Ufc 3 550 01
Ufc 3 550 01
Ufc 3 550 01
February 3, 2010
Including Change 1, July 1, 2012
UFC 3-550-01
February 3, 2010
Including Change 1, July 1, 2012
EXTERIOR ELECTRICAL POWER DISTRIBUTION
Any copyrighted material included in this UFC is identified at the point of use. Use of the
copyrighted material apart from this UFC must have the permission of the copyright
holder.
Date
01 Jul 2012
Location
Incorporates changes associated with the issuance of
UFC 3-575-01; NFPA 70 and IEEE C2 delineation;
grounding requirements and miscellaneous changes
throughout.
UFC 3-550-01
February 3, 2010
Including Change 1, July 1, 2012
FOREWORD
The Unified Facilities Criteria (UFC) system is prescribed by MIL-STD 3007 and provides The
Unified Facilities Criteria (UFC) system is prescribed by MIL-STD 3007 and provides planning,
design, construction, sustainment, restoration, and modernization criteria, and applies to the
Military Departments, the Defense Agencies, and the DoD Field Activities in accordance with
USD (AT&L) Memorandum dated 29 May 2002. UFC will be used for all DoD projects and work
for other customers where appropriate. All construction outside of the United States is also
governed by Status of forces Agreements (SOFA), Host Nation Funded Construction
Agreements (HNFA), and in some instances, Bilateral Infrastructure Agreements (BIA.)
Therefore, the acquisition team must ensure compliance with the more stringent of the UFC, the
SOFA, the HNFA, and the BIA, as applicable.
UFC are living documents and will be periodically reviewed, updated, and made available to
users as part of the Services responsibility for providing technical criteria for military
construction. Headquarters, U.S. Army Corps of Engineers (HQUSACE), Naval Facilities
Engineering Command (NAVFAC), and Air Force Civil Engineer Support Agency (AFCESA) are
responsible for administration of the UFC system. Defense agencies should contact the
preparing service for document interpretation and improvements. Technical content of UFC is
the responsibility of the cognizant DoD working group. Recommended changes with supporting
rationale should be sent to the respective service proponent office by the following electronic
form: Criteria Change Request (CCR). The form is also accessible from the Internet sites listed
below.
UFC are effective upon issuance and are distributed only in electronic media from the following
source:
Whole Building Design Guide web site http://www.wbdg.org/.
Hard copies of UFC printed from electronic media should be checked against the current
electronic version prior to use to ensure that they are current.
______________________________________
JAMES C. DALTON, P.E.
Chief, Engineering and Construction
U.S. Army Corps of Engineers
______________________________________
JOSEPH E. GOTT, P.E.
Chief Engineer
Naval Facilities Engineering Command
______________________________________
DENNIS FIRMAN
Director of the Air Force Center for Engineering
and the Environment
Department of the Air Force
______________________________________
MICHAEL McANDREW
Director, Facility Investment and
Management
Office of the Deputy Under Secretary of Defense
(Installations and Environment)
UFC 3-550-01
February 3, 2010
Including Change 1, July 1, 2012
UNIFIED FACILITIES CRITERIA (UFC)
NEW DOCUMENT SUMMARY SHEET
Document: 3-550-01, Exterior Electrical Power Distribution
Superseding:
Description: This UFC 3-550-01 provides design guidance for the design of exterior
distribution systems.
Reasons for Document:
Impact: There are negligible cost impacts associated with this UFC. However, the
following benefits should be realized.
UFC 3-550-01
February 3, 2010
Including Change 1, July 1, 2012
CONTENTS
Page
CHAPTER 1 GENERAL .................................................................................................. 1
1-1
1-2
1-3
1-4
1-5
1-6
PURPOSE. ....................................................................................................... 1
APPLICABILITY. ............................................................................................... 1
GENERAL BUILDING REQUIREMENTS. ........................................................ 2
CRITERIA AND EXEMPTION WAIVER PROCESS. ........................................ 2
REFERENCES. ................................................................................................ 2
UTILITY-OWNED AND OPERATED DISTRIBUTION SYSTEMS ON
FEDERAL PROPERTY. .................................................................................... 2
UFC 3-550-01
February 3, 2010
Including Change 1, July 1, 2012
3-11.1 Underground Distribution General Criteria. .............................................. 14
3-11.2 Ductbanks. ............................................................................................... 15
3-11.3 Direct Buried Wiring Methods. ................................................................. 16
3-11.4 Directional Boring. ................................................................................... 18
3-11.5 Underground Structures (Manholes and Handholes). .............................. 19
3-11.6 Locating Underground Structures. ........................................................... 20
3-11.7 Pull Boxes. ............................................................................................... 20
3-11.8 Medium Voltage Cable............................................................................. 20
3-12 CONCRETE FOR UNDERGROUND ELECTRICAL SYSTEMS..................... 21
3-13 HOUSING DISTRIBUTION. ............................................................................ 21
3-14 DISTRIBUTION SYSTEM GROUNDING. ....................................................... 22
3-14.1 Main Electric Supply Station .................................................................... 22
3-14.2 Utilization Electric Supply Station ............................................................ 22
3-14.3 Separation of Grounding Conductors....................................................... 22
3-14.4 Materials and Special Requirements ....................................................... 23
3-14.5 Low Voltage Grounding Interface With Utilization Electric
Supply Stations ........................................................................................ 23
3-14.6 Grounding Requirements Fences ......................................................... 24
3-15 METERING. .................................................................................................... 24
3-16 EXTERIOR SITE LIGHTING. .......................................................................... 24
3-17 CATHODIC PROTECTION SYSTEMS. .......................................................... 24
3-18 ENVIRONMENTAL CONSIDERATIONS. ....................................................... 24
3-19 FIRE PROTECTION CONSIDERATIONS. ..................................................... 25
GLOSSARY .................................................................................................................. 26
APPENDIX A REFERENCES ....................................................................................... 29
APPENDIX B DIRECTIONAL BORING......................................................................... 32
B-1
B-2
B-3
FIGURES
Figure B-1. HDPE or Rigid Conduit Electrical Equipment Transition ............................. 34
Figure B-2. Pavement Covered Area to Electrical Equipment Transition
Rigid Conduit (4590) .......................................................................................... 35
Figure B-3. Pavement Covered Area to Electrical Equipment Transition
HDPE Conduit (2045) ........................................................................................ 36
Figure B-4. Non-Pavement Covered Area to Electrical Equipment Transition
Rigid Conduit (4590) .......................................................................................... 37
ii
UFC 3-550-01
February 3, 2010
Including Change 1, July 1, 2012
Figure B-5. Non-Pavement Covered Area to Electrical Equipment Transition
HDPE Conduit (2045) ........................................................................................ 38
Figure B-6. HDPE-to-PVC Pavement Covered Area Concrete Ductbank
Transition ............................................................................................................... 40
Figure B-7. HDPE-to-PVC Non-Pavement Covered Area Concrete Ductbank
Transition ............................................................................................................... 41
Figure B-8. HDPE-to-Manhole Pavement Covered Area Transition .............................. 42
Figure B-9. HDPE-to-Manhole Pavement Covered Area Transition .............................. 43
iii
UFC 3-550-01
February 3, 2010
Including Change 1, July 1, 2012
CHAPTER 1 GENERAL
1-1
PURPOSE.
This UFC provides policy and guidance for design criteria and standards for electrical
power and distribution systems.
The information provided here must be utilized by electrical engineers in the
development of the plans, specifications, calculations, and Design/Build Request for
Proposals (RFP) and must serve as the minimum electrical design requirements. It is
applicable to the traditional electrical services customary for Design-Bid-Build
construction contracts and for Design-Build construction contracts. Project conditions
may dictate the need for a design that exceeds these minimum requirements.
UFC 3-501-01 provides the governing criteria for electrical systems, explains the
delineation between the different electrical-related UFCs, and refers to UFC 3-550-01
for exterior electrical system requirements. Refer to UFC 3-501-01 for design analysis,
calculation, and drawing requirements.
Onsite generation is not addressed by this UFC.
1-2
APPLICABILITY.
The design criteria and standards contained within are the minimum requirements
acceptable for military installations for efficiency, economy, durability, maintainability,
and reliability of electrical power supply and distribution systems. The criteria and
standards herein are not intended to be retroactively mandatory.
Comply with the requirements of NFPA 70 and IEEE C2. Generally, IEEE C2 is the
basis for UFC 3-550-01 and NFPA 70 is the basis for UFC 3-520-01. However, there
are exceptions to which standard applies to each UFC, including:
Systems covered by other UFCs, such as airfield lighting and shore power
systems.
Comply with UFC 3-560-01 for electrical safety requirements applicable to the
installation and operation of electrical systems.
Comply with UFC 4-010-01 and UFC 4-020-01 for security requirements related to
exterior electrical distribution systems.
Codes and standards are referenced throughout this UFC. The publication date of the
code or standard is not routinely included with the document identification throughout
the text of the document. In general, the latest issuance of a code or standard has been
1
UFC 3-550-01
February 3, 2010
Including Change 1, July 1, 2012
assumed for use. Refer to Appendix A to determine the publication date of the codes
and standards referenced in this UFC.
\1\
1-3
GENERAL BUILDING REQUIREMENTS.
UFC 1-200-01, "General Building Requirements", provides applicability of model
building codes and government-unique criteria for typical design disciplines and building
systems, as well as for accessibility, antiterrorism, security, sustainability, and safety.
Use this UFC in addition to UFC 1-200-01 and the UFCs and government criteria
referenced therein.
1-4
UFC 3-550-01
February 3, 2010
Including Change 1, July 1, 2012
CHAPTER 2 ELECTRICAL POWER REQUIREMENTS
2-1
Virtually all military bases have an existing overhead and underground distribution
system that has been in service for many years. As part of any new design project,
review the existing design with base personnel to determine which existing features
should not be duplicated in future designs. Address design preferences with
responsible engineering and operations personnel as part of the system design
analysis.
2-2
NEMA C84.1 establishes typical voltages and voltage ranges for 60 Hz systems.
Facilities located outside of the United States must also comply with the applicable host
nation standards; refer to UFC 3-510-01 for additional information.
2-3
UFC 3-550-01
February 3, 2010
Including Change 1, July 1, 2012
CHAPTER 3 DESIGN CRITERIA
\1\
3-1
All main and electric supply stations/substations shall conform to the requirements of
IEEE C2 Part 1, Rules for the Installation and Maintenance of Electric Supply Stations
and Equipment, as follows:
3-1.1
Electric Supply Stations shall be defined as stations that transform the energy
level (voltage) for further bulk distribution at medium voltage levels.
The main electric supply station is the installation/utility interface point where further
transmission, distribution and utilization of electrical power, the monitoring and control of
such power or equipment and the protection of electrical equipment or systems usually
becomes the sole responsibility of the Government or their contracted representatives.
Coordinate the design of new stations, or modifications to existing stations with the
supplying utility and with any other suppliers or users of power supplied through the
station.
3-1.2
Utilization Electric Supply Stations are defined as equipment such as pole or padmounted transformers or secondary unit substations that transforms the energy level
(voltage) to a utilization voltage for consumer use. Some examples of Utilization
Electric Supply Stations are station service transformers (serving low voltage equipment
in a Main Electric Supply Station), a lighting transformer (serving equipment for a
roadway lighting system), a pole or pad-mounted transformer (serving a building), or a
secondary unit substation (serving piers and wharfs electrical systems).
3-2
Overhead facilities shall conform to the requirements of IEEE C2 Part 2, Safety Rules
for the Installation and Maintenance of Overhead Electric Supply and Communication
Lines.
Underground facilities shall conform to the requirements of IEEE C2 Part 3, Safety
Rules for the Installation and Maintenance of Underground Electric Supply and
Communication Lines.
UFC 3-550-01
February 3, 2010
Including Change 1, July 1, 2012
Refer to UFC 3-560-01 Section 1-4.1.1 for arc-flash criteria and the delineation points
between IEEE C2 and NFPA 70E conformance requirements.
Design new primary distribution systems as four wire, multi-grounded systems that are
wye connected at the source transformer. Provide a system grounded neutral
conductor throughout the system. The neutral shall be bare conductor for overhead
systems.
Note: For the Navy, the neutral shall be 600 volt insulated conductor for pole riser and
underground systems.
When a project is limited to connecting to an existing three wire system and the primary
electrical characteristics are established and defined, continuation of the existing
system shall be permitted with the following requirements:
For extensions from underground structures, provide a four wire extension. Bond
the grounded neutral conductor at each end of the extension to the applicable
grounding electrode systems.
For extensions from overhead pole lines, provide a four wire extension. Bond the
grounded neutral conductor at each end of the extension to the applicable
grounding electrode systems.
Note: Design of the extensions as four wire systems does not change any circuit
classifications. It provides an extended grounding electrode system to facilitate any
future circuit conversions to four wire systems.
Provide equipment foundation pads and ensure a minimum of 10 ft (3 m) clear
workspace in front of pad-mounted equipment for hot stick work. Orient equipment so
that adjacent equipment will not interfere with the clear workspace. Provide bollards in
areas where equipment is subject to vehicular damage.
Refer to Appendix C for general electrical system criteria. /1/
3-3
IEEE C37.46, High Voltage Expulsion and Current-Limiting Type Power Class
Fuses and Fuse Disconnection Switches.
UFC 3-550-01
February 3, 2010
Including Change 1, July 1, 2012
3-4
Provide secondary unit substations when secondary currents exceed 3,000 amperes.
Secondary unit substations shall comply with the following industry standards as
applicable for the specified configuration:
UFC 3-550-01
February 3, 2010
Including Change 1, July 1, 2012
3-5
3-5.1
Reference Criteria.
3-5.2
IEEE C57.12.34, Pad-Mounted, Compartmental-Type, Self-Cooled, ThreePhase Distribution Transformers (2500 kVA and Smaller) High-Voltage,
34,500 GrdY/19,200 Volts and Below; Low-Voltage: 480 Volts and Below.
IEEE C57.12.22, Transformers Pad-Mounted, Compartmental-Type, SelfCooled, Three-Phase Distribution Transformers with High-Voltage Bushings,
2500 kVA and Smaller: High Voltage, 34,500 Grd Y/19,920 Volts and Below;
Low Voltage, 480 Volts and Below.
Configuration.
Use dead-front construction for pad-mounted transformers unless not available within
system parameters. Use pad-mounted transformers, separately protected with vacuum
fault interrupter equipped switches for 34.5 kV systems.
Do not use pad-mounted transformers with secondary currents exceeding 3,000
amperes because of the size and quantity of secondary conductors. Transformers
rated above 1,000 kVA serving 208Y/120 volt loads and above 2,500 kVA serving
480Y/277 volt loads must be in a secondary unit substation configuration.
Minimize double transformations to reduce energy consumption and to minimize items
of equipment. Provide two oil-filled pad-mounted transformers in lieu of one 480Y/277
volt service if the required 208Y/120 volt load using dry-type transformers exceeds 40
7
UFC 3-550-01
February 3, 2010
Including Change 1, July 1, 2012
percent of the 480 volt service transformer capability. Connect equipment at the highest
available voltage to minimize the capital cost and energy losses of transformation
equipment.
Three-phase pad-mounted transformers must be loop-feed capable with 6 bushings.
Provide two-position, oil-immersed, load break switches that are appropriate for the
application. If the transformer might be used as part of a loop-feed design, provide
three switches to permit closed transition loop feed and sectionalizing. If the
transformer will be installed at the end of a radial supply with no intention of future loop
feed capability, provide a single on-off switch. Provide a spare conduit in the high
voltage section extending 5 ft (1.5 m) out from the transformer pad.
3-5.3
Transformer Connections.
Surge Protection.
Provide bushing-mounted elbow type arresters at the ends of all radials and in normally
open locations in loops. Provide arresters for all voltage levels above 5 kV.
3-5.5
Drawing Details.
3-6.1
Metal-Clad Switchgear.
Metal-clad switchgear can include either SF6 or vacuum style breakers and must
consist of a single section or multiple section line-up of NEMA 1 or NEMA 3R
enclosures. Either walk-in or non-walk-in construction can be provided. Medium
voltage metal-clad switchgear can be provided as unit substation construction or as
stand-alone switchgear. The sections must contain the breakers and the necessary
accessory components. The equipment must be factory-assembled (except for
necessary shipping splits) and be operationally checked before shipment. Consider
remote racking device designs (robots) to rack breakers in and out.
8
UFC 3-550-01
February 3, 2010
Including Change 1, July 1, 2012
Metal clad switchgear shall comply with the following industry standards:
IEEE C37.90, Relays and Relay Systems Associated with Electric Power
Apparatus.
Provide batteries for dc opening and closing of circuit breakers. Do not use ac or
capacitor control methods.
3-6.2
Metal-Enclosed Switchgear.
Do not use metal-enclosed switchgear. Instead, use either a vacuum fault interrupter
(VFI) in a unit substation configuration or an upstream pad-mounted switchgear.
3-7
\1\ For the Navy, utilize multi-way pad-mounted switchgear when switching, isolation, or
electrical protection is required. Specify SF6 gas or high fire point liquid (nontemperature dependent) insulation technology and vacuum bottle interruption
technology. Specify dead front construction with stainless steel tanks and operator full
size viewing windows for each switching way. Specify three position (On/Off/Ground)
switch ways for all new construction. For switch replacements when existing switching
arrangement is On/Off/Tie, a similar arrangement without ground position is permissible.
Specify switch design which incorporates operating handles on the opposite side of the
tank from the cable entrance bushings, terminations and cables. Specify 600 ampere
dead break connectors with 200 ampere interface bushings for each switch way. Air
Insulated (fused or non-fused) technology is not permitted. Pad-mount switchgear shall
comply with the following industry standards: /1/
UFC 3-550-01
February 3, 2010
Including Change 1, July 1, 2012
For the Army and Air Force, \1\ air-insulated and fused switches can be used in either a
live-front or dead-front configuration. Do not use air-insulated switches in corrosive
/1/and high humidity areas as defined in UFC 3-501-01 unless the installation
experience for the installed location confirms that switch corrosion and tracking is not a
problem.
3-8
CAPACITORS.
Do not use capacitors unless they are needed for power factor correction or to minimize
line losses. Verify the need by a system analysis; the analysis must consider the
potential adverse effects of transients caused by capacitor switching. Refer to TSEWG
TP-2: Capacitors for Power Factor Correction, at
http://www.wbdg.org/ccb/browse_cat.php?o=29&c=248 for additional information if
power factor correction is considered.
Underground distribution has more capacitance than equivalent overhead distribution.
When converting from overhead distribution to underground distribution, provide padmounted capacitors on a distribution system only if supported by the design analysis.
Do not automatically replace existing pole-mounted capacitors with equivalent padmounted capacitors.
For safety purposes, include an oil switch disconnect with pole-mounted capacitors.
3-10
\1\ Design overhead lines to IEEE C2 Grade B construction complying with the
following:
a. Limit the initial loaded conductor tension to a maximum of 50% of the conductor
rated breaking strength. Lesser tensions are usually applicable and generally
more preferred. Utility distribution line design is generally in the range of 25% to
35% of the rated breaking strength.
b. Provide clearance requirements using final sag values in conformance with IEEE
C2 Part 2.
c. Limit the maximum design tensions for any conductors to 4,750 pounds (2,154
kg). All clearance values shall be based on the following maximum conductor
10
UFC 3-550-01
February 3, 2010
Including Change 1, July 1, 2012
temperatures.
Neutral conductors for multi-phase circuits 120 degrees F (49 degrees C).
/1/
Match the existing base construction methods. Match those construction methods used
by the local utility when directed. Where new overhead distribution is required, route
the overhead distribution along roadways and other major topographical features; the
poles must be accessible for future maintenance or work. Coordinate pole locations
with land-use planning to ensure that new poles do not interfere with future facility
plans. \1\ /1/
Use NAVFAC pole details OH-1.1 through OH-41 whenever applicable. NAVFAC pole
details are available in Adobe PDF format and in AutoCAD format
http://www.wbdg.org/ccb/NAVGRAPH/graphtoc.pdf. In situations where an applicable
pole detail has not been developed, provide new detail drawings as required. Designer
developed details shall contain a level of detail equivalent to NAVFAC pole details and
include material requirements. Refer to UFC 3-501-01 for additional pole detail
requirements.
3-10.1
Pole Types.
Use solid wood poles for electric distribution lines; concrete and steel poles can be used
for roadway or area lighting circuits carried underground or separately from distribution
lines. Concrete or steel poles may be justified for medium-voltage distribution circuits
where wood poles do not provide adequate strength, or where climatic conditions cause
wood poles to deteriorate rapidly. Do not use laminated wood poles for electric
distribution lines.
3-10.2
Conductors.
\1\ Due to the increasing technology improvements with aluminum conductors and
connectors, and the economic disadvantage of providing copper conductors, provide
aluminum conductor steel reinforced (ACSR) or aluminum alloys for new overhead lines
and extensions of existing lines. Except for grounding systems, the use of copper
conductors is prohibited without specific approval and documentation by the applicable
local engineering authority. Do not use ACSR conductors in corrosive and high
humidity areas. For corrosive and high humidity areas, provide Type ACSS conductors.
For the Navy, the Facilities Engineering Command (FEC) organizations chief engineer
shall have the authority to use copper product for their applicable jurisdiction. Provide
11
UFC 3-550-01
February 3, 2010
Including Change 1, July 1, 2012
documented correspondence, that supports this decision, to the technical criteria office
(NAVFAC LANT CI47) responsible for issuing subject criteria.
For the Army, the Installation Department of Public Works Chief Engineer shall have the
authority to use copper product for their applicable jurisdiction if documented in the
planning process and the design analysis.
For the Air Force, the Base Civil Engineer shall have the authority to exercise the
criteria option of copper product for their applicable jurisdiction if documented in the
planning process and the design analysis. /1/
3-10.3
Pole-Mounted Transformers.
\1\ Provide pad-mounted transformers rather than pole-mounted transformers for new
three-phase installations larger than 75 kVA.
Use only single phase transformers for pole-mounted installations. For single phase
installations and when banking single phase transformers for three phase applications,
apply phase-to-neutral primary connections unless installed on three wire distribution
systems.
Limit pole-mounted transformer sizes (except for projects involving system conversions
to a different operating voltage) as follows:
Pole top switches are installed at important system locations to allow either isolation of
the downstream circuit or cross-connection to a different circuit. Where ground
operated, gang type, three phase, air break switches are used with non-insulated
operator handles, provide a metal plate or grate at ground level for the operator to stand
on when operating the switch. Connect the metal plate or grate to the pole ground
conductor as well as through a braided conductor connection to the switch handle
mechanism. Include a provision for locking ground accessible switch handles in the
open and closed position.
12
UFC 3-550-01
February 3, 2010
Including Change 1, July 1, 2012
Single-pole knife blade switches and copper barrels inside distribution cutouts are only
acceptable for use in locations where frequent switching is not expected.
3-10.5
Surge Arresters.
3-10.6
Fuse Protection.
Provide IEEE C37.41 rated backup current limiting fuses in series with Type K expulsion
fuses on systems that are:
15 kV and lower that have available fault currents equal to or greater than
7,000 asymmetrical amperes.
Note: Existing systems should continue to use the expulsion fuse link type that
represents the standard for that system.
3-10.7
Grounding Connections.
Keep ground wires straight and short. Minimize bends in all ground connections.
13
UFC 3-550-01
February 3, 2010
Including Change 1, July 1, 2012
3-11
3-11.1
In areas where storm and hurricane damage can damage \1\ /1/overhead
distribution.
\1\ Due to the increasing technology improvements with aluminum conductors and
connectors and the economic disadvantage of providing copper conductors, provide
aluminum conductors for new underground lines and extensions of existing lines. This
includes all new medium voltage system designs that do not require interface (splicing
copper to aluminum in underground structures) with existing copper infrastructure.
Grounding electrode systems shall always be copper.
The use of copper conductors is authorized for extensions of existing systems in which
the use of aluminum results in technical limitations, such as:
Conduit size. All phases are required to be installed in the same conduit.
14
UFC 3-550-01
February 3, 2010
Including Change 1, July 1, 2012
For the Navy, the Facilities Engineering Command (FEC) organizations chief engineer
shall also have the authority to use copper product for applications within their
applicable jurisdiction, in addition to the above authorized use for extensions. In this
case, provide documented correspondence, that supports this decision, to the technical
criteria office (NAVFAC LANT CI47) responsible for issuing subject criteria.
For the Army, the Installation Department of Public Works Chief Engineer shall also
have the authority to use copper product, in addition to the above authorized use for
extensions, within their applicable jurisdiction if documented in the planning process and
the design analysis.
For the Air Force, the Base Civil Engineer shall also have the authority to exercise the
criteria option of copper product, in addition to the above authorized use for extensions,
within their applicable jurisdiction if documented in the planning process and the design
analysis. /1/
Do not route primary underground utilities under buildings. Systems greater than 600
volts shall also not be routed under buildings except as a direct service entrance to a
single interior transformer.
Tag all underground cables in all accessible locations such as in manholes,
transformers, switches and switchgear. Install a detectable locator tape above all
buried underground circuits. Marking must meet the base utility standards.
3-11.2
Ductbanks.
The definition of the terms ductbank, conduit, and duct are often confused. Within this
UFC, a ductbank consists of two or more conduits (or ducts) routed together in a
common excavation with or without concrete encasement. Refer to paragraph \1\ 311.4 /1/ for criteria applicable to directional boring.
3-11.2.1 Conduit Size.
Minimum conduit sizes must be as follows:
15
UFC 3-550-01
February 3, 2010
Including Change 1, July 1, 2012
not apply to street lighting circuits, housing service drops, or secondary
circuits originating from an interior panel. /1/
3-11.2.2 Installation.
Use Schedule 40 PVC conduit (minimum thickness) for conduits that are not
installed in concrete encasement.
Provide spare conduits such that at least 1/3 of the ductbank contains empty
conduits.
Include pull wires (pull string or pull rope) in all spare ducts.
3-11.3
For permafrost locations, use ductbank installation methods that are the
standard for the base, post, or local utility.
Direct Buried Wiring Methods.
The term direct buried wiring refers to the direct burial of conductors without any conduit
or concrete encasement. \1\
16
UFC 3-550-01
February 3, 2010
Including Change 1, July 1, 2012
3-11.3.1 Army and Air Force Criteria.
Direct buried wiring for medium voltage systems is not allowed.
Direct buried wiring for low voltage systems from the distribution transformer to the
facility service entrance is not allowed.
Direct buried wiring for low voltage systems is acceptable in large open areas only, such
as ranges or outlying training areas.
Sleeve all direct buried conductors under existing roads, paved areas and railroad
tracks. Use galvanized rigid steel conduit.
Sleeve all direct buried conductors under new roads and use concrete encased
conduits extending 5 ft (1.5 m) beyond the edge of the pavement. Use galvanized rigid
steel or minimum Schedule 40 PVC conduit.
3-11.3.2 Navy Criteria.
Direct buried wiring methods for low or medium voltage systems may be allowed for
certain applications. as follows: All applications must be submitted by the using the
criteria and exemption waiver process (Paragraph 1-4) and supported with the required
documented justification during the planning process of subject design project. Any
application which constitutes a part of the facility core distribution infrastructure will not
be authorized.
All direct burial systems shall meet ANSI C2 requirements for multi-grounded systems
and shall be energized at a maximum nominal system voltage of 34.5 kV.
All approved direct burial medium voltage systems shall be allowed to utilize standard
concentric neutral cable design instead of the typical power cable design utilizing a
separate 600 insulated volt neutral conductor.
Direct buried systems shall also provide a spare conduit system with associated
enclosures under all streets, roads, and parking areas to provide for future maintenance
capability without having to disrupt pavements. Provide minimum Schedule 40 PVC
extending 5 feet on each side and capped for future use.
For crossing existing paved areas, the direct boring (DB) technology referenced in
Section 3-11.4 shall apply for installation of the direct buried system.
The following are examples of applications that merit consideration:
UFC 3-550-01
February 3, 2010
Including Change 1, July 1, 2012
Bulk power transfer (feeder) from point to point crossing remote or controlled real
estate which will revert to public utility ownership and maintenance upon
completion. /1/
3-11.4
Directional Boring.
Roads.
Parking lots.
Bodies of water.
3-11.4.2 Limitations.
DB is applicable to medium-voltage (HV) underground distribution systems between
1000 volts (V) and 34.5 kilovolts (kV) (nominal) and all low-voltage distribution systems
(less than 1000 V). It is not applicable to airfield lighting circuits.
Use of DB techniques to install electrical conduit distribution for voltages greater than
34.5 kV (nominal) is prohibited.
Refer to Appendix B regarding depth of DB. The depth can be less if a detailed survey
is performed and documented before starting boring.
18
UFC 3-550-01
February 3, 2010
Including Change 1, July 1, 2012
3-11.5
Load junctions.
For the Air Force, T-splices and Y-splices on medium voltage systems rated
for less than 15 kV.
Design covers for 100,000 lb (45,000 kg) wheel loads with 250 psi (1.72 MPa)
tire pressure.
For spans of less than 2 ft (0.6 m) in the least direction, use a uniform live
load of 325 psi (2.24 MPa).
For spans of 2 ft (0.6 m) or greater in the least direction, the design must be
based on the number of wheels which will fit the span. Use wheel loads of
75,000 lb (34,000 kg) each.
Note: For the Air Force, do not install electrical manholes in aprons. Maintain a
distance of 50 ft (15 m) from the edge of paving, 50 ft (15 m) from any hydrant lateral
control pit, and 200 ft (60 m) from a fueling point for all manholes.
19
UFC 3-550-01
February 3, 2010
Including Change 1, July 1, 2012
Determine the size of power manholes by the number of circuits, voltage ratings and
splicing requirements of the cables within. Manholes shall be a minimum 2 m (6.5 ft)
deep. Provide cable racks in all new manholes. When reworking cables in existing
manholes, provide racks for new cables. Route cable installations inside manholes
along those walls providing the longest route and the maximum spare cable lengths.
For circuits rated above 15 kV, manholes shall be a minimum of 9 ft by 12 ft (2.8 m by
3.7 m) in interior size.
Size communications manholes for equipment and splices contained, including future
projections. Manholes must accommodate racking of splice closure of largest multi-pair
cable while keeping cable bending radii greater than 10 times cable diameter.
Provide manhole foldout details or exploded views for all multiple-circuit primary
systems and all primary systems requiring splices. Indicate the entrance of all conduits
and the routing of all conductors in the manholes. Manhole details are available in
Adobe PDF format at http://www.wbdg.org/ccb/NAVGRAPH/graphtoc.pdf and in
AutoCAD format at http://www.wbdg.org/ccb/browse_cat.php?o=78&c=232.
3-11.6
Provide where splices are required, where duct lines change direction, and within 100 ft
(30 m) of every riser pole, pad mounted transformer, or unit substation unless a
calculation is provided to justify a greater distance. The distance must not exceed 200
ft (60 m).
Separation on straight runs must not exceed 400 ft (120 m). In situations where greater
separation is desired and this greater separation is not prohibited by either excessive
pulling tension or site requirements, separation of up to 600 ft (180 m) is permitted.
3-11.7
Pull Boxes.
Pull boxes are used for electric circuits supplying low-voltage electric loads which
require conductors no larger than 1/0 awg and no more than one 2-inch (52 mm)
conduit entrance at each side. Wherever larger conduits are installed, use handholes or
manholes. Do not use pull boxes in areas subject to vehicular traffic.
3-11.8
\1\ Medium voltage cables shall comply with NEMA WC 74, be type MV (105C)
aluminum or copper based on the specific applications as defined in Para. 3-11.1, and
shall contain a 600 volt insulated neutral when required. For the Army and Air Force,
concentric neutral conductors are also authorized.
Cables shall meet the following criteria:
UFC 3-550-01
February 3, 2010
Including Change 1, July 1, 2012
Insulation Type Provide ethylene propylene rubber (EPR). For the Army
and Air Force, cross-linked polyethylene is also authorized. Do not use paper
insulated lead covered (PILC) for new installations.
Insulation Level The insulation level for all circuits classified as multigrounded (4 wire systems throughout the entire circuit) shall be 100%
minimum. Insulation level for all other classification of circuits shall be 133%.
3-12
Concrete for encasement of underground ducts must be 3000 psi (20 MPa), minimum
28-day compressive strength. Concrete associated with electrical work for other than
encasement of underground ducts must be 4000 psi (30 MPa), minimum 28-day
compressive strength unless specified otherwise.
3-13
HOUSING DISTRIBUTION.
The following requirements shall be met for electrical distribution to housing units:
Design the distribution system such that the available fault current at the
service equipment is less than 10,000 amperes.
21
UFC 3-550-01
February 3, 2010
Including Change 1, July 1, 2012
Where an underground 3-phase circuit is used to feed single-phase transformers,
provide a separate 3-phase pad-mounted switch or sectionalizing cabinet with a radial
supply to the single-phase transformers.
3-14
\1\ Distribution system grounding (medium voltage systems classified as multigrounded, single point grounded at source transformer either solidly or with grounding
resistors, and ungrounded) shall comply with the requirements of IEEE C2 Section 9
entitled Grounding Methods for Electric Supply and Communication Facilities.
3-14.1
Main electric supply stations and all supply stations consisting of equipment for the
purpose of transforming the voltage level for further bulk distribution shall be designed
in conformance with IEEE Standard 80. The station grounding system shall require
measurement prior to inter-connection with other systems and prior to station
energization to assure the limits of step and touch potentials as required by IEEE
Standard 80 have been attained.
3-14.2
A Utilization Electric Supply Station is defined as any station where the medium voltage
system transforms the energy level (voltage) to utilization for consumer use on any kind
of facility. Examples of some utilization electric supply stations are roadway lighting
transformers, a building pad-mounted transformer, or a pier or wharf secondary unit
substation.
3-14.3
22
UFC 3-550-01
February 3, 2010
Including Change 1, July 1, 2012
3-14.4
The service point for low-voltage conductors from utilization electric supply
stations containing no secondary overcurrent protection device shall be
defined as the line side terminals for the facility service equipment.
23
UFC 3-550-01
February 3, 2010
Including Change 1, July 1, 2012
3-14.6
Metal fences for electrical equipment and ordnance facilities shall be grounded in
accordance with IEEE C2 Section 9.
Other metal fences that are electrically continuous with metal posts extending at least
24 inches (610 mm) into the ground require no additional grounding unless specifically
required by other criteria.
For Army and Air Force, ground all metal fences at or near points crossed by overhead
power lines in excess of 600 volts and also at distances of 150 ft (46 m) on each side of
the line crossing.
Where plastic coated fabric is used, remove plastic coating where it overlaps the post to
be grounded and braze or bolt conductor to post.
/1/
3-15
METERING.
Supply housing units with meter sockets only. Sockets must be single phase, four
terminal, and ring-less with manual bypass device and polycarbonate blank cover plate.
For all other services, provide electronic programmable watt-hour meters with solidstate demand registers. Include necessary KYZ initiation hardware for Energy
Management and Control System (EMCS) coordinated with the mechanical Direct
Digital Control System (DDC). Locate watt-hour meters directly on pad mounted
transformers or integral to unit substations.
3-16
Provide cathodic protection in accordance with UFC 3-570-02N for the Navy and UFC
3-570-02A for the Army.
3-18
ENVIRONMENTAL CONSIDERATIONS.
24
UFC 3-550-01
February 3, 2010
Including Change 1, July 1, 2012
Do not use askarel-insulated and nonflammable, fluid-insulated transformers because of
environmental concerns as to their insulation liquid.
3-19
Provide fire protection and specify installation location for oil-filled equipment in
accordance with UFC 3-600-01.
Oil-filled transformers using mineral oil can only be used outdoors. Less-flammable
liquid transformers may be used either outdoors or indoors; these liquids shall have a
fire point of not less than 300 degrees C (575 degrees F).
25
UFC 3-550-01
February 3, 2010
Including Change 1, July 1, 2012
GLOSSARY
Acronyms and Abbreviations
AC
ACSR
\1\ACSS
A/E
AFCESA
AHJ
AL
ASTM
AWG
UFC
BCE
BIL
CT
CU
DB
DDC
DIA
DoD
EMCS
\1\ ESS
Degrees F
fc
ft
ft2
GPS
HDPE
HQUSACE
HV
HVAC
Hz
IEEE
in
kcmil
kg
kV
kVA
kVAR
lb
LTC
m
m2
Max
Min
Alternating Current
Aluminum Conductor Steel-Reinforced
Aluminum Conductor Steel Supported /1/
Architect/Engineer
Air Force Civil Engineer Support Agency
Authority Having Jurisdiction
Aluminum
American Society for Testing and Materials
American Wire Gauge
Unified Facilities Criteria
Base Civil Engineer
Basic Insulation Level
Current Transformer
Copper
Directional Boring
Direct Digital Control
Diameter
Department of Defense
Energy Management and Control System
Electric Supply Station /1/
Degrees Fahrenheit
Footcandles
Feet (or Foot)
Foot Squared
Global Positioning System
High Density Polyethylene Electrical
Headquarters, US Army Corps of Engineers
High Voltage
Heating Ventilation and Air Conditioning
Hertz
formerly Institute of Electrical and Electronic Engineers
Inch
Thousand circular mils
Kilograms
Kilovolts
Kilo-Volt-Ampere
Kilo-Volt-Ampere-Reactive
Pound
Load-Tap Changing
Meter
Meter Squared
Maximum
Minimum
26
UFC 3-550-01
February 3, 2010
Including Change 1, July 1, 2012
mm
MPa
MTS
MVA
NAVFAC
NEC
NEMA
NETA
NFPA
OH
O&M
PE
psi
PILC
PPE
PT
PVC
RFP
SCADA
SF6
TSEWG
\1\ UESS
UL
UFC
V
VA
VFI
W/ft2
W/m2
Millimeter
Mega-Pascals
Maintenance Testing Specifications
Mega-Volt-Ampere
Naval Facilities Engineering Command
National Electrical Code
National Electrical Manufacturers Association
InterNational Electrical Testing Association
National Fire Protection Association
Overhead
Operation and Maintenance
Professional Engineer
Pounds per square inch
Paper Insulated Lead Covered
Personal Protective Clothing
Potential Transformer
Polyvinyl Chloride
Request for Proposal
System Control and Data Acquisition
Sodium Hexafluoride
Tri-Service Electrical Working Group
Utilization Electric Supply Station /1/
Underwriters Laboratories
Unified Facilities Criteria
Volt
Volt-Amp
Vacuum Fault Interrupter
Watts per Foot Squared
Watts per Meter Squared
Terms
Activity The end user of a facility.
\1\
Contractor Person(s) doing actual construction portion of a project.
Corrosive Area An area identified by the Technical Reviewing Authority as requiring
special equipment corrosion mitigation methods.
/1/
Designer of Record The engineer responsible for the actual preparation of the
construction documents.
\1\
Electric Supply Station A station that transforms the energy level (voltage) for further
bulk distribution at medium voltage levels.
27
UFC 3-550-01
February 3, 2010
Including Change 1, July 1, 2012
Facility Core Distribution Infrastructure System components that constitute a part
of the base infrastructure system that are required to provide electrical service to
multiple users.
/1/
Low Voltage System An electrical system having a maximum root-mean-square
(rms) voltage of less than 1,000 volts.
Medium Voltage System An electrical system having a maximum RMS ac voltage of
1,000 volts to 34.5 kV. Some documents such as NEMA C84.1 define the medium
voltage upper limit as 100 kV, but this definition is inappropriate for facility applications.
Project Manager Engineer charged with the administration of the project.
Service The conductors and equipment for delivering electrical energy from the
serving utility or Government-owned system to the wiring system of the premises
served.
Site Electrical Utilities Site Electrical Utilities are the primary electric power
distribution to the facilities and other electrical loads, all exterior lighting not attached to
the building; and all telecommunication services (fiber optic, copper cable, CATV, etc.)
required by the Facilities.
\1\
Utilization Electric Supply Station Equipment such as pole or pad-mounted
transformers or secondary unit substations that transforms the energy level (voltage) to
a utilization voltage for consumer use.
/1/
28
UFC 3-550-01
February 3, 2010
Including Change 1, July 1, 2012
APPENDIX A REFERENCES
Note: The most recent edition of referenced publications applies, unless otherwise
specified. 1
Military Publications
\1\ UFC 3-260-01, Airfield and Heliport Planning and Design. /1/
UFC3-501-01,Electrical Engineering.
UFC 3-510-01, Foreign Voltages and Frequencies Guide.
UFC 3-530-01, Design: Interior and Exterior Lighting and Controls.
UFC 3-560-01, Electrical Safety, O&M.
UFC 3-570-02A, Cathodic Protection.
UFC 3-570-02N, Electrical Engineering Cathodic Protection.
\1\ UFC 3-575-01, Lightning and Static Electricity Protection Systems. /1/
UFC 3-600-01, Fire Protection Engineering for Facilities.
UFC 4-010-01, DoD Minimum Anti-Terrorism Standards for Buildings.
UFC 4-020-01, DoD Security Engineering Facilities Planning Manual.
\1\ UFC 4-211-01N, Aircraft Maintenance Hangars: Type I, Type II and Type III.
UFC 4-211-02NF, Corrosion Control and Paint Finishing Hangars. /1/
IEEE (formerly Institute of Electrical and Electronics Engineers)
IEEE C2, National Electrical Safety Code.
IEEE C37.04, Rating Structure for AC High-Voltage Circuit Breakers Rated on a
Symmetrical Current Basis.
IEEE C37.06, AC High-Voltage Circuit Breakers Rated on a Symmetrical Current Basis
Preferred Ratings and Related Required Capabilities.
IEEE C37.20.2, Metal-Clad Switchgear.
IEEE C37.41, Design Tests for High-Voltage Fuses, Distribution Enclosed Single-Pole
Air Switches, Fuse Disconnecting Switches, and Accessories.
IEEE C37.46, High Voltage Expulsion and Current-Limiting Type Power Class Fuses
and Fuse Disconnection Switches.
IEEE C37.60, Requirements for Overhead, Pad-Mounted, Dry Vault, and Submersible
Automatic Circuit Reclosers and Fault Interrupters for Alternating Current Systems
Up to 38 kV.
IEEE C37.74, IEEE Standard Requirements for Subsurface, Vault, and Padmounted
Load- Interrupter Switchgear and Fused Load-Interrupter Switchgear for Alternating
Current Systems up to 38 kV.
IEEE C37.90, Relays and Relay Systems Associated with Electric Power Apparatus.
1
29
UFC 3-550-01
February 3, 2010
Including Change 1, July 1, 2012
IEEE C37.121, Switchgear Unit Substations Requirements.
IEEE C57.12.00, General Requirements for Liquid-Immersed Distribution, Power, and
Regulating Transformers.
IEEE C57.12.01, General Requirements for Dry-Type Distribution and Power
Transformers Including Those with Solid-Cast and/or Resin-Encapsulated Windings.
IEEE C57.12.22, Transformers Pad-Mounted, Compartmental-Type, Self-Cooled,
Three-Phase Distribution Transformers with High-Voltage Bushings, 2500 kVA and
Smaller: High Voltage, 34,500 Grd Y/19,920 Volts and Below; Low Voltage, 480 Volts
and Below.
IEEE C57.12.28, Pad-Mounted Equipment Enclosure Integrity.
IEEE C57.12.34, Pad-Mounted, Compartmental-Type, Self-Cooled, Three-Phase
Distribution Transformers (2500 kVA and Smaller) High-Voltage, 34,500
GrdY/19,200 Volts and Below; Low-Voltage: 480 Volts and Below.
IEEE C57.12.50, Ventilated Dry-Type Distribution Transformers, 1 to 500 kVA, SinglePhase, and 15 to 500 kVA Three-Phase, with High-Voltage 601 to 34,500 Volts, LowVoltage 120-600 Volts.
IEEE C57.12.51, Ventilated Dry-Type Power Transformers, 501 kVA and larger, ThreePhase, with High-Voltage 601 to 34,500 Volts, Low-Voltage 208Y/120 to 4160 Volts.
IEEE C57.12.80, Terminology for Power and Distribution Transformers.
IEEE C57.12.90, Test Code for Liquid-Immersed Distribution, Power, and Regulating
Transformers.
IEEE C57.12.91, Test Code for Dry-Type Distribution and Power Transformers.
IEEE C57.96, Loading Dry-Type Distribution and Power Transformers.
IEEE C57.98, Guide for Transformer Impulse Tests.
IEEE C57.124, Detection of Partial Discharge and the Measurement of Apparent
Charge in Dry-Type Transformers.
IEEE 80, IEEE Guide for Safety in AC Substation Grounding.
National Fire Protection Association
NFPA 70, National Electrical Code.
NFPA 70B, Electrical Equipment Maintenance.
\1\ NFPA 70E-2012, Standard for Electrical Safety in the Workplace. The 2012 edition
has been published and is under review by the Tri-Services Electrical Working
Group. Additional applicable changes in the 2012 edition will be incorporated into
criteria in the next revision. /1/
National Electrical Manufacturers Association
NEMA C84.1, Electric Power Systems and Equipment-Voltage Ratings (60 Hz).
Miscellaneous Documents
ASTM D2447, Standard Specification for Polyethylene (PE) Plastic Pipe, Schedules 40
and 80, Based on Outside Diameter.
FAA Advisory Circular 150/5320-6D, Airport Pavement Design and Evaluation.
30
UFC 3-550-01
February 3, 2010
Including Change 1, July 1, 2012
IEEE C57.12.22, Transformers Pad-Mounted, Compartmental-Type, Self-Cooled,
Three-Phase Distribution Transformers with High-Voltage Bushing, 2500 kVA and
Smaller: High Voltage, 34,500 Grd Y/19,920 Volts and Below; Low Voltage, 480 Volts
and Below.
NEMA WC 74, 5-46 KV Shielded Power Cable for Use in the Transmission and
Distribution of Electric Energy.
NEMA TC7, Smooth-Wall Coilable Polyethylene Electrical Plastic Conduit.
NETA MTS, Maintenance Testing Specifications.
31
UFC 3-550-01
February 3, 2010
Including Change 1, July 1, 2012
APPENDIX B DIRECTIONAL BORING
B-1
CONDUIT TYPE.
B.1.1.2.
B.1.2.
Minimum size HDPE conduit shall be 4 inches for distribution voltages less
than 1,000 V.
B.1.2.1.
B.1.2.2. Installed HDPE conduit shall have a minimum ground cover of 48 inches in
pavement- or non-pavement-covered areas.
B.1.3.
Minimum size HDPE conduit for branch circuit wiring less than 600 V shall be
determined by calculation, addressing, as a minimum, branch circuit conductor size,
maximum allowable pulling tension, and maximum 5 percent voltage drop.
B.1.3.1.
INSTALLATION METHODS.
The use of specific conductor or insulation types for either high- or low-voltage
installations is not mandated here. However, the combination of a chosen conductor
and insulation type may not meet the requirements for the installation methods required
in the following paragraphs where length, depth, and routing of the directional bore
conduit may require an alternative conductor material and/or insulation type (i.e.,
maximum pulling tensions are different for aluminum and copper conductors).
32
UFC 3-550-01
February 3, 2010
Including Change 1, July 1, 2012
B.2.1.
If the directional bored portion of the cable run is more than 25 percent of the
total run length, evaluate and document the conductor derated ampacity in accordance
with NFPA 70 Article 310.60 (C) (2).
B.2.2.
B.2.3.
B.2.4.
Drilling fluids used for DB methods shall be approved by federal, state, and
local codes and authorized for use by the BCE.
B.2.5.
The conduit(s) shall be installed immediately after the conduit hole is
completed.
B.2.6.
There is no restriction on DB distances provided the allowable pulling tension
of the conduit and installed conductors are not exceeded, conductor splices are not
within the conduit, and maximum ampacity of conductors due to depth derating is not
exceeded.
B.2.6.1. A registered Professional Engineer (PE) shall calculate pulling tension
requirements for each directional bore, taking into consideration the HDPE conduit(s)
size and type, bend radius, elevation changes, vertical and horizontal path deviations,
installed electrical conductor size and type, and any conductor ampacity derating due to
depth of HDPE conduit.
B.2.6.2. The electrical contractor shall provide certification of compliance with the PEs
design requirements.
B.2.6.3. The professional engineering design process must include consideration of
tensile forces and bend radii created during the installation so that allowable limits are
not exceeded.
B.2.6.4. Allowable tensile forces must be determined by a PE. The PE certifying the
installation shall account for the conduits allowable bend radius to prevent ovalization
and kinking from installation. Ovalization of the conduit shall not exceed 5 percent.
B.2.7.
HDPE conduits shall terminate into concrete-pad-mounted electrical
equipment from either a pavement or non-pavement transitional area as indicated in
Figures B-1 through B-5. HDPE or rigid conduit shall be routed and terminated within
the concrete pad such that no conductor exiting the conduit shall be bent past the
vertical plane formed with the equipment pad when routed to conductor terminations
and with approved insulated bushings (Figure B-1).
33
UFC 3-550-01
February 3, 2010
Including Change 1, July 1, 2012
34
UFC 3-550-01
February 3, 2010
Including Change 1, July 1, 2012
Figure B-2. Pavement Covered Area to Electrical Equipment Transition Rigid Conduit (4590)
35
UFC 3-550-01
February 3, 2010
Including Change 1, July 1, 2012
Figure B-3. Pavement Covered Area to Electrical Equipment Transition HDPE Conduit (2045)
36
UFC 3-550-01
February 3, 2010
Including Change 1, July 1, 2012
Figure B-4. Non-Pavement Covered Area to Electrical Equipment Transition Rigid Conduit (4590)
37
UFC 3-550-01
February 3, 2010
Including Change 1, July 1, 2012
Figure B-5. Non-Pavement Covered Area to Electrical Equipment Transition HDPE Conduit (2045)
38
UFC 3-550-01
February 3, 2010
Including Change 1, July 1, 2012
B.2.8.
B.2.8.1. Multiple HDPE conduits are permitted to be pulled through each bore.
Designs requiring multiple conduits to accommodate parallel conductor installations
must comply with NFPA 70 grounding and wiring methods requirements. As an
example, one set of paralleled conductor requirements is illustrated in the following
excerpt from NFPA 70, Article 310.4, which states:
The paralleled conductors in each phase, polarity, neutral, or grounded circuit
conductor shall comply with all of the following:
(1) Be the same length
(2) Have the same conductor material
(3) Be the same size in circular mil area
(4) Have the same insulation type
(5) Be terminated in the same manner
Thus, using DB methods to comply with (1) from the NFPA 70 excerpt, as well as other
requirements, may not be possible, especially for long boring distances. NFPA 70 has
other requirements for paralleled conductor installations that must also be considered
when designing for these types of installations.
Note: Any deviations from NFPA 70 requirements must be approved by the AHJ.
B.2.8.2. If the directional bored portion of the cable run is more than 25 percent of the
total run length, evaluate and document the conductor derated ampacity in accordance
with NFPA 70 Article 310.60 (C) (2).
B.2.9.
Joining Methods. Butt and electrofusion joining means are the only joining
methods approved for HDPE conduit installations and shall be accomplished by
persons certified in the process and in accordance with the manufacturers procedures.
B.2.10. Transition from HDPE to PVC. Transition from HDPE to PVC shall be made
using only electrofusion coupling means with approved and listed materials. Coupling
means shall be accomplished by persons certified on the equipment and process.
B.2.10.1. Coupling between HDPE and concrete-encased duct banks from pavement or
non-pavement transitional areas shall be accomplished as indicated in Figures B-6 and
B-7.
B.2.10.2. Transition from HDPE to concrete manholes from pavement or non-pavement
transitional areas shall be accomplished as indicated in Figures B-8 and B-9.
39
UFC 3-550-01
February 3, 2010
Including Change 1, July 1, 2012
40
UFC 3-550-01
February 3, 2010
Including Change 1, July 1, 2012
41
UFC 3-550-01
February 3, 2010
Including Change 1, July 1, 2012
42
UFC 3-550-01
February 3, 2010
Including Change 1, July 1, 2012
43
UFC 3-550-01
February 3, 2010
Including Change 1, July 1, 2012
B-3
DOCUMENTATION.
The location and depth of DB-installed HDPE electrical conduit shall be recorded and
noted on applicable as-built drawings. Global Positioning System (GPS) recording
means with resource grade accuracy shall be used to record HDPE conduit bore path.
GPS coordinates shall be recorded at intervals not to exceed 50 feet along the bore
path. This information, along with the size of conduit, number of conductors, conductor
size, and insulation type, shall be provided to the appropriate base civil engineering
office for incorporation into the GeoBase database.
44
UFC 3-550-01
February 3, 2010
Including Change 1, July 1, 2012
Consider the following general criteria as part of any exterior electrical system
Reliability and maintenance. NFPA 70B, NETA MTS, and the manufacturers
documents provide periodic maintenance criteria applicable to exterior
electrical equipment. Consider maintenance requirements in the specification
of equipment and in the installation design of the equipment. As an example,
a single manhole located near a substation should not contain the cables for
all base feeders; in this example, the design should install multiple manholes
with fewer distribution feeders located inside each manhole.
C.2
Use or modify existing substations unless a new substation is required for
capacity or unique requirements. Aging substations will often require complete
replacement.
45
UFC 3-550-01
February 3, 2010
Including Change 1, July 1, 2012
C.3
Coordinate metering, system design, protection, electrical coordination, load
requirements, and short circuit limitations with the local utility. If the supply
station/substation is owned by the utility, obtain sufficient design information for the
utility-owned equipment to help establish design requirements for downstream
equipment.
C.4
Coordinate revenue metering requirements with the local utility. Provide a
government-owned revenue meter for the supply station/substation even when the local
utility meters the incoming supply.
C.5
Clearly define the point of demarcation between the utility-owned system and
the government owned equipment. Define ownership for the incoming utility supply
lines if there are any shared equipment, such as overhead distribution with utility and
government-owned lines sharing the same power poles.
C.6
Design a main electric supply station/substation for reliability of service and
maintenance. The design analysis for the supply station/substation shall address the
following:
UFC 3-550-01
February 3, 2010
Including Change 1, July 1, 2012
Connections between the transformer secondary and the main circuit breaker.
Preferred connection methods include cables in conduit or cable trays.
Busway transitions are discouraged, but if they are used, it must be labeled
for the application by Underwriters Laboratories, or equivalent; designed for
outdoor service, including a stainless steel housing and hardware for
corrosion control; rated and braced for the maximum expected continuous
current and short circuit current; designed to control condensation and its
effects; and designed to allow access for periodic inspection following the
NETA MTS guidance.
\1\ /1/
47