CN110405932A
CN110405932A CN201910539350.8A CN201910539350A CN110405932A CN 110405932 A CN110405932 A CN 110405932A CN 201910539350 A CN201910539350 A CN 201910539350A CN 110405932 A CN110405932 A CN 110405932A
Authority
CN
China
Prior art keywords
installation
double
assembly line
side mode
arranging
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910539350.8A
Other languages
Chinese (zh)
Inventor
覃晓君
张晓峰
高杰文
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China 22MCC Group Corp Ltd
Original Assignee
China 22MCC Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China 22MCC Group Corp Ltd filed Critical China 22MCC Group Corp Ltd
Priority to CN201910539350.8A priority Critical patent/CN110405932A/en
Publication of CN110405932A publication Critical patent/CN110405932A/en
Pending legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B15/00General arrangement or layout of plant ; Industrial outlines or plant installations

Landscapes

  • Chemical & Material Sciences (AREA)
  • Engineering & Computer Science (AREA)
  • Ceramic Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Devices For Post-Treatments, Processing, Supply, Discharge, And Other Processes (AREA)

Abstract

The present invention relates to a kind of double skin wall member production line double-cycle process method for arranging, assembly line includes the following steps: mold cleaning;Release agent spraying;Side mode scribing line;Side mode installation;Reinforcement installation;Embedded part installation;Casting is vibrated for the first time;It strikes off;It stands, precuring;Hair pulling treatment;Steam curing;Demoulding;Secondary formwork;Overturning;Side mode installation;Reinforcement installation;Embedded part installation;Second of casting is vibrated;It strikes off;It stands, precuring;Hair pulling treatment;Steam curing;Demoulding;Coarse surface treatment;Storage;Assembly line is using the two independent loops assembly line constructions of interior circulation and outer circulation.The present invention uses inside and outside independent Two-way Cycle streamline round-robin method: making full use of place and resource, production efficiency is increased to twice of regular pipeline.

Description

Double skin wall member production line double-cycle process method for arranging
Technical field
The present invention relates to a kind of construction techniques, in particular to a kind of double skin wall member production line Two-way Cycles Method for arranging technological process.
Background technique
Popularization with country to assembled architecture, PC element precast factory develop rapidly like the mushrooms after rain.Component The reasonability of the technology arrangement of production line directly determines the quality and efficiency of component production.
So far, the arrangement of PC component production line is circulating automatic assembly line, is generally distributed in the production line There are two, three or four lines, endless form is single cycle, as shown in Figures 4 and 5.
Current line configurations mode all there is the unbalanced technique waiting time, causes the discontinuous of assembly line Property, process portion work holdup state is caused, the efficiency of production and the quality of component are reduced.
Summary of the invention
In view of the deficiency of the prior art, the present invention provides a kind of raising production efficiency, reduces the double of production cost Skin wall member production line double-cycle process method for arranging.
The technical solution used in the present invention is:
A kind of double skin wall member production line double-cycle process method for arranging,
Assembly line includes the following steps:
Mold cleaning;
Release agent spraying;
Side mode scribing line;
Side mode installation;
Reinforcement installation;
Embedded part installation;
Casting is vibrated for the first time;
It strikes off;
It stands, precuring;
Hair pulling treatment;
Steam curing;
Demoulding;
Secondary formwork;
Overturning;
Side mode installation;
Reinforcement installation;
Embedded part installation;
Second of casting is vibrated;
It strikes off;
It stands, precuring;
Hair pulling treatment;
Steam curing;
Demoulding;
Coarse surface treatment;
Storage;
Assembly line is using the two independent loops assembly line constructions of interior circulation and outer circulation.
The present invention compared with the prior art the utility model has the advantages that
Double skin wall member production line double-cycle process method for arranging of the invention, avoid common process from arranging caused by single cycle Assembly line Caton, personnel's work holdup, the present invention use inside and outside independent Two-way Cycle streamline round-robin method: making full use of place and money Production efficiency is increased to twice of regular pipeline by source.
Detailed description of the invention
Fig. 1 is superimposed sheet production line station layout drawing of the invention;
Fig. 2 is superimposed sheet production line station flow chart of the invention;
Fig. 3 is superimposed sheet production line process flow diagram of the invention.
Fig. 4 is the three line single cycle station layout drawing of superimposed sheet production line of the prior art;
Fig. 5 is the four line single cycle station layout drawing of superimposed sheet production line of the prior art.
Main component symbol description in attached drawing:
In figure:
1, station turning 2, ferry-boat station
3, station 4, spray station are cleared up
5, scribing line station 6, demoulding station
7, station turning 8, reinforcement installation station
9, ferry-boat station 10, ferry-boat station
11, reinforcement installation station 12, vibrate cloth station
13, transition station 14, inspection station
15, precuring station 16, plucking station
17, demoulding station.
Specific embodiment
Referring to the drawings and embodiment the present invention will be described in detail:
Attached drawing 1-3 it is found that a kind of double skin wall member production line double-cycle process method for arranging,
Assembly line includes the following steps:
Mold cleaning;
Release agent spraying;
Side mode scribing line;
Side mode installation;
Reinforcement installation;
Embedded part installation;
Casting is vibrated for the first time;
It strikes off;
It stands, precuring;
Hair pulling treatment;
Steam curing;
Demoulding;
Secondary formwork;
Overturning;
Side mode installation;
Reinforcement installation;
Embedded part installation;
Second of casting is vibrated;
It strikes off;
It stands, precuring;
Hair pulling treatment;
Steam curing;
Demoulding;
Coarse surface treatment;
Storage;
Assembly line is using the two independent loops assembly line constructions of interior circulation and outer circulation.
Double skin wall member production line double-cycle process method for arranging of the invention, avoid common process from arranging caused by single cycle Assembly line Caton, personnel's work holdup, the present invention use inside and outside independent Two-way Cycle streamline round-robin method: making full use of place and money Production efficiency is increased to twice of regular pipeline by source.
The above described is only a preferred embodiment of the present invention, not making in any form to structure of the invention Limitation.Any simple modification, equivalent change and modification to the above embodiments according to the technical essence of the invention, Belong within the scope of technical solution of the present invention.

Claims (1)

1. a kind of double skin wall member production line double-cycle process method for arranging, it is characterised in that:
Assembly line includes the following steps:
Mold cleaning;
Release agent spraying;
Side mode scribing line;
Side mode installation;
Reinforcement installation;
Embedded part installation;
Casting is vibrated for the first time;
It strikes off;
It stands, precuring;
Hair pulling treatment;
Steam curing;
Demoulding;
Secondary formwork;
Overturning;
Side mode installation;
Reinforcement installation;
Embedded part installation;
Second of casting is vibrated;
It strikes off;
It stands, precuring;
Hair pulling treatment;
Steam curing;
Demoulding;
Coarse surface treatment;
Storage;
Assembly line is using the two independent loops assembly line constructions of interior circulation and outer circulation.
CN201910539350.8A 2019-06-20 2019-06-20 Double skin wall member production line double-cycle process method for arranging Pending CN110405932A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910539350.8A CN110405932A (en) 2019-06-20 2019-06-20 Double skin wall member production line double-cycle process method for arranging

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910539350.8A CN110405932A (en) 2019-06-20 2019-06-20 Double skin wall member production line double-cycle process method for arranging

Publications (1)

Publication Number Publication Date
CN110405932A true CN110405932A (en) 2019-11-05

Family

ID=68359447

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910539350.8A Pending CN110405932A (en) 2019-06-20 2019-06-20 Double skin wall member production line double-cycle process method for arranging

Country Status (1)

Country Link
CN (1) CN110405932A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110861210A (en) * 2019-11-29 2020-03-06 三一筑工科技有限公司 Production device and production method of double-skin wall prefabricated member
CN113478633A (en) * 2021-07-27 2021-10-08 湖南三一快而居住宅工业有限公司 Production method of cavity wall and concrete prefabricated part production line

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE29608329U1 (en) * 1996-05-08 1996-08-01 Tema GmbH, 85551 Kirchheim Press device for pressure molding roof tile compacts
GB2426750A (en) * 2005-05-31 2006-12-06 Forticrete Ltd Mixing tiles on a production line
CN109333800A (en) * 2018-11-21 2019-02-15 远大住宅工业(天津)有限公司 A kind of prefabricated components production line
CN109483717A (en) * 2018-11-21 2019-03-19 远大住宅工业(上海)有限公司 A kind of component production line
CN109732768A (en) * 2019-02-27 2019-05-10 中清大装配式建筑有限公司 Building prefabricated components forming production line and production technology with central dispatch system

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE29608329U1 (en) * 1996-05-08 1996-08-01 Tema GmbH, 85551 Kirchheim Press device for pressure molding roof tile compacts
GB2426750A (en) * 2005-05-31 2006-12-06 Forticrete Ltd Mixing tiles on a production line
CN109333800A (en) * 2018-11-21 2019-02-15 远大住宅工业(天津)有限公司 A kind of prefabricated components production line
CN109483717A (en) * 2018-11-21 2019-03-19 远大住宅工业(上海)有限公司 A kind of component production line
CN109732768A (en) * 2019-02-27 2019-05-10 中清大装配式建筑有限公司 Building prefabricated components forming production line and production technology with central dispatch system

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110861210A (en) * 2019-11-29 2020-03-06 三一筑工科技有限公司 Production device and production method of double-skin wall prefabricated member
CN113478633A (en) * 2021-07-27 2021-10-08 湖南三一快而居住宅工业有限公司 Production method of cavity wall and concrete prefabricated part production line

Similar Documents

Publication Publication Date Title
CN101508144B (en) Concrete casting production technique with energy-saving environmental-protection function
CN104723449B (en) A kind of automatic assembly line of building industrialization concrete prefabricated element
CN102584138B (en) Precast glass fiber reinforced cement (GRC) composite member and manufacturing method thereof
CN208068545U (en) A kind of three-dimensional production system of prefabricated component
CN110405932A (en) Double skin wall member production line double-cycle process method for arranging
CN202787577U (en) Prefabricated wall body shell structure of reinforced concrete superposed shear wall
CN103029212A (en) Production process of automatic assembly line in factory for pre-fabricating and assembling wall panel of integral shear wall structure
CN205134792U (en) Light -duty reinforced concrete prefabricated staircase
CN205962480U (en) Medical kit and load plant protection unmanned aerial vehicle of said medical kit
CN206351146U (en) A kind of continous way automatic flushing device for auto parts
CN105155836B (en) Aluminum alloy mould plate for building and its using method
CN110370447A (en) Overlap board member production line double-cycle process method for arranging
CN110228134A (en) Interior wall board member production line double-cycle process method for arranging
CN110450275A (en) PC component integrated production line double-cycle process method for arranging
CN207593817U (en) A kind of PC Numerical control production lines manipulator
CN208197158U (en) A kind of reinforcing bar tire suspender of precast segment box beam
CN110886473A (en) Automatic chimney paint spraying machine device and construction method
CN104652673A (en) Assembled integrated type prefabricated concrete floor slab and connection method thereof
CN210239094U (en) Hanging basket device for decorating outer wall of grouped cylindrical silo
CN108081448B (en) Production process of integrally decorated and electromechanical prefabricated GRC formwork structural column
CN108068206A (en) The spray pipe network support device of concrete curing and its automation curing system
CN208578056U (en) A kind of assembling concrete cushion cap template
CN202000010U (en) Bright dipping and washing device in automatic membrane passivation production line
CN207469280U (en) A kind of green light steel integrated housing basis rapid construction device
CN203999671U (en) A kind of shaft furnace steel-making converter lining processing device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20191105

RJ01 Rejection of invention patent application after publication