An SAP implementation project must change the database system
before going
into production, because of strategic customer decisions. The
customer system
configuration was setup as a standard three-system landscape
(development,
quality assurance, production). Each system is configured as ABAP
Web AS
with JAVA Add-In.
1. Is it necessary to order a SAP OS/DB Migration Check for the
planned
database change?
a) The system landscape contains a pre-production system only. In
this
case, no OS/DB Migration Check service is necessary, as its intention
is to be used for productive systems only.
2. According the SAP System copy rules, who must do the system copies?
a) The change of a database involves a heterogeneous system copy, which
must be done from someone who is certified for OS/DB migrations.
The fact that the systems are not productive is regardless.