JPH0813649A - Entrance wall structure - Google Patents
Entrance wall structureInfo
- Publication number
- JPH0813649A JPH0813649A JP14437094A JP14437094A JPH0813649A JP H0813649 A JPH0813649 A JP H0813649A JP 14437094 A JP14437094 A JP 14437094A JP 14437094 A JP14437094 A JP 14437094A JP H0813649 A JPH0813649 A JP H0813649A
- Authority
- JP
- Japan
- Prior art keywords
- wall
- wall panel
- panel
- hanging
- panels
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Load-Bearing And Curtain Walls (AREA)
Abstract
Description
【0001】[0001]
【産業上の利用分野】本発明は建物の開口部に設けられ
る入口壁構造体に関する。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to an entrance wall structure provided in an opening of a building.
【0002】[0002]
【従来の技術】従来、ユニット建物等の工業化住宅で
は、特開平3-199543号公報に記載の如く、玄関開口部回
りの入口壁構造体を構成するに際し、該開口部回りに設
置される門型フレームに壁面材を取付けることにて構成
されている。2. Description of the Related Art Conventionally, in an industrialized house such as a unit building, as described in Japanese Patent Laid-Open No. 3-199543, when an entrance wall structure around an entrance opening is constructed, a gate is installed around the entrance opening. It is configured by attaching wall material to the mold frame.
【0003】[0003]
【発明が解決しようとする課題】然しながら、従来技術
には、下記〜の問題点がある。 門型フレームに壁面材を取付けるに際し、壁面材の表
面側から該壁面材を該フレームに取付けているため、取
付施工部が外観に露出し、見栄えが悪い。However, the prior art has the following problems. When the wall material is attached to the gate-shaped frame, the wall material is attached to the frame from the front side of the wall material, so that the installation portion is exposed to the outside and the appearance is poor.
【0004】工場生産した大型の門型のフレームを現
地に輸送する必要があり、輸送スペースの制約と、輸送
作業性が悪い。It is necessary to transport the large-scale gate-shaped frame produced in the factory to the site, which limits the transportation space and the workability of transportation.
【0005】入口壁構造体を建物ユニットに接合する
に際しては、壁構造体施工部分回りに足場を設け、大き
くて重い門型フレームを手作業で取り扱う必要があり、
現地作業性が悪い。When joining the entrance wall structure to the building unit, it is necessary to provide a scaffold around the wall structure construction portion and manually handle a large and heavy gate frame.
Local workability is poor.
【0006】本発明は、入口壁構造体を形成するに際
し、外観の見栄えを向上するとともに、輸送作業性、現
地作業性を向上することを目的とする。It is an object of the present invention to improve the appearance of the entrance wall structure, as well as the transportation workability and on-site workability.
【0007】[0007]
【課題を解決するための手段】請求項1に記載の本発明
は左右の袖壁パネルと、左右の袖壁パネル間の上部に固
定される垂壁パネルとからなる門型の入口壁構造体にお
いて、垂壁パネルは、壁枠組に外壁面材を取付けた外垂
壁パネルと、内壁面材に取付材を取付けた内垂壁パネル
とからなり、外垂壁パネルの壁枠組が左右の袖壁パネル
間の上部屋外側にて、袖壁パネルの壁枠組内部から該壁
枠組に取付けられ、内垂壁パネルの取付材が左右の袖壁
パネル間の上部屋内側にて、袖壁パネルの壁枠組内部か
ら該壁枠組に取付けられてなるようにしたものである。The present invention according to claim 1 is a portal type entrance wall structure comprising left and right sleeve wall panels and a hanging wall panel fixed to an upper portion between the left and right sleeve wall panels. In the above, the hanging wall panel is composed of an outer hanging wall panel in which an outer wall material is attached to the wall framework and an inner hanging wall panel in which a mounting material is attached to the inner wall material, and the wall framework of the outer hanging wall panel has left and right sleeves. Outside the upper room between the wall panels, it is attached to the wall framework from the inside of the wall framework of the sleeve wall panel, and the attachment material for the inner wall panel is inside the upper room between the left and right sleeve wall panels. It is adapted to be attached to the wall framework from inside the wall framework.
【0008】請求項2に記載の本発明は、請求項1に記
載の本発明において更に、前記袖壁パネルの壁枠組に吊
り具を設け、前記外垂壁パネルの壁枠組に吊り具を設け
てなるようにしたものである。According to a second aspect of the present invention, in addition to the first aspect of the present invention, a suspending tool is provided on the wall framework of the sleeve wall panel, and a suspending tool is provided on the wall framework of the outer hanging wall panel. It is designed to be
【0009】[0009]
【作用】請求項1に記載の本発明によれば下記、の
作用がある。 門型の入口壁構造体が左右の袖壁パネルと、垂壁パネ
ルとに3分され、更に、垂壁パネルが外垂壁パネルと内
垂壁パネルとに2分される結果、入口壁構造体の構成部
品を細分化できる。これにより、輸送スペースの自由度
を高める等、輸送作業性を向上できる。また、現地での
取扱い部品を細分軽量化でき、現地作業性が良い。According to the present invention described in claim 1, the following effects are obtained. The portal-shaped entrance wall structure is divided into left and right sleeve wall panels and a hanging wall panel, and the hanging wall panel is further divided into an outer hanging wall panel and an inner hanging wall panel. The components of the body can be subdivided. As a result, it is possible to improve the workability of transportation, such as increasing the flexibility of the transportation space. In addition, the parts handled locally can be subdivided into lighter weights, and local workability is good.
【0010】外垂壁パネルと内垂壁パネルの両方が、
袖壁パネル間の上部にて、袖壁パネルの壁枠組内部から
該壁枠組に取付けられるので、それらの取付施工部が外
壁面材と内壁面材とにサンドイッチされる如くになる。
即ち、垂壁パネルの取付施工部が外観に露出せず、見栄
えを向上できる。Both the outer wall panel and the inner wall panel are
Since it is attached to the wall framework from the inside of the wall framework of the sleeve wall panel at the upper portion between the sleeve wall panels, the mounting construction parts are sandwiched between the outer wall material and the inner wall material.
That is, the mounting construction portion of the hanging wall panel is not exposed to the outside, and the appearance can be improved.
【0011】請求項2に記載の本発明によれば下記の
作用がある。 袖壁パネルと外垂壁パネルを現地で設置するに際し、
それらの壁枠組に設けた吊り具を利用してレッカー等で
吊り作業でき、足場も必要とせず、現地作業性が良い。The present invention according to claim 2 has the following effects. When installing the sleeve wall panel and outer hanging wall panel locally,
It can be hung by a tow truck using the hangings provided on those wall frameworks, does not require a scaffold, and has good local workability.
【0012】[0012]
【実施例】図1は袖壁パネルを示す模式図、図2は袖壁
パネルの組立手順を示す模式図、図3は外垂壁パネルを
示す模式図、図4は内垂壁パネルを示す模式図、図5は
外垂壁パネルの組立手順を示す模式図、図6は内垂壁パ
ネルの組立手順を示す模式図、図7は離し置きユニット
建物の入口壁構造体を示す模式図、図8は入口壁構造体
を分解して示す模式図、図9は入口壁構造体を示す横断
面図、図10は入口壁構造体の施工手順を示す模式図、
図11は入口壁構造体の施工手順を示す模式図、図12
は入口壁構造体を示す縦断面図、図13は入口壁構造体
を示す横断面図、図14はユニット建物と建物ユニット
を示す模式図である。EXAMPLE FIG. 1 is a schematic view showing a sleeve wall panel, FIG. 2 is a schematic view showing an assembling procedure of the sleeve wall panel, FIG. 3 is a schematic view showing an outer hanging wall panel, and FIG. 4 is an inner hanging wall panel. Schematic diagram, FIG. 5 is a schematic diagram showing the assembling procedure of the outer hanging wall panel, FIG. 6 is a schematic diagram showing the assembling procedure of the inner hanging wall panel, FIG. 7 is a schematic diagram showing the entrance wall structure of the detachable unit building, FIG. 8 is a schematic view showing the inlet wall structure in a disassembled state, FIG. 9 is a cross-sectional view showing the inlet wall structure, and FIG. 10 is a schematic diagram showing a procedure for constructing the inlet wall structure.
FIG. 11 is a schematic view showing the construction procedure of the entrance wall structure, FIG.
Is a vertical sectional view showing the inlet wall structure, FIG. 13 is a horizontal sectional view showing the inlet wall structure, and FIG. 14 is a schematic view showing a unit building and a building unit.
【0013】ユニット建物10は、図14(A)に示す
如く、複数の建物ユニット11を水平、鉛直方向に隣接
配置して構築された集合住宅である。このユニット建物
10は、左右の建物ユニット11A、11Bを離し置き
し、それらの離し置き建物ユニット11A、11Bの間
に廊下12を設け、廊下12の奥側に1階奥壁構造体1
3、2階奥壁構造体14を設け、廊下12の入口側に1
階入口壁構造体15を設けている。16は階段である。As shown in FIG. 14 (A), the unit building 10 is an apartment house constructed by arranging a plurality of building units 11 adjacent to each other in the horizontal and vertical directions. In this unit building 10, left and right building units 11A and 11B are separated from each other, a corridor 12 is provided between the separated building units 11A and 11B, and the first floor back wall structure 1 is provided on the back side of the corridor 12.
The back wall structure 14 on the 3rd and 2nd floors is provided, and 1 is provided on the entrance side of the corridor 12.
A floor entrance wall structure 15 is provided. 16 is a staircase.
【0014】尚、建物ユニット11は、図14(B)に
示す如く、4本の形鋼製床梁21と、4本の角鋼管製柱
22と、4本の形鋼製天井梁23とを箱型に接合した骨
組構造体である。As shown in FIG. 14B, the building unit 11 includes four shaped steel floor beams 21, four square steel pipe columns 22, and four shaped steel ceiling beams 23. The frame structure is a box-shaped joint.
【0015】以下、入口壁構造体15、及びその入口壁
構造体15の取付構造について説明する。The inlet wall structure 15 and the mounting structure of the inlet wall structure 15 will be described below.
【0016】(A) 入口壁構造体15(図1〜図7)入口
壁構造体15は、図7に示す如く、左右の袖壁パネル3
0、30と、左右の袖壁パネル30、30の間の上部に
固定される垂壁パネル40とからなり、門型をなす。そ
して、垂壁パネル40は、外垂壁パネル50と内垂壁パ
ネル60とからなる。(A) Entrance wall structure 15 (FIGS. 1 to 7) The entrance wall structure 15 is, as shown in FIG.
0, 30 and a hanging wall panel 40 fixed to the upper portion between the left and right sleeve wall panels 30, 30 and forming a gate shape. The hanging wall panel 40 includes an outer hanging wall panel 50 and an inner hanging wall panel 60.
【0017】(A-1) 袖壁パネル30は、図1に示す如
く、壁枠組31に外壁面材32を取付けて構成されてい
る。そして、壁枠組31の両側下端部に取付脚部33、
33を備えている。また、壁枠組31の上部2位置には
吊り具34、34が設けられている。(A-1) As shown in FIG. 1, the sleeve wall panel 30 is constructed by attaching an outer wall material 32 to a wall frame 31. Then, the mounting leg portions 33 are provided at the lower end portions on both sides of the wall frame 31,
33 is provided. Further, suspenders 34, 34 are provided at the upper two positions of the wall framework 31.
【0018】以下、袖壁パネル30の組立手順について
説明する(図2)。 (1) 壁枠組31の外面に外壁面材32をリベット35及
びねじ36にて固定する。 (2) 壁枠組31の裏ナット孔に吊り具34を取付ける。The procedure for assembling the sleeve wall panel 30 will be described below (FIG. 2). (1) The outer wall material 32 is fixed to the outer surface of the wall frame 31 with the rivet 35 and the screw 36. (2) Attach the hanger 34 to the back nut hole of the wall frame 31.
【0019】(A-2) 外垂壁パネル50は、図3に示す如
く、壁枠組51に外壁面材52を取付けて構成されてい
る。そして、壁枠組51の上部2位置には、吊り具5
3、53が設けられている。(A-2) As shown in FIG. 3, the outer wall panel 50 is constructed by attaching an outer wall material 52 to a wall frame 51. Then, at the upper two positions of the wall framework 51, the hanging device 5
3, 53 are provided.
【0020】以下、外垂壁パネル50の組立手順につい
て説明する(図5)。 (1) 壁枠組51の外面に外壁面材52をリベット54に
て固定する。 (2) 壁枠組51の裏ナット孔に吊り具53を取付ける。The procedure for assembling the outer hanging wall panel 50 will be described below (FIG. 5). (1) The outer wall material 52 is fixed to the outer surface of the wall framework 51 with rivets 54. (2) Attach the hanger 53 to the back nut hole of the wall frame 51.
【0021】(A-3) 内垂壁パネル60は、図4に示す如
く、内壁面材62の両側縁部に取付材61、61を取付
けて構成されている。(A-3) As shown in FIG. 4, the inner hanging wall panel 60 is constructed by attaching mounting members 61, 61 to both side edges of an inner wall member 62.
【0022】以下、内垂壁パネル60の組立手順につい
て説明する(図6)。 (1) 内壁面材62の両側縁部に取付材61、61を位置
決めし、内壁面材62と取付材61とをリベット63に
て固定する。The procedure for assembling the inner wall panel 60 will be described below (FIG. 6). (1) The mounting materials 61, 61 are positioned on both side edges of the inner wall material 62, and the inner wall material 62 and the mounting material 61 are fixed by the rivets 63.
【0023】(B) 入口壁構造体15の取付構造(図8〜
図13) (1) 外壁パネル30の壁枠組31に設けてある吊り具3
4を用い、袖壁パネル30をレッカーで吊り、離し置き
建物ユニット11A、11Bの側部に設置されている基
礎71上に据付ける(図10(A))。袖壁パネル30
の取付脚部33をボルトナットセット72により基礎7
1のアンカーボルト71Aに固定する。(B) Mounting structure for the inlet wall structure 15 (see FIGS.
(Fig. 13) (1) Hanging device 3 provided on the wall frame 31 of the outer wall panel 30
4, the sleeve wall panel 30 is hung by a tow truck, and is installed on the foundation 71 installed on the side of the separated building units 11A and 11B (FIG. 10 (A)). Sleeve wall panel 30
Attach the mounting leg 33 of the foundation 7 with the bolt nut set 72.
1 anchor bolt 71A.
【0024】(2) 外垂壁パネル50の壁枠組51に設け
ている吊り具53を用い、外垂壁パネル50をレッカー
で吊り、外垂壁パネル50を左右の袖壁パネル30、3
0の間に入れ込む(図10(B))。外垂壁パネル50
の壁枠組51を、左右の袖壁パネル30、30の間の上
部屋外側にて、袖壁パネル30の壁枠組31内部から該
壁枠組31にボルトナットセット73で取付ける。(2) The hanging tool 53 provided on the wall frame 51 of the hanging wall panel 50 is used to hang the hanging wall panel 50 with a tow, and the hanging wall panel 50 is attached to the left and right sleeve wall panels 30, 3
It inserts between 0 (FIG.10 (B)). External wall panel 50
The wall framework 51 is mounted on the outside of the upper room between the left and right sleeve wall panels 30, 30 from inside the wall framework 31 of the sleeve wall panel 30 to the wall framework 31 with a bolt nut set 73.
【0025】(3) 袖壁パネル30の壁枠組31を、止め
ねじ74により、離し置き建物ユニット11A、11B
のスタッド24にそれらの外壁面材25を通して固定す
る(図11(B))。外垂壁パネル50の壁枠組51
を、止めねじ75により、廊下フレーム26にそれらの
天井面材27を通して固定する(図11(B))。(3) The wall frame 31 of the sleeve wall panel 30 is separated by the setscrew 74 and the building units 11A and 11B are separated.
The outer wall surface members 25 are passed through the studs 24 to be fixed (FIG. 11B). Wall frame 51 of the hanging wall panel 50
Are fixed to the corridor frame 26 by passing them through the ceiling surface members 27 (FIG. 11 (B)).
【0026】(4) 内垂壁パネル60を、外垂壁パネル5
0の裏面にて、左右の外壁パネル30、30の間に位置
付ける。そして、内垂壁パネル60の取付材61を、左
右の袖壁パネル30、30の間の上部屋内側にて、袖壁
パネル30の壁枠組31内部から該壁枠組31にボルト
ナットセット76で取付ける(図11(B))。(4) The inner hanging wall panel 60 is replaced with the outer hanging wall panel 5
It is positioned between the left and right outer wall panels 30, 30 on the back surface of 0. Then, the mounting material 61 of the inner hanging wall panel 60 is attached from the inside of the wall framework 31 of the sleeve wall panel 30 to the wall framework 31 with a bolt nut set 76 inside the upper room between the left and right sleeve wall panels 30, 30. Attach (Fig. 11 (B)).
【0027】(5) 袖壁パネル30の壁枠組31に、内壁
面材77を止めねじ78で取付ける(図11(A))。(5) The inner wall surface material 77 is attached to the wall frame 31 of the sleeve wall panel 30 with the set screw 78 (FIG. 11A).
【0028】以下、本実施例の作用について説明する。 門型の入口壁構造体15が左右の袖壁パネル30と、
垂壁パネル40とに3分され、更に、垂壁パネル40が
外垂壁パネル50と内垂壁パネル60とに2分される結
果、入口壁構造体15の構成部品を細分化できる。これ
により、輸送スペースの自由度を高める等、輸送作業性
を向上できる。また、現地での取扱い部品を細分軽量化
でき、現地作業性が良い。The operation of this embodiment will be described below. The gate-shaped entrance wall structure 15 has left and right sleeve wall panels 30,
The vertical wall panel 40 is divided into three parts, and the vertical wall panel 40 is divided into the outer vertical wall panel 50 and the internal vertical wall panel 60. As a result, the components of the inlet wall structure 15 can be subdivided. As a result, it is possible to improve the workability of transportation, such as increasing the flexibility of the transportation space. In addition, the parts handled locally can be subdivided into lighter weights, and local workability is good.
【0029】外垂壁パネル50と内垂壁パネル60の
両方が、袖壁パネル30間の上部にて、袖壁パネル30
の壁枠組31内部から該壁枠組31に取付けられるの
で、それらの取付施工部(ボルトナットセット73、7
6)が外壁面材52と内壁面材62とにサンドイッチさ
れる如くになる。即ち、垂壁パネル40の取付施工部が
外観に露出せず、見栄えを向上できる。Both the outer wall panel 50 and the inner wall panel 60 are located above the sleeve wall panel 30 at the upper portion thereof.
Since it is attached to the wall framework 31 from the inside of the wall framework 31, the mounting construction parts (bolt nut sets 73, 7)
6) is sandwiched between the outer wall surface material 52 and the inner wall surface material 62. That is, the installation work portion of the hanging wall panel 40 is not exposed to the outside, and the appearance can be improved.
【0030】袖壁パネル30と外垂壁パネル50を現
地で設置するに際し、それらの壁枠組31、51に設け
た吊り具34、53を利用してレッカー等で吊り作業で
き、足場も必要とせず、現地作業性が良い。When the sleeve wall panel 30 and the hanging wall panel 50 are to be installed at the site, they can be hung by a tow truck using the suspenders 34 and 53 provided on the wall frameworks 31 and 51, and a scaffold is also required. The local workability is good.
【0031】以上、本発明の実施例を図面により詳述し
たが、本発明の具体的な構成はこの実施例に限られるも
のではなく、本発明の要旨を逸脱しない範囲の設計の変
更等があっても本発明に含まれる。例えば、本発明の実
施において、垂壁パネルは、工場生産段階で、その壁枠
組に外壁面材と内壁面材のそれぞれを取付けられてなる
ものであっても良い。また、袖壁パネルも、工場生産段
階で、その壁枠組に外壁面材と内壁面材のそれぞれを取
付けられてなるものであっても良い。The embodiment of the present invention has been described in detail above with reference to the drawings. However, the specific configuration of the present invention is not limited to this embodiment, and changes in design within the scope not departing from the gist of the present invention can be made. Even if it exists, it is included in the present invention. For example, in the implementation of the present invention, the vertical wall panel may be one in which the outer wall material and the inner wall material are attached to the wall frame at the factory production stage. Further, the sleeve wall panel may also be one in which the outer wall material and the inner wall material are attached to the wall frame at the factory production stage.
【0032】[0032]
【発明の効果】以上のように本発明によれば、入口壁構
造体を形成するに際し、外観の見栄えを向上するととも
に、輸送作業性、現地作業性を向上することができる。As described above, according to the present invention, when forming the inlet wall structure, it is possible to improve not only the appearance but also the transport workability and on-site workability.
【図1】図1は袖壁パネルを示す模式図である。FIG. 1 is a schematic view showing a sleeve wall panel.
【図2】図2は袖壁パネルの組立手順を示す模式図であ
る。FIG. 2 is a schematic diagram showing a procedure for assembling a sleeve wall panel.
【図3】図3は外垂壁パネルを示す模式図である。FIG. 3 is a schematic view showing an outer wall panel.
【図4】図4は内垂壁パネルを示す模式図である。FIG. 4 is a schematic view showing an inner wall panel.
【図5】図5は外垂壁パネルの組立手順を示す模式図で
ある。FIG. 5 is a schematic diagram showing a procedure for assembling the outer hanging wall panel.
【図6】図6は内垂壁パネルの組立手順を示す模式図で
ある。FIG. 6 is a schematic diagram showing an assembling procedure of the inner hanging wall panel.
【図7】図7は離し置きユニット建物の入口壁構造体を
示す模式図である。FIG. 7 is a schematic view showing an entrance wall structure of a separated unit building.
【図8】図8は入口壁構造体を分解して示す模式図であ
る。FIG. 8 is a schematic view showing an inlet wall structure in an exploded manner.
【図9】図9は入口壁構造体を示す横断面図である。FIG. 9 is a cross-sectional view showing an inlet wall structure.
【図10】図10は入口壁構造体の施工手順を示す模式
図である。FIG. 10 is a schematic diagram showing a procedure for constructing an inlet wall structure.
【図11】図11は入口壁構造体の施工手順を示す模式
図である。FIG. 11 is a schematic diagram showing a procedure for constructing an inlet wall structure.
【図12】図12は入口壁構造体を示す縦断面図であ
る。FIG. 12 is a vertical cross-sectional view showing an inlet wall structure.
【図13】図13は入口壁構造体を示す横断面図であ
る。FIG. 13 is a cross-sectional view showing an inlet wall structure.
【図14】図14はユニット建物と建物ユニットを示す
模式図である。FIG. 14 is a schematic diagram showing a unit building and a building unit.
15 入口壁構造体 30 袖壁パネル 31 壁枠組 34 吊り具 40 垂壁パネル 50 外垂壁パネル 51 壁枠組 52 外壁面材 53 吊り具 60 内垂壁パネル 61 取付材 62 内壁面材 15 entrance wall structure 30 sleeve wall panel 31 wall frame 34 hanging tool 40 hanging wall panel 50 outer hanging wall panel 51 wall framework 52 outer wall material 53 hanging tool 60 inner hanging wall panel 61 mounting material 62 inner wall material
Claims (2)
間の上部に固定される垂壁パネルとからなる門型の入口
壁構造体において、 垂壁パネルは、壁枠組に外壁面材を取付けた外垂壁パネ
ルと、内壁面材に取付材を取付けた内垂壁パネルとから
なり、 外垂壁パネルの壁枠組が左右の袖壁パネル間の上部屋外
側にて、袖壁パネルの壁枠組内部から該壁枠組に取付け
られ、 内垂壁パネルの取付材が左右の袖壁パネル間の上部屋内
側にて、袖壁パネルの壁枠組内部から該壁枠組に取付け
られてなることを特徴とする入口壁構造体。1. A portal-type entrance wall structure comprising left and right sleeve wall panels and a hanging wall panel fixed to an upper portion between the left and right sleeve wall panels, wherein the hanging wall panel is a wall frame and an outer wall material. The outer wall panel is attached to the outer wall panel and the inner wall material is attached to the inner wall panel, and the wall frame of the outer wall panel is located between the left and right sleeve wall panels outside the upper room. The inside wall frame is attached to the wall frame, and the mounting material for the inner wall panel is attached to the wall frame from inside the wall frame of the sleeve wall panel inside the upper room between the left and right sleeve wall panels. The entrance wall structure characterized by.
け、前記外垂壁パネルの壁枠組に吊り具を設けてなる請
求項1記載の入口壁構造体。2. The inlet wall structure according to claim 1, wherein a suspending tool is provided on the wall framework of the sleeve wall panel, and a suspending tool is provided on the wall framework of the outer hanging wall panel.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP06144370A JP3105133B2 (en) | 1994-06-27 | 1994-06-27 | Inlet wall structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP06144370A JP3105133B2 (en) | 1994-06-27 | 1994-06-27 | Inlet wall structure |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH0813649A true JPH0813649A (en) | 1996-01-16 |
JP3105133B2 JP3105133B2 (en) | 2000-10-30 |
Family
ID=15360543
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP06144370A Expired - Fee Related JP3105133B2 (en) | 1994-06-27 | 1994-06-27 | Inlet wall structure |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP3105133B2 (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US6579475B2 (en) | 1999-12-10 | 2003-06-17 | Fmc Corporation | Lithium cobalt oxides and methods of making same |
-
1994
- 1994-06-27 JP JP06144370A patent/JP3105133B2/en not_active Expired - Fee Related
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US6579475B2 (en) | 1999-12-10 | 2003-06-17 | Fmc Corporation | Lithium cobalt oxides and methods of making same |
US6932922B2 (en) | 1999-12-10 | 2005-08-23 | Fmc Corporation | Lithium cobalt oxides and methods of making same |
Also Published As
Publication number | Publication date |
---|---|
JP3105133B2 (en) | 2000-10-30 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR20190000117A (en) | House combination apparatus | |
JPH0813649A (en) | Entrance wall structure | |
JPH0813618A (en) | Unit building | |
JP7397723B2 (en) | Building trunk structure | |
JP2000273952A (en) | Connecting device of structural material for building | |
JPH084154A (en) | Wall panel | |
KR200407075Y1 (en) | framework unit | |
JPH0519446U (en) | Suspended structure of prefabricated building | |
JPH09125671A (en) | Floor-ceiling integrated unit | |
JP2002294874A (en) | Method for manufacturing building unit | |
JP3079449B2 (en) | Sprinkler fire extinguishing equipment | |
JPS6349443Y2 (en) | ||
JP2018031188A (en) | Building unit | |
JPH084118A (en) | Unit building | |
JPH05311760A (en) | Panel mounting method | |
JPH042266Y2 (en) | ||
JPH0813617A (en) | Unit building | |
JPH0326827Y2 (en) | ||
JPH02221542A (en) | Structure for wall | |
JPH0874321A (en) | Unit building | |
JP2015094127A (en) | Partition wall and construction method of wall | |
JPH04203038A (en) | Assembly structure for corridor | |
JPH0813686A (en) | Wall panel | |
JPH0497049A (en) | Mounting construction of corner panel | |
JPH08144361A (en) | Balcony fitting structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
LAPS | Cancellation because of no payment of annual fees |