KR102549806B1 - Construction method of substructure and foundation - Google Patents
Construction method of substructure and foundation Download PDFInfo
- Publication number
- KR102549806B1 KR102549806B1 KR1020210039907A KR20210039907A KR102549806B1 KR 102549806 B1 KR102549806 B1 KR 102549806B1 KR 1020210039907 A KR1020210039907 A KR 1020210039907A KR 20210039907 A KR20210039907 A KR 20210039907A KR 102549806 B1 KR102549806 B1 KR 102549806B1
- Authority
- KR
- South Korea
- Prior art keywords
- foundation
- anchor
- double button
- button
- concrete
- Prior art date
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/18—Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
- E04B1/26—Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of wood
- E04B1/2604—Connections specially adapted therefor
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/18—Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
- E04B1/26—Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of wood
- E04B1/2604—Connections specially adapted therefor
- E04B2001/2652—Details of nailing, screwing, or bolting
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/18—Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
- E04B1/26—Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of wood
- E04B1/2604—Connections specially adapted therefor
- E04B2001/268—Connection to foundations
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Physics & Mathematics (AREA)
- Electromagnetism (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Joining Of Building Structures In Genera (AREA)
Abstract
본 발명은 목조주택 토대 수평작업 및 기초와의 연결 시공방법은 토대목 위에 더블버튼이 포개지도록 한 것을 거푸집의 내측면에 표시된 토대목 수평라인과 더블버튼 수평라인 사이에 위치하도록 하면서 거푸집의 바깥쪽으로부터 안쪽으로 스크류볼트를 박아서 상기 토대목과 상기 더블버튼이 거푸집의 내측면으로부터 안쪽으로 돌출된 상태로 고정되게 하는 토대목 및 더블버튼 고정 단계와, 상기 토대목과 상기 더블버튼이 붙어있는 상태에서 상하 방향으로 다수의 L앙카자리 구멍을 뚫는 구멍 형성 단계와, L앙카를 상기 L앙카자리 구멍에 끼워 아래에서 위로 관통시킨 다음 상기 L앙카 중 상기 더블버튼보다 위에 위치하는 부분에는 와샤와 너트를 체결하여 상기 L앙카를 고정하고 상기 L앙카 중 상기 토대목보다 아래에 위치하는 부분은 철근에 용접하여 연결하는 L앙카 고정 단계와, 콘크리트의 상단이 상기 토대목의 수평 하단선에 해당하는 콘크리트수평라인에 도달할 때까지 콘크리트를 타설하는 콘크리트 타설 단계와, 상기 콘크리트가 굳어지면 벽체 하부의 버튼 플레이트를 상기 더블버튼 위에 세워 고정하기 위해 상기 벽체하부의 버튼 플레이트 중 다수의 상기 L앙카와 대응되는 부위에 L앙카 구멍을 뚫어 상기 L앙카를 끼워넣고 와샤와 너트로 조여서 기초와 벽체까지가 상기 L앙카로 연결되도록 하는 벽체 연결 단계를 포함한다.In the present invention, the wooden house foundation horizontal work and connection construction method is to place the double button overlapped on the foundation timber to the outside of the formwork while positioning it between the foundation timber horizontal line and the double button horizontal line displayed on the inner surface of the formwork. A step of fixing the foundation tree and the double button by driving a screw bolt inward from the foundation tree and the double button so that the foundation tree and the double button are fixed in a state in which they protrude inward from the inner surface of the formwork, and the state in which the foundation tree and the double button are attached A hole forming step of drilling a plurality of L anchor holes in the vertical direction, inserting L anchors into the L anchor holes and penetrating them from bottom to top, and then placing washers and nuts on the part located above the double button among the L anchors L anchor fixing step of fixing the L anchor by fastening and welding and connecting the part located below the foundation timber of the L anchor to the reinforcing bar, and the concrete level where the upper end of the concrete corresponds to the horizontal lower line of the foundation timber A concrete pouring step of pouring concrete until it reaches the line, and when the concrete is hardened, a portion corresponding to a plurality of L anchors among button plates at the bottom of the wall to stand and fix the button plate at the bottom of the wall on top of the double button. A wall connection step of drilling an L anchor hole, inserting the L anchor, and tightening the L anchor with a washer and a nut so that the foundation and the wall are connected to the L anchor.
Description
본 발명은 목조주택 토대 수평작업 및 기초와의 연결 시공방법에 관한 것으로, 더욱 자세하게는 불편하고 작업 능률이 떨어지는 종래 기술에 비하여 작업자들의 피로도가 훨씬 적고 더욱 견고한 기초와 벽체의 연결이 가능한 목조주택 토대 수평작업 및 기초와의 연결 시공방법에 관한 것이다.The present invention relates to a method for horizontally connecting a foundation of a wooden house and connecting it to the foundation, and more particularly, to a foundation for a wooden house that enables workers to be connected with a more solid foundation and walls with much less fatigue than the prior art, which is inconvenient and has low work efficiency. It is about horizontal work and connection construction method with foundation.
종래에는 도 1a에 도시된 것 같이 다수의 거푸집(J) 설치 후 다수의 L앙카(A)를 철근(I)에 용접하여 고정시킨 다음, 도 1b에 도시된 것과 같이 다수의 거푸집(J)에 콘크리트 수평라인(M)을 표시하여 수평에 맞게 콘크리트(L)를 타설한다.Conventionally, as shown in FIG. 1A, after installing a plurality of formworks (J), a plurality of L anchors (A) are welded and fixed to reinforcing bars (I), and then, as shown in FIG. 1B, a plurality of formworks (J) Mark the concrete horizontal line (M) and pour the concrete (L) horizontally.
타설 후 콘크리트(L)가 굳게 되면 도 1c 및 도 1d에 도시된 것과 같이 토대목라인(F)에 맞춰 토대목(B)을 설치하기 위해 다수의 L앙카(A) 위치를 줄자로 재서 다수의 토대목(B)에 표기하고 도 1e에 도시된 것과 같이 다수의 L앙카타공구멍(C)을 뚫어 다수의 L앙카(A)에 끼워 와샤(A-1) 및 볼트(A-2)로 조여 고정시킨다.When the concrete (L) is hardened after pouring, as shown in FIGS. Mark the foundation tree (B) and drill a number of L anchor hole holes (C) as shown in Figure 1e, insert it into a number of L anchors (A) and tighten with washers (A-1) and bolts (A-2) fix it
그런 다음, 도 1f에 도시된 것과 같이 고정된 토대목(B) 위에 더블버튼(B2)을 고정하기 위해 다수의 L앙카타공구멍(C-1) 위치를 줄자로 재고 파내서 토대목(B)에 다수의 못으로 고정한 후 도 1g에 도시된 것과 같이 더블버튼(B2) 수평라인에 맞춰 대패로 갈아낸 다음 도 1h에 도시된 것과 같이 벽체를 세워 다수의 못으로 더블버튼(B)에 고정시키는 목조주택 토대 시공방법이다.Then, as shown in FIG. 1F, in order to fix the double button (B2) on the fixed foundation tree (B), the location of a plurality of L anchor holes (C-1) is measured and dug with a tape measure to secure the foundation tree (B) After fixing with a plurality of nails, as shown in Fig. 1g, grind the double button (B2) with a planer in line with the horizontal line, and then build a wall as shown in Fig. 1h and fix it to the double button (B) with a plurality of nails. It is a method of constructing a foundation for a wooden house.
종래의 기술을 다시 간략하게 순서대로 설명하면, 첫째 다수의 앙카를 철근에 용접하여 수평을 맞춰 콘크리트를 타설 양생 후 단단하게 굳게 하고, 둘째 다수의 토대목에 구멍을 뚫어 L앙카에 끼워 넣고 와샤와 너트로 조여서 고정하며, 셋째 토대목 상면을 더블버튼으로 덮기 위해 다수의 L앙카 자리마다 L앙카타공구멍을 파내 다수의 못으로 고정시키고, 넷째 더블버튼에 수평라인을 표기하여 대패로 갈아내서 벽체를 세우는 것이다.Briefly explaining the conventional technology again, first, a plurality of anchors are welded to reinforcing bars, leveled, and hardened after pouring and curing concrete, and second, drilled holes in a plurality of foundation trees and inserted them into L anchors, and It is tightened and fixed with a nut, and in order to cover the upper surface of the third foundation tree with double buttons, dig holes for L anchorages at every L anchor position and fix them with a number of nails, mark a horizontal line on the fourth double button, grind it with a planer, and is to build
그러나 위와 같은 종래의 목조주택 토대 시공방법의 문제점은 다음과 같다.However, the problems of the conventional wooden house foundation construction method as above are as follows.
위 시공방법에서는 다수의 L앙카(A) 자리를 표기하기 위해 허리를 구부리고 줄자로 하나하나 재서 토대목(B)에 표기하고 다수의 L앙카타공구멍(C)을 뚫어 와샤(A-1)와 볼트(A-2)로 조여 고정하고, 다수의 토대목(B)에 와샤(A-1)와 볼트(A-2) 자리를 표기하기 위해 허리를 구부려 줄자로 하나하나 재서 더블버튼(B2)에 표기하고 다수의 L앙카타공구멍(C-1)을 파내 토대목(B) 위에 와샤(A-1)와 볼트(A-2) 자리를 덮어 다수의 못으로 고정하며, 다수의 더블버튼(B2)을 수평에 맞게 허리를 구부려서 대패작업을 한다. In the above construction method, to mark the positions of multiple L anchors (A), bend the waist and measure one by one with a tape measure to mark on the foundation tree (B), and drill a number of L anchor holes (C) to Tighten and fix with bolts (A-2), bend at the waist to mark the positions of washers (A-1) and bolts (A-2) on multiple foundation trees (B), measure each one with a tape measure, and double button (B2) Mark on and dig out a number of L anchor holes (C-1), cover the washer (A-1) and bolt (A-2) positions on the foundation tree (B) and fix them with a number of nails, and a number of double buttons ( Plan B2) by bending the waist horizontally.
그런데 이러한 공정들은 모두 바닥에서 이뤄지는 일들이라 작업자들이 허리를 구부려서 장시간 일을 할 수밖에 없고 이로 인하여 작업자들의 작업능률이 떨어진다는 문제점이 있고, 능률이 떨어지는 작업으로 인하여 공사기간이 길어져 인건비 상승 요인이 크다는 문제점이 있다.However, since all of these processes are performed on the floor, workers have no choice but to bend their backs and work for a long time, which reduces the work efficiency of workers. there is
또한 기초와 벽체의 연결도 L앙카(A)가 토대목(B)까지만 볼트로 조여서 L앙카(A)가 벽체까지는 연결이 안돼 외력에 의한 저항력이 다소 떨어지게 된다는 단점이 있다.In addition, the connection between the foundation and the wall also has the disadvantage that the anchor (A) is tightened with bolts only up to the foundation tree (B), so that the anchor (A) is not connected to the wall, so the resistance due to external force is somewhat reduced.
본 발명은 이러한 종래 기술의 문제점을 해결하기 위해서 안출된 것으로서, 본 발명은 종래기술에 의한 토대작업에 비하여 작업능률 상승 효과와 공사기간 단축으로 인한 인건비 절감 효과를 높이고 더욱 견고하게 기초와 벽체를 연결하기 위한 목조주택 토대 수평작업 및 기초와의 연결 시공방법을 제공하는 데 그 목적이 있다.The present invention has been made to solve the problems of the prior art, and the present invention increases work efficiency and reduces labor costs due to shortened construction period compared to foundation work according to the prior art, and connects the foundation and the wall more firmly. The purpose is to provide a construction method for leveling the foundation of a wooden house and connecting it to the foundation.
이와 같은 상기의 목적을 달성하기 위한 본 발명에 따른 목조주택 토대 수평작업 및 기초와의 연결 시공방법은 토대목 위에 더블버튼이 포개지도록 한 것을 거푸집의 내측면에 표시된 토대목 수평라인과 더블버튼 수평라인 사이에 위치하도록 하면서 거푸집의 바깥쪽으로부터 안쪽으로 스크류볼트를 박아서 상기 토대목과 상기 더블버튼이 거푸집의 내측면으로부터 안쪽으로 돌출된 상태로 고정되게 하는 토대목 및 더블버튼 고정 단계와, 상기 토대목과 상기 더블버튼이 붙어있는 상태에서 상하 방향으로 다수의 L앙카자리 구멍을 뚫는 구멍 형성 단계와, L앙카를 상기 L앙카자리 구멍에 끼워 아래에서 위로 관통시킨 다음 상기 L앙카 중 상기 더블버튼보다 위에 위치하는 부분에는 와샤와 너트를 체결하여 상기 L앙카를 고정하고 상기 L앙카 중 상기 토대목보다 아래에 위치하는 부분은 철근에 용접하여 연결하는 L앙카 고정 단계와, 콘크리트의 상단이 상기 토대목의 수평 하단선에 해당하는 콘크리트수평라인에 도달할 때까지 콘크리트를 타설하는 콘크리트 타설 단계와, 상기 콘크리트가 굳어지면 벽체 하부의 버튼 플레이트를 상기 더블버튼 위에 세워 고정하기 위해 상기 벽체하부의 버튼 플레이트 중 다수의 상기 L앙카와 대응되는 부위에 L앙카 구멍을 뚫어 상기 L앙카를 끼워넣고 와샤와 너트로 조여서 기초와 벽체까지가 상기 L앙카로 연결되도록 하는 벽체 연결 단계를 포함한다.In order to achieve the above object, the wooden house foundation leveling work and connection construction method with the foundation according to the present invention is such that the double button is superimposed on the foundation tree, and the foundation tree horizontal line displayed on the inner surface of the formwork and the double button level A foundation tree and double button fixing step of driving a screw bolt from the outside to the inside of the formwork while positioning it between the lines so that the foundation tree and the double button are fixed in a state in which they protrude inward from the inner surface of the formwork; A hole forming step of drilling a plurality of L anchor holes in the vertical direction in a state where the foundation tree and the double button are attached, and inserting the L anchor into the L anchor hole to pass through from bottom to top, and then the double button of the L anchor The L anchor fixing step of fixing the L anchor by fastening a washer and a nut to the part located above and welding and connecting the part located below the foundation tree of the L anchor to the reinforcing bar, and the top of the concrete is A concrete pouring step of pouring concrete until reaching the concrete horizontal line corresponding to the horizontal bottom line of the stock, and when the concrete is hardened, the button plate at the bottom of the wall to stand and fix the button plate at the bottom of the wall on top of the double button. A wall connection step of drilling an L anchor hole in a portion corresponding to a plurality of L anchors, inserting the L anchor, and tightening with a washer and a nut so that the foundation and the wall are connected to the L anchor.
이상에서와 같이, 종래기술의 작업공정에서는 큰 비중을 차지하는 다수의 L앙카 자리를 줄자로 재서 표기하는 작업, 표기된 L앙카 자리 구멍을 뚫는 작업, 이를 반복하는 작업, 최종 벽체가 세워지는 더블버튼의 수평을 잡기 위한 대패작업 등의 일련의 작업들이 필요했으나, 본 발명에 의한 목조주택 토대 수평작업 및 기초와의 연결 시공방법에 의하면 임의로 구멍을 뚫으면 되어 L앙카 자리를 줄자로 재서 표기할 필요가 없고, L앙카 자리 구멍도 두 번이 아닌 한 번만 뚫으면 되며 대패작업을 할 필요가 없어서 공사기간 단축으로 인한 인건비 절감 효과가 생기고 허리를 구부려 일하는 시간이 줄어들어 작업자들의 작업 능률이 개선되어 피로도가 현저하게 낮아지며, 종래 다수의 L앙카로 토대목까지만 연결했던 것을 벽체 하부의 버튼 플레이트까지 완벽하게 연결하도록 하여 구조적인 견고함을 향상시키는 효과가 있다.As described above, in the work process of the prior art, the operation of measuring and marking a large number of L anchor positions with a tape measure, the operation of drilling a hole in the marked L anchor position, the operation of repeating this, and the double button on which the final wall is erected A series of works such as planing work to level it was necessary, but according to the wooden house foundation leveling work and connection construction method with the foundation according to the present invention, it is necessary to arbitrarily drill a hole and mark the L anchor position with a tape measure There is no need to drill a hole for the L anchor seat once instead of twice, and there is no need for planing work, which reduces labor costs due to shortened construction period and reduces work time bending at the waist, which improves work efficiency and significantly reduces fatigue. It is lowered, and it has the effect of improving structural rigidity by perfectly connecting what was conventionally connected only to the foundation tree with a plurality of L anchors to the button plate at the bottom of the wall.
도 1a 내지 도 1h는 종래의 목조주택 토대 시공방법을 순서대로 나타낸 그림 및 사진.
도 2 및 도 3은 본 발명의 일 실시 예에 의한 목조주택 토대 수평작업 및 기초와의 연결 시공방법의 토대목 및 더블버튼 고정 단계, 구멍 형성 단계 및 L앙카 고정 단계를 나타낸 그림.
도 4는 본 발명의 일 실시 예에 의한 목조주택 토대 수평작업 및 기초와의 연결 시공방법의 콘크리트 타설 단계를 나타낸 그림.
도 5는 본 발명의 일 실시 예에 의한 목조주택 토대 수평작업 및 기초와의 연결 시공방법의 벽체 연결 단계를 나타낸 그림.1a to 1h are pictures and photographs showing a conventional wooden house foundation construction method in order.
2 and 3 are diagrams showing the step of fixing the foundation wood and double button, the step of forming a hole, and the step of L anchor fixing of the wooden house foundation leveling work and connection construction method with the foundation according to an embodiment of the present invention.
Figure 4 is a diagram showing the concrete pouring step of the wooden house foundation leveling work and connection construction method with the foundation according to an embodiment of the present invention.
Figure 5 is a picture showing the wall connection step of the wooden house foundation leveling work and connection construction method with the foundation according to an embodiment of the present invention.
이하, 본 발명의 구체적인 실시 예를 첨부된 도면을 참고하여 상세하게 설명한다.Hereinafter, specific embodiments of the present invention will be described in detail with reference to the accompanying drawings.
도 2 내지 5는 본 발명의 일 실시 예에 의한 목조주택 토대 수평작업 및 기초와의 연결 시공방법이다.2 to 5 are a construction method for leveling the wooden house foundation and connecting it to the foundation according to an embodiment of the present invention.
본 발명의 일 실시 예에 의한 목조주택 토대 수평작업 및 기초와의 연결 시공방법은 토대목 및 더블버튼 고정 단계, 구멍 형성 단계, L앙카 고정 단계, 콘크리트 타설 단계 및 벽체 연결 단계가 순서대로 이루어지는 것을 통해 구성된다.According to an embodiment of the present invention, the wooden house foundation leveling work and the connection construction method with the foundation include the foundation timber and double button fixing step, hole formation step, L anchor fixing step, concrete pouring step, and wall connection step in order. constituted through
토대목 및 더블버튼 고정 단계는 거푸집(100)의 내측면에 표시된 토대목 수평라인과 더블버튼 수평라인(110) 사이에 토대목(10)과 더블버튼(20)을 위치하도록 하면서 거푸집(100)의 바깥쪽으로부터 안쪽으로 스크류볼트(40)를 박아서 토대목(10)과 더블버튼(20)이 거푸집(100)의 내측면으로부터 안쪽으로 돌출된 상태로 고정되게 하는 단계이다. 토대목(10)과 더블버튼(20)은 각각 수평 방향으로 길게 뻗는 각목 형태의 부재로서 토대목(10)이 아래에 있고 더블버튼(20)이 위에 있도록 토대목(10)과 더블버튼(20)이 위아래로 포개지게 한다. 토대목(10)의 수평한 하단선이 토대목 수평라인과 일치하고 더블버튼(20)의 수평한 상단선이 더블버튼 수평라인(120)과 일치하는 상태에서 거푸집(100)의 외측면으로부터 거푸집(100)의 안쪽으로 들어가도록 박아넣는 스크류볼트(40)를 이용해 토대목(10)과 더블버튼(20)을 고정한다.The step of fixing the foundation tree and the double button is to place the
구멍 형성 단계는 토대목(10)과 더블버튼(20)이 위아래로 적층된 상태에서 상하 방향으로 관통하는 다수의 L앙카자리 구멍을 뚫는 단계이다.The hole forming step is a step of drilling a plurality of L anchor holes penetrating in the vertical direction in a state in which the
L앙카 고정 단계는 L앙카(30)를 L앙카자리 구멍에 끼워 아래에서 위로 관통시킨 다음 L앙카(30) 중 더블버튼(20)보다 위에 위치하는 부분에는 와샤(50)와 너트(60)를 체결하여 L앙카(30)를 고정시키는 한편, L앙카(30) 중 토대목(10)보다 아래에 위치하는 부분에는 수평 방향으로 길게 뻗는 철근(70)에 용접함으로써 철근(70)에 연결시키는 단계이다.In the L anchor fixing step, the
콘크리트 타설 단계는 콘크리트(130)의 상단이 토대목(10)의 수평 하단선에 해당하는 콘크리트수평라인(120)에 도달할 때까지 콘크리트(130)를 타설하는 단계이다.The concrete pouring step is a step of pouring the
벽체 연결 단계는 콘크리트(130)가 양생 후 굳어지고 나서 탑플레이트(210), 스터드(220), 버튼플레이트(230)로 구성되는 벽체(200)의 하단부를 구성하는 버튼 플레이트(230)를 더블버튼(20) 위에 세워 고정하기 위해 벽체(200) 하부의 버튼플레이트(230) 중 다수의 L앙카(30)와 대응되는 부위에 L앙카 구멍을 뚫어 L앙카(30)를 끼워넣고 와샤(50)와 너트(60)로 조여서 기초와 벽체까지가 L앙카(30)로 연결되도록 하는 단계이다.In the wall connection step, after the
본 발명의 포인트는 종래기술에서 서술했듯이 L앙카(30)를 콘크리트(130) 타설 후 토대목(10)과 더블버튼(20)에 L앙카자리 표기와 구멍 뚫기를 작업자가 허리를 구부려서 힘들게 작업해야 하는 것을 불필요하게 하여 획기적으로 작업자의 노동력과 작업 시간을 줄여주고, 기초작업 시 거푸집(100)에 표시된 수평라인에 맞춰 토대목(10)과 더블버튼(20)을 고정하고 다수의 L앙카 구멍을 편한 자세로 한번에 간편하게 뚫는 시공법을 제공해주며, 토대목(10)이 처음부터 수평에 맞춰 시공되기 때문에 허리를 구부려서 대패작업을 할 필요가 없고, 기초와의 연결이 종래에는 토대목(10)까지만 결합된 구조였으나 본 발명의 경우 벽체(200)의 버튼플레이트(230)까지를 결합시킴으로써 더욱 견고한 구조적 결합이 가능하다.As described in the prior art, the point of the present invention is that after placing the L anchor (30) in the concrete (130), the worker must work hard by bending the waist to mark the L anchor position and drill a hole in the foundation tree (10) and the double button (20). It makes it unnecessary to do so, drastically reducing the labor force and working time of the worker, fixing the
이상의 설명에서와 같이 본 발명은 바람직한 구체적인 예들에 대해서만 기술하였으나, 상기의 구체적인 예들을 바탕으로 한 본 발명의 기술사상 범위 내에서의 다양한 변형 및 수정이 가능함은 당업자에게 있어서 명백한 것이며, 또한, 이러한 변형 및 수정이 첨부된 청구범위에 속함은 당연한 것이다.As described above, the present invention has been described only with preferred specific examples, but it is clear to those skilled in the art that various changes and modifications are possible within the scope of the technical spirit of the present invention based on the specific examples described above, and these variations and modifications are within the scope of the appended claims.
10 : 토대목 20 : 더블버튼
30 : L앙카 40 : 스크류볼트
50 : 와샤 60 : 너트
70 : 철근 100 : 거푸집
110 : 더블버튼 수평라인 120 : 콘크리트 수평라인
130 : 콘크리트 200 : 벽체
210 : 탑플레이트 220 : 스터드
230 : 버튼플레이트10: foundation tree 20: double button
30: L anchor 40: screw bolt
50: washer 60: nut
70: rebar 100: formwork
110: double button horizontal line 120: concrete horizontal line
130: concrete 200: wall
210: top plate 220: stud
230: button plate
Claims (1)
상기 토대목과 상기 더블버튼이 붙어있는 상태에서 상하 방향으로 다수의 L앙카자리 구멍을 뚫는 구멍 형성 단계;
L앙카를 상기 L앙카자리 구멍에 끼워 아래에서 위로 관통시킨 다음 상기 L앙카 중 상기 더블버튼보다 위에 위치하는 부분에는 와샤와 너트를 체결하여 상기 L앙카를 고정하고, 상기 L앙카 중 상기 토대목보다 아래에 위치하는 부분은 철근에 용접하여 연결하는 L앙카 고정 단계;
콘크리트의 상단이 상기 토대목의 수평 하단선에 해당하는 콘크리트수평라인에 도달할 때까지 콘크리트를 타설하는 콘크리트 타설 단계;
상기 콘크리트가 굳어지면 벽체 하부의 버튼 플레이트를 상기 더블버튼 위에 세워 고정하기 위해 상기 벽체하부의 버튼 플레이트 중 다수의 상기 L앙카와 대응되는 부위에 L앙카 구멍을 뚫어 상기 L앙카를 끼워넣고 와샤와 너트로 조여서 기초와 벽체까지가 상기 L앙카로 연결되도록 하는 벽체 연결 단계를 포함하는 것을 특징으로 하는 목조주택 토대 수평작업 및 기초와의 연결 시공방법.The foundation timber and the double button are formed by driving a screw bolt from the outside to the inside of the formwork while positioning the double button overlapping on the foundation timber between the horizontal line of the foundation timber and the double button horizontal line marked on the inner surface of the formwork. Foundation wood and double button fixing step to be fixed in a state protruding inward from the inner surface of the formwork;
A hole forming step of drilling a plurality of L anchor holes in the vertical direction in a state where the foundation tree and the double button are attached;
Insert the L anchor into the hole of the L anchor and pass it through from the bottom to the top, then fix the L anchor by fastening a washer and a nut to the part located above the double button of the L anchor, L anchor fixing step of connecting the part located below by welding to the reinforcing bar;
A concrete pouring step of pouring concrete until the top of the concrete reaches a concrete horizontal line corresponding to the horizontal bottom line of the foundation timber;
When the concrete hardens, in order to fix the button plate at the bottom of the wall on the double button, drill L anchor holes in the parts corresponding to the plurality of L anchors among the button plates at the bottom of the wall, insert the L anchors, and insert the washers and nuts Wooden house foundation leveling work and connection construction method with the foundation, characterized in that it comprises a wall connection step so that the foundation and the wall are connected to the L anchor by tightening with.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020210039907A KR102549806B1 (en) | 2021-03-26 | 2021-03-26 | Construction method of substructure and foundation |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020210039907A KR102549806B1 (en) | 2021-03-26 | 2021-03-26 | Construction method of substructure and foundation |
Publications (2)
Publication Number | Publication Date |
---|---|
KR20220134352A KR20220134352A (en) | 2022-10-05 |
KR102549806B1 true KR102549806B1 (en) | 2023-07-05 |
Family
ID=83596427
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
KR1020210039907A KR102549806B1 (en) | 2021-03-26 | 2021-03-26 | Construction method of substructure and foundation |
Country Status (1)
Country | Link |
---|---|
KR (1) | KR102549806B1 (en) |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2000192475A (en) | 1998-12-25 | 2000-07-11 | Tsuchiya Home Co Ltd | Airtight holding method in hybrid heat-insulating construction method for sill and foundation of wooden building, and its structure |
JP2002070035A (en) | 2000-08-31 | 2002-03-08 | Takiron Co Ltd | Continuous footing form |
JP2006322278A (en) | 2005-05-20 | 2006-11-30 | Uehara:Kk | Aseismatic reinforcement device |
JP2016153559A (en) | 2015-02-20 | 2016-08-25 | 株式会社ポラス暮し科学研究所 | Construction method of wooden building and foundation member used for construction method |
Family Cites Families (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR102275170B1 (en) * | 2019-05-31 | 2021-07-09 | 단국대학교 산학협력단 | A sill for an ondol building and method using the same |
-
2021
- 2021-03-26 KR KR1020210039907A patent/KR102549806B1/en active IP Right Grant
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2000192475A (en) | 1998-12-25 | 2000-07-11 | Tsuchiya Home Co Ltd | Airtight holding method in hybrid heat-insulating construction method for sill and foundation of wooden building, and its structure |
JP2002070035A (en) | 2000-08-31 | 2002-03-08 | Takiron Co Ltd | Continuous footing form |
JP2006322278A (en) | 2005-05-20 | 2006-11-30 | Uehara:Kk | Aseismatic reinforcement device |
JP2016153559A (en) | 2015-02-20 | 2016-08-25 | 株式会社ポラス暮し科学研究所 | Construction method of wooden building and foundation member used for construction method |
Also Published As
Publication number | Publication date |
---|---|
KR20220134352A (en) | 2022-10-05 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US8099918B2 (en) | Special and improved configurations for unitized post tension block systems for masonry structures | |
JP4732915B2 (en) | Foundation construction method and device, and anchor bolt support device for construction | |
US3258888A (en) | Building structure and method of erecting same | |
US20230258006A1 (en) | Anchorage template for building walls and method | |
US4378664A (en) | System for constructing a building | |
KR102549806B1 (en) | Construction method of substructure and foundation | |
CN111636691A (en) | Modularized recyclable prefabricated inner wall dowel positioning system and construction method using same | |
JP7339865B2 (en) | How to install wall panels | |
JP5527644B2 (en) | Forming method of outer underground beam, inner underground beam and post in pressure-resistant plate post foundation | |
JP2002371633A (en) | Foundation anchor bolt of building and settlement correcting method of the building | |
JP3774451B2 (en) | Slab reinforcement method | |
US5150552A (en) | Building system for extension of progressive housing | |
CN217053441U (en) | Concrete independent foundation and frame column formwork structure of construction elevator | |
KR100590178B1 (en) | Fixing apparatus of cast using a dirt wall | |
JPS6026724A (en) | Integration work of steel-framed building structure and composite underground beam | |
JP3244102U (en) | Steel house foundation structure and anchor set used therein | |
KR200298098Y1 (en) | Mold supporting structure | |
JP2000192664A (en) | Method for construction of building | |
JP7049609B2 (en) | Construction method of earthquake-resistant memorial tower and earthquake-resistant memorial tower | |
KR200348605Y1 (en) | Fixing apparatus of cast using a dirt wall | |
JP2023151597A (en) | Unit structure, and construction method of unit structure | |
JP2003013502A (en) | Strut joining hardware, joining structure of foundation and strut, manufacturing method for strut joining hardware, installation method for strut joining hardware, installation tool, and building steel product | |
JP3360234B2 (en) | Construction method of underground skeleton | |
JP2016524665A (en) | Member temporary fixing system and installation method in prefabricated construction system | |
JP2022118966A (en) | Joining structure of concrete foundation and pca column, and joining method of concrete foundation and pca column using the same |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
E701 | Decision to grant or registration of patent right | ||
GRNT | Written decision to grant |