Earned Value Problems
Earned Value Problems
Earned Value Problems
1) Compute Estimate At Completion (EAC) and Variance At Completion (VAC) if both SPI
and CPI influence the project work when given variables are
Budget At Completion (BAC) = $22,000
Earned Value (EV) = $13,000
Planned Value (PV) = $14,000
Actual Cost (AC) = $15,000
State the importance of CPI and SPI
2) For the following project calculate SV,CV, SPI and CPI at the end of second month.
Month 1 2 3 4
Planned Value ₹ 11,10,000 ₹ 6,00,000 ₹ 25,00,000 ₹ 8,00,000
Earned Value ₹ 10,00,000 ₹ 7,50,000
Actual Cost ₹ 12,50,000 ₹ 5,00,000
3) You are managing a project which is into six months of its execution. You are now
reviewing the project status and you have ascertained that project is behind schedule. The
actual cost of Activity A is ₹ 2,00,000 and that of Activity B is ₹ 1,00,000. The planned
value of these activities are ₹ 1,80,000 and ₹ 80,000 respectively. The Activity A is
100% complete. However, Activity B is only 75% complete. Calculate the schedule
performance index and cost performance index of the project on the review date.
4) A project that must be completed in 12 months and the budget is 100,000 USD. Six months have
passed, and the schedule says that 50% of the work should be completed. What is the project’s
Planned Value (PV)?
5) A project to be completed in 12 months. The budget is 100,000 USD. Six months have passed,
and 60,000 USD has been spent already, but upon closer review, you find that only 40%
of the work has been completed so far. What is the project’s Actual Cost (AC)?
7) The project is expected to be completed in 8 months at a cost of $10,000 per month. After
2 months, you realize that the project is 30 percent completed at a cost of $40,000. You
need to determine whether the project is on-time and on-budget after 2 months.