EP0943745A2 - Anchoring device for a tension bar in a reinforced concrete mass - Google Patents
Anchoring device for a tension bar in a reinforced concrete mass Download PDFInfo
- Publication number
- EP0943745A2 EP0943745A2 EP99810233A EP99810233A EP0943745A2 EP 0943745 A2 EP0943745 A2 EP 0943745A2 EP 99810233 A EP99810233 A EP 99810233A EP 99810233 A EP99810233 A EP 99810233A EP 0943745 A2 EP0943745 A2 EP 0943745A2
- Authority
- EP
- European Patent Office
- Prior art keywords
- holder
- rod
- opening
- parts
- protective tube
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04C—STRUCTURAL ELEMENTS; BUILDING MATERIALS
- E04C5/00—Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
- E04C5/08—Members specially adapted to be used in prestressed constructions
- E04C5/12—Anchoring devices
Definitions
- the invention relates to a device for anchoring a tie rod in a reinforced concrete mass, with one for laying and fastening on the Reinforcement provided holder element, the tie rod the holder element penetrates and through the holder element at a predetermined angle is held to the support plane of the holder element.
- Single-sided concrete walls are made with the help of trestles.
- the up for complete hardening of the concrete mass to be picked up from the trestles Concrete pressure is introduced into the ground via tension rods.
- the Tension rod via a holder plate tied to the upper reinforcement layer fixed for concreting.
- the holder plate has a correspondingly angled V-shaped Middle part on.
- This guide part enables a stable position and direction Installation of the tie rod.
- the disadvantage of this anchoring device is that in addition to the holder plate, a separate guide sleeve for the tie rod must be provided, mainly due to the increase of the production costs for the anchoring device.
- the invention is therefore based on the object of a device at the outset to create the type mentioned, which overcomes the aforementioned disadvantages, is inexpensive to manufacture and easy to use position and directionally stable installation of a tie rod enables.
- the holder element leads to the achievement of the object according to the invention consists of two holder parts, at least a first holder part one for Implementation of the tie rod provided opening, the opening width is selected in at least one direction so that the maximum possible Tilt angle of the tie rod corresponds to the installation angle, and where the second holder part is arranged at a distance from the opening in the first holder part Stop for fixing the tension rod in the specified installation angle having.
- At least those holder parts which have openings as plate-shaped flat parts designed, wherein the holder element preferably from a single Flat part blank is shaped.
- the second one Holder part also an opening provided for the passage of the tie rod on.
- the stop for fixing the tie rod in the predetermined installation angle formed by part of the opening are the plate-shaped flat parts in this embodiment arranged parallel to each other, so that openings of the same dimension can be arranged. Basically, however the two holder parts in a wide range at any angle to each other stand.
- the plate-shaped flat parts are essentially vertical arranged to each other.
- the second holder part is preferably made of Part of the first holder part is punched out and out of the support plane of the holder element bent into its final position.
- the two are Holder parts formed from rod or wire material
- the holder element is preferably formed from a single bar or wire blank.
- the main advantage of the holder element according to the invention over The holder plates according to the prior art is that the holder parts in a simple way for screwing a tie rod into the holder element can be prepared by just the shape of the openings in the holder parts and, if necessary, the mutual distance between the two openings in the holder parts to the thread of a screwable into the holder element Must be adjusted.
- the invention Device penetrates one provided for receiving the tie rod Protection tube the openings in the holder parts and is non-positive in these and held in the specified installation angle via the stop.
- the Protective tube is put together a sleeve-shaped anchoring element, this anchoring element on the one hand a threaded part for a this usable tie rod and on the other hand an anchoring part for Remains in the concrete mass.
- any materials can be used to manufacture the holder element are used, which meet the requirements regarding deformability, mechanical strength and corrosion resistance.
- a preferred one Material is steel, but there are also designs in, for example Plastic or composite materials possible.
- Anchoring device with a protective tube are the openings in the holder parts designed so that the standardized and on construction sites Spacer tubes usually used in the inventive Holder element can be used and the specified installation angle without further measures.
- the outside diameter is the same of the sleeve-shaped anchoring element in the area of it Plug connection with the protective tube the inside diameter of the standardized Spacer tubes adapted. This has the advantage of being a standard spacer tube in the anchoring element according to the invention without further ado Protection tube can be used.
- a holder element 10 for a tie rod 12 shown in FIGS. 1 to 3 or for a protective tube 14 provided for receiving a tension rod has a strip-shaped support plate 16. Approximately in the middle of a longitudinal side edge the support plate 16 protrudes at right angles to this and with a Inclination according to the axial direction z of the tie rod 12 or a protective strip 14 from a side strip 18. The free end of the side strip 18 is bent at right angles to a holder strip 20, so that it is cross-sectional results in a C-shaped profile, the support plate 16 and the holder strips 20 are parallel to each other.
- an opening 22, 24 is arranged for the passage of the tie rod 12 and the protective tube 14, respectively.
- the dimension of the openings 22, 24 at a distance from one another is selected such that the tension rod 12 or the protective tube 14 inserted into the holder element 10 assumes the maximum possible angle of inclination and is thus held in the holder element 10 in a positive and / or non-positive manner .
- the maximum possible installation angle of the tension rod 12 or the protective tube 14 corresponds to the predetermined installation angle ⁇ with respect to a support plane E defined by the support plate 16.
- the shape and the dimension of the two openings 22, 24 can vary within wide limits.
- the opening width in the direction of inclination is decisive for setting the installation angle ⁇ ; this is corresponding to the installation angle ⁇ to be set larger than the diameter D of the tension rod 12 or the protective tube 14.
- the shape of the opening 22, 24 is, for example, an ellipse, the small diameter Y of which essentially corresponds to the diameter D of the tension rod 12 or the protective tube 14 corresponds and whose large diameter X is selected so that the desired installation angle ⁇ between the rod or protective tube axis z and the support plane E is obtained.
- strip-shaped platen 16 are to facilitate tying the holder plate 10 on a reinforcement layer longitudinal slots 26 for Carrying iron trusses arranged.
- the strip-shaped Platen 16 at one end to form the side stripe 18 and the holder strip 20 bent twice at right angles.
- the support plate is also here 16 and the holder strip 20 arranged parallel to each other.
- the location of the openings 22, 24 corresponds to that of FIG. 1.
- a holder element 10 shown in FIG. 5 is made of a sheet metal blank to form a U-shaped cross section with parallel mutually standing leg strips 28, 30 are formed.
- openings 32, 34 are arranged in pairs. These openings 32, 34 can have the same or different dimensions in pairs and also define different installation angles ⁇ . This makes it possible only holder element for tie rods 12 or protective tubes 14 different To provide diameters. It should be noted here that for a screw-in tie rod, the shape of the openings and, if applicable, mutual distance of the openings can be easily adjusted can.
- FIG. 6 shows a holder element 10 in which the strip-shaped support plate 16 is bent at the end to the holder strip 20.
- the tie rod 12 or that Protective tube 14 penetrates the opening 22 in the support plate 16 and is from Holder strip 20, the free end of which forms a stop 36, in its Installation angle a corresponding maximum inclination angle fixed.
- FIG. 7 is the same in the embodiment of a holder element 10 according to FIG Way as in the embodiment according to FIGS. 1 to 3 on the platen 16 approximately in the middle of one of its longitudinal edges of the side strips 18 below Formation of a stop strip 42 bent twice at right angles.
- This Embodiment corresponds essentially to that of FIGS. 1 to 3, wherein however, only the opening 22 is present in the platen and the holder strip 20 with opening 24 on the minimally required stop strips 42, whose one longitudinal edge forms the stop 36 has been reduced.
- Fig. 8 is a modification of the holder element of Fig. 7, wherein the stop strip 42 chosen so wide and positioned is that it has two stops 36a, b for the two possible tilt positions the tension rod 12 or the protective tube 14 offers.
- this Holder element can thus be a tension rod 12 penetrating opening 22 or a protective tube 14 can be positioned in two different directions.
- holder element 8 modified variant is instead of the wide stop strip 42 a holder part with two differently dimensioned openings for example for a tie rod and a protective tube.
- the opening 22 in the holder part 16 is dimensioned in this case so that it forms a stop for both a tie rod and a protective tube.
- FIGS. 9 to 11 10 are two instead of a strip-shaped support plate 16
- Support strips 38, 40 are provided.
- a first support strip 38 protrudes from the side strip in one direction in the support plane E.
- the second support strip 40 is with the side strip 18 via a stop strip 42 forming connecting web and protrudes into the first contact strip 38 opposite direction in the support plane E.
- From the hard shoulder 18 protrudes at right angles from the holder strip 20 with the opening 24.
- An in the opening 24 inserted tie rod 12 or a protective tube 14 is from Stop 42 in its inclined position predetermined by opening 24 Formation of the installation angle a held non-positively.
- the support strips 38, 40 rising from the support level E are on their Roughened upper edge or provided with teeth 44. This gives a better position stabilization of the holder element 10, if this with Iron trusses are tied to a reinforcement. Of course you can the support strips 38, 40 also with slots or holes for implementation be provided by iron binders.
- the embodiment variant of a holder element 10 shown in FIG. 12 is from a wire or rod 46 formed.
- a first support loop 48 forms the support plane E.
- An additional turn delimits an opening 50 for Implementation of a tie rod 12 or a protective tube 14.
- the wire or the rod 46 is to a further holder loop 52 as a second opening formed at a distance a from the first opening 50.
- 12 is readily understandable that instead of a closed holder loop 52, a stop for fixing the tension rod 12 or the protective tube 14 in its maximum, the inclination corresponding to the installation angle ⁇ is sufficient.
- Opening loops for the passage of a tie rod or a protective tube to arrange, such as above in connection with that of Fig. 8 modified embodiment is described.
- FIGS. 1 to 12 and 14 and 15 represent only a small selection from a large number of possible variations a holder element with two openings or one opening and a stop for fixing a tie rod or a protective tube represents.
- an anchoring device shown in FIG. 13 1 is a protective tube 14 made of plastic inserted into the openings 22, 24 in the support plate 16 or in the holder strip 20.
- An anchoring element 56 with a threaded part 58 and one Anchoring part 60 is inserted into protective tube 14 at one end.
- the tie rod 12 passes through the protective tube 14 and is with the threaded part 58 of the anchoring element 56 screwed.
- the free end of the protective tube 14 is a closure cap 62 is placed. From the inner wall of the cap 62 protrudes an integrally molded flexible and tapering inward trained sealing ring 64 from, the clear width about the core diameter of the tie rod 12 used corresponds.
- an opening for the tie rod 10 to be used later closing plug 66 may be provided as a lid.
- the anchoring element 56 is positioned before the pouring the concrete mass 68 by tying the holder element 10 to the upper Reinforcement layer 54 of reinforcement.
- the holder member 10 can Slots 26 are tied in the platen 16.
- a wall formwork created and supported on trestles After pouring and hardening the concrete mass 68, a wall formwork created and supported on trestles.
- the trestles are in in a known manner via the tie rod protruding from the concrete mass 68 12 anchored. It is particularly important that the tension rod in an angle of 45 ° to the foundation is built in, because of the manufacturing the concrete pressure on the wall is anchored in the floor slab or must be introduced into the foundation. Because the dimension of Openings 22, 24 in the support plate 16 and in the holder strip 20 are selected in this way is that an inserted tie rod or a protective tube with the support level E of the support plate 16 the predetermined angle ⁇ of 45 °, for example forms, the angle of inclination of the protective tube 14 to the foundation professional arrangement of the holder element also 45 °. After making the wall becomes the tie rod 12 from the anchoring element 56 unscrewed and can be used again. That in the concrete mass 68 Protective tube 14 remaining is then cut off at ground level.
- a second holder part 70 is partially punched out of the strip-shaped support plate 16 and at right angles leaving an opening 72 in the platen 16 bent over to this.
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Joining Of Building Structures In Genera (AREA)
- Reinforcement Elements For Buildings (AREA)
- Piles And Underground Anchors (AREA)
Abstract
Description
Die Erfindung betrifft eine Vorrichtung zur Verankerung eines Spannstabes in einer bewehrten Betonmasse, mit einem zur Auflage und Befestigung auf der Bewehrung vorgesehenen Halterelement, wobei der Spannstab das Halterelement durchdringt und durch das Halterelement in einem vorgegebenen Winkel zur Auflageebene des Halterelementes gehalten ist.The invention relates to a device for anchoring a tie rod in a reinforced concrete mass, with one for laying and fastening on the Reinforcement provided holder element, the tie rod the holder element penetrates and through the holder element at a predetermined angle is held to the support plane of the holder element.
Einhäuptige Betonwände werden mit Hilfe von Stützböcken hergestellt. Der bis zum vollständigen Aushärten der Betonmasse von den Stützböcken aufzunehmende Betondruck wird über Spannstäbe in den Boden eingeleitet.Single-sided concrete walls are made with the help of trestles. The up for complete hardening of the concrete mass to be picked up from the trestles Concrete pressure is introduced into the ground via tension rods.
Bei der Verankerung von Stützböcken in Bodenplatten oder Fundamenten ist der lage- und richtungsstabile Einbau der Verankerungsteile von wesentlicher Bedeutung. Insbesondere muss streng darauf geachtet werden, dass der üblicherweise mit einem Verankerungselement bestückte Spannstab in einem Winkel von 45° zur Ebene der Bodenplatte bzw. des Fundamentes eingebaut wird.When anchoring trestles in floor slabs or foundations the positionally and directionally stable installation of the anchoring parts is essential Meaning. In particular, care must be taken to ensure that the usual tension rod equipped with an anchoring element in one Angle of 45 ° to the level of the base plate or the foundation installed becomes.
Bei einer aus DE-C-42 34 892 bekannten Verankerungsvorrichtung wird der Spannstab über eine auf der oberen Bewehrungslage festgebundene Halterplatte zum Einbetonieren fixiert. Zur Einhaltung des genannten Einbauwinkels von 45° weist die Halterplatte einen entsprechend abgewinkelten V-förmigen Mittelteil auf. In einer der beiden Schenkelteile des V-förmigen Mittelteils ist eine den Schenkelteil durchsetzende Hülse zur Durchführung des Spannstabes eingesetzt. Dieses Führungsteil ermöglicht einen lage- und richtungsstabilen Einbau des Spannstabes. Der Nachteil dieser Verankerungsvorrichtung liegt darin, dass zusätzlich zur Halterplatte eine separate Führungshülse für den Spannstab bereitgestellt werden muss, was sich vor allem auf die Erhöhung der Gestehungskosten für die Verankerungsvorrichtung auswirkt.In an anchoring device known from DE-C-42 34 892 the Tension rod via a holder plate tied to the upper reinforcement layer fixed for concreting. To maintain the specified installation angle of 45 °, the holder plate has a correspondingly angled V-shaped Middle part on. In one of the two leg parts of the V-shaped middle part a sleeve passing through the leg part for carrying out the tension rod used. This guide part enables a stable position and direction Installation of the tie rod. The disadvantage of this anchoring device is that in addition to the holder plate, a separate guide sleeve for the tie rod must be provided, mainly due to the increase of the production costs for the anchoring device.
Bei einer anderen, ebenfalls aus DE-C-42 34 892 bekannten Verankerungsvorrichtung ist anstelle des V-förmigen Mittelteils an der Halterplatte ein Führungsrohr für den Spannstab im vorgegebenen Einbauwinkel angesetzt. Ein wesentlicher Nachteil dieser Ausführungsform liegt darin, dass das Führungsrohr in einem separaten, zusätzliche Kosten verursachenden Arbeitsgang an die Halterplatte angesetzt werden muss. Zudem ist das Einschrauben eines Gewindestabes nur möglich, wenn ein Führungsrohr mit entsprechendem Innengewinde bzw. mit einem speziellen Gewindeeinsatz verwendet wird. Hinzu kommt, dass es bei starker Verschmutzung des Führungsrohres, wenn beispielsweise Betonmasse in das Rohrinnere eindringt, praktisch nicht mehr möglich ist, einen Spannstab ohne vorgängige mühsame Reinigung einzuführen oder gar einzuschrauben.In another anchoring device, also known from DE-C-42 34 892 is a guide tube instead of the V-shaped middle part on the holder plate for the tie rod in the specified installation angle. An essential one The disadvantage of this embodiment is that the guide tube in a separate, additional costly operation on the holder plate must be applied. In addition, screwing in a threaded rod only possible if a guide tube with a corresponding internal thread or used with a special thread insert. Come in addition, that if the guide tube is very dirty, for example Concrete mass penetrates into the pipe interior, is practically no longer possible Inserting the tension rod without prior laborious cleaning or even screw in.
Der Erfindung liegt deshalb die Aufgabe zugrunde, eine Vorrichtung der eingangs genannten Art zu schaffen, welche die vorerwähnten Nachteile überwindet, kostengünstig in der Herstellung ist und bei einfacher Handhabung einen lage- und richtungsstabilen Einbau eines Spannstabes ermöglicht.The invention is therefore based on the object of a device at the outset to create the type mentioned, which overcomes the aforementioned disadvantages, is inexpensive to manufacture and easy to use position and directionally stable installation of a tie rod enables.
Zur erfindungsgemässen Lösung der Aufgabe führt, dass das Halterelement aus zwei Halterteilen besteht, wobei zumindest ein erster Halterteil eine zur Durchführung des Spannstabes vorgesehene Öffnung aufweist, deren Öffnungsweite in zumindest einer Richtung so gewählt ist, dass der maximal mögliche Neigungswinkel des Spannstabes dem Einbauwinkel entspricht, und wobei der zweite Halterteil einen in Abstand zur Öffnung im ersten Halterteil angeordneten Anschlag zur Fixierung des Spannstabes im vorgegebenen Einbauwinkel aufweist.The holder element leads to the achievement of the object according to the invention consists of two holder parts, at least a first holder part one for Implementation of the tie rod provided opening, the opening width is selected in at least one direction so that the maximum possible Tilt angle of the tie rod corresponds to the installation angle, and where the second holder part is arranged at a distance from the opening in the first holder part Stop for fixing the tension rod in the specified installation angle having.
Mit dem erfindungsgemässen Halterelement ergeben sich bezüglich des lage- und richtungsstabilen Einbaus eines Spannstabes die gleichen Vorteile wie mit einem Führungsrohr, jedoch ohne die Nachteile einer erschwerten Handhabung bei Verschmutzung.With the holder element according to the invention, and directionally stable installation of a tie rod the same advantages as with a guide tube, but without the disadvantages of difficult handling when dirty.
Bei einer ersten bevorzugten Ausführungsform der Erfindung sind zumindest diejenigen Halterteile, welche Öffnungen aufweisen, als plattenförmige Flachteile ausgestaltet, wobei das Halterelement bevorzugt aus einem einzigen Flachteilzuschnitt geformt ist.In a first preferred embodiment of the invention, at least those holder parts which have openings as plate-shaped flat parts designed, wherein the holder element preferably from a single Flat part blank is shaped.
Bei einer besonders stabilen Ausführungsform der Erfindung weist der zweite Halterteil ebenfalls eine zur Durchführung des Spannstabes vorgesehene Öffnung auf. In diesem Fall wird der Anschlag zur Fixierung des Spannstabes im vorgegebenen Einbauwinkel von einem Teil der Öffnung gebildet. Zweck-mässigerweise sind bei dieser Ausführungsform die plattenförmigen Flachteile parallel zueinander angeordnet, so dass in beiden Halterteilen Öffnungen der gleichen Dimension angeordnet werden können. Grundsätzlich können jedoch die beiden Halterteile in einem weiten Bereich in einen beliebigen Winkel zueinander stehen.In a particularly stable embodiment of the invention, the second one Holder part also an opening provided for the passage of the tie rod on. In this case, the stop for fixing the tie rod in the predetermined installation angle formed by part of the opening. Appropriately are the plate-shaped flat parts in this embodiment arranged parallel to each other, so that openings of the same dimension can be arranged. Basically, however the two holder parts in a wide range at any angle to each other stand.
Bei einer einfachen und daher kostengünstig herzustellenden Ausführungsform der Erfindung sind die plattenförmigen Flachteile im wesentlichen senkrecht zueinander angeordnet. Hierbei ist der zweite Halterteil bevorzugt aus dem ersten Halterteil teilweise ausgestanzt und aus der Auflageebene des Halterelementes in seine Endlage umgebogen.In a simple and therefore inexpensive embodiment According to the invention, the plate-shaped flat parts are essentially vertical arranged to each other. Here, the second holder part is preferably made of Part of the first holder part is punched out and out of the support plane of the holder element bent into its final position.
Bei einer zweiten bevorzugten Ausführungsform der Erfindung sind die beiden Halterteile aus Stangen- oder Drahtmaterial geformt, wobei das Halterelement bevorzugt aus einem einzigen Stangen- oder Drahtzuschnitt geformt ist.In a second preferred embodiment of the invention, the two are Holder parts formed from rod or wire material, the holder element is preferably formed from a single bar or wire blank.
Der wesentliche Vorteil des erfindungsgemässen Halterelementes gegenüber den Halterplatten nach dem Stand der Technik liegt darin, dass die Halterteile auf einfache Weise für das Einschrauben eines Spannstabes in das Halterelement vorbereitet werden können, indem lediglich die Form der Öffnungen in den Halterteilen sowie ggf. der gegenseitige Abstand der beiden Öffnungen in den Halterteilen an das Gewinde eines in das Halterelement einschraubbaren Spannstabes angepasst werden müssen.The main advantage of the holder element according to the invention over The holder plates according to the prior art is that the holder parts in a simple way for screwing a tie rod into the holder element can be prepared by just the shape of the openings in the holder parts and, if necessary, the mutual distance between the two openings in the holder parts to the thread of a screwable into the holder element Must be adjusted.
Bei einer besonders zweckmässigen Ausgestaltung der erfindungsgemässen Vorrichtung durchdringt ein zur Aufnahme des Spannstabes vorgesehenes Schutzrohr die Öffnungen in den Halterteilen und ist in diesen kraftschlüssig und über den Anschlag im vorgegebenen Einbauwinkel gehalten. Mit dem Schutzrohr ist ein hülsenförmiges Verankerungselement zusammengesteckt, wobei dieses Verankerungselement einerseits einen Gewindeteil für einen in diesen einsetzbaren Spannstab und andererseits einen Verankerungsteil zum Verbleib in der Betonmasse aufweist. Durch die Verwendung dieser Anordnung mit einem Schutzrohr kann das Einsetzen eines Spannstabes nach erfolgtem Einbetonieren erfolgen. Dadurch wird die Unfallgefahr auf Baustellen infolge der nach dem Stand der Technik direkt einbetonierten und demzufolge frei aufragenden Spannstäbe erheblich reduziert. Zudem entfällt das umständliche Abtrennen der Spannstäbe mittels einer Trennscheibe nach dem Einbetonieren, da die Spannstäbe bei Verwendung des Schutzrohres einfach herausgedreht und wieder verwendet werden können.In a particularly expedient embodiment of the invention Device penetrates one provided for receiving the tie rod Protection tube the openings in the holder parts and is non-positive in these and held in the specified installation angle via the stop. With the Protective tube is put together a sleeve-shaped anchoring element, this anchoring element on the one hand a threaded part for a this usable tie rod and on the other hand an anchoring part for Remains in the concrete mass. By using this arrangement with a protective tube, the insertion of a tie rod after the Set in concrete. This will result in the risk of accidents on construction sites that directly concreted in according to the state of the art and consequently freely towering Tension rods significantly reduced. In addition, the cumbersome Cutting off the tension rods using a cutting disc after concreting in, because the tension rods are simply unscrewed when using the protective tube and can be used again.
Zum Schutz gegen das Eindringen von noch flüssiger Betonmasse ist dem freien Ende des Schutzrohres bevorzugt eine Verschlusskappe aufgesetzt, wobei bei einer besonders bevorzugten Variante im Innern der Verschlusskappe ein nach innen gerichteter und einem in den Gewindeteil eingesetzten und das Schutzrohr sowie die aufgesetzte Verschlusskappe durchdringenden Spannstab anliegender Dichtungsring angeordnet ist. Wird das Verankerungselement ohne in den Gewindeteil eingesetzten Spann- oder Ankerstab einbetoniert, d.h. wird der Ankerstab erst nach erfolgtem Einbetonieren in das Verankerungselement eingeschraubt, so kann zum Verschliessen der Öffnung am freien Ende der aufgesetzten Verschlusskappe ein Verschlusszapfen eingesetzt werden. Weitere zur Verwendung mit dem erfindungsgemässen Verankerungselement bevorzugte Verschlusskappen sind beispielsweise der DE-U-9314656 zu entnehmen.This is to protect against the penetration of still liquid concrete free end of the protective tube preferably placed a cap, wherein in a particularly preferred variant inside the cap one inward and one inserted in the threaded part and that Protective tube and the tension rod penetrating the cap adjacent sealing ring is arranged. Becomes the anchoring element Concreted without tension or anchor rod inserted in the threaded part, i.e. the anchor rod is only after concreting into the anchoring element screwed in so that the opening can be closed at the open A plug is inserted at the end of the cap become. Others for use with the anchoring element according to the invention preferred caps are for example DE-U-9314656 refer to.
Grundsätzlich können für die Herstellung des Halterelementes beliebige Werkstoffe eingesetzt werden, welche die Anforderungen bezüglich Verformbarkeit, mechanischer Festigkeit sowie Korrosionsbeständigkeit erfüllen. Ein bevorzugter Werkstoff ist Stahl, jedoch sind auch Ausführungen in beispielsweise Kunststoff oder Verbundmaterialien denkbar.In principle, any materials can be used to manufacture the holder element are used, which meet the requirements regarding deformability, mechanical strength and corrosion resistance. A preferred one Material is steel, but there are also designs in, for example Plastic or composite materials possible.
Bei einer besonders zweckmässigen Ausführungsform der erfindungsgemässen Verankerungsvorrichtung mit einem Schutzrohr sind die Öffnungen in den Halterteilen derart ausgestaltet, dass die standardisierten und auf Baustellen üblicherweise verwendeten Distanzrohre in das erfindungsgemässe Halterelement eingesetzt werden können und sich der vorgegebene Einbauwinkel ohne weitere Massnahmen einstellt. In gleicher Weise ist der Aussen-durchmesser des hülsenförmigen Verankerungselementes im Bereich seiner Steckverbindung mit dem Schutzrohr dem Innendurchmesser der standardisierten Distanzrohre angepasst. Dies hat den Vorteil, dass ein Standard-Distanzrohr beim erfindungsgemässen Verankerungselement ohne weiteres als Schutzrohr verwendet werden kann.In a particularly expedient embodiment of the invention Anchoring device with a protective tube are the openings in the holder parts designed so that the standardized and on construction sites Spacer tubes usually used in the inventive Holder element can be used and the specified installation angle without further measures. The outside diameter is the same of the sleeve-shaped anchoring element in the area of it Plug connection with the protective tube the inside diameter of the standardized Spacer tubes adapted. This has the advantage of being a standard spacer tube in the anchoring element according to the invention without further ado Protection tube can be used.
Weitere Vorteile, Merkmale und Einzelheiten der Erfindung ergeben sich aus
der nachfolgenden Beschreibung bevorzugter Ausführungsbeispiele sowie anhand
der Zeichnung; diese zeigt schematisch in
Ein in den Fig. 1 bis 3 dargestelltes Halterelement 10 für einen Spannstab 12
bzw. für ein zur Aufnahme eines Spannstabes vorgesehenes Schutzrohr 14
weist eine streifenförmige Auflageplatte 16 auf. Etwa in der Mitte einer Längs-seitenkante
der Auflageplatte 16 ragt in rechtem Winkel zu dieser und mit einer
Schrägneigung entsprechend der Achsenrichtung z des Spannstabes 12 bzw.
des Schutzrohres 14 ein Seitenstreifen 18 ab. Das freie Ende des Seitenstrei-fens
18 ist rechtwinklig zu einem Halterstreifen 20 gebogen, so dass sich quer-schnittlich
eine C-förmige Profilierung ergibt, wobei die Auflageplatte 16 und
der Halterstreifen 20 einander parallel gegenüber stehen. A
In der Auflageplatte 16 und im Halterstreifen 20 ist je eine Öffnung 22, 24 zur
Durchführung des Spannstabes 12 bzw. des Schutzrohres 14 angeordnet. Die
Dimension der in Abstand a zueinander stehenden Öffnungen 22, 24 ist so gewählt,
dass der in das Halterelement 10 eingesetzte Spannstab 12 bzw. das
Schutzrohr 14 den maximal möglichen Neigungswinkel einnimmt und auf diese
Weise im Halterelement 10 form- und/oder kraftschlüssig gehalten wird. Der
maximal mögliche Einbauwinkel des Spannstabes 12 bzw. des Schutzrohres
14 entspricht dem vorgegebenen Einbauwinkel α bezüglich einer durch die
Auflageplatte 16 definierten Auflageebene E.In the
Die Form und die Dimension der beiden Öffnungen 22, 24 kann in weiten
Grenzen variieren. Zur Einstellung des Einbauwinkels α ist die Öffnungsweite
in Neigungsrichtung massgebend; diese ist entsprechend dem einzustellenden
Einbauwinkel α grösser als der Durchmesser D des Spannstabes 12 bzw. des
Schutzrohres 14. Die Form der Öffnung 22, 24 ist beispielsweise eine Ellipse,
deren kleiner Durchmesser Y im wesentlichen dem Durchmesser D des Spannstabes
12 bzw. des Schutzrohres 14 entspricht und deren grosser Durchmes-ser
X so gewählt wird, dass sich der gewünschte Einbauwinkel α zwischen
Stab- bzw. Schutzrohrachse z und Auflageebene E ergibt.The shape and the dimension of the two
In der streifenförmigen Auflageplatte 16 sind zur Erleichterung des Festbindens
der Halterplatte 10 auf einer Bewehrungslage längslaufende Schlitze 26 zur
Durchführung von Eisenbindern angeordnet.In the strip-shaped
Bei der in Fig. 4 gezeigten Ausführungsform einer Halterplatte 10 ist die streifenförmige
Auflageplatte 16 an einem ihrer Enden unter Bildung des Seiten-streifens
18 und des Halterstreifens 20 zweimal rechtwinklig umgebogen. Wie
bei der Ausführungsform gemäss den Fig. 1 bis 3 sind auch hier die Auflageplatte
16 und der Halterstreifen 20 parallel zueinander angeordnet. Die Lage
der Öffnungen 22, 24 entspricht derjenigen von Fig. 1. In the embodiment of a
Die in Fig. 5 dargestellte Ausführungsform eines Halterelementes 10 ist aus
einem Blechzuschnitt unter Bildung eines U-förmigen Querschnitts mit parallel
zueinander stehenden Schenkelstreifen 28, 30 geformt. In den Schenkelstreifen
28, 30 sind paarweise Öffnungen 32, 34 angeordnet. Diese Öffnungen 32,
34 können paarweise gleiche oder verschiedene Dimensionen aufweisen und
auch unterschiedliche Einbauwinkel α definieren. Dadurch ist es möglich, ein
einziges Halterelement für Spannstäbe 12 bzw. Schutzrohre 14 unterschiedlicher
Durchmesser zur Verfügung zu stellen. Es sei hier noch angemerkt, dass
für einen einschraubbaren Spannstab die Form der Öffnungen sowie ggf. der
gegenseitige Abstand der Öffnungen auf einfache Weise angepasst werden
kann.The embodiment of a
Da der maximale Neigungswinkel des Spannstabes 12 bzw. des Schutzrohres
14 durch die Weite einer der beiden Öffnungen 20, 24 bzw. 32, 34 in der Neigungsrichtung
vorgegeben ist, ist grundsätzlich eine einzige Öffnung ausreichend.
Anstelle einer zweiten Öffnung ist ein Anschlagelement, welches den
Spannstab 12 bzw. das Schutzrohr 14 in seiner dem Einbauwinkel α entsprechenden
maximalen Neigestellung fixiert. Derartige Ausführungsformen mit
einer Öffnung und einem zugehörigen Anschlagelement sind in den Fig. 6 bis
11 dargestellt.Since the maximum angle of inclination of the
Fig. 6 zeigt ein Halterelement 10, bei dem die streifenförmige Auflageplatte 16
endständig zum Halterstreifen 20 umgebogen ist. Der Spannstab 12 bzw. das
Schutzrohr 14 durchdringt die Öffnung 22 in der Auflageplatte 16 und wird vom
Halterstreifen 20, dessen freies Ende einen Anschlag 36 bildet, in seinem dem
Einbauwinkel a entsprechenden maximalen Neigungswinkel fixiert.6 shows a
Bei der Ausführungsform eines Halterelementes 10 gemäss Fig. 7 ist in gleicher
Weise wie bei der Ausführungsform gemäss den Fig. 1 bis 3 an der Auflageplatte
16 etwa in der Mitte einer ihrer Längskanten der Seitenstreifen 18 unter
Bildung eines Anschlagstreifens 42 zweimal rechtwinklig abgebogen. Diese
Ausführungsform entspricht im wesentlichen derjenigen der Fig. 1 bis 3, wobei
jedoch nur die Öffnung 22 in der Auflageplatte vorhanden ist und der Halterstreifen
20 mit Öffnung 24 auf den minimal erforderlichen Anschlagstreifen 42,
dessen eine Längskante den Anschlag 36 bildet, reduziert worden ist.7 is the same in the embodiment of a
Die in Fig. 8 gezeigte Ausführungsform ist eine Abwandlung des Halterelementes
von Fig. 7, wobei der Anschlagstreifen 42 so breit gewählt und so positioniert
ist, dass er zwei Anschläge 36a, b für die beiden möglichen Kippstellungen
des Spannstabes 12 bzw. des Schutzrohres 14 anbietet. Bei diesem
Halterelement kann somit ein die Öffnung 22 durchdringender Spannstab 12
bzw. ein Schutzrohr 14 in zwei verschiedenen Richtungen positioniert werden.The embodiment shown in Fig. 8 is a modification of the holder element
of Fig. 7, wherein the
Bei einer in der Zeichnung nicht dargestellten weiteren, vom Halterelement
gemäss Fig. 8 abgewandelten Ausführungsvariante ist anstelle des breiten Anschlagstreifens
42 ein Halterteil mit zwei unterschiedlich dimensionierten Öffnungen
für beispielsweise einen Spannstab und ein Schutzrohr vorgesehen.
Die Öffnung 22 im Halterteil 16 ist in diesem Fall so dimensioniert, dass sie
sowohl für einen Spannstab als auch für ein Schutzrohr einen Anschlag bildet.In another, not shown in the drawing, from the holder element
8 modified variant is instead of the wide stop strip
42 a holder part with two differently dimensioned openings
for example for a tie rod and a protective tube.
The
Bei der in den Fig. 9 bis 11 dargestellten Ausführungsvariante eines Halterelementes
10 sind anstelle einer streifenförmigen Auflageplatte 16 zwei
Auflagestreifen 38, 40 vorgesehen. Ein erster Auflagestreifen 38 ragt vom Seitenstreifen
in einer Richtung in der Auflageebene E ab. Der zweite Auflagestreifen
40 ist mit dem Seitenstreifen 18 über einen den Anschlagstreifen 42
bildenden Verbindungssteg verbunden und ragt in die dem ersten Auflagestreifen
38 entgegengesetzte Richtung in der Auflageebene E ab. Vom Seitenstreifen
18 ragt rechtwinklig der Halterstreifen 20 mit der Öffnung 24 ab. Ein in
die Öffnung 24 eingesetzter Spannstab 12 bzw. ein Schutzrohr 14 wird vom
Anschlag 42 in seiner durch die Öffnung 24 vorgegebenen Schräglage unter
Bildung des Einbauwinkels a kraftschlüssig gehalten. In the embodiment variant of a holder element shown in FIGS. 9 to 11
10 are two instead of a strip-shaped
Die von der Auflageebene E aufragenden Auflagestreifen 38, 40 sind an ihrer
Oberkante aufgerauht bzw. mit einer Zahnung 44 versehen. Dadurch ergibt
sich eine bessere Lagestabilisierung des Halterelementes 10, wenn dieses mit
Eisenbindern auf einer Bewehrung festgebunden wird. Selbstverständlich können
die Auflagestreifen 38, 40 auch mit Schlitzen oder Löchern zur Durchführung
von Eisenbindern versehen sein.The support strips 38, 40 rising from the support level E are on their
Roughened upper edge or provided with
Die in Fig. 12 gezeigte Ausführungsvariante eines Halterelementes 10 ist aus
einem Draht bzw. einer Stange 46 geformt. Eine erste Auflageschleife 48 bildet
die Auflageebene E. Eine zusätzliche Windung begrenzt eine Öffnung 50 zur
Durchführung eines Spannstabes 12 bzw. eines Schutzrohres 14. Der Draht
bzw. die Stange 46 ist zu einer weiteren Halterschlaufe 52 als zweite Öffnung
im Abstand a zur ersten Öffnung 50 geformt. Aus Fig. 12 ist ohne weiteres verständlich,
dass anstelle einer geschlossenen Halterschlaufe 52 ein Anschlag
zur Fixierung des Spannstabes 12 bzw. des Schutzrohres 14 in seiner maximalen,
dem Einbauwinkel α entsprechenden Schrägneigung ausreichend ist.
Selbstverständlich ist es auch möglich, mehrere unterschiedlich dimensionierte
Öffnungsschlaufen zur Durchführung eines Spannstabes oder eines Schutzrohres
anzuordnen, wie dies beispielsweise oben im Zusammenhang mit der von
Fig. 8 abgewandelten Ausführungsform beschrieben ist.The embodiment variant of a
Die in den Fig. 1 bis 12 sowie 14 und 15 dargestellten Ausführungsvarianten stellen nur einen kleinen Ausschnitt aus einer grossen Anzahl von Variationsmöglichkeiten eines Halterelementes mit zwei Öffnungen bzw. einer Öffnung und einem Anschlag zur Fixierung eines Spannstabes bzw. eines Schutzrohres dar.The embodiment variants shown in FIGS. 1 to 12 and 14 and 15 represent only a small selection from a large number of possible variations a holder element with two openings or one opening and a stop for fixing a tie rod or a protective tube represents.
Bei dem in Fig. 13 dargestellten Ausführungsbeispiel einer Verankerungsvorrichtung
mit dem Halterelement von Fig. 1 ist ein Schutzrohr 14 aus Kunststoff
in die Öffnungen 22, 24 in der Auflageplatte 16 bzw. im Halterstreifen 20 eingesetzt.
Ein Verankerungselement 56 mit einem Gewindeteil 58 und einem
Verankerungsteil 60 ist einends in das Schutzrohr 14 eingesteckt. Der Spannstab
12 durchsetzt das Schutzrohr 14 und ist mit dem Gewindeteil 58 des Verankerungselementes
56 verschraubt. Dem freien Ende des Schutzrohres 14 ist
eine Verschlusskappe 62 aufgesetzt. Von der Innenwandung der Verschlusskappe
62 ragt ein integral angeformter flexibler und nach innen verjüngend
ausgebildeter Dichtungsring 64 ab, dessen lichte Weite etwa dem Kerndurchmesser
des eingesetzten Spannstabes 12 entspricht. Wird das Verankerungselement
56 ohne eingesetzten Spannstab 12 einbetoniert, so kann an der Verschlusskappe
62 ein die Öffnung für den später einzusetzenden Spannstab 10
verschliessender Verschlusszapfen 66 als Deckel vorgesehen sein.In the embodiment of an anchoring device shown in FIG. 13
1 is a
Die Positionierung des Verankerungselementes 56 erfolgt vor dem Aufgiessen
der Betonmasse 68 durch Festbinden des Halterelementes 10 auf der oberen
Bewehrungslage 54 einer Armierung. Das Halterelement 10 kann über die
Schlitze 26 in der Auflageplatte 16 festgebunden werden.The anchoring
Nach dem Aufgiessen und Aushärten der Betonmasse 68 wird eine Wand-schalung
erstellt und über Stützböcke abgestützt. Die Stützböcke werden in
bekannter Weise über den aus der Betonmasse 68 herausragenden Spannstab
12 verankert. Hierbei ist es von besonderer Bedeutung, dass der Spannstab in
einem Winkel von 45° zum Fundament eingebaut ist, da der bei der Herstellung
der Wand auftretende Betondruck über die Verankerung in die Bodenplatte
bzw. in das Fundament eingeleitet werden muss. Da die Dimension der
Öffnungen 22, 24 in der Auflageplatte 16 und im Halterstreifen 20 so gewählt
ist, dass ein eingesetzter Spannstab bzw. ein Schutzrohr mit der Auflageebene
E der Auflageplatte 16 den vorgegebenen Winkel α von beispielsweise 45°
bildet, beträgt der Neigungswinkel des Schutzrohres 14 zum Fundament bei
fachgerechter Anordnung des Halterelementes ebenfalls 45°. Nach der Herstellung
der Wand wird der Spannstab 12 aus dem Verankerungselement 56
herausgedreht und kann wieder verwendet werden. Das in der Betonmasse 68
zurückbleibende Schutzrohr 14 wird sodann ebenerdig abgeschnitten.After pouring and hardening the
Bei der in Fig. 4 und 5 gezeigten Ausführungsform einer Halterplatte 10 ist aus
der streifenförmigen Auflageplatte 16 ein zweites Halterteil 70 teilweise ausgestanzt
und unter Freilassung einer Öffnung 72 in der Auflageplatte 16 rechtwinklig
zu dieser umgebogen.In the embodiment of a
Claims (13)
dadurch gekennzeichnet, dass
das Halterelement (10) aus zwei Halterteilen (16,20;28,30;38,40) besteht, wobei zumindest ein erster Halterteil eine zur Durchführung des Spannstabes (12) vorgesehene Öffnung (22,24;32,34;50,52) aufweist, deren Öffnungsweite in zumindest einer Richtung (x) so gewählt ist, dass der maximal mögliche Neigungswinkel des Spannstabes (12) dem Einbauwinkel (α) entspricht, und wobei der zweite Halterteil einen in Abstand (α) zur Öffnung im ersten Halterteil angeordneten Anschlag zur Fixierung des Spannstabes (12) im vorgegebenen Einbauwinkel (α) aufweist.Device for anchoring a tie rod (12) of a reinforced concrete mass (68), with a holder element (10) provided for resting and fastening on the reinforcement (54), the tie rod (12) penetrating the holder element (10) and through the holder element ( 10) is held at a predetermined installation angle (α) to the support plane (E) of the holder element (10),
characterized in that
the holder element (10) consists of two holder parts (16, 20; 28, 30; 38, 40), at least one first holder part having an opening (22, 24; 32, 34; 50, 52) provided for the passage of the tensioning rod (12) ), the opening width of which is selected in at least one direction (x) such that the maximum possible angle of inclination of the tensioning rod (12) corresponds to the installation angle ( α ), and the second holder part being arranged at a distance (α) from the opening in the first holder part Has stop for fixing the tie rod (12) in the specified installation angle ( α ).
Applications Claiming Priority (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CH65398 | 1998-03-18 | ||
CH65398 | 1998-03-18 |
Publications (3)
Publication Number | Publication Date |
---|---|
EP0943745A2 true EP0943745A2 (en) | 1999-09-22 |
EP0943745A3 EP0943745A3 (en) | 2001-01-10 |
EP0943745B1 EP0943745B1 (en) | 2005-05-04 |
Family
ID=4192028
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
EP99810233A Expired - Lifetime EP0943745B1 (en) | 1998-03-18 | 1999-03-15 | Anchoring device for a tension bar in a reinforced concrete mass |
Country Status (3)
Country | Link |
---|---|
EP (1) | EP0943745B1 (en) |
AT (1) | ATE294904T1 (en) |
DE (1) | DE59911998D1 (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE10258435A1 (en) * | 2002-12-13 | 2004-08-12 | Doka Industrie Gmbh | Anchor holder used during concrete arrangement, has two holding section marked by through holes, in which second holding section is inclined at an angle larger than zero degrees with respect to direction perpendicular to retaining direction |
WO2006134266A1 (en) | 2005-06-15 | 2006-12-21 | Tolemecane Sas | Support for shuttering and passing through a conduit, cable and a flexible hose |
WO2010051379A1 (en) * | 2008-10-31 | 2010-05-06 | Simpson Strong-Tie Company, Inc. | Construction frame shear lug |
EP2096223A3 (en) * | 2008-02-27 | 2012-06-06 | Pino Albanese | Device for positioning and anchoring a tensioning rod with a precise position and angle |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE9314656U1 (en) | 1992-09-30 | 1994-01-27 | Albanese, Giulio, Winterthur | Spacer tube |
DE4234892A1 (en) | 1992-10-16 | 1994-05-19 | Karl Bisani | Anchor for steel rod in concrete block - has expanded anchor head and distance piece separating it from bent reinforcing plate in concrete |
Family Cites Families (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US5388804A (en) * | 1993-07-19 | 1995-02-14 | Cohen; Jack H. | Anchor bolt holder-spacer |
US5670076A (en) * | 1994-08-04 | 1997-09-23 | Simpson Strong-Tie Company, Inc. | Reusable coupler for foundation anchor |
CH690727A5 (en) * | 1995-11-09 | 2000-12-29 | Giulio Albanese | Sleeve-shaped anchoring element to embed in Betongiessmasse. |
US5937609A (en) * | 1995-11-27 | 1999-08-17 | Roth; Steven A. | Concrete insert to support anchor bolt |
EP0943744B1 (en) * | 1998-03-20 | 2004-01-28 | Reto Bonomo | Process and element for introducing shear forces in a reinforced concrete element and reinforced concrete element |
-
1999
- 1999-03-15 DE DE59911998T patent/DE59911998D1/en not_active Expired - Lifetime
- 1999-03-15 EP EP99810233A patent/EP0943745B1/en not_active Expired - Lifetime
- 1999-03-15 AT AT99810233T patent/ATE294904T1/en active
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE9314656U1 (en) | 1992-09-30 | 1994-01-27 | Albanese, Giulio, Winterthur | Spacer tube |
DE4234892A1 (en) | 1992-10-16 | 1994-05-19 | Karl Bisani | Anchor for steel rod in concrete block - has expanded anchor head and distance piece separating it from bent reinforcing plate in concrete |
Cited By (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE10258435A1 (en) * | 2002-12-13 | 2004-08-12 | Doka Industrie Gmbh | Anchor holder used during concrete arrangement, has two holding section marked by through holes, in which second holding section is inclined at an angle larger than zero degrees with respect to direction perpendicular to retaining direction |
AT500503A1 (en) * | 2002-12-13 | 2006-01-15 | Doka Ind Gmbh | ANCHOR BRACKET |
AT500503B1 (en) * | 2002-12-13 | 2006-07-15 | Doka Ind Gmbh | ANCHORING ELEMENT |
DE10258435B4 (en) * | 2002-12-13 | 2008-03-13 | Doka Industrie Gmbh | anchoring element |
WO2006134266A1 (en) | 2005-06-15 | 2006-12-21 | Tolemecane Sas | Support for shuttering and passing through a conduit, cable and a flexible hose |
FR2887320A1 (en) * | 2005-06-15 | 2006-12-22 | Tolemecane Sarl | FORMWORK AND TRAVERSE SUPPORT FOR CONDUITS, CABLES AND FLEXIBLE. |
EP2096223A3 (en) * | 2008-02-27 | 2012-06-06 | Pino Albanese | Device for positioning and anchoring a tensioning rod with a precise position and angle |
EP2977520A1 (en) * | 2008-02-27 | 2016-01-27 | Pino Albanese | Device for anchoring of tensioning rods and positioning it in a precise angle and position |
WO2010051379A1 (en) * | 2008-10-31 | 2010-05-06 | Simpson Strong-Tie Company, Inc. | Construction frame shear lug |
US8336267B2 (en) | 2008-10-31 | 2012-12-25 | Simpson Strong-Tie Company, Inc. | Construction frame shear lug |
AU2016204963B2 (en) * | 2008-10-31 | 2018-07-26 | Simpson Strong-Tie Company Inc. | Construction frame shear lug |
Also Published As
Publication number | Publication date |
---|---|
EP0943745B1 (en) | 2005-05-04 |
ATE294904T1 (en) | 2005-05-15 |
DE59911998D1 (en) | 2005-06-09 |
EP0943745A3 (en) | 2001-01-10 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
DE69837524T2 (en) | Method for producing an anchoring, anchoring part and tensioning element for this purpose | |
DE3224986C2 (en) | Device for attaching assembly parts to a concrete wall | |
DE2229093A1 (en) | Assembly or fastening element for reinforcement or a reinforcement element in reinforced concrete construction | |
EP3569795B1 (en) | Device for positioning a transport anchor | |
EP0410079A1 (en) | Connecting casing for linked concrete slabs | |
EP0943745B1 (en) | Anchoring device for a tension bar in a reinforced concrete mass | |
EP0697047B1 (en) | Device for anchoring safety barrier posts in a foundation | |
EP2516761B1 (en) | Device for connecting two components separated by a gap and for absorbing transverse forces that occur between the components | |
EP3892789B1 (en) | Formwork system | |
DE19548440A1 (en) | Wall component with at least two sheathing components | |
DE19645759C2 (en) | Sleeve-shaped anchoring element for embedding in a concrete casting compound | |
DE2732183B2 (en) | Connection of two reinforced concrete parts facing each other with their end faces | |
DE2952700C2 (en) | Anchor sleeve | |
DE10258435B4 (en) | anchoring element | |
DE19522280A1 (en) | Reinforcement establishment | |
DE2853349C2 (en) | Locking device | |
DE19517233C2 (en) | Marking device for attaching measuring points | |
DE1609878A1 (en) | Hollow column made of steel with a base plate for use in steel frame buildings | |
DE19810034C2 (en) | Stop bracket for a wall formwork | |
DE29617673U1 (en) | Shuttering element | |
DE20216945U1 (en) | Anchor strip for structural engineering has through-anchors each with anchor head connected to strip section and immovably fastened on strip section by polymer connecting element which shrinks under heat action | |
DE1900476C3 (en) | Holding device for posts of a guardrail | |
DE202023103836U1 (en) | Positioning device | |
DE29517654U1 (en) | Device for determining a measuring point in a site | |
DE3322869A1 (en) | Sleeve anchor |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PUAI | Public reference made under article 153(3) epc to a published international application that has entered the european phase |
Free format text: ORIGINAL CODE: 0009012 |
|
AK | Designated contracting states |
Kind code of ref document: A2 Designated state(s): AT CH DE GB LI |
|
AX | Request for extension of the european patent |
Free format text: AL;LT;LV;MK;RO;SI |
|
PUAL | Search report despatched |
Free format text: ORIGINAL CODE: 0009013 |
|
AK | Designated contracting states |
Kind code of ref document: A3 Designated state(s): AT BE CH CY DE DK ES FI FR GB GR IE IT LI LU MC NL PT SE |
|
AX | Request for extension of the european patent |
Free format text: AL;LT;LV;MK;RO;SI |
|
RIC1 | Information provided on ipc code assigned before grant |
Free format text: 7E 04C 5/12 A, 7E 04G 21/12 B, 7E 04B 1/41 B |
|
17P | Request for examination filed |
Effective date: 20010703 |
|
AKX | Designation fees paid |
Free format text: AT CH DE GB LI |
|
17Q | First examination report despatched |
Effective date: 20030523 |
|
GRAP | Despatch of communication of intention to grant a patent |
Free format text: ORIGINAL CODE: EPIDOSNIGR1 |
|
GRAS | Grant fee paid |
Free format text: ORIGINAL CODE: EPIDOSNIGR3 |
|
GRAA | (expected) grant |
Free format text: ORIGINAL CODE: 0009210 |
|
AK | Designated contracting states |
Kind code of ref document: B1 Designated state(s): AT CH DE GB LI |
|
REG | Reference to a national code |
Ref country code: GB Ref legal event code: FG4D Free format text: NOT ENGLISH |
|
REG | Reference to a national code |
Ref country code: CH Ref legal event code: EP |
|
REF | Corresponds to: |
Ref document number: 59911998 Country of ref document: DE Date of ref document: 20050609 Kind code of ref document: P |
|
REG | Reference to a national code |
Ref country code: CH Ref legal event code: NV Representative=s name: PATENTANWAELTE BREITER + WIEDMER AG |
|
GBT | Gb: translation of ep patent filed (gb section 77(6)(a)/1977) |
Effective date: 20050624 |
|
PLBE | No opposition filed within time limit |
Free format text: ORIGINAL CODE: 0009261 |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: NO OPPOSITION FILED WITHIN TIME LIMIT |
|
26N | No opposition filed |
Effective date: 20060207 |
|
REG | Reference to a national code |
Ref country code: CH Ref legal event code: NV Representative=s name: HANS RUDOLF GACHNANG PATENTANWALT |
|
REG | Reference to a national code |
Ref country code: CH Ref legal event code: NV Representative=s name: GACHNANG AG PATENTANWAELTE, CH |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: GB Payment date: 20180326 Year of fee payment: 20 Ref country code: DE Payment date: 20180322 Year of fee payment: 20 Ref country code: CH Payment date: 20180323 Year of fee payment: 20 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: AT Payment date: 20180320 Year of fee payment: 20 |
|
REG | Reference to a national code |
Ref country code: DE Ref legal event code: R071 Ref document number: 59911998 Country of ref document: DE |
|
REG | Reference to a national code |
Ref country code: CH Ref legal event code: PL |
|
REG | Reference to a national code |
Ref country code: GB Ref legal event code: PE20 Expiry date: 20190314 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: GB Free format text: LAPSE BECAUSE OF EXPIRATION OF PROTECTION Effective date: 20190314 |
|
REG | Reference to a national code |
Ref country code: AT Ref legal event code: MK07 Ref document number: 294904 Country of ref document: AT Kind code of ref document: T Effective date: 20190315 |