JPH0559728A - Sheathing work above underground structure - Google Patents
Sheathing work above underground structureInfo
- Publication number
- JPH0559728A JPH0559728A JP21700891A JP21700891A JPH0559728A JP H0559728 A JPH0559728 A JP H0559728A JP 21700891 A JP21700891 A JP 21700891A JP 21700891 A JP21700891 A JP 21700891A JP H0559728 A JPH0559728 A JP H0559728A
- Authority
- JP
- Japan
- Prior art keywords
- retaining
- pile
- ground
- piles
- underground structure
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Bulkheads Adapted To Foundation Construction (AREA)
Abstract
Description
【0001】[0001]
【産業上の利用分野】この発明は、建造物を構築するた
めに地面を掘削する際、土砂の崩壊を防止するために行
う山留工法に関する。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a mountain retaining method for preventing collapse of earth and sand when excavating the ground for constructing a building.
【0002】[0002]
【従来の技術】建造物、例えばビルなどを構築する際、
ビルの高層化や大規模化に伴い地下室を何層にも深く造
成することが多くなると、これに伴い構築前に地面を掘
削する必要が生じてくる。2. Description of the Related Art When constructing a building such as a building,
With the increase in the height and scale of buildings, it is becoming more necessary to excavate the ground before building the basement, as the number of layers of basement is increased.
【0003】また地下街など、地下に建造物を構築する
場合にも掘削が必要である。このような掘削において
は、周囲の土砂が崩壊しないように土留壁を設け、この
土留壁を、梁や柱で支える支保工をつくる。Excavation is also required when constructing an underground structure such as an underground shopping mall. In such excavation, a retaining wall is provided to prevent the surrounding sediment from collapsing, and a supporting structure is provided to support the retaining wall with beams and columns.
【0004】このような土留壁及び支保工を施工するた
めの山留工法には、建造物の規模の大きさや地面の状態
などいろいろな条件から、種々のものが存在する。例え
ば、図5は従来の土留工法によって作られた一般的な支
保工を内部から見た斜視図である。土留壁1を構成する
横矢板3は、H型鋼からなる親杭5によって支持され、
これら横矢板3及び親杭5は、内側に撓んでしまわない
ように腹起こし7を介して切梁9によって支えられる。
この切梁9は、相対杭する2つの土留壁1の間に設けら
れジャッキ11などで支持する力が調整されると共に、
支持杭13によって支えられている。There are various mountain retaining methods for constructing such retaining walls and supporting works, depending on various conditions such as the size of a building and the condition of the ground. For example, FIG. 5 is a perspective view of a general supporting work made by a conventional earth retaining method as seen from the inside. The horizontal sheet pile 3 that constitutes the retaining wall 1 is supported by the main pile 5 made of H-shaped steel,
The transverse sheet pile 3 and the main pile 5 are supported by the cross beam 9 via the abdomen 7 so as not to bend inside.
This girder 9 is provided between two soil retaining walls 1 that are relatively piled, and the force to be supported by the jack 11 or the like is adjusted,
It is supported by the support pile 13.
【0005】この支持杭13及び前記親杭5の一部また
は全部を、土留杭として予め地中深く打ち込むことがあ
る。このように、高層ビル等のように深く地面を掘削す
る必要がある場合には、支保工を構成する柱、すなわち
予め土留杭を地中深く打ち込んでおき、その後地面を掘
削する必要がある。例えば、まずボーリングを行い、ボ
ーリングにより形成された縦穴にコンクリートを打設し
て深礎を形成し、同時に土留杭を立て込む。そして地面
を掘り進みつつ、掘った地面の内壁に土留壁をあて、土
留杭に梁を設け土留を支持する。この支持を行いながら
さらに地面を深く掘削していく。A part or all of the support pile 13 and the parent pile 5 may be previously driven deep into the ground as a retaining pile. In this way, when it is necessary to excavate the ground deeply such as in a high-rise building, it is necessary to drive the pillars that constitute the support work, that is, the earth retaining piles into the ground beforehand and then excavate the ground. For example, boring is performed first, and concrete is placed in the vertical hole formed by boring to form a deep foundation, and at the same time, a retaining pile is erected. Then, while digging the ground, the earth retaining wall is applied to the inner wall of the excavated ground, and beams are attached to the earth retaining pile to support the earth retaining. While supporting this, the ground is further excavated deeper.
【0006】なお、深礎を形成せずに、土留杭をさらに
深く打ち込んでおくことでその替わりとすることも可能
である。しかしながら、首都圏や都市部において地下に
既にコンクリート構造物などが設けられている場合に
は、深礎を形成するためのボーリングが行えなかった
り、土留杭を深く打ち込むことができない場合がある。
このような場合には、支保工が十分に設けられないので
土留壁を支持する力が弱くなり、土砂の崩壊のおそれが
大きくなるので、土砂を固めるための薬液を大規模に注
入していた。Incidentally, it is also possible to drive the earth retaining pile further deeply without forming the deep foundation to replace it. However, when a concrete structure or the like is already provided underground in the metropolitan area or urban areas, it may not be possible to perform boring for forming a deep foundation, or it may be impossible to drive the retaining pile deep.
In such a case, since the supporting work is not provided sufficiently, the force to support the retaining wall becomes weak and the risk of collapse of the sediment increases, so a chemical solution for solidifying the sediment was injected on a large scale. ..
【0007】また、土留杭を深く打ち込むことができな
いので、土留杭の数を増大させ支保工全体の強度を高め
ていた。さらにまた、既設構造物が十分に浅い所に存在
する場合には、この既設構造物を切りまわし、あるいは
改造することにより、できるだけ十分な山留が行えるよ
うにしていた。Further, since the retaining pile cannot be driven deeply, the number of retaining piles is increased and the strength of the entire support work is increased. Furthermore, when the existing structure exists in a sufficiently shallow place, the existing structure is cut around or modified so that the mountain can be retained as much as possible.
【0008】[0008]
【発明が解決しようとする課題】しかしながら、大規模
薬液注入、土留杭の数の増大、既設構造物の切りまわし
や改造は、山留のコスト高を招くものであり、さらには
地下の既設構造物が輻輳する地区においては、これら従
来の山留工法ではきわめて多くの費用や時間がかかって
しまうものであった。However, large-scale chemical solution injection, an increase in the number of retaining piles, cutting and remodeling of existing structures lead to high cost of mountain retaining, and moreover, existing underground structures. In the area where things are congested, these conventional Yamatome construction methods are extremely expensive and time consuming.
【0009】この発明は以上の問題点を解決するために
なされたもので、地下に既設構造物を有する地区におい
ても容易に山留を行うことができ、建設コストや時間を
節約できる地下既設構造物上方における山留工法を提供
することを目的とする。The present invention has been made in order to solve the above problems, and it is possible to easily make a mountain detention even in an area having an existing underground structure, which can save construction cost and time. The purpose is to provide a mountain retaining method above the object.
【0010】[0010]
【課題を解決するための手段】この発明は以上の目的を
達成するため、地下の既設構造物に達するまで深礎掘削
を行う工程と、深礎掘削した縦穴に土留杭を立て込む工
程と、土留杭の下端を既設構造物に根固めする工程と、
根固めされた土留杭に対し切梁を設けて土留壁を支持す
る工程と、を有する山留工法である。[Means for Solving the Problems] In order to achieve the above object, the present invention comprises a step of excavating a deep foundation until reaching an existing underground structure, and a step of setting up a retaining pile in a vertical hole for excavating a deep foundation, A step of cementing the lower end of the soil retaining pile to the existing structure,
A mountain retaining method, which comprises a step of supporting a retaining wall by providing a cutting beam for the consolidated retaining pile.
【0011】また前記切梁を、地面の掘削が深く進むに
従い複数段設け、これらの切梁間に、切梁同士を連結す
る連結部材を傾斜状態に設置して支保工全体をトラス構
造として、その強化を図ることもできる。Further, the cutting beams are provided in a plurality of stages as the ground excavation proceeds deeply, and a connecting member for connecting the cutting beams to each other is installed in an inclined state between the cutting beams to form a truss structure for the entire supporting work. It can also be strengthened.
【0012】[0012]
【作用】既設構造物の強度を利用して土留杭を根固めす
れば、強度の充分な大きな支保工を作ることができ、土
留壁を確実に支持することができる。[Operation] By strengthening the soil retaining piles by utilizing the strength of the existing structure, it is possible to make a supporting structure having a sufficiently large strength and reliably support the soil retaining wall.
【0013】また支保工全体をトラス構造とした場合
は、これをさらに強固なものにすることができる。Further, when the entire supporting work has a truss structure, it can be made stronger.
【0014】[0014]
【実施例】以下、この発明の第1実施例を図1〜図4に
おいて説明する。図1はこの実施例の山留工法によって
作られた支保工の全体正面図であり、図1の土留杭の拡
大図を図2に示す。また図2の要部を図3に示す。図3
の平面図を図4に示す。DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS A first embodiment of the present invention will be described below with reference to FIGS. FIG. 1 is an overall front view of a support work made by the mountain retaining method of this embodiment, and FIG. 2 shows an enlarged view of the retaining pile in FIG. Further, FIG. 3 shows a main part of FIG. Figure 3
A plan view of is shown in FIG.
【0015】この実施例において、建造物を構築しよう
とする地区の地下には既にコンクリート構造物(既設構
造物15)が設けられている。この地区で山留を行うた
めの支保工17をつくるため、予め土留杭19を地中に
設ける必要がある。このためまず、土留杭19を設ける
位置の履行を行い、その後、掘削バケット(例えばクラ
ムシュルバケット)などにより深礎掘削を行なって縦穴
21を形成し、既設構造物15の表面にまで達する。In this embodiment, a concrete structure (existing structure 15) is already installed underground in the area where the structure is to be constructed. In order to create the support work 17 for mountain retaining in this area, it is necessary to install the retaining pile 19 in the ground beforehand. For this reason, first, the position where the soil retaining pile 19 is provided is performed, and thereafter, deep foundation excavation is performed by an excavation bucket (for example, a clam-sur-bucket) or the like to form the vertical hole 21 and reach the surface of the existing structure 15.
【0016】そして、この土留杭19を根固めするため
の、根固め工23を据え付ける。この据え付けは、図3
及び図4に示すように、既設構造物15のコンクリート
表面に細い複数の縦穴25を掘り、ケミカルアンカー2
7を設け、このケミカルアンカー27により根固め工2
3を取り付けて行う。Then, a consolidation work 23 for securing the soil retaining pile 19 is installed. This installation is shown in Figure 3.
And, as shown in FIG. 4, a plurality of thin vertical holes 25 are dug in the concrete surface of the existing structure 15 to form the chemical anchor 2
7 is provided, and this chemical anchor 27 is used for root consolidation 2
Attach with 3.
【0017】その後、土留杭19を前記深礎掘削によっ
て形成した縦穴21に立て込む。そして根固め工23に
対し土留杭19の下端を根固めする。この縦穴21は根
固め後、埋め戻す。Then, the retaining pile 19 is erected in the vertical hole 21 formed by the deep foundation excavation. Then, the bottom end of the soil retaining pile 19 is consolidated with respect to the consolidation work 23. The vertical hole 21 is backfilled after being hardened.
【0018】このようにして土留杭19を設けた後に
は、この土留杭19を元にして支保工17を作る方法は
種々の方法が考えられる。例えば、地面29を掘削しつ
つ、この土留杭19に対し土留壁1を構成するための横
矢板3を設ける。そしてさらに、この土留壁1が内側に
撓むのを防止するために腹起こし7を水平方向に設け、
この腹起こし7を切梁9で支持する。この切梁9は相対
杭する2つの土留壁1を突っ張るようにして設けられ、
中央のジャッキなどで突張力を調整する。また切梁9は
支持杭13などによって支持される。この支持杭13
は、本実施例に係る土留杭であってもよいし、あるいは
根固めの行われない単なる中間杭であってもよい。この
ような切梁9は、地面の掘削が深く進むにつれて複数段
設けられていくが、この複数段の切梁9の間を、傾斜状
態に設けられる連結部材31(切梁9と同じ材料)で連
結し、支保工17全体が強い構造物を有するトラス構造
とすることもできる。After the earth retaining piles 19 are provided in this manner, various methods can be considered as a method of forming the support work 17 based on the earth retaining piles 19. For example, while excavating the ground 29, the cross pile 3 for forming the earth retaining wall 1 is provided to the earth retaining pile 19. Further, in order to prevent the retaining wall 1 from being bent inward, a bellows raising member 7 is provided horizontally.
The abdomen 7 is supported by the beam 9. This girder 9 is provided so as to stretch two earth retaining walls 1 which are staken relative to each other,
Adjust the thrust with a jack in the center. Further, the cross beam 9 is supported by a support pile 13 or the like. This support pile 13
May be the soil retaining pile according to the present embodiment, or may be a simple intermediate pile without root consolidation. The cutting beams 9 are provided in a plurality of stages as the ground is deeply excavated, and the connecting members 31 (the same material as the cutting beams 9) provided in an inclined state between the plurality of stages of the cutting beams 9. It is also possible to form a truss structure in which the entire supporting structure 17 has a strong structure.
【0019】なお、このようにして支保工を作る際に利
用される地下の既設構造物15については、強度の確認
あるいは他の必要な状況の調査を行う。以上の実施例に
よれば、土留杭19は十分に地中深く打ち込むことがで
きないものの、すでに設けられていたコンクリート構造
物(既設構造物15)に対し根固めされるので、この土
留杭19を元に作られた支保工17は、十分に大きな強
度を有する。Regarding the existing underground structure 15 used for making the support work in this way, the strength is confirmed or other necessary conditions are investigated. According to the above-mentioned embodiment, although the soil retaining pile 19 cannot be driven sufficiently deep into the ground, it is hardened to the concrete structure (existing structure 15) already provided. The originally-supported shoring 17 has a sufficiently large strength.
【0020】また、土留杭19は、地中深く打ち込めら
れた場合に比較して単にコンクリート構造物に止められ
ているだけなので、土砂によって加えられる横方向の荷
重に対し撓みやすいが、この撓みに対し、前記トラス構
造が支保工17全体の強度を高めて支持するので、支保
工全体の安定性を増加させることができる。これによっ
て安定して土留壁1を支持することができる。Further, since the retaining pile 19 is simply stopped by the concrete structure as compared with the case where the retaining pile 19 is driven deep into the ground, the retaining pile 19 is easily deflected by the lateral load applied by the earth and sand. On the other hand, since the truss structure increases the strength of the supporting structure 17 and supports the supporting structure 17, the stability of the entire supporting structure can be increased. Thereby, the soil retaining wall 1 can be stably supported.
【0021】このように首都圏や都市部などのように、
地下に既設構造物15が輻輳する地区においても十分な
強度を有する支保工17を作ることができ、従って地下
の大規模な掘削が可能となる。Thus, like in the metropolitan area and urban areas,
Even in the area where the existing structure 15 is congested underground, the supporting structure 17 having sufficient strength can be formed, and therefore large-scale underground excavation becomes possible.
【0022】[0022]
【発明の効果】以上説明したように、この発明の地下既
設構造物上方における土留工法によれば、地下の既設構
造物を利用して土留杭を根固めし、十分に大きな強度の
支保工を設け、土留壁を支持することができるので、従
来のように土留壁を十分に支持できないため地中の土砂
を固めるための薬液を大規模に注入する必要もなく、土
留杭の数を増大させずに済み、また既設構造物を切りま
わしたり改造する手間も不要となるので、コスト及び時
間を節約して山留を行うことができる。As described above, according to the earth retaining method above the existing underground structure of the present invention, the earth retaining pile is solidified by utilizing the existing underground structure, and the supporting work of sufficiently large strength is performed. Since it can be installed and can support the retaining wall, it cannot support the retaining wall as in the past, so it is not necessary to inject a large-scale chemical solution to harden the soil in the ground, and the number of retaining piles can be increased. This eliminates the need for cutting and remodeling the existing structure, thus saving the cost and time and making the mountain stay.
【図1】 この発明の一実施例に係る山留工法による支
保工の正面図FIG. 1 is a front view of a support work by a mountain retaining method according to an embodiment of the present invention.
【図2】 図1の土留杭の拡大図FIG. 2 is an enlarged view of the soil retaining pile of FIG.
【図3】 図2の土留杭の下端を示す拡大図FIG. 3 is an enlarged view showing the lower end of the retaining pile in FIG.
【図4】 図3の水平断面図4 is a horizontal sectional view of FIG.
【図5】 従来の山留工法による支保工を内側から見た
斜視図FIG. 5 is a perspective view of a conventional shoring method, which is seen from the inside.
1 土留壁 3 横矢板 5 親杭 7 腹起こし 9 切梁 13 支持杭 15 既設構造物 17 支保工 19 土留杭 21 縦穴 23 根固め工 1 Soil retaining wall 3 Horizontal sheet pile 5 Parent pile 7 Raised belly 9 Girder 13 Support pile 15 Existing structure 17 Support work 19 Soil retaining pile 21 Vertical hole 23 Consolidation work
Claims (2)
山留工法において、地下の既設構造物に達するまで深礎
掘削を行う工程と、深礎掘削した縦穴に土留杭を立て込
む工程と、土留杭の下端を既設構造物に根固めする工程
と、根固めされた土留杭に対し切梁を設けて土留壁を支
持する工程と、を有する山留工法。1. In the mountain retaining method in an area having an existing underground structure, a step of excavating a deep foundation until reaching the existing underground structure, a step of setting up a retaining pile in a vertical hole for excavating the deep foundation, and a soil retaining method. A mountain retaining method comprising a step of consolidating a lower end of a pile to an existing structure and a step of supporting a retaining wall by providing a cutting beam for the consolidated retaining pile.
い複数段設け、これらの切梁間に、切梁同士を連結する
連結部材を傾斜状態に設置して支保工全体をトラス構造
とした請求項1の山留工法。2. A truss structure for the entire supporting work by providing the cutting beams in a plurality of stages as the ground excavation proceeds deeper and installing a connecting member connecting the cutting beams in an inclined state between the cutting beams. The Yamadome method of claim 1.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP21700891A JP2868651B2 (en) | 1991-08-28 | 1991-08-28 | Earth retaining method above existing underground structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP21700891A JP2868651B2 (en) | 1991-08-28 | 1991-08-28 | Earth retaining method above existing underground structure |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH0559728A true JPH0559728A (en) | 1993-03-09 |
JP2868651B2 JP2868651B2 (en) | 1999-03-10 |
Family
ID=16697383
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP21700891A Expired - Fee Related JP2868651B2 (en) | 1991-08-28 | 1991-08-28 | Earth retaining method above existing underground structure |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP2868651B2 (en) |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100855098B1 (en) * | 2007-05-22 | 2008-08-29 | 정택동 | Strut structure as temporary system using a vertical truss at the end and the method thereof |
CN102352629A (en) * | 2011-07-25 | 2012-02-15 | 上海建工集团股份有限公司 | Large-tonnage double-limb steel concrete combined environment-friendly supporting structure |
CN104032748A (en) * | 2014-06-10 | 2014-09-10 | 德清鑫德机械有限公司 | Opposite-brace support system for foundation pit reflex angle position |
CN105484268A (en) * | 2015-11-24 | 2016-04-13 | 上海建工一建集团有限公司 | Construction method of bottom plate of foundation pit |
JP6200550B1 (en) * | 2016-05-27 | 2017-09-20 | 鹿島建設株式会社 | Temporary deadline method, temporary deadline structure |
JP2017210865A (en) * | 2017-07-31 | 2017-11-30 | 鹿島建設株式会社 | Temporary cut-off method, temporary cut-off structure, supporting, supporting unit |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105569050A (en) * | 2015-12-29 | 2016-05-11 | 华东交通大学 | Design method of angle brace supporting structure for foundation pit with lateral pressures of adjacent boundaries being imbalanced |
-
1991
- 1991-08-28 JP JP21700891A patent/JP2868651B2/en not_active Expired - Fee Related
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100855098B1 (en) * | 2007-05-22 | 2008-08-29 | 정택동 | Strut structure as temporary system using a vertical truss at the end and the method thereof |
CN102352629A (en) * | 2011-07-25 | 2012-02-15 | 上海建工集团股份有限公司 | Large-tonnage double-limb steel concrete combined environment-friendly supporting structure |
CN104032748A (en) * | 2014-06-10 | 2014-09-10 | 德清鑫德机械有限公司 | Opposite-brace support system for foundation pit reflex angle position |
CN104032748B (en) * | 2014-06-10 | 2016-01-27 | 德清鑫德机械有限公司 | A kind of foundation ditch angle position to support support system |
CN105484268A (en) * | 2015-11-24 | 2016-04-13 | 上海建工一建集团有限公司 | Construction method of bottom plate of foundation pit |
JP6200550B1 (en) * | 2016-05-27 | 2017-09-20 | 鹿島建設株式会社 | Temporary deadline method, temporary deadline structure |
JP2017210865A (en) * | 2017-07-31 | 2017-11-30 | 鹿島建設株式会社 | Temporary cut-off method, temporary cut-off structure, supporting, supporting unit |
Also Published As
Publication number | Publication date |
---|---|
JP2868651B2 (en) | 1999-03-10 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US20220098817A1 (en) | Method for constructing structure | |
KR20200029079A (en) | Construction method for Eearth self-retaining wall using reinforcing member and CIP construction method | |
JP4069509B2 (en) | Construction method of reverse struts in the outer periphery of underground excavation space | |
KR102555541B1 (en) | Temporary retaining facility using guide bracket and ground anchor for step-by-step support of deep excavation and its construction method | |
JP2012112121A (en) | Excavation method of ground under spread foundation and base-isolating method of existing building | |
JP2000352296A (en) | Method o constructing passage just under underground structure | |
JP2868651B2 (en) | Earth retaining method above existing underground structure | |
JP2596798B2 (en) | Existing building seismic isolation method | |
KR20200029080A (en) | Construction method for earth self-retaining wall using reinforcing member and PHC pile | |
CN108035360A (en) | A kind of method for pattern foundation pit supporting structure | |
KR20000058239A (en) | Multi-phased underground construction method for wide excavation using permanent structural members as temporary struts | |
JP3129676B2 (en) | Piling columns in building structures using piles as pillars | |
JP2858997B2 (en) | Temporary support column used for reverse driving method | |
KR102195496B1 (en) | Pile for earth self-retaining wall using cast in place concrete pile with double I beam | |
JP3244324B2 (en) | Mountain retaining method | |
JP3790310B2 (en) | Construction method of the building by the prior construction of steel frame | |
JPH06341154A (en) | Construction of underground building frame | |
KR100615149B1 (en) | A method of construction top-down for the ground fabric construction | |
JPH09111754A (en) | Soldier pile cut-of wall construction method | |
CN216193926U (en) | Construction site trestle structure | |
JP2838019B2 (en) | Caisson blade framing method | |
JPS5921831A (en) | Reverse placement work | |
JPH09302682A (en) | Support structure of existing underground structure, and method of supporting it | |
JP2711748B2 (en) | Construction method of large-scale underground space | |
JPH09125405A (en) | Deep foundation for inclined tower leg |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 19981208 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20081225 Year of fee payment: 10 |
|
LAPS | Cancellation because of no payment of annual fees |