Project Delays / Cancellations Tracker: Date Power Plant Name

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 10

Project Delays / Cancellations Tracker

Date Power Plant Name


14-Apr-2020 Dinginin Power Station
14-Apr-2020 Uskmouth Power Station
08-Apr-2020 Glen Kyllachy Wind Farm
04-Apr-2020 Salima Solar PV Park
01-Apr-2020 Vogtle 3
01-Apr-2020 Vogtle 4
01-Apr-2020 Forty Mile Wind Power Project
06-Mar-2020 Hwange Power Station II
06-Mar-2020 Hwange Power Station
03-Mar-2020 Batang Toru
05-Feb-2020 Payra Coal Fired Power Plant
27-Mar-2018 Waipipi Wind Farm
27-Mar-2018 Tidong I
27-Mar-2018 Los Lagos
27-Mar-2018 Windy Rig Wind Farm
26-Mar-2018 Teesside Biomass CHP Plant
25-Mar-2018 Turitea Wind Farm
24-Mar-2018 Reliance Meghnaghat Power Plant
19-Mar-2018 Al Dhafra Solar PV Park
17-Mar-2018 Bordersley Power Plant
13-Mar-2018 Badger Hollow Solar PV Park
11-Mar-2018 OPC Hadera Power Plant

Extracted Date: 22-Apr-2020

Disclaimer : All Rights Reserved.


This information has been extracted from GlobalData Power by a registered
No part of this publication may be reproduced, stored in a retrieval system or
The facts of this report are believed to be correct at the time of publication bu
cellations Tracker

Fuel Category Region


Thermal Asia-Pacific
Biopower Europe
Wind Europe
Solar PV Middle East and Africa
Nuclear North America
Nuclear North America
Wind North America
Thermal Middle East and Africa
Thermal Middle East and Africa
Hydro Asia-Pacific
Thermal Asia-Pacific
Wind Asia-Pacific
Hydro Asia-Pacific
Hydro South and Central America
Wind Europe
Biopower Europe
Wind Asia-Pacific
Thermal Asia-Pacific
Solar PV Middle East and Africa
Thermal Europe
Solar PV North America
Thermal Middle East and Africa

extracted from GlobalData Power by a registered user.


may be reproduced, stored in a retrieval system or transmitted in any form by any means, electronic, mechanical, photocopying, recording
e believed to be correct at the time of publication but cannot be guaranteed. Please note that the findings, conclusions and recommendation
Country Total Capacity (MW)
Philippines 1336
United Kingdom 220
United Kingdom 50
Malawi 75.6
United States 1250
United States 1250
Canada 400.5
Zimbabwe 600
Zimbabwe 920
Indonesia 510
Bangladesh 2640
New Zealand 133.3
India 102
Chile 51.6
United Kingdom 43.2
United Kingdom 299
New Zealand 221.4
Bangladesh 750
United Arab Emirates 1500
United Kingdom 5
United States 300
Israel 148

y any means, electronic, mechanical, photocopying, recording or otherwise, without the prior permission of the publisher, GlobalData.
Please note that the findings, conclusions and recommendations that GlobalData delivers will be based on information gathered in good faith
Owner Status
AboitizPower; Ayala Corp Under Construction
SIMEC Atlantis Energy Ltd Permitting
Innogy Renewables UK Ltd Under Construction
JCM Power Corp; InfraCo Africa Ltd Under Construction
Dalton Utilities; Georgia Power Co; Under Construction
Dalton Utilities; Georgia Power Co; Under Construction
Suncor Energy Inc Permitting
Zimbabwe Power Co Ltd Under Construction
Zimbabwe Power Co Ltd Partially Active
PT Dharma Hydro Nusantara; PT Pemb Under Construction
North West Power Generation Co Ltd; Under Construction
Tilt Renewables Ltd Under Construction
Statkraft AS Under Construction
Statkraft AS Under Construction
Statkraft AS Under Construction
MGT Teesside Ltd Under Construction
Mercury NZ Ltd Under Construction
Reliance Power Ltd; JERA Co Inc Permitting
Emirates Water and Electricity Co Announced
Bordersley Power Ltd Permitting
Wisconsin Public Service Corp; Madis Under Construction
OPC Energy Ltd Under Construction

ithout the prior permission of the publisher, GlobalData.


ata delivers will be based on information gathered in good faith from both primary and secondary sources, whose accuracy we are not alwa
Impact Remarks
Delayed The department indicated that the first unit of the 1,336-megawatt Dinginin coal-fired po
Delayed SIMEC Atlantis Energy (Atlantis) has said that it is anticipating a delay in the financial cl
Delayed Construction at Innogy’s planned 50MW Glen Kyllachy wind farm in the Scottish Highlan
Delayed Construction of solar plant halted by coronavirus dueto halt in travel and other activities.
Delayed Southern Co. in a filing with the Securities and Exchange Commission (SEC) on April 1
Delayed Southern Co. in a filing with the Securities and Exchange Commission (SEC) on April 1
Delayed As per Suncor's latest revised guidance to investors amid COVID-19 pandemic and sta
Delayed Construction at Hwange power plant are underway, but they are affected by the Corona
Delayed Renovations in Hwange power plant are underway, but they are affected by the Corona
Delayed Work on the 510 MW Batang Toru hydropower plants in North Sumatra Province, Indon
Delayed Due to Coronavirus outbreak, the Chinese engineers and workers who went to their hom
Delayed On-site work has been temporarily halted because of COVID-19 restrictions
Delayed Statkraft has put the project on hold due to the COVID-19 outbreak.
Delayed Statkraft has put the project on hold due to the COVID-19 outbreak.
Delayed Statkraft has put the project on hold due to the COVID-19 outbreak.
Delayed Construction on the Tees Renewable Energy Plant (Tees REP) a 299 megawatt (MW) b
Delayed New Zealand energy company Mercury has suspended construction of the Turitea wind
Delayed The Indian company Reliance Bangladesh LNG and Power Plant Limited has sought to
Delayed The final bids by consortia vying to develop the 1.5 GW Al-Dhafra solar field in Abu Dha
Delayed In March 2020, Kibo Energy PLC said work on its Bordersley power plant in the UK has
Delayed Invenergy, which is developing the 300-megawatt Badger Hollow solar farm in Iowa Cou
Delayed This is partly due to the delay in the arrival of a foreign technical team to carry out certai

mary and secondary sources, whose accuracy we are not always in a position to guarantee. As such GlobalData can accept no liability what
egawatt Dinginin coal-fired power facility will likely have its commercial operations moved, instead of it getting on stream by June this year
ting a delay in the financial closure for the Uskmouth Power Station conversion project due to the Covid-19 coronavirus pandemic.
d farm in the Scottish Highlands is suspended due to the COVID-19 pandemic, might delay the project timelines.
t in travel and other activities.
Commission (SEC) on April 1 said the COVID-19 pandemic “could disrupt or delay construction, testing, supervisory and support activities” a
Commission (SEC) on April 1 said the COVID-19 pandemic “could disrupt or delay construction, testing, supervisory and support activities” a
COVID-19 pandemic and staggering low world oil prices touched off by a price war between Saudi Arabia and Russia. The company annou
ey are affected by the Coronavirus epidemic. A significant number of staff members of the company in charge of the works are still in China
ey are affected by the Coronavirus epidemic. A significant number of staff members of the company in charge of the works are still in China.
orth Sumatra Province, Indonesia, was temporarily shut down in mid-February because workers from mainland China are unable to fly to th
workers who went to their homeland on vacation could not come back to Bangladesh. There are more than 6,000 workers in the Payra plan
ID-19 restrictions

REP) a 299 megawatt (MW) biomass power plant in the U.K. was suspended on March 24 due to the COVID-19 pandemic. Tees REP was
nstruction of the Turitea wind farm in Manawatu as a result of the coronavirus.
r Plant Limited has sought to extend their 718-megawatt (MW) power plant for indefinite period due to coronavirus The Indian company wil
-Dhafra solar field in Abu Dhabi was reportedly postponed because coronavirus-related restrictions on public gatherings in the emirate
ey power plant in the UK has been delayed by coronavirus and it will not be commissioned by the end of the first quarter.
Hollow solar farm in Iowa County, notified its utility buyers of the potential for delays but said uncertainty around the outbreak make it difficu
hnical team to carry out certain operations required to complete a power plant testing.

ta can accept no liability whatever for actions taken based on any information that may subsequently prove to be incorrect.
on stream by June this year
oronavirus pandemic.

rvisory and support activities” at the Plant Vogtle nuclear expansion project in Georgia.
rvisory and support activities” at the Plant Vogtle nuclear expansion project in Georgia.
d Russia. The company announced its "Forty Milne Wind Power Plant" near Bow Island, which was earlier scheduled to enter construction
of the works are still in China.
of the works are still in China.
nd China are unable to fly to the country due to a coronavirus-related travel ban.
000 workers in the Payra plant, including around 3,000 Chinese nationals.

-19 pandemic. Tees REP was scheduled to become operational in 2020. MGT did not comment on how the COVID-19-related delay could i

avirus The Indian company will supply the electricity by 36 months from the first date of the signing the deals.outbreak. The delay has resul
gatherings in the emirate

nd the outbreak make it difficult to predict the final impact.

o be incorrect.
cheduled to enter construction in 2019, could be delayed up to two years.

COVID-19-related delay could impact that timeline.

outbreak. The delay has resulted in procuring the required financial closure and the required commercial operations date (RCOD) of the Me
rations date (RCOD) of the Meghnaghat Power Plant. The Indian company will supply the electricity by 36 months from the first date of the
onths from the first date of the signing the deals.