KR101258330B1 - Temporary supporting system of steel beam and construstion method thereof - Google Patents
Temporary supporting system of steel beam and construstion method thereof Download PDFInfo
- Publication number
- KR101258330B1 KR101258330B1 KR1020100108424A KR20100108424A KR101258330B1 KR 101258330 B1 KR101258330 B1 KR 101258330B1 KR 1020100108424 A KR1020100108424 A KR 1020100108424A KR 20100108424 A KR20100108424 A KR 20100108424A KR 101258330 B1 KR101258330 B1 KR 101258330B1
- Authority
- KR
- South Korea
- Prior art keywords
- post
- steel beam
- steel
- support
- support system
- Prior art date
Links
Images
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Physics & Mathematics (AREA)
- Electromagnetism (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
- Mechanical Engineering (AREA)
Abstract
A steel beam temporary support system configured to allow construction of a steel beam extending from an outer steel column to an inner core wall before construction of the core wall, and vertically facing each other from a floor slab to correspond to a gap of the steel beam. And a support for supporting the load of the steel beam between the first post and the second post, and the first post and the second post.
Description
The present invention provides a steel beam temporary support system and its construction method, more specifically, the steel frame so that the steel beam can be installed between the outer steel column and concrete core wall before the construction of the concrete core wall located inside the ground and underground construction of the construction site The present invention relates to a beam hypothesis supporting system and a construction method thereof.
In the conventional construction and construction of civil engineering, as a construction method of connecting the reinforced concrete wall of the core and the steel structure, for example, steel beams, when the reinforced concrete wall construction is embedded in the steel plate in advance and after the concrete is poured again in the embedded steel plate Welding gusset plates and securing steel beams to them were widely used.
In this conventional method, the reinforced concrete wall must be constructed in advance before the installation of steel structures such as steel beams. To this end, it is common to pre-install the internal reinforced concrete walls using expensive system foams, which causes a lot of cost and labor to construct the internal reinforced concrete walls.
In addition, in the conventional method, there was a case in which steel pillars for installing steel structures outside the core wall were installed inside the core walls and assembled outside steel structures, but in this case, steel pillars for installing external steel structures in the interior wall concrete installation Landfilling caused excessive costs. In addition, steel pillars, which serve as temporary columns, have a lot of interference in the reinforcement work of reinforced concrete walls inside, which leads to a long work period for wall formwork and a large labor cost.
In the present invention, in order to solve the above problems, to install the steel beams in advance to install the inner core wall or to install the steel beams connected to the outer steel pillars without embedding the temporary pillars in the core wall It is an object of the present invention to provide a steel beam temporary support system and a construction method thereof capable of supporting a load of the steel beam.
Steel beam temporary support system according to the present invention is a steel beam temporary support system for constructing the steel beam extending from the outer steel pillars to the inner core wall before construction of the core wall, in the vertical direction facing each other from the floor slab A first post and a second post that are extended and spaced apart to correspond to the interval of the steel beam; It characterized in that it comprises a support for supporting the load of the steel beam between the first post and the second post.
In addition, the steel beam provisional support system according to the present invention, the sliding groove is provided on the side of the first post and the second post, respectively; The support is formed in a bar (bar) so that both ends are inserted into the sliding groove; The support block for preventing the free fall of the bar-shaped support is inserted into the sliding groove is characterized in that each installed in the sliding groove.
In addition, the steel beam provisional support system according to the present invention, characterized in that the bottom of the first post and the second post further comprises a lower fixing device of the first post and the second post.
In addition, the steel beam hypothesis supporting system according to the present invention, characterized in that it further comprises an auxiliary band configured to prevent any deformation of the first post and the second post while surrounding the outer peripheral surface of the first post and the second post. do.
In addition, the steel beam temporary support system according to the present invention, the support is composed of a bracket installed between the first post and the second post of the lower end of the steel beam in order to support the load of the steel beam; The bracket is fixed to the first post and the second post.
In addition, the steel beam hypothesis support system according to the present invention, the support is two bands surrounding the outer periphery of the first post and the second post, respectively, and to transfer the load of the steel beam to the band of the steel beam The bracket is positioned between the first post and the second post at the bottom and connected to the band.
In addition, the steel beam provisional support system according to the present invention, the steel plate is installed on the left and right sides of the web at one end close to the core wall of the steel beams in parallel to the formwork of the core wall, the steel beam of the core wall U-trap for connecting to the wall reinforcement is characterized in that coupled to the iron plate.
In addition, the steel beam provisional support system according to the present invention, characterized in that the fixing plate is installed on the upper end of the first post and the second post is coupled to the first post and the second post to the fixing plate.
In addition, another steel beam temporary support system according to the present invention is a steel beam temporary construction support system for constructing a steel beam extending from the external steel pillars to the inner core wall before construction of the core wall, the steel pillar for temporary construction ; A first base plate coupled to the bottom of the steel column; A second base plate installed on an extension line of the steel frame column so as to face the first base plate; A connecting jack bonded to the first base plate and the second base plate; The outer peripheral portion of the second base plate is characterized in that a plurality of through-holes are formed.
In addition, the method of constructing a steel beam temporary support system according to the present invention is a floor slab as a method of constructing a steel beam temporary construction support system for constructing a steel beam extending from an external steel column to an internal core wall before construction of the core wall. Constructing a steel column on the; Constructing a first post and a second post spaced apart from each other to correspond to the interval of the steel beams while extending in a vertical direction facing each other from the bottom slab to support the steel beams; And constructing a support for supporting the load of the steel beam between the first post and the second post.
In addition, the method of constructing a steel beam temporary support system according to the present invention, the support is configured in the form of a bar; Constructing sliding grooves on side surfaces of the first post and the second post, respectively; Inserting both ends of the bar-shaped support into the sliding groove; It characterized in that it further comprises the step of installing each of the support blocks in the sliding groove for preventing the free fall of the bar-shaped support is inserted into the sliding groove.
In addition, the steel beam temporary support system construction method according to the invention, characterized in that it further comprises the step of installing the lower fixing device of the first post and the second post on the bottom of the first post and the second post. .
In addition, the steel beam temporary support system construction method according to the present invention, surrounding the outer circumferential surface of the first post and the second post while installing an auxiliary band configured to prevent any deformation of the first post and the second post It is characterized in that it further comprises.
In addition, another method of constructing a steel beam temporary support system according to the present invention is a method of constructing a steel beam temporary construction support system for constructing a steel beam extending from an external steel column to an internal core wall before construction of the core wall. Constructing a steel column on the slab; Constructing a second base plate on the floor slab; Installing a connection jack on the second base plate; Installing a first base plate on the connection jack; And installing a temporary steel frame pillar on the first base plate to support the steel beam.
According to the steel beam temporary support system and the construction method of the present invention, there is no need for prior construction of the internal reinforced concrete wall used to support the steel frame in the conventional construction method, and also the need to embed steel steel in the wall none. In addition, it is also possible to reuse the steel beam temporary support system can be expected to reduce the cost of steel support, and the structural safety is increased during construction by continuing to install the steel beam temporary support system after construction.
1 is a perspective view of a steel beam temporary support system according to the present invention.
Figure 2 is a front view of the steel beam temporary support system according to the present invention.
3 is an enlarged view of a first embodiment of a support of a steel beam temporary support system according to the present invention;
4 is an enlarged view of a second embodiment of a support of a steel beam hypothesis supporting system according to the present invention;
5 is an enlarged view of a third embodiment of a support of a steel beam hypothesis supporting system according to the present invention.
Figure 6 is a view showing an embodiment in which the auxiliary band is installed on the connecting jack and the post of the lower portion of the steel beam temporary support system according to the present invention.
Figure 7 schematically shows that the steel beam hypothesis supporting system according to the invention is constructed separately between floor slabs.
8 is a view schematically showing that the steel beam temporary support system according to the present invention is constructed while being reused by being raised from two floors to a higher floor from a lower floor.
9 is a perspective view showing a structure in which a steel beam temporary support system is constructed according to the present invention.
10 is another perspective view showing the construction process of the steel beam temporary construction support system according to the present invention and the connection between the steel beam and the core wall.
11 is a perspective view of another embodiment of a steel beam temporary support system.
Hereinafter, exemplary embodiments of the present invention will be described in detail with reference to the accompanying drawings. In the accompanying drawings, similar or identical components are denoted by like or identical reference numerals.
Referring to FIGS. 1 and 2, the steel beam temporary support system of the present invention includes a
The
In addition, as shown in FIG. 3, in order to prevent the bar-
In addition, the
In addition, as shown in Figure 8 in the construction method of the steel beam temporary construction support system according to the present invention in the embodiment of vertically raised to the high floor after using the steel beam temporary construction support system, the steel beam temporary construction support The
In addition, the
In addition, as shown in FIG. 6, a connecting
In addition, as shown in FIG. 6, in order to additionally fix the
In addition, as shown in FIG. 11, in another embodiment of the steel beam temporary support system according to the present invention, a
In addition, the steel beam provisional support system according to the present invention using the
4 is a view showing another embodiment of the support of the steel beam temporary support system according to the present invention. According to the embodiment shown in FIG. 4,
5 is a view showing another embodiment of the support of the steel beam temporary support system according to the present invention. The
Steel beam hypothesis supporting system according to the present invention as described above may be constructed in the manner of manufacturing the
Hereinafter, with reference to Figures 7 to 10 will be described using a preferred embodiment of the construction method of the steel beam temporary support system according to the present invention.
9 to 10, in the method of constructing a steel beam temporary support system according to the present invention, in order to construct a steel structure on the inner side of the inner core wall, generally reinforced
7 to 8, in the method of constructing a steel beam temporary support system according to the present invention, it is common to install a steel beam temporary support system by floor as shown in FIG. 7, but it is used in a low floor as shown in FIG. 8. The steel beam hypothesis supporting system can be vertically transferred to a higher floor for reuse. To this end, the construction method of the steel beam temporary support system according to the present invention is a through hole through which the posts (1, 2) are moved through so as to vertically raise the first post (1) and the second post (2) Perforating the
In addition, as illustrated in FIG. 6, the method may further include installing
In addition, according to the present invention, the method of constructing a steel beam temporary support system may further include installing a fixing
In addition, as shown in FIG. 10, in order to construct the
Posts of the steel beam temporary construction support system according to the present invention may adopt a circular steel pipe, a square steel pipe, a support bar shape according to the site situation and the structural characteristics of the structure, the steel beam temporary construction support system to prevent rust and use period It can be tinted with antirust coating to extend.
In the above, an embodiment using two
Although the present invention has been shown and described with reference to certain preferred embodiments, the present invention is not limited to the above-described embodiments and the general knowledge in the technical field to which the present invention pertains without departing from the technical spirit of the present invention. Of course, various changes and modifications are possible. In addition, in order to explain the technical idea of the present invention, the accompanying drawings are partially enlarged and reduced, not drawn to scale.
1: first post
2: second post
3: Support
4: bottom fixing device
10: steel beam
11: temporary steel column
13a, 13b: bracket
20: core wall
21: core wall formwork
22: wall rebar
23a: band
23b: bracket
30: steel column
31: support block
40: slab
50: sliding groove
60: auxiliary band
70, 71, 72: connecting jack
90: connecting plate
91: U-trap
100: fixing plate
Claims (14)
A first post and a second post, which face each other from a floor slab and are vertically spaced apart from each other to correspond to an interval of the steel beam;
A support for supporting the load of the steel beam between the first post and the second post,
Sliding grooves are provided on side surfaces of the first post and the second post,
The support is constructed in the form of a bar (bar) is steel beam temporary support system, characterized in that both ends are inserted into the sliding groove.
Steel beam provisional support system, characterized in that the support block for preventing the free fall of the bar-shaped support is inserted into the sliding groove is installed in the sliding groove, respectively.
Steel beam provisional support system, characterized in that the bottom of the first post and the second post further comprises a lower fixing device of the first post and the second post.
And an auxiliary band configured to prevent any deformation of the first post and the second post while surrounding the outer circumferential surfaces of the first post and the second post.
Steel plates are installed in the left and right sides of the web at one end close to the core wall among the two ends of the steel beam in parallel with the formwork of the core wall.
Steel beam construction support system, characterized in that the U-trap for connecting the steel beam to the wall reinforcement of the core wall is coupled to the steel plate.
Steel plate provisional support system, characterized in that the fixing plate is installed on the upper end of the first post and the second post is coupled to the first post and the second post to the fixing plate.
Constructing steel columns on the floor slab,
Constructing first and second posts spaced to correspond to the interval of the steel beams while extending in a vertical direction while facing each other from the bottom slab to support the steel beams;
Constructing a bar-shaped support between the first post and the second post to support the load of the steel beam;
Constructing sliding grooves on side surfaces of the first post and the second post, respectively;
And inserting both ends of the support bar having a bar shape into the sliding groove.
And installing each of the support blocks in the sliding groove to prevent the bar-shaped support inserted into the sliding groove from falling freely.
And installing a lower fixing device of the first post and the second post to the bottom of the first post and the second post.
And installing an auxiliary band configured to prevent any deformation of the first post and the second post while surrounding the outer circumferential surfaces of the first post and the second post. .
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020100108424A KR101258330B1 (en) | 2010-11-02 | 2010-11-02 | Temporary supporting system of steel beam and construstion method thereof |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020100108424A KR101258330B1 (en) | 2010-11-02 | 2010-11-02 | Temporary supporting system of steel beam and construstion method thereof |
Publications (2)
Publication Number | Publication Date |
---|---|
KR20120046644A KR20120046644A (en) | 2012-05-10 |
KR101258330B1 true KR101258330B1 (en) | 2013-04-25 |
Family
ID=46265691
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
KR1020100108424A KR101258330B1 (en) | 2010-11-02 | 2010-11-02 | Temporary supporting system of steel beam and construstion method thereof |
Country Status (1)
Country | Link |
---|---|
KR (1) | KR101258330B1 (en) |
Families Citing this family (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106768992B (en) * | 2017-03-13 | 2023-11-24 | 天津城建大学 | Be suitable for experimental land beam fixing support of wall body |
CN113293993B (en) * | 2021-05-21 | 2024-08-16 | 中冶天工集团有限公司 | Supporting device for cantilever plate construction |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS6417968A (en) * | 1987-07-14 | 1989-01-20 | Fujita Corp | Method of assembling beam reinforcement |
JP2001254520A (en) * | 2000-03-09 | 2001-09-21 | Kunimoto Co Ltd | Beam form supporting method and connecting fittings |
KR200428506Y1 (en) * | 2006-07-24 | 2006-10-13 | 서정돈 | height variable support |
KR20100008920A (en) * | 2008-07-17 | 2010-01-27 | 에스앤피시스템(주) | A system support with direct connecting beam |
-
2010
- 2010-11-02 KR KR1020100108424A patent/KR101258330B1/en not_active IP Right Cessation
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS6417968A (en) * | 1987-07-14 | 1989-01-20 | Fujita Corp | Method of assembling beam reinforcement |
JP2001254520A (en) * | 2000-03-09 | 2001-09-21 | Kunimoto Co Ltd | Beam form supporting method and connecting fittings |
KR200428506Y1 (en) * | 2006-07-24 | 2006-10-13 | 서정돈 | height variable support |
KR20100008920A (en) * | 2008-07-17 | 2010-01-27 | 에스앤피시스템(주) | A system support with direct connecting beam |
Also Published As
Publication number | Publication date |
---|---|
KR20120046644A (en) | 2012-05-10 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP4823790B2 (en) | Column unit and method of building building using column unit | |
KR20120096605A (en) | Bracket support type downward construction system and method | |
KR100955788B1 (en) | A pile head reinforcement structure ofprecastconcrete pile | |
KR101600845B1 (en) | The horizontal structural frame and the underground construction methods using it | |
JP5405337B2 (en) | Construction method of railway RC ramen structure viaduct | |
KR100923564B1 (en) | Precast concrete panel, construction method and structure of precast concrete panel using steel plate | |
JP2009184756A (en) | Tower crane support structure and building method thereof | |
CN112282048B (en) | Steel pipe column and composite beam connecting node and construction method thereof | |
JP6543077B2 (en) | Construction method of structure | |
JP4235079B2 (en) | Structure of joint between reinforced concrete column and steel beam | |
KR101258330B1 (en) | Temporary supporting system of steel beam and construstion method thereof | |
JP4449875B2 (en) | Large-section tunnel structure and its construction method | |
JP2013238095A (en) | Construction method of reinforced concrete skeleton and reinforced concrete structural skeleton | |
KR100814442B1 (en) | Concrete mold for flat plate slab/flat slab and construction method using the same | |
KR101726068B1 (en) | Precast panel structure and construction method thereof | |
JP2018003559A (en) | Column-beam frame repairing method and repaired column-beam frame | |
JP6849491B2 (en) | Exposed column base structure of steel columns and its construction method | |
KR20210004289A (en) | Transfer Structure Construction Method Using U-shaped Steel Girder | |
KR200378210Y1 (en) | A pile head reinforcement structure of precastconcrete pile | |
KR20100045740A (en) | Support assembly for precast half depth cantilever deck, constructing method of such cantilever deck, bridge using such assembly and constructing method for such bridge | |
KR101485563B1 (en) | The horizontal structural frame | |
JP5345238B1 (en) | Construction method of base-isolated base structure and base-isolated base structure | |
JP5437876B2 (en) | Method of dismantling and removing support members in the construction process of RC RC ramen structure viaduct | |
JP6752006B2 (en) | Fixed structure of building unit and unit building | |
KR20070035183A (en) | Separating method of Monowall with spandrel girders |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A201 | Request for examination | ||
E701 | Decision to grant or registration of patent right | ||
GRNT | Written decision to grant | ||
LAPS | Lapse due to unpaid annual fee |