MDT job is designed after evaluating the open hole logs. There are few
main points which should be keep in mind before planning the job.
1- Select the depth points for formation pressure.
2- Select at least three (3) pressure points in one bed.
3-Pressure points should fall in oil/gas zones and water bearing zone.
4- Select the oil/gas sample point, which should be clean and try to get it
from top of the reservoir.
5-Also select a point for water sample in water bearing zone.
6- MDT oil/gas sample is very suitable for PVT analysis.
MDT Operation:-
If you have to QC or witness the MDT operation then you should consider
the points which are given below:-
• The formation water analysis is also very useful for well completion
equipment.