Nothing Special   »   [go: up one dir, main page]

CN114086771A - Steel column installation process - Google Patents

Steel column installation process Download PDF

Info

Publication number
CN114086771A
CN114086771A CN202111412456.5A CN202111412456A CN114086771A CN 114086771 A CN114086771 A CN 114086771A CN 202111412456 A CN202111412456 A CN 202111412456A CN 114086771 A CN114086771 A CN 114086771A
Authority
CN
China
Prior art keywords
steel column
steel
hoisting
ladder
installation process
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202111412456.5A
Other languages
Chinese (zh)
Inventor
孟昆
周海洋
张家俊
林虎
刘杰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Construction Group Co Ltd
East China Engineering Co Ltd of China Railway Construction Group Co Ltd
Original Assignee
China Railway Construction Group Co Ltd
East China Engineering Co Ltd of China Railway Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Construction Group Co Ltd, East China Engineering Co Ltd of China Railway Construction Group Co Ltd filed Critical China Railway Construction Group Co Ltd
Priority to CN202111412456.5A priority Critical patent/CN114086771A/en
Publication of CN114086771A publication Critical patent/CN114086771A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • E04G21/16Tools or apparatus
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • E04G21/16Tools or apparatus
    • E04G21/18Adjusting tools; Templates
    • E04G21/1841Means for positioning building parts or elements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G3/00Scaffolds essentially supported by building constructions, e.g. adjustable in height
    • E04G3/24Scaffolds essentially supported by building constructions, e.g. adjustable in height specially adapted for particular parts of buildings or for buildings of particular shape, e.g. chimney stacks or pylons
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00Component parts or accessories for scaffolds
    • E04G5/001Safety or protective measures against falling down relating to scaffoldings
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00Component parts or accessories for scaffolds
    • E04G5/04Means for fastening, supporting, or bracing scaffolds on or against building constructions
    • E04G5/045Means for fastening, supporting, or bracing scaffolds on or against building constructions for fastening scaffoldings on profiles, e.g. I or H profiles
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00Component parts or accessories for scaffolds
    • E04G5/10Steps or ladders specially adapted for scaffolds

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Ladders (AREA)

Abstract

The invention discloses a steel column installation process which comprises measurement paying-off, hoisting preparation, temporary facility installation, steel column hoisting butt joint, steel column position correction and welding fixation. The invention has the beneficial effects that: the steel crawling ladder is connected with the steel column in a binding manner, one side of the steel crawling ladder is welded with a safety ring provided with a safety rope in a pulling manner, the steel crawling ladder is arranged so that an operator can conveniently remove the lifting rope for lifting the steel column, and the steel crawling ladder can be prevented from floating to cause potential safety hazards so as to ensure the safety of the operator who executes the next procedure; the lower plate surface of the operating platform is fixedly connected with a temporary channel steel welded at a position 1.2 meters below the top of the steel column body column through welding, so that an operator can stand on the operating platform to operate through climbing the steel ladder, and meanwhile, the operating platform is high in stability, large in size and capable of reducing potential safety hazards; the lifting device is provided with a horizontal adjusting seat and a vertical adjusting seat, and a jack for horizontal adjustment and vertical adjustment is placed in the adjusting seat, so that the position of the lifted steel column is corrected.

Description

Steel column installation process
Technical Field
The invention relates to a steel column installation process, in particular to a steel column installation process, and belongs to the technical field of building construction.
Background
For the construction of the existing ultrahigh buildings, a concrete filled steel tube frame-reinforced concrete core tube system is often adopted for construction, so that the steel columns need to be installed before construction.
And in current steel column installation construction process, to the hoist and mount of steel column, only carry out the operation from top to bottom through simple and easy cat ladder, bring great potential safety hazard for operating personnel, to the steel column after the hoist and mount in addition, also be convenient for carry out horizontal position and straightness's that hangs down correction, bring great trouble for actual construction, and then seriously influence the construction progress.
Disclosure of Invention
The invention aims to provide a steel column mounting process for solving the problems.
The invention realizes the purpose through the following technical scheme: a steel column installation process comprises
Firstly, measuring and paying off, namely measuring and paying off the steel column according to the steel column layout. After the foundation pit is excavated, the steel column installation lofting work is started;
and step two, hoisting preparation, namely checking the component number in detail to ensure no error. Cleaning up slag, floating rust and the like on the surface of the steel column, checking the length, the geometric dimension, paint and the like of the steel column, correcting and repairing deformation, paint damage and the like before hoisting, and checking the central line, the axis and the mark of the steel column;
step three, installing temporary facilities, namely installing the detachable temporary facilities on the steel column before the steel column is hoisted, and using the detachable temporary facilities to assist in hoisting the steel column;
hoisting and butting the steel columns, hoisting the steel columns through a hoisting tower, hanging four steel wire ropes with enough strength under a lifting hook for hoisting, and padding sleepers below the steel columns;
step five, correcting the position of the steel column, and after the steel column is hoisted in place, correcting the horizontal position and the verticality of the steel column to align and fit the center line of the steel column with the center line of the next section of the steel column and take all the four sides into consideration;
and step six, welding and fixing, namely welding and fixing the butt joint surfaces of the upper steel column and the lower steel column.
As a still further scheme of the invention: in the third step, the temporary facilities installed on the steel column body comprise a steel crawling ladder used for climbing of operators and an operating platform used for standing of the operators, the steel crawling ladder is connected with the steel column body through a buckle on the top end, the steel column body and the steel crawling ladder are bound and connected through 8# iron wires every three meters, and a safety ring for pulling safety ropes is welded on one side of the steel crawling ladder.
As a still further scheme of the invention: operation platform's lower plate surface carries out fixed connection through welding and steel column body capital down 1.2 meters welded interim channel-section steel, just operation platform offers the last manhole that is used for passing the steel cat ladder, operation platform four sides welded fastening has the protection rail.
As a still further scheme of the invention: the steel column comprises a steel column body, wherein the upper end side wall and the lower end side wall of the steel column body are welded and fixed with L-shaped hoisting connecting plates, and the upper end hoisting connecting plate and the lower end hoisting connecting plate are uniformly and respectively arranged.
As a still further scheme of the invention: the side wall of the upper end and the lower end of the steel column body are respectively welded with a horizontal adjusting seat and a vertical adjusting seat which are positioned between two adjacent hoisting connecting plates, and a jack for horizontal adjustment and vertical adjustment is placed in the adjusting seat.
As a still further scheme of the invention: the upper and lower two sections steel column body straightness correction that hangs down can add and subtract the gasket in the otic placode junction of lower section post, two sections about steel column body horizontal direction correction adopts two theodolites to arrange in mutually perpendicular's axis control line respectively on, accurate centering flattening back, the same axis control line in back sight the place ahead to fixed portion of alighting, then indulge the telescope, alighting overhead scale and the reading of steel column.
The invention has the beneficial effects that:
1. the steel crawling ladder is connected with the steel column in a binding manner, one side of the steel crawling ladder is welded with a safety ring provided with a safety rope in a pulling manner, the steel crawling ladder is arranged so that an operator can conveniently remove the lifting rope for lifting the steel column, and the steel crawling ladder can be prevented from floating to cause potential safety hazards so as to ensure the safety of the operator who executes the next procedure;
2. the lower plate surface of the operating platform is fixedly connected with a temporary channel steel welded at a position 1.2 meters below the top of the steel column body column through welding, so that an operator can stand on the operating platform to operate through climbing the steel ladder, and meanwhile, the operating platform is high in stability, large in size and capable of reducing potential safety hazards;
3. the lifting device is provided with a horizontal adjusting seat and a vertical adjusting seat, and a jack for horizontal adjustment and vertical adjustment is placed in the adjusting seat, so that the position of the lifted steel column is corrected.
Drawings
FIG. 1 is a schematic flow chart of the present invention.
Fig. 2 is a schematic view of the installation structure of the temporary facility according to the present invention.
FIG. 3 is a schematic view of the horizontal adjustment structure of the present invention.
FIG. 4 is a schematic diagram of the verticality structure of the present invention.
FIG. 5 is a schematic view of the connection structure of steel columns according to the present invention.
In the figure: 1. the steel column body, 2, the steel cat ladder, 3, operation platform, 4, protection rail, 5, hoist and mount connecting plate, 6, level (l) ing seat, 7, the straightness that hangs down adjust seat and 8, jack.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
Example one
Referring to fig. 1 to 5, a steel column installation process includes
Firstly, measuring and paying off, namely measuring and paying off the steel column according to the steel column layout. After the foundation pit is excavated, the steel column installation lofting work is started;
and step two, hoisting preparation, namely checking the component number in detail to ensure no error. Cleaning up slag, floating rust and the like on the surface of the steel column, checking the length, the geometric dimension, paint and the like of the steel column, correcting and repairing deformation, paint damage and the like before hoisting, and checking the central line, the axis and the mark of the steel column;
step three, installing temporary facilities, namely installing the detachable temporary facilities on the steel column before the steel column is hoisted, and using the detachable temporary facilities to assist in hoisting the steel column;
hoisting and butting the steel columns, hoisting the steel columns through a hoisting tower, hanging four steel wire ropes with enough strength under a lifting hook for hoisting, and padding sleepers below the steel columns;
step five, correcting the position of the steel column, and after the steel column is hoisted in place, correcting the horizontal position and the verticality of the steel column to align and fit the center line of the steel column with the center line of the next section of the steel column and take all the four sides into consideration;
and step six, welding and fixing, namely welding and fixing the butt joint surfaces of the upper steel column and the lower steel column.
In the third step, the temporary facility installed on the steel column body 1 comprises a steel ladder 2 used for an operator to climb and an operating platform 3 used for the operator to stand, the steel ladder 2 is connected with the steel column body 1 through a buckle at the top end, the steel column body 1 and the steel ladder 2 are bound and connected through 8# iron wires every three meters, a safety ring for pulling a safety rope is welded on one side of the steel ladder 2, the steel ladder 2 is arranged so that the operator can conveniently remove a lifting rope for lifting the steel column, and the steel ladder 2 can be prevented from floating to cause potential safety hazards, so that the safety of the operator who performs the next procedure is ensured.
In the embodiment of the invention, the lower plate surface of the operating platform 3 is fixedly connected with a temporary channel steel welded at a position 1.2 meters below the top of the steel column body 1 through welding, the operating platform 3 is provided with an upper manhole used for penetrating through the steel ladder stand 2, and the four sides of the operating platform 3 are fixedly welded with the protective fence 4, so that an operator can stand on the operating platform to operate through climbing the steel ladder stand 3, meanwhile, the operating platform is high in stability and large in size, and potential safety hazards are reduced.
In the embodiment of the invention, the side walls of the upper end and the lower end of the steel column body 1 are welded and fixed with the L-shaped hoisting connecting plates 5, and the hoisting connecting plates 5 at the upper end and the lower end are uniformly and respectively arranged, so that when the upper steel column body 1 and the lower steel column body 1 are butted, the hoisting connecting plates 5 at the lower end of the upper steel column can be butted with the hoisting connecting plates 5 at the upper end of the lower steel column, and further, the upper steel column body and the lower steel column body can be preliminarily connected and fixed through the connection of bolts.
Example two
Referring to fig. 1 to 5, a steel column installation process includes
Firstly, measuring and paying off, namely measuring and paying off the steel column according to the steel column layout. After the foundation pit is excavated, the steel column installation lofting work is started;
and step two, hoisting preparation, namely checking the component number in detail to ensure no error. Cleaning up slag, floating rust and the like on the surface of the steel column, checking the length, the geometric dimension, paint and the like of the steel column, correcting and repairing deformation, paint damage and the like before hoisting, and checking the central line, the axis and the mark of the steel column;
step three, installing temporary facilities, namely installing the detachable temporary facilities on the steel column before the steel column is hoisted, and using the detachable temporary facilities to assist in hoisting the steel column;
hoisting and butting the steel columns, hoisting the steel columns through a hoisting tower, hanging four steel wire ropes with enough strength under a lifting hook for hoisting, and padding sleepers below the steel columns;
step five, correcting the position of the steel column, and after the steel column is hoisted in place, correcting the horizontal position and the verticality of the steel column to align and fit the center line of the steel column with the center line of the next section of the steel column and take all the four sides into consideration;
and step six, welding and fixing, namely welding and fixing the butt joint surfaces of the upper steel column and the lower steel column.
In the embodiment of the invention, the upper side wall and the lower side wall of the steel column body 1 are respectively welded with a horizontal adjusting seat 6 and a verticality adjusting seat 7 which are positioned between two adjacent hoisting connecting plates 5, and a jack 8 for horizontal adjustment and verticality adjustment is placed in the adjusting seat, so as to realize the position correction of the hoisted steel column.
In the embodiment of the invention, a gasket can be added and subtracted at the joint of the lug plates of the lower section column for the verticality correction of the upper and lower sections of the steel column body 1, two theodolites are respectively arranged on the mutually vertical axis control lines for the horizontal direction correction of the upper and lower sections of the steel column body 1, after accurate centering and leveling, the same axis control line in front is viewed from the back, an alignment part is fixed, then a telescope is longitudinally rotated, a scale on a steel column head is aligned and read, and after the calibration direction is compared with a designed control value, a correction direction is judged and a lifting worker is instructed to correct the steel column until the correct position is corrected in two orthogonal directions.
The working principle is as follows: firstly, according to a steel column layout drawing, measuring and paying off steel columns, and then inspecting the steel columns to be hoisted; before the steel column is hoisted, a steel ladder 2, an operating platform 3, a protective fence 4, a hoisting connecting plate 5, a horizontal adjusting seat 6 and a verticality adjusting seat 7 which can be disassembled are firstly installed on the steel column and used for assisting in hoisting the steel column; the steel column is hoisted by a hoisting tower, four steel wire ropes with enough strength are hung under a hook for hoisting, and sleepers are padded below the steel column; after the steel column is hoisted in place, the center line of the steel column is aligned and matched with the center line of the next section of the steel column by correcting the horizontal position and the verticality of the steel column, and the four sides are considered; and welding and fixing the butt joint surfaces of the upper steel column and the lower steel column.
It will be evident to those skilled in the art that the invention is not limited to the details of the foregoing illustrative embodiments, and that the present invention may be embodied in other specific forms without departing from the spirit or essential attributes thereof. The present embodiments are therefore to be considered in all respects as illustrative and not restrictive, the scope of the invention being indicated by the appended claims rather than by the foregoing description, and all changes which come within the meaning and range of equivalency of the claims are therefore intended to be embraced therein. Any reference sign in a claim should not be construed as limiting the claim concerned.
Furthermore, it should be understood that although the present description refers to embodiments, not every embodiment may contain only a single embodiment, and such description is for clarity only, and those skilled in the art should integrate the description, and the embodiments may be combined as appropriate to form other embodiments understood by those skilled in the art.

Claims (6)

1. A steel column installation process is characterized in that: comprises that
Firstly, measuring and paying off, namely measuring and paying off the steel column according to the steel column layout. After the foundation pit is excavated, the steel column installation lofting work is started;
and step two, hoisting preparation, namely checking the component number in detail to ensure no error. Cleaning up slag, floating rust and the like on the surface of the steel column, checking the length, the geometric dimension, paint and the like of the steel column, correcting and repairing deformation, paint damage and the like before hoisting, and checking the central line, the axis and the mark of the steel column;
step three, installing temporary facilities, namely installing the detachable temporary facilities on the steel column before the steel column is hoisted, and using the detachable temporary facilities to assist in hoisting the steel column;
hoisting and butting the steel columns, hoisting the steel columns through a hoisting tower, hanging four steel wire ropes with enough strength under a lifting hook for hoisting, and padding sleepers below the steel columns;
step five, correcting the position of the steel column, and after the steel column is hoisted in place, correcting the horizontal position and the verticality of the steel column to align and fit the center line of the steel column with the center line of the next section of the steel column and take all the four sides into consideration;
and step six, welding and fixing, namely welding and fixing the butt joint surfaces of the upper steel column and the lower steel column.
2. The steel column installation process according to claim 1, wherein: in the third step, the temporary facilities installed on the steel column body (1) comprise a steel ladder (2) used for climbing of an operator and an operating platform (3) used for standing of the operator, the steel ladder (2) is connected with the steel column body (1) through a buckle on the top end, the steel column body (1) and the steel ladder (2) are bound and connected through 8# iron wires every three meters, and a safety ring for pulling a safety rope is welded on one side of the steel ladder (2).
3. A steel column installation process according to claim 2, wherein: the lower plate surface of the operation platform (3) is fixedly connected with a temporary channel steel welded at a position 1.2 meters below the top of the steel column body (1) through welding, an upper manhole used for penetrating the steel crawling ladder (2) is arranged on the operation platform (3), and four sides of the operation platform (3) are fixedly welded with protection fences (4).
4. A steel column installation process according to claim 3, wherein: the steel column is characterized in that the side walls of the upper end and the lower end of the steel column body (1) are fixedly welded with L-shaped hoisting connecting plates (5), and the hoisting connecting plates (5) of the upper end and the lower end are uniformly and respectively arranged.
5. The steel column installation process according to claim 4, wherein: the steel column is characterized in that the side walls of the upper end and the lower end of the steel column body (1) are respectively welded with a horizontal adjusting seat (6) and a vertical adjusting seat (7) which are positioned between two adjacent hoisting connecting plates (5), and a jack (8) for horizontal adjustment and vertical adjustment is placed in each adjusting seat.
6. The steel column installation process according to claim 1, wherein: two sections about steel column body (1) straightness correction that hangs down can add the subtraction gasket in the otic placode junction of lower section post, two sections about steel column body (1) horizontal direction is rectified and is adopted two theodolites to arrange mutually perpendicular's axis control line respectively in, accurate centering flattening back, the same axis control line in back sight the place ahead to fixed portion of alighting, then indulge the telescope, alighting the overhead scale of steel column and reading.
CN202111412456.5A 2021-11-25 2021-11-25 Steel column installation process Pending CN114086771A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202111412456.5A CN114086771A (en) 2021-11-25 2021-11-25 Steel column installation process

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202111412456.5A CN114086771A (en) 2021-11-25 2021-11-25 Steel column installation process

Publications (1)

Publication Number Publication Date
CN114086771A true CN114086771A (en) 2022-02-25

Family

ID=80304501

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202111412456.5A Pending CN114086771A (en) 2021-11-25 2021-11-25 Steel column installation process

Country Status (1)

Country Link
CN (1) CN114086771A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114439248A (en) * 2022-04-07 2022-05-06 北京建工集团有限责任公司 Steel column installation method
CN114809654A (en) * 2022-06-02 2022-07-29 合肥工业大学 Sectional construction method for H-shaped steel column
CN114858148A (en) * 2022-03-22 2022-08-05 莱芜钢铁集团建筑安装工程有限公司 Steel column installation verticality measuring method
CN115676621A (en) * 2022-09-07 2023-02-03 浙江长兴金诺预制构件有限公司 High-efficient installation device of prefab for capital construction
CN116241061A (en) * 2023-01-30 2023-06-09 中国十七冶集团有限公司 Reusable vertical operation platform setting method

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO1998015696A1 (en) * 1996-10-07 1998-04-16 Genghou Deng A method of lifting structure from above to below
CN106760197A (en) * 2016-12-02 2017-05-31 江苏沪宁钢机股份有限公司 A kind of method that allowable error is installed in steel column structure and its control
CN107938841A (en) * 2017-11-27 2018-04-20 江苏沪宁钢机股份有限公司 A kind of positioning adjusting of steel column pairing and method of temporarily fixing
CN111424950A (en) * 2020-04-01 2020-07-17 天津市建设工程监理公司 Steel column hoisting device, steel column hoisting construction method and supervision method thereof

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO1998015696A1 (en) * 1996-10-07 1998-04-16 Genghou Deng A method of lifting structure from above to below
CN106760197A (en) * 2016-12-02 2017-05-31 江苏沪宁钢机股份有限公司 A kind of method that allowable error is installed in steel column structure and its control
CN107938841A (en) * 2017-11-27 2018-04-20 江苏沪宁钢机股份有限公司 A kind of positioning adjusting of steel column pairing and method of temporarily fixing
CN111424950A (en) * 2020-04-01 2020-07-17 天津市建设工程监理公司 Steel column hoisting device, steel column hoisting construction method and supervision method thereof

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114858148A (en) * 2022-03-22 2022-08-05 莱芜钢铁集团建筑安装工程有限公司 Steel column installation verticality measuring method
CN114439248A (en) * 2022-04-07 2022-05-06 北京建工集团有限责任公司 Steel column installation method
CN114809654A (en) * 2022-06-02 2022-07-29 合肥工业大学 Sectional construction method for H-shaped steel column
CN115676621A (en) * 2022-09-07 2023-02-03 浙江长兴金诺预制构件有限公司 High-efficient installation device of prefab for capital construction
CN115676621B (en) * 2022-09-07 2024-05-07 山西宏图清明建设工程有限公司 Prefabricated member efficient installation device for foundation construction
CN116241061A (en) * 2023-01-30 2023-06-09 中国十七冶集团有限公司 Reusable vertical operation platform setting method

Similar Documents

Publication Publication Date Title
CN114086771A (en) Steel column installation process
CN101967886B (en) Assembly and installation methods of steel containment vessel of nuclear power station
CN106760197B (en) Method for allowing error in installation of steel column structure
CN111851565B (en) Steel structure stand column alignment structure with cup-mouth type foundation and construction method thereof
CN106193618B (en) A kind of aerial steel structure truss construction of Long span
CN109911770B (en) Construction method for hoisting gantry crane
CN106848938B (en) Cable testing bridge hangs installation method under a kind of High Altitude Platform
CN114232805B (en) Construction method of ultrahigh-height large-span steel concrete beam hanging structure
CN104477736A (en) Shaft elevator installation method
CN107090775A (en) A kind of full framing space beam-ends cable guide pipe construction localization method
CN112211103A (en) Special safe construction process for assembling and installing coal conveying trestle steel truss
CN108678388A (en) The short mast multiple spot integral hoisting construction engineering method of large capacity circle storage tank
CN107227686A (en) A kind of tunnel-type anchorage pre-stress system locating support construction method
CN212532065U (en) Gantry crane capable of being used in different height difference places
CN108179749B (en) Lattice column positioner and positioning method thereof
CN114000635B (en) Assembly process based on metal roof framework sliding installation
CN210827478U (en) Deep foundation pit underground structure reverse construction method steel pipe column positioning device
CN107217912A (en) It is a kind of to be used for the superelevation physical isolation construction method of neighbouring high ferro Business Line construction
CN113279620A (en) Sleeve type multi-pipe chimney construction method
CN113501404A (en) Ultrahigh construction elevator and wall attaching method for same
CN111485727A (en) Construction method for hoisting and welding arched beam of steel-structure rainshed house
CN221502617U (en) Movable layer operation platform that encorbelments
CN113957805B (en) Installation device and method for bridge under-hanging water supply and drainage pipeline
CN117735416A (en) Combined hoisting method for blast furnace shaft frame
CN218664876U (en) Construction elevator structure for circular underground excavation shaft

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20220225

RJ01 Rejection of invention patent application after publication