General Civil Assumptions For Man-Hour Estimate For Township Work
General Civil Assumptions For Man-Hour Estimate For Township Work
General Civil Assumptions For Man-Hour Estimate For Township Work
Assumptions:
1. Drinking Water System
At 18 (i.e. 50 % of total sites )sites augmentation of water system has been considered i.e. intake,
conveyance, storage & pumping system has been envisaged along with distribution system.
At 18 (i.e.50 % of total site) locations only extension of existing drinking water system has been
considered.
No Raw Water Treatment plant has been envisaged.
2. Plumbing
Typical plumbing layout of type-I, II, III & IV quarters shall be applicable for all the locations. (It is
assumed that the internal quarter plan shall be same at all the locations for type-I,II, III and IV
quarters).
3. Roads & Drainage
Roads and drains shall be constructed in two phases.
4. Sewage Treatment Plant
Sewage Treatment Plant has only been considered for 6 locations.
5. Sanitary Sewer System
No pumping has been considered for sanitary sewer system.
6. Tender
Reduced manhour have been considered for similar tenders with minor modifications.
7. The man-hour projection given is based on the following assumption:
For 1st and 2nd quarter the work shall be carried out for 4 sites.
For 3rd and 4th quarter the work shall be carried out for 8 sites.
For 5th and 6th quarter the work shall be carried out for 12 sites.
For 7th and 8th quarter the work shall be carried out for remaining 12 sites.
QUARTERLY MANPOWER PROJECTION FOR GENERAL CIVIL DEPARTMENT
(FOR 24 MONTHS COMPLETION TIME)
OPTION TOTAL 1st 2nd 3rd 4th 5th 6th 7th 8th
MANHOUR Quarter Quarter Quarter Quarter Quarter Quarter Quarter Quarter
I 29400 3 3 6 6 9 9 9 9
II 15150 2 2 3 3 5 5 5 5