Nothing Special   »   [go: up one dir, main page]

Relay Commission Testing Methods For Protection Systems

Download as pdf or txt
Download as pdf or txt
You are on page 1of 34
At a glance
Powered by AI
The key takeaways from the document are that protection systems require commission testing at various stages to ensure proper and safe operation. Commission testing verifies that all components are functioning correctly according to the unique application and provides baseline data for ongoing maintenance.

The three stages of testing for protection systems over their lifetime are type testing, commission testing, and life-cycle maintenance testing.

The goals of commission testing for protection systems are to assure that the protection system is performing correctly as required for its unique application and that it tests all five NERC PRC-005-2 components (voltage and current sensing devices, protection system DC supply, control circuitry, communication systems, and protective relays). Commission testing also verifies energizing procedures and in-service load checks.

Commission Testing

Methods for Protection


Systems

Ken Sletten – Minnesota Power


Tom Ernst– GE Grid Solutions

2017 Minnesota Power Systems Conference


Agenda

• Introduction
• Goals and objectives of protection system commission testing
• Maintenance Testing
• Re-commission testing
• Case Studies
• Conclusions
Introduction
• Protection systems require testing to assure proper operation
• 3 separate stages of testing over protection system’s life
• Type testing
• Commission testing
• Life-cycle maintenance testing
• Commission testing is critical
• Assure safety
• Functional operation
• Equally critical in both utility and industrial systems
• Commission testing provides baseline data for maintenance
• Critical for utility installations subject to NERC PRC-005
• Commission and maintenance testing have different goals
and objectives
Goals and objectives of protection
system commission testing
• Commission tests are preformed to assure that the protection
system is performing correctly as required for the unique
application
• Must commission test all 5 NERC PRC-005-2 components
• Voltage and current sensing devices
• Protection system DC supply (including batteries, chargers, monitoring
circuitry, and power supplies/inverters whether they include batteries
or not)
• Control circuitry (including wiring, trip coils, electro-mechanical
auxiliary relays and lock-outs, etc.)
• Communication systems required for protection system operation
• Protective relays
• Must also perform energizing procedures and in service load
checks
Voltage and Current Sensing Devices
• Magnetic core devices
• VT commission tests
• Ground leakage test - no
unintentional grounds
• Turns ration check (TTR)
• Polarity check
• Test voltage applied to a VT applied
to the primary winding to avoid the
presence unsafe high voltages
• CT commission tests
• Ground leakage test - no unintentional grounds
• Turns ration check (TTR)
• Polarity check
• Excitation check
Voltage and Current Sensing Devices

• Non-magnetic core device commission


tests
• Optical VTs, CTs
• Devices have self-testing
functionality
• Rogowski coils
• Typically have unique calibration
characteristics provided by
manufacturer
• Primary injection
• In-service load checks
Protection system DC supply
• Batteries, chargers, monitoring circuitry, and power
supplies/inverters whether they include batteries or not
• Tests based on the technology used
• Battery banks - verify the bank meets design specs and
industry standards
• Battery load/capacity tests
• Cell impedance measurement
• Inter-cell connection resistance measurement
• Specific gravity measurement
• Cell voltage checks
Protection system DC supply

• Batteries, chargers, monitoring circuitry, and power


supplies/inverters whether they include batteries or not
• Battery chargers
• Function testing
• Verification of battery charger
settings
• Alarm verification
• Methods and tools used for testing
and the results of the tests should be
saved as base-line data for future
maintenance tests
Control circuitry
• Includes wiring, trip coils, electro-mechanical auxiliary relays,
lock-outs, etc.
• AC and DC wiring should be checked physically and
electrically
• Point to point wire checks
• Wiring is physically in agreement with the design
documents
• Injection of electrical quantities
• Wiring performs the necessary functions
• Helps to identify any errors in the design
• Develope a system to document each test
Control circuitry
• AC and DC wiring electrical tests (cont.)
• Check DC circuits before energizing
• Pull fuses to isolate
• Use an ohm meter to verify there are no short circuits
• Reinstall load fuses one circuit at a time
• Verify no DC grounds are acquired
Control circuitry
• CT secondary injection
• Inject 3-phase test set currents into CT circuit
• Clipping onto the CT wires (no lifting wires)
• Directly on the CT secondary terminals if accessible
• Otherwise on the CT shorting block terminals
• Virtually none of the injected current goes into the CT
• Inject varying magnitudes of current on the three phases
• Ex: 0.5, 1.0 and 1.5 amps into phases A, B and C
respectively
• Verify with receiving relays’ metering functions
Control circuitry
• VT secondary injection
• Isolate the VT winding from the secondary wiring
• Pull the VT secondary fuses
• Clip test set to the load side of the open fuse block
• Wye connected VTs
• Apply varying magnitude phase-neutral voltages
• Open delta connected VTs
• Apply varying magnitude phase-phase voltages
• Verify with the relays’ metering
• Check each device that receives
the VT signal
Control circuitry
• Primary injection less common than secondary injection
• Use a 3-phase generator (typically LV) to energize the
substation bus
• Apply loads on each circuit to cause current flow
• Check relays’ metering to assure functionally correct
• Magnitudes and angles
• Requires a thorough understanding of relay phasor angle
referencing
• Often subject to or controlled by relay settings
• Take care when interpreting the metered values to
assure correct phase identification
• DC control wiring electrically tested
while function testing the relay
Communication systems
• All communication systems need to be verified
• Used by protection system for protection
• Pilot channels, transfer trip, etc.
• Used for operation and control
• SCADA, voice, LANs, data remote access, etc.
• Typically not subject to PRC-005 requirements
• Point to point communications functionally verified and
documented
• Signal levels and data transfer rates
• SCADA remote control functions
• Verify perform as expected
Communication systems
• All communication systems need to be verified (cont.)
• SCADA remote control functions
• Verify perform as expected
• SCADA metering from standalone metering devices
(transducers, meters, etc.)
• Inject current and voltage device
• SCADA metering from relay memory registers
• Test as part of relay functional tests
Communication systems
• All communication systems need to be verified (cont.)
• Stand-alone communications for transfer trip and/or pilot
wire (power line carrier, audio or digital tone systems, etc.)
• Verify end-end functionality before protective relay
functional tests
• Digital relay communications used for transfer trip and/or
pilot wire
• Verify end-end functionality as part of relay functional
tests
Protective relays
• Relay acceptance testing
• Owner preferences
• Verify 100% of all included analog and digital I/O
• Even if not all the I/O are used
• Load Relay Settings
• Digital relays
• Setting files loaded into relays
• Vendor specific software tools
• Verify by comparing relay to setting file
• Should be no differences
• If differences resend or manually correct
• Save an image of the compare report showing no
differences
Protective relays
• Load Relay Settings (cont.)
• Non-digital relays
• Settings entered (adjusted) manually
• Verify with current and/or voltage injection
• Function testing
• Verify all enabled feature as a complete system
• Protection elements, metered values, logic,
communications and I/O
• Demonstrate system functions as designed
Protective relays
• Function testing (cont.)
• Automated testing programs are not suited for
commission function testing
• Inject current and voltage based on relay’s settings
• Not be able to detect setting errors
• Typos
• Bad system data
• Do not test programmed logic or specific I/O functions
• Used at end to establish a base-line testing report for
future maintenance
Protective relays
• Function testing (cont.)
• Use test values derived from system studies
• Not values calculated from relay settings
• Line protection test values from SC program
• Close-in reverse fault
• Close-in forward fault
• Mid-line or balance point
fault
• Remote end fault
• Run tests with the pilot communication system
operational
• Transformer protection
• Test values derived based on the transformer winding
connections and SC program
Protective relays
• Function testing (cont.)
• Programmed logic functional testing (including I/O)
• Inject current and voltage to operate protection
functions used in the logic
• Operate inputs to the relay that are used in the logic
• Verify outputs that are operated by the logic
• Verify DC circuitry correct to end device
• Auxiliary relays, lock-out relays, trip coils, etc.
• Logic diagram useful for complex logic
BUS 1 OP

BKR FAIL 1 RETRIP

1 1096TC#1/3PH (P1)
1096 TRIP (VO11) Operate I on
BKR FAIL 2 TRIP OP OR
OR I off
V on
Seal-In
1096TC#1/3PH IOn (P1) V off

BKR FAIL 3 TRIP OP

BKR FAIL 4 TRIP OP


Energizing procedures and in service
load checks
• Energizing procedures vary widely from owner to owner
• Common goal of energizing the equipment in a logical and
safe manner
• Associated protection systems in service
• In service load checks
• Phase identification
• Voltage readings taken after energization
• All voltage measuring devices
• Assure secondary levels and phase identification
are correct
• Challenging on a totally new power system
• References from existing facilities not available
Energizing procedures and in service
load checks
• In service load checks (cont.)
• Phase identification (cont.)
• Use end-end communication signal (ex: transfer trip)
• Temporarily trigger waveform capture reports in
relays
• At new substation and in remote existing
system
• Compare waveforms to assure correct phase
identification
• Phasor measurement unit (PMU) data
Energizing procedures and in service
load checks
• In service load checks (cont.)
• Phase identification (cont.)
• Cellular based phase checking systems
• Compare phase angle between remote and local
voltages
• Remove any temporary settings after test complete
• Examine metering of current measuring devices
• Assure correct ratios, phasing and phase shifts
Energizing procedures and in service
load checks
• In service load checks (cont.)
• Current based differential elements
• Examine differential and restraint quantities
• Differential quantity is near or equal to zero
• Restraint quantity is significant
• Requires a significant amount of load for reliable
results
• High impedance bus differential
• Examine operating quantity
• Voltage across or current through the resistor
• Measure current from each CT to verify ratios
• Record load check data for future comparison
Maintenance Testing
• Commission testing data is baseline for the life-cycle
maintenance
• Date of commissioning records define time 0 for PRC-005
• Current and voltage measuring device insulation failure
detected
• Battery and charger performance degradation observed
• Communication channel degradation flagged
• As-left relay settings are base-line for maintenance
• Changes must be researched and validated
• Automated testing program results remain consistent
Re-commissioning
• Re-commissioning required if significant changes are made
• Only re-commission aspects of system affected
• Physical equipment replacement
• Communication equipment
• CT/VT
• Battery or charger
• Relay
• Re-commission replaced equipment
Re-commissioning
• Re-commissioning required if significant changes are made
• Wiring changes
• Re-commission anything that might have reasonably
been affected
• Setting changes
• Re-commission those elements/systems affected
• Firmware upgrade that requires setting file conversion
• Complete relay re-commission
Case Study: Protection problems at
mine ID need to re-commission
switchgear
• New cubicles added to existing gear
• No commission testing performed on additions
• Trips during loading attempts
• Wiring errors discovered
• Missing settings discovered
• Similar problems found in existing cubicles
• No commissioning records found
• Safety concerns – workers no longer comfortable
• Re-commission entire line-up during next outage
Case Study: Modelling error discovered
during commissioning
• New replacement 115 kV line panel
• Test quantities for distance elements from SC program
• Ground distance zone 1 operated for remote bus fault
• Math check confirmed that test fault was within reach
• Zero-sequence line impedance error discovered in SC
program data base
• Caused wrong Z0/Z1 ratio
• Resulted in element over-reach
• Modelling error corrected and settings (Z0/Z1) changed
• New test values issued for 1LG faults
• Ground distance performed correctly
• Avoided future false trip
Case Study: Setting errors discovered
while commissioning replacement
generator protective relay
• New generator protection to replace existing obsolete relay
• Settings calculations based on previous relay’s settings
• Tech ran automated testing program
• Report indicated no errors
• Field Engineer and Tech performed commissioning tests
• Discovered logic and setting omissions
• Trip output for field breaker wired but not
programmed
• Bus ground detection voltage input wired
• No associated element enabled and set
• No output contact programmed or wired
Case Study: Verification of relaying
functions in relay using simulated
faults discovered firmware issues
• New replacement 115 kV line panel
• Test quantities for distance elements from SC program
• Phase distance failed to operated for 3LG faults
• Examination of SER data discovered that Loss of Potential
(LOP) was operating and blocking the elements
• No similar problems observed with other panels using
same relay models
• This terminal is weak-feed
• Voltage drops unusually low during 3LG faults
• LOP blocks even though memory voltage available for
correct distance element operation
• Waiting for a firmware fix from manufacturer
Conclusions
• Protection systems require testing to assure proper operation
• 3 separate stages of testing over protection system’s life
• Type testing
• Commission testing
• Life-cycle maintenance testing
• Commission testing is critical
• Assure safety
• Functional operation
• Equally critical in both utility and industrial systems
• Commission testing provides baseline data for maintenance
• Critical for utility installations subject to NERC PRC-005
• Commission and maintenance testing have different goals
and objectives
Thank You

Questions?

You might also like