QAQC Form - Architechture
QAQC Form - Architechture
QAQC Form - Architechture
: P15-3B
PESTECH SDN BHD Rev. No. : 1
The following works are/ will be ready for inspection at ______________________ (time) on _____________________ (date)
B Inspection Response
Inspection passed, works are allowed to proceed.
Remedial work listed to be carried out. No further inspection required.
Remedial work listed to be carried out. Re-inspection required.
C Remedial Action
Site Supervisor / Site Engineer Clerk of Work (C.O.W) / QAQC Engineer Client Representative
: PLS 150129
:
_________ (date)
G WORK
:
:
Witness By:
Client Representative
The following works are/ will be ready for inspection at ______________________ (time) on _____________________ (date)
B Inspection Response
Inspection passed, works are allowed to proceed.
Remedial work listed to be carried out. No further inspection required.
Remedial work listed to be carried out. Re-inspection required.
C Remedial Action
Site Supervisor / Site Engineer Clerk of Work (C.O.W) / QAQC Engineer Client Representative
The following works are/ will be ready for inspection at ______________________ (time) on _____________________ (date)
B Inspection Response
Inspection passed, works are allowed to proceed.
Remedial work listed to be carried out. No further inspection required.
Remedial work listed to be carried out. Re-inspection required.
C Remedial Action
Site Supervisor / Site Engineer Clerk of Work (C.O.W) / QAQC Engineer Client Representative
The following works are/ will be ready for inspection at ______________________ (time) on _____________________ (date)
B Inspection Response
Inspection passed, works are allowed to proceed.
Remedial work listed to be carried out. No further inspection required.
Remedial work listed to be carried out. Re-inspection required.
C Remedial Action
Site Supervisor / Site Engineer Clerk of Work (C.O.W) / QAQC Engineer Client Representative
The following works are/ will be ready for inspection at ______________________ (time) on _____________________ (date)
B Inspection Response
Inspection passed, works are allowed to proceed.
Remedial work listed to be carried out. No further inspection required.
Remedial work listed to be carried out. Re-inspection required.
C Remedial Action
Site Supervisor / Site Engineer Clerk of Work (C.O.W) / QAQC Engineer Client Representative
: PLS 150129
:
_________ (date)
ALLATION WORK
:
:
Witness By:
Client Representative
Requested by : Received by :
Date/Time : Date/Time :
The following works are/ will be ready for inspection at ______________________ (time) on _____________________ (date)
B Inspection Response
Inspection passed, works are allowed to proceed.
Remedial work listed to be carried out. No further inspection required.
Remedial work listed to be carried out. Re-inspection required.
C Remedial Action
Site Supervisor / Site Engineer Clerk of Work (C.O.W) / QAQC Engineer Client Representative
_ (date)
Witness By:
nt Representative
Requested by : Received by :
Date/Time : Date/Time :
The following works are/ will be ready for inspection at ______________________ (time) on _____________________ (date)
B Inspection Response
Inspection passed, works are allowed to proceed.
Remedial work listed to be carried out. No further inspection required.
Remedial work listed to be carried out. Re-inspection required.
C Remedial Action
Site Supervisor / Site Engineer Clerk of Work (C.O.W) / QAQC Engineer Client Representative
_ (date)
Witness By:
nt Representative
Requested by : Received by :
Date/Time : Date/Time :
The following works are/ will be ready for inspection at ______________________ (time) on _____________________ (date)
B Inspection Response
Inspection passed, works are allowed to proceed.
Remedial work listed to be carried out. No further inspection required.
Remedial work listed to be carried out. Re-inspection required.
C Remedial Action
Site Supervisor / Site Engineer Clerk of Work (C.O.W) / QAQC Engineer Client Representative
_ (date)
Witness By:
nt Representative
Requested by : Received by :
Date/Time : Date/Time :
The following works are/ will be ready for inspection at ______________________ (time) on _____________________ (date)
B Inspection Response
Inspection passed, works are allowed to proceed.
Remedial work listed to be carried out. No further inspection required.
Remedial work listed to be carried out. Re-inspection required.
C Remedial Action
Site Supervisor / Site Engineer Clerk of Work (C.O.W) / QAQC Engineer Client Representative
_ (date)
Witness By:
nt Representative
A Inspection Items
Acceptability
Item No. Description Remarks & Rectification
Yes No
1 Falsework / formwork erected as per PE endorsed drawings
2 Falsework erected on firm ground/proper foundation
3 Ground properly compacted and levelled
4 Falsework not endangered by open excavation
5 Proper sole plates used
6 Base plates are fitted to all standards
7 Vertical standards/posts or vertical frames
8 Ledgers and transoms levelled
9 Connections are tightened and secured
10 Braces are tightened and secured
11 Ties are placed in position as per drawing
12 Soffit formwork is installed as per drawing.
13 Reshoring/back prop is erected as per drawing.
B Inspection Response
Inspection passed, works are allowed to proceed.
Remedial work listed to be carried out. No further inspection required.
Remedial work listed to be carried out. Re-inspection required.
C Remedial Action
Designated Person / Formwork Inspector Professional Engineer for Temporary Works (PETW)
Name: Name:
Date: Date:
PESTECH SDN BHD
The following works are/ will be ready for inspection at ______________________ (time) on _____________________ (date)
B Inspection Response
Inspection passed, works are allowed to proceed.
Remedial work listed to be carried out. No further inspection required.
Remedial work listed to be carried out. Re-inspection required.
C Remedial Action
Site Supervisor / Site Engineer Clerk of Work (C.O.W) / QAQC Engineer Client Representative
__________ (date)
Witness By:
nt Representative
The following works are/ will be ready for inspection at ______________________ (time) on _____________________ (date)
B Inspection Response
Inspection passed, works are allowed to proceed.
Remedial work listed to be carried out. No further inspection required.
Remedial work listed to be carried out. Re-inspection required.
C Remedial Action
Site Supervisor / Site Engineer Clerk of Work (C.O.W) / QAQC Engineer Client Representative
The following works are/ will be ready for inspection at ______________________ (time) on _____________________ (date)
B Inspection Response
Inspection passed, works are allowed to proceed.
Remedial work listed to be carried out. No further inspection required.
Remedial work listed to be carried out. Re-inspection required.
C Remedial Action
Site Supervisor / Site Engineer Clerk of Work (C.O.W) / QAQC Engineer Client Representative
__________ (date)
Witness By:
nt Representative