within safety period. This Paper contains a detail Supply and distribution of material.
study of Material Management module implemented by a Quality assurance.
Kalpataru Ltd. A real estate company from pune. Good supplier and customer relationship.
Improved departmental efficiency.
Key Words: Material Management (MM), Construction
Material, SAP (System Application and Product) 1.2 Functions of Material Management
© 2016, IRJET | Impact Factor value: 4.45 | ISO 9001:2008 Certified Journal | Page 252
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056
Volume: 03 Issue: 12 | Dec -2016 www.irjet.net p-ISSN: 2395-0072
© 2016, IRJET | Impact Factor value: 4.45 | ISO 9001:2008 Certified Journal | Page 253
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056
Volume: 03 Issue: 12 | Dec -2016 www.irjet.net p-ISSN: 2395-0072
© 2016, IRJET | Impact Factor value: 4.45 | ISO 9001:2008 Certified Journal | Page 254
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056
Volume: 03 Issue: 12 | Dec -2016 www.irjet.net p-ISSN: 2395-0072
GATE ENTRY
After Issuing the PO, Suppliers is arranging to deliver the
material. When the material reaches on Gate, a security
Guard makes the entry of same in the Inward Register &
gives the Gate Entry No. on Delivery Challan.
Transaction Code used for Posting GRN is MIGO.
Movement type used for Posting Gate Entry is 103.
Material Code
Required Quantity Figure 6 Gate Entry
Plant No for which material is required
Requisihner Name. GOODS RECEIPT NUMBER (GRN)
Class of material. Goods receipt is the phase where the material is received
by the ordering party and its condition and quality are
PURCHASE ORDER (PO) verified. Depending upon the movement type, stock is
When the PR gets released at all levels, the same is posted in inventory with the help of goods receipt. Goods
displayed to Purchase Department. Then the PO of receipt will show the increase in warehouse stock. When
required material is prepared & when it gets released at the material is delivered on site, referring the Delivery
all level then the PO is honored to the respective supplier. Challan & PO, GRN of the Material is posted in the System.
Transaction Code used for Posting GRN is MIGO.
Movement type used for Posting GRN is 105.
© 2016, IRJET | Impact Factor value: 4.45 | ISO 9001:2008 Certified Journal | Page 255
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056
Volume: 03 Issue: 12 | Dec -2016 www.irjet.net p-ISSN: 2395-0072
Accuracy increases
© 2016, IRJET | Impact Factor value: 4.45 | ISO 9001:2008 Certified Journal | Page 256
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056
Volume: 03 Issue: 12 | Dec -2016 www.irjet.net p-ISSN: 2395-0072
By only one click, one can easily get all details REFERENCES
Nawaj Kalim Hannure, Sushma Shekhar Kulkarni-
It can be useful in planning and procurement of
“Comparative study of Traditional Material
materials
Management and Material Management with ICT
Application” ISSN: 2279- 0535. Volume: 3, Issue:
Wastage of materials get reduced
4(June-July 2014)
Work becomes easy A.A.Lakade, A.K.Gupta, D.B.Desai – “A project
management approach using ERP & Primavera in
Manual errors get reduced construction industry” ISSN: 2278-1684, PP: 21-
24
Time can be reduced for management of materials Sudhanva Kadoli, Digvijay Patil, Ajit Mane, Ajinkya
Shinde, Shrikant Kokate – “An Enterprise
Disadvantages of material management Resource Planning (ERP) for a construction
by SAP Enterprise along with business intelligence (BI)”
IJIRSET, Vol. 3, Issue 2, February 2014
High initial cost Aditya Pande, Syed Sbihuddin – “Material
management for construction sites – A review” E-
Need technically skilled workers ISSN No:2349-0721,Vol 1 Issue 5
Ashwini R. Patil “Analyzing Material Management
Estimation department is to be required Strong Techniques on Construction Project” International
Journal of Engineering and Innovative Technology
Not affordable for small construction companies. (IJEIT) Volume 3, Issue 4, October 2013
Kasim, N B, Anumba, C J and Dainty, A R J (2005)
5 - CONCLUSION
Improving materials management practices on
By using SAP technique, exact consumption of fast-track construction projects. In:
material, stocked material, and location of Khosrowshahi, F (Ed.), 21st Annual ARCOM
material can be obtained. Conference, 7-9September 2005, SOAS, University
of London. Association of Researchers in
The requirement of material on the specific site is
Construction Management, Vol. 2, 793-802.
verified and processed within 24 hours from the
manual creation of purchase requisition. Mr. Abhijeet Zunzarrao Patil, Prof. Dr. A. C. Attar
“Optimizing Construction Resources Using ERP”
The consumption of material is exactly identified
ISSN: 2278-0181- Vol. 2 Issue 8, August – 2013.
to keep control on wastage and prepare a Material
Requirement Planning. Deepak Kumar Vishwakarma, K. J. Satao
“Customization of materials management module
By just a single click Data was made available till
of sap erp for Chhattisgarh steel industries"
Higher Management Level.
IJCSMC, Vol. 4, Issue. 5, May 2015, pg.469 – 478
Paper work reduced due to system
Implementation.
Tracking of Order was easy.
It reduces manual errors and it is easy to
communicate.
Reduces Manpower required in stores.
Inventory record was easily available.
© 2016, IRJET | Impact Factor value: 4.45 | ISO 9001:2008 Certified Journal | Page 257