Typical Loadout Flowchart
Typical Loadout Flowchart
Typical Loadout Flowchart
INSTALL
LOADOUT/
TRANSPORTATION
CROSS BEAM
START
Pre-Loadout :
Job Safety analysis Meeting / Risk analysis
Mobilization of MWS
Pre-loadout meeting
BARGE PORT IN @
WHARF/QUAY
END
SAILAWAY
WHARF ALONGSIDE
& MOORING
CASTING OF
MOORING LINE &
BARGE HANDOVER
SETTING
SPMT
INSPECTION BY
MWS
INSTALL
RAMP BETWEEN
BARGE & WHARF
BARGE HANDOVER
COMPLETE
SEAFASTENING
LOADOUT
CERTIFICATE ISSUED
BY MWS
TOWING BALLAST
BARGE PREBALLASTING
LOADOUT TO BARGE
difference between
pre-ballasting & towing
ballast
To be done by MULTIPANEL
To be done by BARGE/BUYER
INITIAL SEA
FASTENING