Preliminary Estimate Preparation Guide
Preliminary Estimate Preparation Guide
Preliminary Estimate Preparation Guide
2. After the preliminary plans are made, the general specification of the
building i.e. type of foundation system, type of super structure,
architectural features, special structural and architectural requirements
are identified.
3. The data from the site is collected for external development, water supply,
sanitary, electrical connections and their requirement for the project is
ascertained.
(d) Delhi Plinth Area Rates are based on Market rates of Materials and
Labour for the year 1992 with the base cost index as 100. The cost
index is revised time to time according to the current Market rates
by zonal Chief Engineer to account for variation in rates due to
location (other than Delhi) & Time.
6. The building is than classified fittings the best available class in the DPAR
1992.
10. The architect fees and contingency cost is further added to it.
11. The sum total of all the cost is called the preliminary estimate of the
project and is put up to the competent authority alongwith preliminary
architectural drawings, specification of the building, and special provisions
etc. for accord of Administrative Approval & Expenditure Sanction.