AL QASR DEVELOPMENT PROJECT

RIYADH SAUDI ARABIA

METHOD OF STATEMENT
OF
UNDERGROUND PIPE INSTALLATION

METHOD OF STATEMENT OF
UNDERGROUND PIPE INSTALLATION
Material to be used:
1. NEPRO / PIPES: Approved (Trans # M-088)
2. NAMAT-PVC FITTINGS: Approved (Trans # M-076)

Summary: This Method of Statement includes all the underground sewer


pipe installation.
1. Procedure
1. Excavate trenches to provide a clearance 300mm on each of the
pipe.
2. Bedding to be compacted in layers not exceeding 150mm to give
uniform bed.
3. Lay the pipe directly on the bedding.
4. The pipes must be installed as indicated on the approved shop
drawing with the required invert level and proper slope using the
approved materials and fittings.
5. Trench is not to be open too far in advance of pipe laying and then
backfilled as soon as possible (24 hours max.)
6. Use fine sand and compact fill firmly between the side of the pipe
and the trench.
7. Brick or hard materials under the pipe are not allowed to be used.
8. Provide a warning tape along the pipe and below the upper layer of
the sand.
9. Until the crown of the pipe is covered by at least two feet of a
tamped sand, considerable care shall be exercised in the back
filling of trenches.
10.The underground pipe must comply with the manufacturer
recommendations for laying the underground pipes.

END