JP2894217B2 - Building structural frame - Google Patents
Building structural frameInfo
- Publication number
- JP2894217B2 JP2894217B2 JP22314294A JP22314294A JP2894217B2 JP 2894217 B2 JP2894217 B2 JP 2894217B2 JP 22314294 A JP22314294 A JP 22314294A JP 22314294 A JP22314294 A JP 22314294A JP 2894217 B2 JP2894217 B2 JP 2894217B2
- Authority
- JP
- Japan
- Prior art keywords
- floor
- pillar
- constructed
- structural frame
- frame
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Description
【0001】[0001]
【産業上の利用分野】この発明は、地下階を有して地上
1〜2階建てに構築される建物の構造架構体に関する。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a structural frame of a building having one or two floors above and below ground.
【0002】[0002]
【従来の技術】一般に、地下階を有する建物の構築にお
いては、建物の地下部分は、最初に山留め壁を構築し、
この山留め壁の内側を床付け面まで掘り下げ、その後で
構築される。2. Description of the Related Art In general, in the construction of a building having a basement floor, an underground portion of the building first constructs a retaining wall,
The inside of this retaining wall is dug down to the flooring surface, and then constructed.
【0003】この場合、地盤の掘り下げにより山留め壁
が崩壊しないように、山留め壁の内側に腹起しや切り梁
を数多く架け渡す必要があるので、多くの仮設資材を必
要とし、また、その組立に多くの手間暇を費やし、工期
の長期化が避けられず、また、仮設工事費が嵩む等の課
題があった。[0003] In this case, a large number of temporary materials are required because a large number of uprights and cut beams need to be bridged inside the mountain retaining wall so that the mountain retaining wall does not collapse due to digging of the ground. However, there is a problem in that a lot of time and labor is spent, the construction period is inevitably prolonged, and temporary construction costs are increased.
【0004】また、地上部は、地下部分の構築後に構築
し、柱と梁との接合部は、RC構造、S構造を問わずラ
ーメン構造又は筋違い入り構造としているので、接合部
が複雑になり、施工が煩雑になる等の課題があった。In addition, the above-ground part is constructed after the underground part is constructed, and the joint between the column and the beam has a rigid frame structure or a staggered structure irrespective of the RC structure or the S structure. However, there were problems such as complicated construction.
【0005】この発明は、以上の課題を解決するために
なされたもので、地下部分の構築時の仮設工事を簡略化
し、かつ、地上部の柱と梁との接合部を簡略化すること
により、工期の短縮化、工事費の低減化、更には施工性
の向上を可能にした建物の構造架構体を提供することを
目的とする。SUMMARY OF THE INVENTION The present invention has been made to solve the above-described problems, and simplifies temporary construction work when constructing an underground part and simplifies a joint between a pillar and a beam in the ground part. It is an object of the present invention to provide a structural frame of a building capable of shortening the construction period, reducing the construction cost, and further improving the workability.
【0006】[0006]
【課題を解決するための手段】この発明に係る建物の構
造架構体は、構造架構体を構成する地下一階の柱、この
柱の上に構築される一階の梁及び一階の柱を鉄筋コンク
リートによって構築し、前記柱の上端部に架設される最
上階の梁を鉄骨材によって構築し、かつ、この梁と前記
一階の柱との接合をピン接合とすることにより構成され
ている。According to the present invention, there is provided a structural frame of a building comprising a pillar on the first basement, a beam on the first floor and a pillar on the first floor which are constructed on the pillar. It is constructed by using reinforced concrete, constructing a beam on the top floor erected at the upper end of the column with a steel frame material, and joining the beam with the column on the first floor by pinning.
【0007】[0007]
実施例1.図1〜図4は、この発明に係る建物の構造架
構体の一実施例を示し、図において、符号1は構築中の
建物の架構体、2は地下一階部分に構築された架構体1
の基礎ばり、3a,3b は一階の梁、4は二階の梁、5は地
下一階の柱、6は地上一階の柱、7は一階の床スラブ、
8は二階の床スラブ、そして、符号9は架構体1を構築
するために、架構体1の周囲に構築された山留め壁であ
る。Embodiment 1 FIG. 1 to 4 show an embodiment of a structural frame of a building according to the present invention. In the drawings, reference numeral 1 denotes a frame of a building under construction, and 2 denotes a frame 1 built on the first basement floor.
3a and 3b are the first floor beams, 4 is the second floor beams, 5 is the basement first floor columns, 6 is the first floor columns, 7 is the first floor slab,
8 is a floor slab on the second floor, and 9 is a retaining wall constructed around the frame 1 to construct the frame 1.
【0008】基礎ばり2、梁3a、柱5及び柱6は、いず
れも鉄筋コンクリートによって構築されている。更に、
梁4はH形鋼等の鉄骨材によって構築されている。The base beam 2, the beam 3a, the columns 5 and the columns 6 are all made of reinforced concrete. Furthermore,
The beam 4 is constructed of a steel frame material such as an H-section steel.
【0009】尚、符号5aは架構体1の構築中、架構体1
を支持するための仮設材なので、最終的に柱5のコンク
リート中に埋め殺されるが、柱5は鉄骨鉄筋コンクリー
トとしてではなく鉄筋コンクリートとして設計されてい
る。Reference numeral 5a denotes the frame 1 during the construction of the frame 1.
Since it is a temporary material for supporting the concrete, it is finally buried in the concrete of the pillar 5, but the pillar 5 is designed not as steel reinforced concrete but as reinforced concrete.
【0010】また、梁4の端部を柱6の上端部に接合す
るには、例えば、柱6の上端部にアンカーボルトを突設
し、このアンカーボルトを介して梁4の端部を柱6の上
端部に接合する等して、接合部に曲げモーメントが発生
しないようになっている。In order to join the end of the beam 4 to the upper end of the column 6, for example, an anchor bolt is projected from the upper end of the column 6, and the end of the beam 4 is connected to the column via the anchor bolt. No bending moment is generated at the joint, for example, by joining to the upper end of 6.
【0011】また、床スラブ7及び8は、梁3a及び4の
上にPC板を敷設するか、若しくはデッキプレートを敷
設し、その上にコンクリートを打設する等して構築され
ている。The floor slabs 7 and 8 are constructed by laying a PC board on the beams 3a and 4 or laying a deck plate and casting concrete thereon.
【0012】このような構成において、地上1階の柱6
は一階の梁3aを固定端とする片持ち柱とし、二階の梁4
は柱6を支点とする単純ばりとして設計され(図7参
照)、従って、梁4は柱6との接合部を剛接合となるよ
うな加工を施す必要がなく、加工度のきわめて少ない鉄
骨材で構築できる。In such a configuration, the first floor pillar 6
Is a cantilever with the beam 3a on the first floor as the fixed end and the beam 4 on the second floor
Is designed as a simple beam with the column 6 as a fulcrum (see FIG. 7). Therefore, the beam 4 does not need to be processed so that the joint with the column 6 becomes a rigid joint, and is a steel frame material with a very small degree of processing. Can be built with
【0013】実施例2.図5は、この発明に係る建物の
構造架構体の他の実施例を示し、図において、実施例1
と同一部分には同一符号を付し、その説明を省略する。Embodiment 2 FIG. FIG. 5 shows another embodiment of the structural frame of the building according to the present invention.
The same parts as those described above are denoted by the same reference numerals, and description thereof will be omitted.
【0014】符号10は二階の柱、11は屋上階の梁であ
り、いずれも、H形鋼等の鉄骨材が使用され、また、柱
10と梁11とは、高力ボルトによるボルト接合によって接
合され、原則として接合部に曲げモーメントが発生しな
いようになっているが(図6参照)、剛接合とすること
により曲げモーメントを負担させる場合もある。Reference numeral 10 denotes a column on the second floor, and 11 denotes a beam on the roof floor. In each case, a steel frame material such as an H-section steel is used.
The beam 10 is joined to the beam 11 by bolt joints using high-strength bolts. In principle, no bending moment is generated at the joint (see FIG. 6). In some cases.
【0015】実施例3.次に、この発明に係る建物の構
造架構体の構築工法を順を追って説明する。Embodiment 3 FIG. Next, a method of constructing a structural frame of a building according to the present invention will be described step by step.
【0016】(1) 最初に、構築される架構体1の周囲に
山止め壁9を所定深さに構築する。山止め壁9は、親杭
横矢板工法やSMW工法等といった従来一般に行われて
いる工法によって構築する。(1) First, a retaining wall 9 is constructed at a predetermined depth around the frame 1 to be constructed. The retaining wall 9 is constructed by a generally used construction method such as a parent pile horizontal sheet pile construction method or an SMW construction method.
【0017】(2) 次に、構築される柱5の位置に、構真
柱5aを所定深さに設置する。構真柱5aは架構体1の構築
中は構築中の架構体を支持する仮設柱として機能し、H
形鋼等が使用される。(2) Next, at the position of the pillar 5 to be constructed, a straight pillar 5a is installed at a predetermined depth. While the frame 1 is being constructed, the pillar 5a functions as a temporary pillar for supporting the frame under construction.
Section steel or the like is used.
【0018】(3) 次に、山留め壁9の内側を全体に渡っ
て一定深さ掘削する。この場合の掘削深さは、構築され
る梁3a,3b の下端部よりやや下方までとする。(3) Next, the inside of the retaining wall 9 is excavated at a constant depth over the whole. The excavation depth in this case shall be slightly below the lower end of the beams 3a, 3b to be constructed.
【0019】(4) 次に、掘削底面を作業足場として梁3
a,3b を構築する。梁3a,3b は鉄筋コンクリート構造に
よって構築し、構真柱5aの上端部に架け渡す。(4) Next, the beam 3
Construct a, 3b. The beams 3a and 3b are constructed by a reinforced concrete structure, and are bridged over the upper end of the timber column 5a.
【0020】(5) 次に、山留め壁9に沿って構築された
梁3bを腹起しとし、これに直角に架け渡された梁3aを切
り梁として、山留め壁9の内側を更に掘削し、構築され
る基礎ばり2のやや下方まで掘り下げる。(5) Next, the inside of the retaining wall 9 is further excavated by using the beam 3b constructed along the retaining wall 9 as a bulge, and using the beam 3a bridged at right angles thereto as a cutting beam. Dig down slightly below the foundation beam 2 to be built.
【0021】この場合、梁3a,3b を山留め壁9を支持す
るための腹起し及び切り梁として利用できるので、山留
め壁9を支持するための腹起し及び切り梁をあえて設置
する必要がなく、仮設工事の省略化が図れる。In this case, since the beams 3a and 3b can be used as bulging and cutting beams for supporting the retaining wall 9, it is necessary to dare install the bulging and cutting beams for supporting the retaining wall 9. Therefore, temporary construction can be omitted.
【0022】(6) 次に、掘削底を整地し、その上に基礎
ばり2を基礎スラブ(図省略)と一体に構築する。(6) Next, the excavated bottom is leveled, and the foundation beam 2 is built thereon integrally with the foundation slab (not shown).
【0023】(7) 次に、構真柱5aの周囲に必要量の補強
鉄筋(図省略)を配筋し、かつ、コンクリートを打設す
ることにより鉄筋コンクリート構造の柱5を基礎ばり2
及び梁3a,3b と一体的に構築する。(7) Next, a necessary amount of reinforcing steel bars (not shown) are arranged around the trussed pillars 5a, and concrete is cast into the pillars 5 having a reinforced concrete structure to form a foundation beam 2
And the beam 3a, 3b.
【0024】(8) 次に、柱5の上に柱6を鉄筋コンクリ
ートによって構築する。柱6は柱5と連続するように構
築する。(8) Next, the pillar 6 is constructed on the pillar 5 by reinforced concrete. The pillar 6 is constructed so as to be continuous with the pillar 5.
【0025】(9) 次に、柱6の上端部に梁4を架け渡
す。梁4にはH形鋼等の鉄骨材を使用し、また、梁4は
柱6の上端部に高力ボルトを使用したボルト接合によっ
て接合する。(9) Next, the beam 4 is bridged over the upper end of the column 6. The beam 4 is made of a steel material such as an H-section steel, and the beam 4 is joined to the upper end of the column 6 by bolting using a high-strength bolt.
【0026】(10) そして、最後に、梁3及び梁4の上
にPC板を敷設するか、若しくはデッキプレートを敷設
し、その上にコンクリートを打設する等して床スラブ7
を構築する。(10) Finally, a PC board or a deck plate is laid on the beams 3 and 4 and concrete is cast on the deck plate and the like, and the floor slab 7 is laid.
To build.
【0027】実施例4.図7は、この発明に係る建物の
構造架構体の構築工法の他の実施例を示し、山留め壁9
が支持強度のきわめて大きい地盤に支持されている場合
に、梁3aの側部に水平にブラケット10を突設し、このブ
ラッケト10を山留め壁9内の鋼杭(図省略)載置し、梁
3aの荷重を山留め壁9に負担させるようにしたものであ
り、この実施例によれば、本来、架構体1の周囲に設置
される鋼真柱及びその設置手間を省略できる効果があ
る。Embodiment 4 FIG. FIG. 7 shows another embodiment of the method of constructing a structural frame of a building according to the present invention, wherein a retaining wall 9 is provided.
Is supported on the ground having extremely large supporting strength, a bracket 10 is protruded horizontally on the side of the beam 3a, and the bracket 10 is placed on a steel pile (not shown) in the retaining wall 9;
The load of 3a is applied to the retaining wall 9, and according to this embodiment, there is an effect that the steel pillars originally installed around the frame 1 and the labor for installing them can be omitted.
【0028】[0028]
【発明の効果】この発明は、以上説明したように構成さ
れ、建物の構造架構体を構成する一階の梁が剛性のきわ
めて大きい鉄筋コンクリートによって構築されているの
で、地下部分の構築に際し、この一階の梁を構造架構体
の周囲に構築された山留め壁を支持する腹起し及び切り
梁として利用できるので、敢えて腹起しや切り梁を設置
する必要がなく、地下部分の仮設工事の省略化及び仮設
工事費の大幅低減化が図れる効果がある。The present invention is constructed as described above, and the beam on the first floor constituting the structural frame of the building is constructed of reinforced concrete having extremely high rigidity. Since the beams on the floor can be used as ridges and beams to support the retaining wall built around the structural frame, there is no need to install ridges or beams, and temporary construction work in the underground is omitted. This has the effect of greatly reducing construction costs and temporary construction costs.
【0029】また、一階の柱は一階の梁の上にこの梁と
一体に剛性のきわめて大きい鉄筋コンクリートによって
構築されているので、一階部分の強度及び水平剛性がき
わめて大きく、このため、敢えて耐震壁や筋違い等の耐
震要素を設置する必要がなく、壁等を非構造材で構築で
きる効果がある。Further, since the first-floor columns are constructed on the first-floor beams integrally with the beams by reinforced concrete having extremely high rigidity, the first-floor portions have extremely high strength and horizontal rigidity. There is no need to install earthquake-resistant elements such as earthquake-resistant walls and streaks, and there is an effect that walls and the like can be constructed with non-structural materials.
【0030】更に、この柱の上端部に架設される最上階
の梁は鉄骨材によって構築され、かつ、この梁と前記柱
との接合はアンカーボルト等を利用してピン接合として
いるので、梁の端部に剛接合となるような複雑な加工を
施す必要がなく、施工が簡単になり施工性の大幅な向上
が図れる効果がある。Further, the beam on the top floor, which is erected at the upper end of the column, is constructed of a steel frame material, and the beam and the column are joined with pins using an anchor bolt or the like. There is no need to perform a complicated process to form a rigid joint at the end of the slab, which simplifies the construction and has the effect of greatly improving the workability.
【図1】この発明に係る建物の構造架構体の一実施例を
示す図2におけるa−a線断面図である。FIG. 1 is a sectional view taken along a line aa in FIG. 2 showing an embodiment of a structural frame structure of a building according to the present invention.
【図2】図1に示す建物の構造架構体の縦断面図であ
る。FIG. 2 is a longitudinal sectional view of a structural frame of the building shown in FIG. 1;
【図3】図2に示す建物の構造架構体のb−b線断面図
である。FIG. 3 is a sectional view taken along line bb of the structural frame of the building shown in FIG. 2;
【図4】この発明に係る建物の構造架構体の構築工法を
示す縦断面図である。FIG. 4 is a longitudinal sectional view showing a construction method of a structural frame of a building according to the present invention.
【図5】この発明に係る建物の構造架構体の他の実施例
を示す縦断面図である。FIG. 5 is a longitudinal sectional view showing another embodiment of the structural frame of the building according to the present invention.
【図6】この発明に係る建物の構造架構体の応力図であ
る。FIG. 6 is a stress diagram of a structural frame of a building according to the present invention.
【図7】この発明に係る建物の構造架構体の他の構築工
法を示す縦断面図である。FIG. 7 is a longitudinal sectional view showing another construction method of the structural frame of the building according to the present invention.
1…建物の架構体、2…基礎ばり、3a,3b …一階の梁、
4…二階の梁、5…地下一階の柱、6…地上一階の柱、
7…一階の床スラブ、8…二階の床スラブ、9…山留め
壁。1 ... building frame, 2 ... foundation beam, 3a, 3b ... 1st floor beam,
4 ... Beam on the second floor, 5 ... Pillar on the first floor underground, 6 ... Pillar on the first floor above ground,
7: floor slab on the first floor, 8: floor slab on the second floor, 9: retaining wall.
Claims (1)
される建物の構造架構体において、前記構造架構体を構
成する地下一階の柱、この柱の上に構築される一階の梁
及び一階の柱を鉄筋コンクリートによって構築し、前記
柱の上端部に架設される最上階の梁を鉄骨材によって構
築し、かつ、この梁と前記一階の柱との接合をピン接合
としたことを特徴とする建物の構造架構体。1. A structural frame of a building having one or two stories above the ground with a basement floor, a pillar on the first basement floor constituting the structural frame, and a pillar built on the pillar. The beam on the floor and the pillar on the first floor are constructed by reinforced concrete, the beam on the top floor constructed at the upper end of the pillar is constructed by steel frame material, and the joint between the beam and the pillar on the first floor is pin-joined. A structural frame of a building, characterized in that:
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP22314294A JP2894217B2 (en) | 1994-09-19 | 1994-09-19 | Building structural frame |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP22314294A JP2894217B2 (en) | 1994-09-19 | 1994-09-19 | Building structural frame |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH0886020A JPH0886020A (en) | 1996-04-02 |
JP2894217B2 true JP2894217B2 (en) | 1999-05-24 |
Family
ID=16793452
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP22314294A Expired - Lifetime JP2894217B2 (en) | 1994-09-19 | 1994-09-19 | Building structural frame |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP2894217B2 (en) |
Families Citing this family (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2008038597A (en) * | 2006-12-28 | 2008-02-21 | Fujika:Kk | Evacuation device from emergency such as tsunami wave or flood |
JP6119074B2 (en) * | 2012-12-06 | 2017-04-26 | 株式会社竹中工務店 | Construction method and rebuilding method |
-
1994
- 1994-09-19 JP JP22314294A patent/JP2894217B2/en not_active Expired - Lifetime
Also Published As
Publication number | Publication date |
---|---|
JPH0886020A (en) | 1996-04-02 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JPH09268583A (en) | Structural steel embedded half precast concrete member and construction method of underground structure using the same member | |
JP4550534B2 (en) | Building basic structure | |
JPH11172710A (en) | Method for constructing underground part of steel encased reinforced concrete building | |
JP2894217B2 (en) | Building structural frame | |
JPH0684690B2 (en) | Building basement extension method | |
JP2979117B2 (en) | Building foundation method | |
JPH11140892A (en) | Method for excavating ground and method for constructing underground structure using the same | |
JP2769937B2 (en) | Steel tube concrete column in underground reverse driving method | |
JPH0657769A (en) | Underground concrete structure and working method thereof | |
JP2572680B2 (en) | Underground structure by reverse strike method | |
JPH08302689A (en) | Construction method for skeleton of underground exterior wall | |
JPH07119465B2 (en) | Underground excavation construction method | |
JPH08291526A (en) | Construction method for underground structure | |
JP3567387B2 (en) | How to build an underground skeleton | |
JPS63277342A (en) | Reverse execution of underground story | |
JP2959436B2 (en) | How to build underground structures | |
JP3061934B2 (en) | Retaining wall construction method | |
JP2002188163A (en) | First-story floor preceding underground construction method | |
JPH0759813B2 (en) | Underground construction method | |
JP3002795B2 (en) | How to build a building with a basement | |
KR20220094841A (en) | Middle connecting structure of steel pilar and construction method thereof | |
JPH0467532B2 (en) | ||
JPH07331784A (en) | Flat slab structure and execution method | |
JP3238510B2 (en) | Construction method of preceding slab floor | |
JPH03132521A (en) | Strut construction method of basement floor excavation work |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 19990202 |