CN107999829A - Bar planting drilling aid at the top of a kind of building secondary structure constructional column - Google Patents

Bar planting drilling aid at the top of a kind of building secondary structure constructional column Download PDF

Info

Publication number
CN107999829A
CN107999829A CN201710992106.8A CN201710992106A CN107999829A CN 107999829 A CN107999829 A CN 107999829A CN 201710992106 A CN201710992106 A CN 201710992106A CN 107999829 A CN107999829 A CN 107999829A
Authority
CN
China
Prior art keywords
supporting rod
working beam
bar
operation lever
hinged
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710992106.8A
Other languages
Chinese (zh)
Inventor
徐骏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC17 Group Co Ltd
Original Assignee
China MCC17 Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC17 Group Co Ltd filed Critical China MCC17 Group Co Ltd
Priority to CN201710992106.8A priority Critical patent/CN107999829A/en
Publication of CN107999829A publication Critical patent/CN107999829A/en
Pending legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B25HAND TOOLS; PORTABLE POWER-DRIVEN TOOLS; MANIPULATORS
    • B25HWORKSHOP EQUIPMENT, e.g. FOR MARKING-OUT WORK; STORAGE MEANS FOR WORKSHOPS
    • B25H1/00Work benches; Portable stands or supports for positioning portable tools or work to be operated on thereby
    • B25H1/0021Stands, supports or guiding devices for positioning portable tools or for securing them to the work
    • B25H1/0035Extensible supports, e.g. telescopic
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B25HAND TOOLS; PORTABLE POWER-DRIVEN TOOLS; MANIPULATORS
    • B25HWORKSHOP EQUIPMENT, e.g. FOR MARKING-OUT WORK; STORAGE MEANS FOR WORKSHOPS
    • B25H1/00Work benches; Portable stands or supports for positioning portable tools or work to be operated on thereby
    • B25H1/0021Stands, supports or guiding devices for positioning portable tools or for securing them to the work

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention discloses bar planting drilling aid at the top of a kind of building secondary structure constructional column, including working beam, operation lever, balancing pole and supporting rod, the working beam and supporting rod are the montant being arranged in parallel, the balancing pole and operation lever are the cross bar being arranged in parallel, the working beam lower end is hinged with operation lever one end, it is hinged in the middle part of the working beam with balancing pole one end, the balancing pole other end is hinged with supporting bar top, it is hinged in the middle part of the operation lever with supporting rod, the working beam, operation lever, balancing pole forms a parallelogram after being connected with supporting rod, the working beam top is connected with electric drill, the one end of the operation lever away from working beam is equipped with operation handle, the bottom of the supporting rod is equipped with backing plate.

Description

Bar planting drilling aid at the top of a kind of building secondary structure constructional column
Technical field
The present invention relates to construction engineering technical field, is specially bar planting drilling at the top of a kind of building secondary structure constructional column Auxiliary device.
Background technology
At the top of building secondary structure constructional column during bar planting drilling construction, due to being influenced by height, bar planting drilling worker It must come back and drill.And since the dust drilled out during drilling can be fallen into worker's eye, it is not only dangerous but also inconvenient, and apply Work difficulty is larger, during construction must hand lift electric drill and construct, often due to worker is short of physical strength, easily trigger safe thing Therefore.
The content of the invention
The technical problem to be solved in the present invention is overcome the defects of existing, there is provided a kind of building secondary structure constructs capital Portion's bar planting drilling aid, according to lever principle, other end working beam bar stress withstands electric drill upwards when being pressed downward operation lever Drill, can effectively solve the problems, such as in background technology.
To achieve the above object, the present invention provides following technical solution:Planted at the top of a kind of building secondary structure constructional column Muscle drilling aid, including working beam, operation lever, balancing pole and supporting rod, the working beam and supporting rod are to be arranged in parallel Montant, the balancing pole and operation lever are the cross bar being arranged in parallel, and the working beam lower end is hinged with operation lever one end, described Be hinged with balancing pole one end in the middle part of working beam, the balancing pole other end is hinged with supporting bar top, the operation lever middle part and Supporting rod is hinged, and the working beam, operation lever, balancing pole form a parallelogram, the work after being connected with supporting rod Bar top is connected with electric drill, and the one end of the operation lever away from working beam is equipped with operation handle, and the bottom of the supporting rod is equipped with Backing plate.
As a preferred technical solution of the present invention, the supporting rod is telescopic rod, and said support bar, which is equipped with, to be fixed Card.
As a preferred technical solution of the present invention, the supporting rod is equipped with observation bar, and the observation bar is equipped with Peephole.
As a preferred technical solution of the present invention, the observation bar is located at supporting rod middle and lower part and hangs down with supporting rod Directly.
As a preferred technical solution of the present invention, the peephole is speculum and the speculum adjustable angle.
As a preferred technical solution of the present invention, the working beam lower end and operation lever one end by movable bolt and Gasket is hinged, and is hinged in the middle part of the working beam with balancing pole one end by movable bolt and gasket, the balancing pole other end and Supporting bar top is hinged by movable bolt and gasket, is cut with scissors in the middle part of the operation lever with supporting rod by movable bolt and gasket Connect.
As a preferred technical solution of the present invention, the working beam, operation lever, balancing pole and supporting rod are the lumps of wood Bar..
Compared with prior art, the beneficial effects of the invention are as follows:The present invention is made simply, working beam, operation lever, balance Bar and supporting rod fix quadrangularly stent using movable bolt, can be up and down, and one end is directly fallen on floor, working beam one End is effectively connected with electric drill, and when drilling holds operation lever and is pressed downward, and according to lever principle, is pressed downward other end montant during operation lever Stress withstands electric drill and drills upwards.Dust was fallen into worker's eye but also time saving and energy saving when the device not only effectively prevent drilling, Greatly improve work efficiency;Install peephole additional in preferable technical solution, more effectively ensure that the accuracy of operation, Telescopic rod is made adjustable lever and ensure that the diversified suitability of construction environment.
Brief description of the drawings
Fig. 1 is the first structure front elevation of the invention.
Fig. 2 is the first texture edge figure of the invention.
Fig. 3 is movable screw node diagram.
Fig. 4 is the first structure diagram of supporting rod in the present invention.
Fig. 5 is second of structure front elevation of the invention.
Fig. 6 is second of texture edge figure of the invention.
Fig. 7 is second of structure diagram of supporting rod in the present invention.
In figure:1st, balancing pole, 2, operation lever, 21, handle, 3, supporting rod, 31, fixing card, 4, working beam, 5, movable screw Bolt, 6, gasket, 7, observation bar, 8, backing plate, 9, electric drill, 10, peephole.
Embodiment
Below in conjunction with the attached drawing in the embodiment of the present invention, the technical solution in the embodiment of the present invention is carried out clear, complete Site preparation describes, it is clear that described embodiment is only part of the embodiment of the present invention, instead of all the embodiments.It is based on Embodiment in the present invention, those of ordinary skill in the art are obtained every other without making creative work Embodiment, belongs to the scope of protection of the invention.
Embodiment one
~Fig. 4 is please referred to Fig.1, the present invention provides a kind of technical solution:Planted at the top of a kind of building secondary structure constructional column Muscle drilling aid, including working beam 4, operation lever 2, balancing pole 1 and supporting rod 3, the working beam 4 and supporting rod 3 are flat The montant that row is set, the balancing pole 1 and operation lever 2 are the cross bar being arranged in parallel, 4 lower end of working beam and operation lever 2 one End is hinged, and the middle part of working beam 4 is hinged with 1 one end of balancing pole, and 1 other end of balancing pole is hinged with 3 top of supporting rod, institute It is hinged with supporting rod 3 to state the middle part of operation lever 2, the working beam 4, operation lever 2, balancing pole 1 and supporting rod 3 form one after connecting Parallelogram, 4 top of working beam are connected with electric drill 9, and the described one end of operation lever 2 away from working beam 4 is equipped with manipulator Handle 21, the bottom of the supporting rod 3 are equipped with backing plate 8, and 4 lower end of working beam passes through movable bolt 5 and pad with 2 one end of operation lever Piece 6 is hinged, and the middle part of working beam 4 is hinged by movable bolt 5 and gasket 6 with 1 one end of balancing pole, and the balancing pole 1 is another End is hinged by movable bolt 5 and gasket 6 with 3 top of supporting rod, and the middle part of operation lever 2 passes through movable bolt 5 with supporting rod 3 It is hinged with gasket 6.
Embodiment two
Fig. 4~Fig. 7 is referred to, the present invention provides a kind of technical solution:Planted at the top of a kind of building secondary structure constructional column Muscle drilling aid, including working beam 4, operation lever 2, balancing pole 1 and supporting rod 3, the working beam 4 and supporting rod 3 are flat The montant that row is set, the balancing pole 1 and operation lever 2 are the cross bar being arranged in parallel, 4 lower end of working beam and operation lever 2 one End is hinged, and the middle part of working beam 4 is hinged with 1 one end of balancing pole, and 1 other end of balancing pole is hinged with 3 top of supporting rod, institute It is hinged with supporting rod 3 to state the middle part of operation lever 2, the working beam 4, operation lever 2, balancing pole 1 and supporting rod 3 form one after connecting Parallelogram, 4 top of working beam are connected with electric drill 9, and the described one end of operation lever 2 away from working beam 4 is equipped with manipulator Handle 21, the bottom of the supporting rod 3 are equipped with backing plate 8.
The supporting rod 3 is telescopic rod, and said support bar 3 is equipped with fixing card 31.
The supporting rod 3 is equipped with observation bar 7, and the observation bar 7 is equipped with peephole 10.
The observation bar 7 is located at 3 middle and lower part of supporting rod and vertical with supporting rod 3.
The peephole 10 is speculum and the speculum adjustable angle.
4 lower end of working beam is hinged by movable bolt 5 and gasket 6 with 2 one end of operation lever, the middle part of working beam 4 Hinged by movable bolt 5 and gasket 6 with 1 one end of balancing pole, 1 other end of balancing pole passes through activity with 3 top of supporting rod Bolt 5 and gasket 6 are hinged, and the middle part of operation lever 2 is hinged by movable bolt 5 and gasket 6 with supporting rod 3.
The working beam 4, operation lever 2, balancing pole 1 and supporting rod 3 are lumps of wood bar.
Although an embodiment of the present invention has been shown and described, for the ordinary skill in the art, can be with Understanding without departing from the principles and spirit of the present invention can carry out these embodiments a variety of changes, modification, replace And modification, the scope of the present invention is defined by the appended.

Claims (7)

  1. A kind of 1. bar planting drilling aid at the top of building secondary structure constructional column, it is characterised in that:Including working beam, operation Bar, balancing pole and supporting rod, the working beam and supporting rod are the montant being arranged in parallel, and the balancing pole and operation lever are parallel The cross bar of setting, the working beam lower end are hinged with operation lever one end, are hinged in the middle part of the working beam with balancing pole one end, described The balancing pole other end is hinged with supporting bar top, is hinged in the middle part of the operation lever with supporting rod, and the working beam, operation lever, put down Weighing apparatus bar forms a parallelogram after being connected with supporting rod, and the working beam top is connected with electric drill, and the operation lever is remote One end of working beam is equipped with operation handle, and the bottom of the supporting rod is equipped with backing plate.
  2. 2. bar planting drilling aid, its feature exist at the top of a kind of building secondary structure constructional column according to claim 1 In:The supporting rod is telescopic rod, and said support bar is equipped with fixing card.
  3. 3. bar planting drilling aid, its feature exist at the top of a kind of building secondary structure constructional column according to claim 1 In:The supporting rod is equipped with observation bar, and the observation bar is equipped with peephole.
  4. 4. bar planting drilling aid, its feature exist at the top of a kind of building secondary structure constructional column according to claim 3 In:The observation bar is located at supporting rod middle and lower part and vertical with supporting rod.
  5. 5. bar planting drilling aid, its feature exist at the top of a kind of building secondary structure constructional column according to claim 3 In:The peephole is speculum and the speculum adjustable angle.
  6. 6. according to bar planting drilling aid at the top of a kind of any one of Claims 1 to 5 building secondary structure constructional column, It is characterized in that:The working beam lower end is hinged with operation lever one end by movable bolt and gasket, in the middle part of the working beam with Balancing pole one end is hinged by movable bolt and gasket, and the balancing pole other end passes through movable bolt and pad with supporting bar top Piece is hinged, and is hinged in the middle part of the operation lever with supporting rod by movable bolt and gasket.
  7. 7. bar planting drilling aid, its feature exist at the top of a kind of building secondary structure constructional column according to claim 6 In:The working beam, operation lever, balancing pole and supporting rod are lumps of wood bar.
CN201710992106.8A 2017-10-23 2017-10-23 Bar planting drilling aid at the top of a kind of building secondary structure constructional column Pending CN107999829A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710992106.8A CN107999829A (en) 2017-10-23 2017-10-23 Bar planting drilling aid at the top of a kind of building secondary structure constructional column

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710992106.8A CN107999829A (en) 2017-10-23 2017-10-23 Bar planting drilling aid at the top of a kind of building secondary structure constructional column

Publications (1)

Publication Number Publication Date
CN107999829A true CN107999829A (en) 2018-05-08

Family

ID=62051073

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710992106.8A Pending CN107999829A (en) 2017-10-23 2017-10-23 Bar planting drilling aid at the top of a kind of building secondary structure constructional column

Country Status (1)

Country Link
CN (1) CN107999829A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108464224A (en) * 2018-07-09 2018-08-31 盐城工业职业技术学院 A kind of cherry plantation irrigation Illumination adjusting device
CN110014521A (en) * 2019-05-13 2019-07-16 中国二十二冶集团有限公司 Bar planting assistor and its construction method at the top of secondary structure constructional column
CN110125883A (en) * 2019-05-10 2019-08-16 中国建筑第六工程局有限公司 A kind of fixed device of beam slab bar planting drilling machine
CN115041730A (en) * 2022-07-11 2022-09-13 中核华辰建筑工程有限公司 Novel portable handheld auxiliary tool for drilling
CN116084703A (en) * 2022-11-25 2023-05-09 中国十七冶集团有限公司 Roof top beam bar planting auxiliary device and use method thereof

Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3015532A1 (en) * 1980-04-23 1981-10-29 Detlef Stach Ceiling and floor panel installation accessory - is frame with lever attached for simultaneously operating electric drills at top and bottom
JPH11104909A (en) * 1997-10-01 1999-04-20 Central Japan Railway Co Working jig for power tool
CN202578536U (en) * 2012-05-21 2012-12-05 新疆兵团水利水电工程集团有限公司 Adjustable support for perforating floor
CN203248090U (en) * 2013-05-14 2013-10-23 中国葛洲坝集团股份有限公司 Adjustable supporting frame used for top drilling
CN203835280U (en) * 2014-04-28 2014-09-17 同济大学 Electric hammer construction support structure
CN204209169U (en) * 2014-09-29 2015-03-18 中建三局集团有限公司 A kind of tool-type ceiling drilling device
CN104589285A (en) * 2015-02-02 2015-05-06 中铁十七局集团电气化工程有限公司 Auxiliary perforating device for self-made electrical hammer
CN204877287U (en) * 2015-07-03 2015-12-16 中建一局集团安装工程有限公司 Height-adjustable removes assembled roof construction auxiliary device
CN205464448U (en) * 2016-01-29 2016-08-17 中铁城建集团第三工程有限公司 Constructional column upper portion bar planting drilling equipment
CN205673646U (en) * 2016-06-01 2016-11-09 中国建筑一局(集团)有限公司 Floor drilling tool with accurate drilling position
CN205967520U (en) * 2016-09-14 2017-02-22 国家电网公司 Top drilling support appurtenance

Patent Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3015532A1 (en) * 1980-04-23 1981-10-29 Detlef Stach Ceiling and floor panel installation accessory - is frame with lever attached for simultaneously operating electric drills at top and bottom
JPH11104909A (en) * 1997-10-01 1999-04-20 Central Japan Railway Co Working jig for power tool
CN202578536U (en) * 2012-05-21 2012-12-05 新疆兵团水利水电工程集团有限公司 Adjustable support for perforating floor
CN203248090U (en) * 2013-05-14 2013-10-23 中国葛洲坝集团股份有限公司 Adjustable supporting frame used for top drilling
CN203835280U (en) * 2014-04-28 2014-09-17 同济大学 Electric hammer construction support structure
CN204209169U (en) * 2014-09-29 2015-03-18 中建三局集团有限公司 A kind of tool-type ceiling drilling device
CN104589285A (en) * 2015-02-02 2015-05-06 中铁十七局集团电气化工程有限公司 Auxiliary perforating device for self-made electrical hammer
CN204877287U (en) * 2015-07-03 2015-12-16 中建一局集团安装工程有限公司 Height-adjustable removes assembled roof construction auxiliary device
CN205464448U (en) * 2016-01-29 2016-08-17 中铁城建集团第三工程有限公司 Constructional column upper portion bar planting drilling equipment
CN205673646U (en) * 2016-06-01 2016-11-09 中国建筑一局(集团)有限公司 Floor drilling tool with accurate drilling position
CN205967520U (en) * 2016-09-14 2017-02-22 国家电网公司 Top drilling support appurtenance

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108464224A (en) * 2018-07-09 2018-08-31 盐城工业职业技术学院 A kind of cherry plantation irrigation Illumination adjusting device
CN110125883A (en) * 2019-05-10 2019-08-16 中国建筑第六工程局有限公司 A kind of fixed device of beam slab bar planting drilling machine
CN110014521A (en) * 2019-05-13 2019-07-16 中国二十二冶集团有限公司 Bar planting assistor and its construction method at the top of secondary structure constructional column
CN115041730A (en) * 2022-07-11 2022-09-13 中核华辰建筑工程有限公司 Novel portable handheld auxiliary tool for drilling
CN116084703A (en) * 2022-11-25 2023-05-09 中国十七冶集团有限公司 Roof top beam bar planting auxiliary device and use method thereof

Similar Documents

Publication Publication Date Title
CN107999829A (en) Bar planting drilling aid at the top of a kind of building secondary structure constructional column
CN103611967B (en) A kind of elevation type percussion drill auxiliary support apparatus
CN204782062U (en) Curtain crossbeam installation appurtenance
CN206140465U (en) Civil engineering pipe fitting placing rack
CN107790787A (en) The lengthening support that a kind of packaged type electric drill drills vertically upward
CN205173906U (en) Surveying instrument bracket
CN201221365Y (en) Front cantilever temporary support
CN201614726U (en) Boring device of top plate
CN211891475U (en) Improved simple top plate drilling device
CN203565916U (en) Drilling tool with rear-mounted member
CN203541623U (en) Novel punching frame
CN102051975A (en) Lever type high-altitude borer
CN214064444U (en) Engineering detector support frame for construction
CN209481105U (en) It is a kind of large size ball screw assembly, assembly use device
CN203530866U (en) Device with bidirectional hooks for adjusting levelness of bridge angle steel bracket
CN204700349U (en) A kind of beam slab bar planting boring bar tool
CN203484704U (en) Simple movable-arm-type drilling device
CN210500860U (en) Secondary structure constructional column top bar planting assistor
CN203509120U (en) Movable vertical-drilling support for building
CN110014521A (en) Bar planting assistor and its construction method at the top of secondary structure constructional column
CN202825751U (en) Movable accurate positioning hanging bar drilling device
CN208215704U (en) A kind of concrete structure drilling aid
CN206816162U (en) A kind of cat ladder for building
CN207448355U (en) Hatchcover rubber mounting tool
CN204053009U (en) A kind of vertical bar planting boring ease of Use frame

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20180508

RJ01 Rejection of invention patent application after publication