DP FMEA Test Procedure PDF
DP FMEA Test Procedure PDF
DP FMEA Test Procedure PDF
ETESCO DRILLSHIP
TEST PROCEDURE
OF DP FMEA PROVING TRIAL
for
ETESCO DRILLSHIP
Report No : SHI-MRI-1899-061211-02 Rev 5.0
DOCUMENT HISToRY
Revision Date Reason for issue Origin Check Appr.
1.0 12/08/11 First issue for review K.J. Kim G.I. Park J.W. Choi
2.0 29/09/11 Issue reflected owner’s comments K.J. Kim G.I. Park J.W. Choi
3.0 24/10/11 Issue for additional tests of newly installed UPS K.J. Kim G.I. Park J.W. Choi
3.1 31/10/11 Issue for updating CAT numbering K.J. Kim G.I. Park J.W. Choi
4.0 14/11/11 Issue for the result of DP FMEA proving trial. K.J. Kim G.I. Park J.W. Choi
punch items
Office Address : 10TH Floor, Production Support Buildings, Geoje Shipyard, Samsung Heavy Industries
Phone Number : + 82 (0) 55 630 5610 FAX : + 82 (0) 55 630 6270
Email Address : risingsun.kim@samsung.com
Test Procedure for DP FMEA ETESCO Drillship
INDEX
Section Description Page
1. Introduction ……………… 05
ABBREVIATIONS
(A)
AVR : Auto Voltage Regulator
(C)
CBU : Capacitor Bank Unit COS : Console Operating System
COU : Control Unit CPU : Central Processing Unit
(D)
DCS : Drilling Control System DCU : Drive Control Unit
DG : Diesel Generator DO : Diesel Oil
DP : Dynamic Positioning DPC : Dynamic Positioning Controller
DPS : Dynamic Positioning System DPS : Differential Position Sensors
(E)
E/R : Engine Room ECR : Engine Control Room
(F)
FMEA : Failure Mode Effect Analysis FO : Fuel Oil
FW : Fresh Water FS : Field Station
(H)
HV : High Voltage (11kV) HiPAP : High Precision Acoustic Positioning
HPR : Hydroacoustic Position Reference
(I)
IALA : International Association of Lighthouse Authorities
IAS : Integrated Automation System INU : Inverter Unit
(K)
K-chief : Kongsberg Vessel Control System K-pos : Kongsberg Dynamic Positioning System
K-thrust : Kongsberg Thruster Control System KM : Kongsberg Maritime
(L)
LAN : Local Area Network LCL : Lever Communication Link
LO : Lubrication Oil LSU : Line Supply Unit
LT : Low Temperature LV : Low Voltage (440V)
(M)
MGE : Main Generator Engine MRU Motion Reference Unit
MSB : Main SwitchBoard
ABBREVIATIONS
(N)
NDU : Network Distribution Unit
(O)
OS : Operator Station
(P)
PLC : Programmable Logic Controller PMS : Power Management System
(Q)
QCV : Quick Closing Valve
(R)
RCS : Remote Control System RIO : Remote Input Output
RMS : Riser Management System RPM : Revolution Per Minute
(S)
SW : Sea Water
(T)
TEU : Terminal Unit
(U)
UPS : Uninterruptible Power Supply
(W)
WCU : Water Cooling Unit
PLAN HISTORY
No Page Why How
For ver. 3.0 – Issue for additional tests of newly installed UPS
7. 17 Owner’s comment We added the following sentence in cell of ‘Pos.
ref. system’: “At least one should be the different
type.”
8. 17 Drawing update UPS test in stbd 220V feeder panel was added.
9. 19 Drawing update UPS test in cent 220V feeder panel was added.
10. 21 Drawing update UPS test in port 220V feeder panel was added.
11. 59 Drawing update UPS tests for DCU and RexCU in each thruster
room were added.
For ver. 4.0 – Issue for the result of DP FMEA proving trial. The status of punch list still open.
13 All Performance of actual tests Actual result and comment were added
For ver. 5.0 – Issue for the revised results of DP FMEA proving trial with closed all punch items.
14 All Closed all punch We updated results with closed all punch.
1. Introduction
The Failure Mode and Effect Analysis (FMEA) study for DP system of the ETESCO drillship (HN1899) has
been performed with class notation DPS-3 as specified in the ABS rule (2010) for steel vessel, 4-3-5/15
section by Samsung Marine Research Institute.
These sheets were prepared to identify the results of FMEA study by testing single failure of main items
selected and simulating the loss of one compartment for some main compartments during DP sea trial.
After trial to prove DP FMEA the conclusion and the recommendations of the tests will be updated.
The normal conditions for DP operation during trial for the tests should be the followings:
1) One generator will at least be working in each engine room and the others will be stand-by to be
started as required (Load dependent start mode).
2) MGEs in cent engine room will be supplied with fuel oil from service tanks in both port and stbd
engine rooms.
3) Control air for cent engine room is also fed from both port and stbd sides
4) For equipments with redundancy such as FO supply pumps one is duty mode and the other stand-by.
5) All 11kV and 440V/220V bus-tie breakers will be normally open. But 11kV bus-tie breakers can be
closed on some tests.
6) The DP system will be normally operated in auto control mode and the back-up DP ready for control
transfer.
7) All thrusters will be working or at least four thrusters working depending on the situation.
8) The number of DP sensors which have to work will at least follow the specification of ABS DPS-3.
9) DGPS and HiPAP system will be together used as position reference system.
10) Printers for checking of alarms and the event logger will be set.
The sequence of the tests presented here is a proposal and may be changed should that be convenient. In
order to avoid that a test could cause damages to equipment the proposed individual failure tests should
be cleared by the yard’s technical experts. Alternative means to simulate the failures may be discussed.
Main switchboard 2 with normally open bus ties 3 with normally open bus ties in
in separate compartments separate compartments
Control Auto control; no. of 2 + 1 in alternate control 3+1 in alternate control station
computer system station
Alternate control station for backup Yes Yes (DP backup room)
unit
Remarks
3. Test items
1) Power Generation
Remarks
Method With one MGE running for each switchboard and bus ties open during this test.
1. Simulate low level alarm, and reinstate.
2. Close quick closing valves of DO service tank.
As expected
No.5 & 6 As expected Load reduced,
MGE No effect HV MSB frequency went
down
ABS DPS-3 : ■ Pass □ Fail
Witness Comments Signed Date
FMEA Practitioner KiJung Kim 05/11/2011
Remarks
Remarks
Method 1. Stop No.1 CFW pump and after recovery, stop No.2 CFW pump
2. Isolate and bleed off air from the valve
3. Push low level alarm button in FW expansion tank
* Repeat for other engine room
Actual result
Expected result
Stbd Cent Port
1 - Alarm and auto change over to stand-by As expected As expected As expected
pump
Remarks
Method 1. Isolate the control air system and drain the air.
Remarks
Method With closed ring operation mode and each one DG running on each MSB
1. Disconnect one pick up sensor at running engine. Reinstate
2. Disconnect second pick up sensor at running engine. Reinstate
* Repeat for other engines
3. Fail the fuel rack on one engine to maximum position manually.
Actual result
Expected result Stbd Cent Port
(No.1 MGE) (No.3 MGE) (No.5 MGE)
1 - Alarm As expected As expected As expected
- No effect on running engine
Remarks
2) Power Distribution
In order to verify complying with ABS DPS-3 rule, carry out a battery capacity and failure test of UPS
during DP trial as follows :
a. Power distribution
b. UPS
2) Power Distribution
2.1) Stbd MSB Room
Objective To check the effect on the failure of stbd 220V feeder panel, LV MSB, HV MSB and the
total loss of stbd MSB room
2 - Alarm As expected.
- Power sources of MGE local control panels and
governor control panels to be auto-changed over
after UPS battery time
- Loss of power source of No.1 DC 110V dist. board
- Power source of No.4 UPS to be auto-changed
over from main supply to emcy power supply
- No effect on DP
3 - Alarm As expected.
- Loss of stbd 220V feeder panel
- Loss of FO, CSW and CFW pumps
- Loss of LO and DO purifiers
- Loss of G/S and starting air compressors
- Loss of No.2 air supply fan
- Power source of MGE LO priming and cylinder
pumps to be auto-changed over
- Emcy air driven DO pump will start
- Loss of No.4 thruster due to power loss of No.4
thruster aux. panel. Remaining 5 thrusters will keep
the position.
5 - Alarm As expected.
- K-chief OS 36 in ECR shut down
- Loss of FS 38 and 39
- Net B error
- No effect on remaining 4 thrusters and 4 generators
Remarks
2) Power Distribution
2.2) Cent MSB Room
Objective To check the effect on the failure of cent 220V feeder panel, LV MSB, HV MSB and the
total loss of cent MSB room
2 - Alarm As expected.
- Power sources of MGE local control panels and
governor control panels to be auto-changed over
after UPS battery time
- Power source of ECC to be auto-changed over
from main supply to emcy power supply
- No effect on DP
3 - Alarm As expected.
- Loss of cent 220V feeder panel
- Loss of FO, CSW and CFW pumps
- Loss of LO and DO purifiers
- Loss of No.1 air supply fan
- Power source of MGE LO priming and cylinder
pumps to be auto-changed over
- Emcy air driven DO pump will start
- Loss of No.6 thruster due to power loss of No.6
thruster aux. panel. Remaining 5 thrusters will keep
the position.
5 - Alarm As expected.
- Loss of FS 40 and 41
- Loss of alternative power source of No. 4,5 UPS
- Loss of alternative power source of FS 38~43
- No effect on remaining 4 thrusters and 4 generators
Remarks
2) Power Distribution
2.3) Port MSB Room
Objective To check the effect on the failure of port 220V feeder panel, LV MSB, HV MSB and the
total loss of port MSB room
2 - Alarm As expected.
- Power sources of MGE local control panels and
governor control panels to be auto-changed over
after UPS battery time
- Loss of power source of No.3 DC 110V dist. board
- Power source of No.5 UPS to be auto-changed
over from main supply to emcy power supply
- No effect on DP
3 - Alarm As expected.
- Loss of port 220V feeder panel
- Loss of FO, CSW and CFW pumps
- Loss of LO and DO purifiers
- Loss of G/S and starting air compressors
- Loss of No.1 air supply fan
- Power source of MGE LO priming and cylinder
pumps to be auto-changed over
- Emcy air driven DO pump will start
- Loss of No.5 thruster due to power loss of No.5
thruster aux. panel. Remaining 5 thrusters will keep
the position.
5 - Alarm As expected.
- Loss of FS 42 and 43
- Loss of K-Chief 35
- Net A error
- No effect on remaining 4 thrusters and 4 generators
Remarks
2) Power Distribution
2.4) Fwd Section
Objective To check the effect on failure of fwd 220V feeder panel, LV switchboard, and total loss of
fwd section
2 - Alarm As expected
- Loss of fwd No.1 220V feeder panel
- Auto change over of SW and FW pumps to
No.2 section
- No effect on DP
3 - Alarm As expected
- No. 2 UPS power and No.2 PA UPS auto
change to emcy feeder panel
- No effect on DP
4 - Alarm As expected
- Loss of fwd No.2 220V feeder panel
- Auto change over of SW and FW pumps to
No.1 section
- No effect on DP
5 - Alarm As expected
- Loss of fwd 220V feeder panels
- Loss of cooling system of No.1 thruster
- No. 1,2,3 UPS and No.1,2 PA UPS power
auto change to emcy feeder panel
Remarks
2) Power Distribution
2.5) Emergency Switchboard
Objective To check the effect on failure of emergency switchboard (440V and 220V)
2 - Alarm As expected.
- Loss of alternative power of LO priming
pumps and cyl. Pumps in each engine
- Loss of one air supply fan in each engine
room
- Loss of stbd and port HPR hoist control unit
- Loss of emergency 220V feeder panel
Remarks
2) Power Distribution
2.6) DC 110V Distribution Board
Objective To check the effect on failure of AVR and one DC 110V dist. board.
Method 1. Fail incoming power supply for each DC 110V dist. board.
2. Check battery discharging time (over 30 minutes)
3. Disconnect DC110V power cable to AVR for each engine.
4. Open battery breaker and all output breakers.
* Restore and repeat for other dist. board
Actual result
Expected result
Port Cent Stbd
1 - Alarm ‘Battery charger abnormal’ As expected. As expected. As expected.
- No effect on DP
Remarks
The other equipments, which are not listed in above “Lost DP equipments”, have redundant
Remarks power. Therefore those equipments could be working normally in spite of loss of power from
UPS 1.
2) Power distribution
2.10) UPS 4 (Stbd MSB Room)
Objective Test a capacity of battery and failure of the UPS 4.
2) Power distribution
2.11) UPS 5 (Port MSB Room)
Objective Test a capacity of battery and failure of the UPS 5
3) Power management
The Field Stations for power management, which used to control and monitor, are classified as follows :
- IAS Field Station in ECR
- MGE Field Station
- Thruster Field Station
In order to verify complying with ABS DPS-3 rule, carry out redundant power and failure test during DP
trial as follow :
CENT SWBD Room PORT SWBD Room CENT SWBD Room STBD SWBD Room
FS 43 FS 44 FS 37 FS 38 FS 39 FS 40 FS 41 FS 42
3.2) Field Station for IAS (FS43, FS44) 3.3) Field Station for PORT MGE (FS37, FS38)
3.4) Field Station for CENT MGE (FS39, FS40)
3.5) Field Station for STBD MGE (FS41, FS42)
FWD AFT
FS 31 FS 32 FS 33 FS 34 FS 35 FS 36
3) Power management
3.1) Overload Prevention for DG
Objective To prove DP/ PMS cut back on thruster load.
Remarks
3) Power management
3.2) Field Station for IAS (FS 36, FS 37)
Objective Simulate failure of the field station for IAS.
Method 1. Fail main supply for FS and after recovery, fail second supply for FS.
2. Fail both supply for FS.
Actual result
Expected result
FS 36 FS 37
1 - “24VDC supply power failure” alarm in the As expected. As expected.
K-CHIEF OS.
- The FS is still working normally by second
power.
Remarks
3) Power management
3.3) Field Station for STBD MGE (FS 38, FS 39)
Objective Simulate failure of the field station for stbd MGE and MSB.
Method 1. Fail main supply for one FS. And after recovery, fail second supply for one FS
2. Disconnect the following signals from DG to FS
a. Generator kW signal, b. Generator Hz signal, c. Generator breaker status
d. Generator voltage, e. Bus voltage (only for FS 39), f. Generator raise/lower signal
3. Fail both power sources for the FS.
Actual result
Expected result
FS 38 FS 39
1 -‘ 24VDC supply power failure’ alarm in the K- As expected. As expected.
CHIEF OS.
- The FS is still working normally by second power.
3) Power management
3.4) Field Station for CENT MGE (FS 40, FS 41)
Objective Simulate failure of the field station for cent MGE and MSB.
Remarks
3) Power management
3.5) Field Station for PORT MGE (FS 42, FS 43)
Objective Simulate failure of the field station for port MGE and MSB.
Actual result
Expected result
FS 42 FS 43
1 - ‘24VDC supply power failure’ alarm in the K- As expected. As expected.
CHIEF OS.
- The FS is still working normally by second power.
Remarks
3) Power management
3.6) Field Station for FWD thruster (FS 32, FS 33, FS 34)
Remarks
3) Power management
3.7) Field Station for AFT thruster (FS 44, FS 45, FS 46)
Actual result
Expected result
FS 44(STBD) FS 45(PORT) FS 46(CENT)
1 - ‘24VDC failure’ alarm in the K-CHIEF OS. As expected.
- The FS is still working normally by second
power.
Remarks
4) DP control system
From the viewpoint of control system and equipments, essential tested systems during proving trial are
summarized as follows :
- DP controller & Operation Station
- Position reference system & Environmental sensors
- Network system
- Independent Joystick System
In order to verify complying with ABS DPS-3 rule, carry out as following tests during DP trial.
Remarks
Remarks
Remarks
4) DP control system
4.4) I/O modules in DPC-3 (Main DP controller)
Objective Test a failure of the I/O modules in DPC-3.
Remarks
4) DP control system
4.5) Power supplies of DPC-3 (Main DP controller)
Objective Test a redundant power of DPC-3.
Remarks
4) DP control system
4.6) NDU (Network Distribution Unit)
Objective Test a redundant network.
Method 1. Power off the UPS 1 for NDU A1 and check a network status.
2. After recovery, power off the UPS 2 for NDU B1/C1, B2.
3. After recovery, power off the UPS 3 for NDU A2.
4. After recovery, power off the UPS 4 for NDU B3/C3.
5. After recovery, power off the UPS 5 for NDU A3.
-------------------------------------------------------------------------------------------------------------
1) The UPS loss causes NDU failure and so a redundant network can be confirmed during
UPS failure test.
Please refer to UPS failure test related to NDU as following in this procedure:
- UPS 1 failure : NDU A1 fail (item 2.7 UPS 1)
- UPS 2 failure : NDU B1/C1, B2 fail (item 2.8 UPS 2)
- UPS 3 failure : NDU A2 fail (item 2.9 UPS 3)
- UPS 4 failure : NDU B3/C3 fail (item 2.10 UPS 4)
- UPS 5 failure : NDU A3 fail (item 2.11 UPS 5)
2) Confirm that a network error alarm is coming and a redundant network is working
normally.
Expected result Actual result
- Error Net alarm. < NDU A1 >
- A network with NDU failure has network As expected. “Error net A” alarm
error but other network is operating healthy as < NDU A2 >
redundancy. As expected. “Error net A” alarm
- No effect on DP.
< NDU A3 >
As expected. “Error net A” alarm
< NDU B1/C1 >
As expected. “Error net B” alarm
< NDU B2 >
As expected. “Error net B” alarm
< NDU B3/C3 >
As expected. “Error net B” alarm
ABS DPS-3 : ■ Pass □ Fail
Witness Comments Signed Date
FMEA Practitioner KyeongKi, 06/11/2011
Kim
Remarks
4) DP control system
4.7) Voting of the position reference system
Objective Test voting performance due to degraded position reference system.
Method Select all of the position reference systems. (DPS systems and one HiPAP system)
1. Remove the differential correction signals or reduce the satellites of DPS 132-1.
2. After recovery, repeat of DPS 232-1.
3. After recovery, repeat DPS 132-2 in backup room.
4. After recovery, repeat DPS 232-2 in backup room.
5. After recovery, raise the transducer of HiPAP 1 stbd.
6. After recovery, restore and then repeat HiPAP 2 port.
Remarks
4) DP control system
4.8) Position reference system (DGPS, HiPAP systems)
Objective Test a redundancy of the position reference systems.
Method Select all of the position reference systems.
(DGPS systems and one HiPAP system)
1. Power off the DPS132-1 from UPS 3.
2/3/4. After recovery, repeat other DPS from UPS 1 or 2.
5/6. After recovery, repeat HiPAP systems from UPS 1 or 2.
-------------------------------------------------------------------------------------------------------------
1) This test can be confirmed from results of test item 2.7 UPS 1, 2.8 UPS 2 and 2.9 UPS
3.
Expected result Actual result
1 < DPS 132-1 > As expected
- DGPS telegram timeout alarm.
- Other systems are working.
- No effect on DP.
2 < DPS 200-1 > As expected
- DGPS telegram timeout alarm.
- Other systems are working.
- No effect on DP.
3 < DPS 132-2 in backup room > As expected
- DGPS telegram timeout alarm.
- Other systems are working.
- No effect on DP.
4 < DPS 200-2 in backup room > As expected
- DGPS telegram timeout alarm.
- Other systems are working.
- No effect on DP.
5 < HiPAP 1 PORT > As expected
- HPR position status invalid alarm.
- Other systems are working.
- No effect on DP.
6 < HiPAP 2 STBD in ECR > As expected
- HPR position status invalid alarm.
- Other systems are working.
- No effect on DP.
ABS DPS-3 : ■ Pass □ Fail
Witness Comments Signed Date
FMEA Practitioner KyeongKi, 06/11/2011
Kim
Remarks
Method 1. Control a positioning alongship and athwartship using the HiPAP or DGPS system.
2. Make ±15˚heading change at low gain.
Remarks
4) DP control system
4.10) MRU (Motion Reference Unit)
Objective Test a performance due to degraded MRU.
Method 1. Make a 4˚difference for roll and pitch of MRU 1 which selected as ‘in use’.
2. After recovery, repeat for MRU 2 which selected as ‘in use’.
3. After recovery, repeat for MRU 3 which selected as ‘in use’ in DP backup room.
Remarks
Method 1. Switch off the MRU 1 which selected as ‘in use’ by disconnecting terminals in DPC-2.
2. After recovery, switch off the MRU 2 which selected as ‘in use’.
3. After recovery, switch off the MRU 3 which selected as ‘in use’ in CENT MSB Room.
-------------------------------------------------------------------------------------------------------------
1) MRU redundancy tests due to power loss are carried out in ‘Environmental Sensor
redundancy test’ during CAT 4.5.4. Please refer to the CAT.
2) Confirm that redundant sensor and no effect to DP control.
Remarks
4) DP control system
4.12) Gyro compass
Objective Test a performance due to degraded Gyro compass.
Method 1. Give a difference for alarm on Gyro 1 which selected as ‘in use’.
2. After recovery, repeat for Gyro 2 which selected as ‘in use’.
3. After recovery, repeat for Gyro 3 which selected as ‘in use’ in backup room.
Remarks
Method 1. Switch off the Gyro 1 which selected as ‘in use’ by disconnecting terminals in DPC-2.
2. After recovery, switch off the Gyro 2 which selected as ‘in use’.
3. After recovery, switch off the Gyro 3 which selected as ‘in use’.
-------------------------------------------------------------------------------------------------------------
1) Gyro compass redundancy tests due to power loss are carried out in ‘Gyro sensor
redundancy test’ during CAT 4.5.5. Please refer to the CAT.
2) Confirm that redundant sensor and no effect to DP control.
Remarks
Method 1. Switch off the wind sensor 1 unit by disconnecting terminals in DPC-2.
2. After recovery, switch off the wind sensor 2.
3. After recovery, switch off the wind sensor 3 of DP backup system.
-------------------------------------------------------------------------------------------------------------
1) Wind sensor redundancy tests due to power loss are carried out in ‘Environmental
Sensor redundancy test’ during CAT 4.5.4. Please refer to the CAT.
2) Confirm that redundant sensor and no effect to DP control.
Remarks
Method 1) Consequence analysis test are carried out in ‘On-line Consequence Analysis’ test
during CAT 4.5.6. Please refer to the CAT.
Remarks
Method 1. Change over to DP backup system from DP main system by operating the selector
switch located at the backup OS, K-POS OS 4.
-------------------------------------------------------------------------------------------------------------
1) Change over between the DP systems test are carried out in ‘Backup Switch’ test
during CAT 5.1. Please refer to the CAT.
2) Confirm that normally change over from main to backup DP system.
Remarks
Method 1) Tests of a manual position control by the joystick system are carried out during CAT
cJoy. Refer to CAT cJoy procedure.
Remarks
5) Thrusters
The thruster system is consisted of 5 sub-systems which are needed necessarily in order to operate
thruster. 5 sub-systems are as follows:
-Power system
-Hydraulic and Lubrication Oil system
-Cooling system
-Thruster drive system
-Control system.
THRUSTER
THRUSTER COOLING
COOLING
DRIVE
DRIVE SYSTEM
SYSTEM SYSTEM
SYSTEM 5.6) Sea water cooling system
5.2) Azimuth Signal
5.3) Speed Signal
2) Power distribution PART 5.7) Fresh water cooling system
CONTROL
CONTROL
SYSTEM
SYSTEM THRUSTER
THRUSTER Electric
Electric Line
Line
PROPULSION
PROPULSION
MOTOR
MOTOR Force
Force Line
Line
5.1) Thruster control panels Water
HYDRAULIC
HYDRAULIC and
and Water Line
Line
5.8) Emergency stops LUBRICATION
LUBRICATION
OIL
OIL SYSTEM
SYSTEM Oil
Oil Line
Line
THRUSTER
THRUSTER Signal
Signal Line
Line
5.4) Azimuth hydraulic system
5.5) Lubrication oil system
The Power system and Thruster drive system are related to supplying thruster power. The effect of these
systems can be confirmed in the power distribution part.
The Cooling system supplies cooling water to equipment related to thruster operating. It has to be
checked that the cooling water is supplied to thruster equipment. So the operation of cooling pumps is
confirmed.
The Oil system supplies oil in order to help thruster operation. The pumps and expansion tanks which are
related to oil supply are evaluated.
The Control system controls the thruster operation signals. Azimuth and speed signals for the thruster to
be operated and emergency stop signals have to be analysed.
5) Thrusters
5.1) Thruster Control Panels
To test a failure of the DCU (Drive Control Unit) power
Objective To test a failure of the RexCU (Rexpeller Control Unit) power
*Repeat for other thrusters.
1. Fail main supply power for DCU. (After recovery, test the other power)
2. Check battery capacity inside DCU after disconnecting two supply powers for DCU.
3. Fail main supply power for RexCU. (After recovery, test the other power)
Method
4. Check battery capacity supplied from THR. AUX. panel after disconnecting two supply
powers (UPS and THR. AUX. panel) for RexCU.
*Repeat for other thrusters.
Expected result Actual result
1 - DCU common alarm As expected.
- The DCU power is auto-changed to the
second power and the DCU will work normally
by second power.
2 - DCU UPS alarm As expected.
- Battery discharging time > 30 minutes
Remarks
5) Thrusters
5.2) Azimuth Signals
Objective To test a failure of azimuth control signals.
Remarks
5) Thrusters
5.3) Speed Signals
Objective To test a failure of speed control signals.
2 - Thruster is in DP As expected.
- Propeller is operating.
- DCU common alarm.
- ‘Feedback’ input signal error
Remarks
5) Thrusters
5.4) Azimuth hydraulic System
Objective To test failure of hydraulic steering pumps.
Remarks
5) Thrusters
5.5) Lubrication Oil System
Objective To check a failures of lubrication oil system.
Remarks
5) Thrusters
5.6) Sea Water Cooling System
Remarks
5) Thrusters
5.7) Fresh Water Cooling System
Moonho 07/11/
FMEA Practitioner
Son 2011
Remarks
5) Thrusters
5.8) Emergency Stops
Objective To check of a failure of emergency stop circuit.
Remarks
6) Communication
6.1) Communication
Objective Test normal operation of communication between DP and Drilling space.
(e.g. Wheelhouse, Driller cabin)
Method 1. Power off auto telephone system and then try to contact with other room.
2. Operate DP alert switch on K-POS OS 1. (green, yellow, red)
Remarks
Method 1. Fail main supply for ESD FS 51. After recovery fail second supply. And fail both supply
2. Fail main supply for F/G FS 49. After recovery fail second supply. And fail both supply
3. Fail main supply for F/G FS 50. After recovery fail second supply. And fail both supply
2 - Alarm As expected.
- Dual power redundancy to be checked
- No effect on DP
3 - Alarm As expected.
- Dual power redundancy to be checked
- No effect on DP
Remarks
4.1 All the DP FMEA tests had been carried out between 5th and 7th November 2011.
4.2 Each test had been performed in condition that owner, class, and SHI were attending.
4.3 Final document for results of FMEA proving DP trials will be submitted after the punch lists
described in chapter 5 will be taken actions by SHI and closed.
4.4 The results of tests proved that this vessel complies with classification of the guidelines for dynamic
positioning system as defined in IMO MSC 645 and ABS DPS 3 requirements.
< Portside in E/R 2nd deck > < Stbdside in E/R 2nd deck >
Verification by
No. Item Test No. Description Action by SHI Status
SHI-MRI
SHI took Noted Closed
No fully insulation for bulkheads in Cent. E/R 4th deck.
complementary
It has to be fully insulated.
measures by A-60
insulating the
undone parts
2. Check on
the number
2 Insulation < Portside in E/R 4th deck >
of required
equipments
Verification by
No. Item Test No. Description Action by SHI Status
SHI-MRI
SHI took Noted Closed
No fully insulation for bulkheads in Fwd. machinery room.
complementary
It has to be fully insulated.
measures by A-60
insulating the
undone parts
Verification by
No. Item Test No. Description Action by SHI Status
SHI-MRI
SHI took Noted Closed
The cable ducts, which for no.1 thruster HV power and net A cable, in the air
complementary
cond. unit room were not A60 insulated ducts.
measures for A-60
These ducts have to be with A60 insulation in accordance with drawing and
insulated ducts the
rules.
undone parts
2. Check on
the number
4 Insulation
of required
equipments
Verification by
No. Item Test No. Description Action by SHI Status
SHI-MRI
SHI took Noted Closed
No fully insulation for bulkheads in Fwd. CO2 room.
complementary
It has to be fully insulated.
measures by A-60
insulating the
undone parts
2. Check on
the number
5 Insulation
of required
equipments
Verification by
No. Item Test No. Description Action by SHI Status
SHI-MRI
The cable duct, which for net A cable, in the aux. store was not A60 SHI took Noted Closed
insulated duct. complementary
This duct has to be with A60 insulation in accordance with drawing and measures for A-60
rules. insulated duct the
undone parts
2. Check on
the number
6 Insulation
of required
equipments
Verification by
No. Item Test No. Description Action by SHI Status
SHI-MRI
Load limitation frequency : Noted Closed
58 Hz, 2SEC -> 57.5 Hz, 5SEC
Overload During stbd side test, when No.1 DG stopped
Thruster lever shall be operated
7 Prevention 3.1) : No.2 MGE was unstable. The load was fluctuating.
slowly in manual mode.
for DG : The loads of No.3, 4 thrusters also were fluctuating.
It was fixed and confirmed
stable operating MGE.
When kw signal of a DG from as below FS was disconnected, It was fixed and confirmed Noted Closed
dummy value (minus value) came in and according to load changing to manual mode.
sharing the other DG was tripped by reverse power. To avoid
this, the corresponding DG should be changed to manual
FS for 3.3)
8 mode.
MGE 3.4)
FS 38 in Stbd MSB room
FS 39 in Stbd MSB room
FS 40 in Cent. MSB room
FS 41 in Cent. MSB room
B) “Important”
Verification
No. Item Test No. Description Action by SHI Status
by SHI-MRI
2. Check It was fixed and confirmed an Noted Closed
No earthing for transceiver and switchbox in both HPR
on the earthing for the equipments.
compartments as follows :
1 Earthing number of
HPR 1 at stbdside
required
HPR 2 at portside
equipments
All dampers in the engine room where control air was failed It was fixed and confirmed a time of Noted Closed
kept the open position by non-return valve. As time goes by, keeping the open position of dampers
they started to close. As the result the corresponding air when control air fails.
Control
supply fans stopped. Finally they were completely shut in
2 Air 1.5)
13mins at stbd engine room and 4mins at port engine room.
System
All non-return valves have some leakage because of their
characteristics. But time that they keep the opening position
is short. So they should be examined.
When one pick-up sensor of a MGE was disconnected circuit The function for breaker trip when Noted Closed
breaker of the corresponding MGE was tripped. But it is one pick-up sensor failure has been
Electric
3 1.6) good that the alarm just comes out without opening the deleted.
Governor
circuit breaker of the corresponding MGE because each
governor has two pick-up sensors.
Verification
No. Item Test No. Description Action by SHI Status
by SHI-MRI
220V UPS’s of as below MSB rooms had no alarm on IAS. It was fixed and confirmed alarm Noted Closed
UPS
Because UPS was newly installed the related name plates occurring.
Alarm 2.1)
should be changed.
4 in 2.2)
Stbd MSB room
MSB 2.3)
Cent. MSB room
Room
Port MSB room
At 220V feeder panel fail test, there was no alarm for loss of It was fixed and confirmed alarm Noted Closed
DC 110V
2.1) one power source of as below DC 110V DB. occurring.
5 DB
2.3) No.1 DC 110V DB in stbd MSB room
Alarm
No.3 DC 110V DB in port MSB room
The alarm for loss of alternative Noted Closed
( During 220V fail test )
Em’cy power of DCU UPS’s and power fail
No alarm for loss of alternative power source of thruster
6 Swbd 2.5) alarm of No.2 DC 110V DB were
No.1~6 DCU UPS.
Alarm fixed correctly and confirmed.
No alarm for power failure of No.2 DC 110V DB.
When UPS 2 was one power loss, the earth failure alarm was It was fixed and confirmed correct Noted Closed
7 UPS 2 2.8) coming incorrectly on K-POS OS. Correct alarm is “auto alarm occurring
switch failure” alarm. It has to be fixed.
Verification
No. Item Test No. Description Action by SHI Status
by SHI-MRI
When UPS 3 was one power loss, the “UPS 3 PDU earth It was fixed and confirmed correct Noted Closed
8 UPS 3 2.9) fail” alarm was coming incorrectly on K-CHIEF OS. Correct alarm occurring
alarm is “auto switch failure: alarm. It has to be fixed.
When as below UPS’s were both power loss, the UPS # It was fixed and confirmed alarm Noted Closed
abnormal alarm was not coming to K-CHIEF OS. coming up.
2.10)
9 UPS 4&5 UPS 4
2.11)
UPS 5
It has to be coming up and fixed.
When breaker status signal of a DG from as below FS was According to KM logic, if the load of Noted Closed
lost, the load of the corresponding DG went to zero and CB the DG is below 10% the DG breaker
tripped. This should be checked. will actually trip and if over 10% the
FS for 3.3)
10 FS 38 in Stbd MSB room DG breaker will still be closed when
MGE 3.4)
FS 39 in Stbd MSB room the signal of DG breaker status is
FS 40 in Cent MSB room disconnected.
FS 41 in Cent MSB room
Verification
No. Item Test No. Description Action by SHI Status
by SHI-MRI
In case that as below FS38 which controls PMS fails, K- It was fixed and confirmed to keep Noted Closed
chief gives the dedicated two thrusters maximum available available power just before the FS
power values (4500kW) regardless of original values. But failure.
3.3) this may cause the MGE to overload or frequency low.
11 PMS FS 3.4) Therefore it is good to keep the values just before the FS
3.5) failure.
FS38 in Stbd MSB room
FS40 in Cent. MSB room
FS43 in Port MSB room
The K-POS OS 1, 2 and K-THRUST OS 5 mimic have The OS mimic was modified correctly Noted Closed
DP OS 4.1)
12 incorrect description of switchboard. The switchboard name by Kongsberg.
Mimic 4.2)
of port and stbd should be exchanged correctly.
The wind sensors have too high difference each other The position and sensor’s value were Noted Closed
Wind
13 4.14) depending on weather condition. fixed properly and confirmed.
Sensor
It has to be checked relocation and fixed.
The battery of no.1 DCU UPS was Noted Closed
The battery capacity of No.1 DCU UPS must be confirmed.
14 DCU 5.1) changed and sufficient capacity was
The battery must last for 30 mins
confirmed.
Verification
No. Item Test No. Description Action by SHI Status
by SHI-MRI
When the hyd. pump was changed the thruster was It was fixed correctly and confirmed. Noted Closed
Azimuth
deselected in the DP mode.
15 Hydraulic 5.4)
It must be modified. In this case the thruster must be in the
Pump
DP mode.
Sea water The auto-change logics for thruster Noted Closed
1.3) In the No.2, 3 and 5, when SWC pump was changed FWC
16 cooling pumps were modified and confirmed.
5.6) pump also was changed at the same time.
system
C) “Nice To Have”
Verification
No. Item Test No. Description Action by SHI Status
by SHI-MRI
SHI took Noted Closed
The cables of relevant DP equipments were exposed to sharp shape of the
complementary
hole on the wall in DP backup room.
measures for
Theses cables have to be protected against the sharp shape.
protection against
2. Check on
exposed sharp
the number
1 Insulation shape.
of required
equipments
Verification
No. Item Test No. Description Action by SHI Status
by SHI-MRI
Incorrect nametags were attached at the top of an entrance as follows : SHI took Noted Closed
Port bow thruster room complementary
Stbd bow thruster room measures to change
Center bow thruster room correct nametags of
Forward machinery room corresponding
These nametags have to be changed correctly. rooms.
2. Check
on the
2 Insulation number of
required
equipments
< Nametag of port bow THR, RM > < Nametag of stbd bow THR, RM >
< Nametag of cent. bow THR, RM > < Nametag of fwd. mach. RM >
Verification
No. Item Test No. Description Action by SHI Status
by SHI-MRI
Labels It was fixed correctly and confirmed. Noted Closed
The labels for the number of thruster on K-POS OS and K-
for
3 THRUST OS panel were mismatched with mimic. It should
thrusters
be changed.
on OS
Labels The labels of control selector switch Noted Closed
of The labels of selector switch on backup K-POS OS 4 were on backup K-POS OS 4 had been
4
selector not attached. It should be indicated. attached after DP trial.
switch 2. Check
on the No nametag of switchboxes in both HPR compartments as It was fixed and confirmed. Noted Closed
S/W box number of follows :
5
Nametag required HPR 1 at stbdside
equipments HPR 2 at portside
The transceiver 2 cable tray in HPR 2 Noted Closed
Cable The transceiver 2 cable tray in HPR 2 compartment (P) was compt. was installed correctly after
6
Tray installed abnormally. It should be fixed correctly. DP trial and confirmed.
Verification
No. Item Test No. Description Action by SHI Status
by SHI-MRI
MGE DO It was updated properly and Noted Closed
There is no engine room name in alarm description of ‘standby
8 supply 1.1) confirmed.
started’.
pump
At fwd 220V fail test two alarm for No.1 and No.3 UPS came out. It was fixed and confirmed Noted Closed
Fwd correct alarm occurring
9 2.4) One is “Auto sw fail” and the other is “abnormal”. But only “Auto
Section
sw fail” alarm for No.2 UPS came out.
Verification
No. Item Test No. Description Action by SHI Status
by SHI-MRI
Unlike stbd and cent, when kw signal of a DG was It was fixed and confirmed changing to Noted Closed
disconnected kW value was fixed and the other DG manual mode.
was not tripped by reverse power. But the
FS
corresponding DG should be not changed to manual
14 for 3.5)
mode either.
Port MGE
Unlike stbd and cent, in case of the loss of breaker
status signal nothing happened. In our opinion this
is normal.
It was fixed and confirmed. Noted Closed
FS power 3.2) ~ Description cell on alarm view was blank at alarm
15
fail alarm 3.7) test for FS power fail.
The standard deviation of DGPS was not increased < Kongsberg reply > Noted Closed
after all corresponding differential correction signals The standard deviation increasing slowly, there
fail and then suddenly the DGPS was rejected. are a few reasons to be aware of as follows:
Normally, in case of all correction signals loss, the 1) Vessel must move slightly since deviation is
Voting
standard deviation of DGPS is increasing due to calculated from present position.
16 of 4.7)
degraded accuracy and then the DGPS might be 2) The XP/HP must be disconnected firstly, and
PRS
rejected on DP by too high deviation. wait at least 2~3mins.
It should be explained why keep on the standard 3) The other correction signals can then be
deviation of DGPS without differential correction disconnected one by one, but give time between
signals. and make sure the vessel does not “stand still”
Verification
No. Item Test No. Description Action by SHI Status
by SHI-MRI
It was fixed and confirmed Noted Closed
The alarm must be triggered when power of DCU is changed.
17 DCU 5.1) correct alarm occurring.
The alarm must be installed.
18 RexCU 5.1) The alarm must be installed when power of RexCU is changed. correct alarm occurring.