Tendering Estimating Assignment 01
Tendering Estimating Assignment 01
Tendering Estimating Assignment 01
Program
Unit / Module
Assessment
Lecturer
Ms. S. Kavitha
Student Name
ID
Student to
Tick if
Attempted
Date Due
HNDQS/MT/26/__
To Be Informed
Re-Submission
Date
Assessor Feedback
P1.1
P1.2
P1.3
P2.1
P2.2
P2.3
P2.4
P3.1
P3.2
P3.3
P3.4
P4.1
P4.2
P4.3
Distinction (D)
Merit (M)
Pass (P)
Assessed by (name):
Signature:
Student Signature & Comments
Date Assessed :
The criteria each task relates to are shown against that task where possible.
Please note that plagiarism is treated as a serious offence and therefore the work you produce
must be individual and original although may work in groups in some instances (Please refer
to Student Handbook on Plagiarism & Cheating).
Please note that the submission date given for this assignment is the final date that you can
hand over the assignment. A one week grace period maybe extended with prior approval
from the Program Manager Undergraduate.
Assignments returned to students for re-working must be re-submitted within 10 days (Please
refer to Student Handbook on Assignments Re-submission).
Failure to re-submit the previously marked assignment with the re-submitted assignment will
mean that results cannot be released for the respective unit.
Please read, follow and reference both the contents of the unit outline and the grading
criteria of the assignment before completing this assignment.
Date: .
Students Comments:
..
......
..
Internal Verifier
Name:
Signature :
Date Verified :
Cost in Rs.
900,250.00
500,000.00
furniture etc.
Salaries of Workshop & Yard store keepers, Drivers, Foreman, Mechanics
10,320,000.00
& Workmen
Fencing & protection
210,000.00
450,000.00
500,000.00
650,000.00
450,000.00
800,000.00
6.2.1. Calculate the head office overhead and site overhead separately. (P3.4)
6.2.2. If the basic cost of the tender is Rs. 321, 315, 300.00. Calculate the head office
overhead margin and site overhead margin of this project.
7. Health, safety & welfare are important issues in the construction. Preplanning of these, will
avoid unwanted big expenditures. Evaluate how the health, safety and welfare plan affects this
tender (P3.3)
8. The client, consultant and the contractor might have several limitations when they are going
for a selective tender. Determine the constraints which may apply to this tender process. (P1.2)
9. Documentation is very important in the construction contracts. Any dispute arises, will be
resolved based on the documentation evidence. Describe the scope of contractual
documentation required to support the tender process (P1.3)
10. There some items of the shopping mall have been given for you to estimate. Calculate the rate
including overhead and profit margin. (P2.4)
Indicative Characteristics
In order to achieve a
Contextualized
evidence
To achieve the
grade will need to
student.
Effective judgments
have been made on
Complex problems with more than one variable
deciding the
have been explored
contract type in
An effective approach to study and research has Task 03.
been applied
M2 Select/design and
apply appropriate
methods/ techniques
and
processed
appropriate
learning
unfamiliar contexts
In order to achieve a
Contextualized
evidence
To achieve the
grade will need to
student.
Conclusions
have
been
arrived
at
through
defined criteria
Realistic improvements
Demonstration of
effective thinking
have been done
throughout the report
and finding solutions
for the scenario by
applying the theory.
contexts