IMPERIAL BUILD TECH PVT LTD

No.2226/A, PNS Complex, 4th main, Banashankari 2nd stage, Bangalore - 560070

PROJECT : KALKUNTE EDUCATION TRUST


23.09.2019
RATE ANALYSIS

No Description of items Quantity unit Rate Amount

Providing and fixing of MS Ladder at Terrace


1
Floor (3250mmX600mm)

a 25mmX50mm MS Pipe 1 Length 550.00 550.00

b 40mmX80mm MS Pipe 2 Length 800.00 1,600.00

Lump
c Primer 1 850.00 850.00
Sum

f Labour Charge for Fabrication and Fixing 1 No 4,500.00 4,500.00

e Transportation 1 No 2,000.00 2,000.00

Total 9,500.00

Miscellaneous items like water, electricity, Labour


facilities,scaffolding lead & lift, tools & tackles etc 712.50
complete @ 7.5%

TOTAL 10,212.50

ADD: Overheads & Contractor profit @ 15% 1,531.88

GRAND TOTAL / NO 11,744

Note: The Above Rate Excludes GST