CN105447247B - A kind of method and system that regulation and controlling of information is checked - Google Patents

A kind of method and system that regulation and controlling of information is checked Download PDF

Info

Publication number
CN105447247B
CN105447247B CN201510821788.7A CN201510821788A CN105447247B CN 105447247 B CN105447247 B CN 105447247B CN 201510821788 A CN201510821788 A CN 201510821788A CN 105447247 B CN105447247 B CN 105447247B
Authority
CN
China
Prior art keywords
information
main website
substation
everything
record
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510821788.7A
Other languages
Chinese (zh)
Other versions
CN105447247A (en
Inventor
丁峰
陆承宇
罗华峰
王松
阮黎翔
吴栋萁
杨涛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Electric Power Research Institute of State Grid Zhejiang Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
Electric Power Research Institute of State Grid Zhejiang Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Electric Power Research Institute of State Grid Zhejiang Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201510821788.7A priority Critical patent/CN105447247B/en
Publication of CN105447247A publication Critical patent/CN105447247A/en
Application granted granted Critical
Publication of CN105447247B publication Critical patent/CN105447247B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/20Design optimisation, verification or simulation
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E60/00Enabling technologies; Technologies with a potential or indirect contribution to GHG emissions mitigation

Landscapes

  • Engineering & Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Computer Hardware Design (AREA)
  • Evolutionary Computation (AREA)
  • Geometry (AREA)
  • General Engineering & Computer Science (AREA)
  • General Physics & Mathematics (AREA)
  • Remote Monitoring And Control Of Power-Distribution Networks (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)
  • Selective Calling Equipment (AREA)

Abstract

The invention discloses the method and system that a kind of regulation and controlling of information is checked, this method comprises: the SCD file of substation is imported into simulated program;Everything information in the substation is spaced to schedule according to the SCD file content and is sent in sequence to telemechanical apparatus and monitoring backstage by the simulated program;The monitoring records the everything information received from the background;The everything information for the telemechanical apparatus forwarding that simulation main website record receives;By the everything information of the everything information of monitoring backstage record and simulation main website record, compared using the scheduling information table of the substation;This method is built without the communication channel between substation and main website and is completed, also it need not interact and carry out the work with main website, it is only necessary to set up simulated environment in substation, utilize automation tools and means, the check for realizing regulation and controlling of information improves regulation and controlling of information and checks working efficiency.

Description

A kind of method and system that regulation and controlling of information is checked
Technical field
The present invention relates to electrical engineering technical field, in particular to a kind of method and system of regulation and controlling of information check.
Background technique
Currently, power grid regulation information data flows to: dispatching automation acquisition information is mainly needed by information acquisition unit, far Dynamic device, scheduling station three-stage apparatus.Information acquisition unit is responsible for remote signalling in acquisition station, telemetry intelligence (TELINT), and is sent to from the background, far The station levels equipment such as dynamic device.Information that each acquisition unit of telemechanical apparatus centralized collection receives simultaneously is forwarded to scheduling station.In intelligence Under energy substation technology, the infomational message of telemechanical apparatus acquisition interval measure and control device is according to 61850 standards, and main website is with 104 messages Reception of beacons telemechanical apparatus uploads data.
Whether regulation and controlling of information check is that substation puts into operation the necessary work of previous item, be used to check the information occurred in station and can So correct that be sent to scheduling station, main identifying object is the information conversion links of telemechanical apparatus.Conventional regulation and controlling of information school Kernel mode are as follows: after the communication channel between substation and main website builds completion, substation and main website staff in place, power transformation Stand staff according to scheduling approval regulation and controlling of information table " act " on the spot one stand in signal, scheduling station receive telemechanical dress Set transmit with address be mark action message after, compare regulation and controlling of information table agreement, and by with the people that works in substation The real-time interaction of member confirms that the description of received regulation and controlling of information with the information of transformer substation end " movement " is corresponding.So One by one, to complete the verifications of all information points.
Conventional control information check method needs transformer substation end and scheduling station coordinated to check every regulation letter one by one Breath, both sides' (when substation is checked with multiple main websites simultaneously, being related to multi-party) need to be closely connected, cooperate.Because of scheduling information amount Huge (thousands of points), and scheduling station quantity is more (2-3), the mode checked point by point makes field adjustable workload heavy, work Make inefficiency, it usually needs time a couple of days goes to complete this work.Working time is longer, it is easier with other work conflicts and It is disturbed.Therefore, how to carry out regulation and controlling of information quickly to check, be those skilled in the art's technical issues that need to address.
Summary of the invention
The object of the present invention is to provide the method and system that a kind of regulation and controlling of information is checked, it is only necessary to emulation is set up in substation Environment realizes the check of regulation and controlling of information using automation tools and means, improves regulation and controlling of information and checks working efficiency.
In order to solve the above technical problems, the present invention provides a kind of method that regulation and controlling of information is checked, comprising:
The SCD file of substation is imported into simulated program;
The simulated program is according to the SCD file content, by everything information in the substation according to pre- timing Between interval be sent in sequence to telemechanical apparatus and monitoring backstage;
The monitoring records the everything information received from the background;
The everything information for the telemechanical apparatus forwarding that simulation main website record receives;
By the everything information of the everything information of monitoring backstage record and simulation main website record, utilize The scheduling information table of the substation compares.
Wherein, further includes:
The number of the everything information of simulation main website record is counted, and is believed with the movement in the scheduling information table The number of breath is compared;
Judge the telemechanical apparatus with the presence or absence of leakage heat condition according to comparison result.
Wherein, the everything of the everything information of monitoring backstage record and simulation main website record is believed Breath, is compared using the scheduling information table of the substation, comprising:
It successively transfers under the same SOE time, what the action message and the monitoring backstage that the simulation main website records recorded Action message;
Using the scheduling information table, change corresponding to the information dot address in the action message of simulation main website record is determined Information description in power station;
Information description and the information description in the action message of monitoring backstage record are compared;
If the same, the telemechanical apparatus forwarding behavior information is correct;
If different, the telemechanical apparatus forwarding behavior information errors.
Wherein, before the SCD file of substation being imported into simulated program, comprising:
Setting simulation main website, leads to the simulation main website by 104 specifications with telemechanical apparatus in the substation Letter.
Wherein, further includes:
According to comparing result, determine whether the telemechanical apparatus forwards mistake;
If so, issuing prompt information.
The present invention provides a kind of system that regulation and controlling of information is checked, comprising:
Simulated program module, for the SCD file of substation to be imported into simulated program;According in the SCD file Hold, everything information in the substation is spaced to schedule and is sent in sequence to telemechanical apparatus and monitoring backstage;
Monitoring backstage, for recording the everything information received;
Telemechanical apparatus, for forwarding the everything information received to simulation main website;
Main website is simulated, for recording the everything information of the telemechanical apparatus received forwarding;
Contrast module, for the everything information of monitoring backstage record to be simulated all of main website record with described Action message is compared using the scheduling information table of the substation.
Wherein, further includes:
Comparison module, the number of the everything information for counting simulation main website record, and believe with the scheduling The number of action message in breath table is compared;
Judgment module, for judging the telemechanical apparatus with the presence or absence of leakage heat condition according to comparison result.
Wherein, the contrast module includes:
Acquiring unit, for successively transferring under the same SOE time, the action message of simulation main website record and the prison The action message of control backstage record;
Determination unit determines the information point in the action message of simulation main website record for utilizing the scheduling information table Information description in substation corresponding to address;
Comparison unit, for by the information description with it is described monitoring backstage record action message in information describe into Row comparison;If the same, the telemechanical apparatus forwarding behavior information is correct;If different, the telemechanical apparatus forwarding behavior Information errors.
Wherein, which includes:
Setup module passes through the simulation main website with telemechanical apparatus for the setting simulation main website in the substation 104 specifications are communicated.
Wherein, further includes:
Cue module, for determining whether the telemechanical apparatus forwards mistake according to comparing result;It is mentioned if so, issuing Show information.
The method and system that regulation and controlling of information provided by the present invention is checked, this method comprises: the SCD file of substation is led Enter into simulated program;The simulated program according to the SCD file content, by everything information in the substation according to Predetermined time interval is sent in sequence to telemechanical apparatus and monitoring backstage;The monitoring records the everything letter received from the background Breath;The everything information for the telemechanical apparatus forwarding that simulation main website record receives;By the institute of monitoring backstage record There is the everything information of action message and simulation main website record, is carried out pair using the scheduling information table of the substation Than;
This method is built without the communication channel between substation and main website and is completed, and need not also interact with main website and carry out work Make, it is only necessary to set up simulated environment in substation, simulation framework is set, using automation tools and means, realize regulation and controlling of information Check, improve regulation and controlling of information check working efficiency.
Detailed description of the invention
In order to more clearly explain the embodiment of the invention or the technical proposal in the existing technology, to embodiment or will show below There is attached drawing needed in technical description to be briefly described, it should be apparent that, the accompanying drawings in the following description is only this The embodiment of invention for those of ordinary skill in the art without creative efforts, can also basis The attached drawing of offer obtains other attached drawings.
Fig. 1 is the flow chart for the method that regulation and controlling of information provided by the embodiment of the present invention is checked;
Fig. 2 is the schematic diagram for the power grid regulation information data flow direction that the prior art provides;
Fig. 3 is the structural block diagram for the system that regulation and controlling of information provided by the embodiment of the present invention is checked;
Fig. 4 is the structural block diagram for the system that another regulation and controlling of information is checked provided by the embodiment of the present invention.
Specific embodiment
Core of the invention is to provide a kind of method and system that regulation and controlling of information is checked, it is only necessary to emulation is set up in substation Environment realizes the check of regulation and controlling of information using automation tools and means, improves regulation and controlling of information and checks working efficiency.
In order to make the object, technical scheme and advantages of the embodiment of the invention clearer, below in conjunction with the embodiment of the present invention In attached drawing, technical scheme in the embodiment of the invention is clearly and completely described, it is clear that described embodiment is A part of the embodiment of the present invention, instead of all the embodiments.Based on the embodiments of the present invention, those of ordinary skill in the art Every other embodiment obtained without making creative work, shall fall within the protection scope of the present invention.
Referring to FIG. 1, Fig. 1 is the flow chart for the method that regulation and controlling of information provided by the embodiment of the present invention is checked;This method May include:
S100, the SCD file of substation is imported into simulated program;
Wherein, SCD (Substation Configuration Description, whole station system configuration file) is whole station Unified data source, this documents describes the communications between the exemplary configuration of all IED and messaging parameter, IED (electronic equipment) Configuration and transforming plant primary system structure and signal contact information.
Currently, referring to FIG. 2, power grid regulation information data flows to: dispatching automation acquisition information is mainly needed by information Acquisition unit, telemechanical apparatus, scheduling station three-stage apparatus.Information acquisition unit is responsible for remote signalling in acquisition station, telemetry intelligence (TELINT), concurrently Give the station levels equipment such as backstage, telemechanical apparatus.Information that each acquisition unit of telemechanical apparatus centralized collection receives simultaneously is forwarded to tune Spend main website.Under intelligent substation technology, the infomational message of telemechanical apparatus acquisition interval measure and control device is main according to 61850 standards It stands and receives telemechanical apparatus upload data with 104 message formats.
For information content up to as many as tens of thousands of, main website does not need its whole in usually standing.Staff will choose one in standing A or several information after making one-to-one or many-to-one merger, form a scheduling information point, and with unique master information object Address is identified.All scheduling information points are aggregated to form the scheduling information table of whole station.The representative content of scheduling information table is such as It include the agreements such as information object address, information description shown in table 1.Information object address is natural number, generally since 0 or 1 Number.Briefly, scheduling information table defines the information and its number that main website need to be transmitted to by telemechanical apparatus.
The representative content of 1 scheduling information table of table
Serial number Master information object address Information description SOE setting Information in corresponding station
…… ……
36 5011 switch control circuits broken string b
37 Double orchid 5011 switch A phase coincidences of line X
38 SF6 pressure is low S
…… ……
During day-to-day operation, telemechanical apparatus receives and the action message in analysis station, once information in the station acted It is corresponding with the information point in scheduling information table, the action message to scheduling station is just formed, and believed with some scheduling with 104 messages The mode of breath point movement is sent to main website, while subsidiary SOE time.Wherein, SOE (Sequence Of Event, event sequence Record) when such as switch is by assigning to conjunction for the variation of power equipment generating state, electrical protection apparatus or intelligent electric instrument can be automatic Displacement time, displacement reason etc. are recorded, SOE record is formed, in order to ex-post analysis.Therefore it is generally comprised in remote signalling message slot Following information: information number (some corresponding record object), information behavior (occur or disappear), information time of origin (year-month-day- When-point-second-millisecond).
Whether regulation and controlling of information check is that substation puts into operation the necessary work of previous item, be used to check the information occurred in station and can So correct that be sent to scheduling station, main identifying object is the information conversion links of telemechanical apparatus.Conventional regulation and controlling of information school Kernel mode are as follows: after the communication channel between substation and main website builds completion, substation and main website staff in place, power transformation Stand staff according to scheduling approval regulation and controlling of information table " act " on the spot one stand in signal, scheduling station receive telemechanical dress Set transmit with address be mark action message after, compare regulation and controlling of information table agreement, and by with the people that works in substation The real-time interaction of member confirms that the description of received regulation and controlling of information with the information of transformer substation end " movement " is corresponding.So One by one, to complete the verifications of all information points.
Therefore this method utilizes simulated program mould for the check of progress regulation and controlling of information rapidly and efficiently in substation Quasi- information acquisition unit, the SCD file of substation is imported into simulated program, simulated program is allowed to simulate true letter Cease the transmission that acquisition unit carries out action message.Being also provided with simulation main website leads to its operation simulation main website with telemechanical apparatus News, obtain the action message of the forwarding of telemechanical apparatus.Include: before the SCD file of substation is imported into simulated program Setting simulation main website, communicates the simulation main website by 104 specifications with telemechanical apparatus in the substation.Wherein, 104 specifications: since International Electrotechnical Commission's nineteen ninety-five publishes IEC60870-5-101, being widely applied, to adapt to network Transmission, has published IEC60870-5-104:2000 in 2000.For the application of specification this standard at home, National Power System control System and its communication standardization technical committee have formulated 2002 standard of DL/T634.5104-, and this standard equally uses IEC60870-5-104:2000 telecontrol equipment and the part system 5-104: transmission protocol is using standard transmission protocol subset The network of IEC60870-5-101 accesses, and suitable for the telecontrol equipment and system of the data transmission encoded with serial data, uses With the monitoring and control to geographical wide area process.
It can be seen that this method does not need to complete without the communication channel construction between substation and main website, it is only necessary to simulation master It stands and is communicated with telemechanical apparatus, simulated program is communicated with telemechanical apparatus;Also need not be interacted with main website carry out the work have simulation main website into Row is received by telemechanical apparatus forwarding behavior information;Therefore simulated environment need to be only set up in substation, using automation tools and Means realize the check of regulation and controlling of information, improve regulation and controlling of information and check working efficiency.
S110, the simulated program are according to the SCD file content, by everything information in the substation according to pre- Fix time interval be sent in sequence to telemechanical apparatus and monitoring backstage;
Wherein, substation's SCD file is imported using simulated program, analog information acquisition unit conjugates whole station signal one by one It is sent to telemechanical apparatus and monitoring backstage.Predetermined time interval can be checked convenient for subsequent according to the time with self-setting.This In the action message that sends there is time identifier can be attached to the SOE time, it is subsequent to be checked according to the subsidiary SOE time.
S120, the monitoring record the everything information received from the background;
Wherein, monitoring backstage does not have the function of forwarding, is used only for completely recording all dynamic of simulated program transmission Make information, as the forwarding of subsequent authentication telemechanical apparatus with the presence or absence of a contrasting foundation of mistake.Setting monitoring backstage can make It is more accurate to check, and the root that can be generated according to monitoring backstage misjudgment information;For example, if the same SOE moment The content for the action message that simulation main website receives and the monitoring content on backstage are consistent but inconsistent with regulation and controlling of information table, Simulated program, which can be then proved to be, there is a problem.Therefore, main using the action message of monitoring backstage record as sieve here Choosing and the benchmark checked.
The everything information for the telemechanical apparatus forwarding that s130, simulation main website record receive;
Wherein, telemechanical apparatus is handled and is forwarded according to the simulated program of identification generation action message, but telemechanical fills Setting to the transmitting of the numerical value such as SOE time numerical value of time is a fixed behavior, after the correct forwarding of telemechanical apparatus, simulation master The signal with the SOE time will be received by standing.Meanwhile it monitoring backstage and generally keeping a record to information in standing, and the also band SOE time. Therefore the information point that simulation main website and monitoring backstage receive all has the SOE time of simulation software label, can be based on constant The SOE time compares, and the SOE time removal search of the signal so as to be received according to simulation main website monitors backstage identical The signal description received under the SOE time.The quick verification to regulation and controlling of information may be implemented.Simulate the signal of main website record Representative content is as shown in table 2.
Table 2 simulates the representative content of the signal of Master Station Software record
Serial number The SOE time Master information object address
···
18:11:00.336 36
18:11:00.337 37
18:11:00.338 38
···
S140, the everything of the everything information of monitoring backstage record and simulation main website record is believed Breath, is compared using the scheduling information table of the substation.
Wherein, all action messages of the whole station issued by simulated program have unique SOE time, simulate main website and prison The information that control backstage receives has the SOE time unchanged, therefore can be obtained according to the uniqueness of SOE time The information description that same SOE time Imitating main website is received with monitoring backstage, and then carry out verification realization with scheduling information table and adjust The consistency for controlling information checks work, improves debugging efforts efficiency.
Optionally, the everything of the everything information of monitoring backstage record and simulation main website record is believed Breath, is compared using the scheduling information table of the substation and may include:
It successively transfers under the same SOE time, what the action message and the monitoring backstage that the simulation main website records recorded Action message;
Using the scheduling information table, change corresponding to the information dot address in the action message of simulation main website record is determined Information description in power station;
Information description and the information description in the action message of monitoring backstage record are compared;
If the same, the telemechanical apparatus forwarding behavior information is correct;
If different, the telemechanical apparatus forwarding behavior information errors.
Above-mentioned specific comparison process is exemplified below, such as in the description of above-mentioned Tables 1 and 2, in table 1, main website Information object address 37, information description: double orchid 5011 switch A phase coincidences of line, SOE setting are opened, information X in corresponding station;Table 2 In it can be seen that the corresponding SOE time 18:11:00.337 of main website object address 37;I.e. in the scheduling information table of table 1, interior x letter of standing Breath corresponds to No. 37 message address of main website.X event-action signal, SOE time time1 on label are issued by simulated program.If The configuration of telemechanical apparatus database is correct, and telemechanical apparatus will issue corresponding letter to simulation main website with 104 messages after receiving the message Breath, simulation main website will shows the information of " 37 events in time1 occur ", at the same monitor backstage will show " x event-action in The SOE message of time1 time ".In this way, No. 37 message address that simulation main website receives are being adjusted at same SOE time time1 Spending information description in corresponding station specified in information table should be corresponding with the event x of monitoring backstage display.If telemechanical apparatus is matched Mistake is set, such as x event has been corresponded to No. 36 message address or the corresponding master information of the unpaired event by telemechanical apparatus Address, simulation main website will receive the information of " 36 events occur in time1 ", when information describes just with this SOE in corresponding station It is not identical to carve the x event that monitoring backstage receives under time1.Then it can be found that telemechanical apparatus forwards mistake.
I.e. the audit process of regulation and controlling of information is decomposed into send in data set by this method judges two separate phases with result. Simulated program quickly sends whole station everything information in standing, and simulation main website is automatically recorded and arranged through the dynamic of telemechanical apparatus forwarding Make information, monitoring backstage automatically records the everything information received.All working can be completed in station, simulate main website side It is simple and clear to the judgment mode of telemechanical apparatus behavior correctness, and can stand in all data be sent completely after at any time into Row, therefore do not need the construction of the communication channel between substation and main website and complete, it need not also interact and carry out the work with main website.To Will in station work and main website work it is independent, very big the staff for having liberated both ends.This method is to help commissioning staff Quickly, good facilitation effect is played in the verification for efficiently, accurately completing substation's scheduling information.This method is not necessarily to existing change Mechanics of communication in power station and between substation and main website makees any change.
Based on the above embodiment, this method can also include:
The number of the everything information of simulation main website record is counted, and is believed with the movement in the scheduling information table The number of breath is compared;
Judge the telemechanical apparatus with the presence or absence of leakage heat condition according to comparison result.
Wherein, simulated program is sent all information of whole station one time point by point by setting time interval, then according to mould Quantity, the information dot address for the information point that quasi- main website receives are compared with scheduling information table, to judge whether telemechanical apparatus has Leak heat condition.
Based on the above embodiment, this method can also include:
According to comparing result, determine whether the telemechanical apparatus forwards mistake;
If so, issuing prompt information.
Wherein, the time for saving substation project commissioning staff, substation project commissioning staff is avoided to be checked one by one, It directly compares automatically, when an error is discovered, prompt information can be provided, and wrong content can be recorded, facilitate change Power plant project commissioning staff checks.It improves regulation and controlling of information and checks working efficiency.
The embodiment of the present invention can by simulated program read SCD file after by all information of whole station by setting time interval by A to send one time to telemechanical apparatus and monitoring backstage, everything information will be recorded in monitoring backstage, and simulation main website will be recorded The everything information of telemechanical apparatus forwarding, the process only need time more than ten minutes.Next stage, substation project debug people Member the quantity for simulating the received information point of main website, information dot address can be compared to judge that telemechanical is filled with scheduling information table Whether set has leakage heat condition;Meanwhile it can be according to simulation main website in the corresponding station of information dot address that certain SOE reception arrives Information describes (knowing from scheduling information table) and is compared with monitoring backstage in the description of the information of same SOE reception, Whether the information forwarding to judge telemechanical apparatus is correct.This compares the process checked and only needs dozens of minutes, compared to tradition A few days easily point-by-point artificial nucleus couple mode, efficiency greatly improves.
The embodiment of the invention provides the methods that regulation and controlling of information is checked, and can be realized the school of regulation and controlling of information by the above method Core improves regulation and controlling of information and checks working efficiency.
The system checked below to regulation and controlling of information provided in an embodiment of the present invention is introduced, regulation and controlling of information described below The system of check can correspond to each other reference with the method that above-described regulation and controlling of information is checked.
Referring to FIG. 3, Fig. 3 is the structural block diagram for the system that regulation and controlling of information provided by the embodiment of the present invention is checked;This is System may include:
Simulated program module 100, for the SCD file of substation to be imported into simulated program;According to the SCD file Everything information in the substation is spaced to schedule and is sent in sequence to telemechanical apparatus and monitoring backstage by content;
Monitoring backstage 200, for recording the everything information received;
Telemechanical apparatus 300, for forwarding the everything information received to simulation main website;
Main website 400 is simulated, for recording the everything information of the telemechanical apparatus received forwarding;
Contrast module 500, for record the everything information for monitoring backstage record and the simulation main website Everything information is compared using the scheduling information table of the substation.
The system includes:
Setup module passes through the simulation main website with telemechanical apparatus for the setting simulation main website in the substation 104 specifications are communicated.
Based on the above embodiment, which can also include:
Comparison module, the number of the everything information for counting simulation main website record, and believe with the scheduling The number of action message in breath table is compared;
Judgment module, for judging the telemechanical apparatus with the presence or absence of leakage heat condition according to comparison result.
Optionally, the contrast module 500 includes:
Acquiring unit, for successively transferring under the same SOE time, the action message of simulation main website record and the prison The action message of control backstage record;
Determination unit determines the information point in the action message of simulation main website record for utilizing the scheduling information table Information description in substation corresponding to address;
Comparison unit, for by the information description with it is described monitoring backstage record action message in information describe into Row comparison;If the same, the telemechanical apparatus forwarding behavior information is correct;If different, the telemechanical apparatus forwarding behavior Information errors.
Based on the above embodiment, referring to FIG. 4, the system can also include:
Cue module 600, for determining whether the telemechanical apparatus forwards mistake according to comparing result;If so, issuing Prompt information.
Each embodiment is described in a progressive manner in specification, the highlights of each of the examples are with other realities The difference of example is applied, the same or similar parts in each embodiment may refer to each other.For device disclosed in embodiment Speech, since it is corresponded to the methods disclosed in the examples, so being described relatively simple, related place is referring to method part illustration ?.
Professional further appreciates that, unit described in conjunction with the examples disclosed in the embodiments of the present disclosure And algorithm steps, can be realized with electronic hardware, computer software, or a combination of the two, in order to clearly demonstrate hardware and The interchangeability of software generally describes each exemplary composition and step according to function in the above description.These Function is implemented in hardware or software actually, the specific application and design constraint depending on technical solution.Profession Technical staff can use different methods to achieve the described function each specific application, but this realization is not answered Think beyond the scope of this invention.
The step of method described in conjunction with the examples disclosed in this document or algorithm, can directly be held with hardware, processor The combination of capable software module or the two is implemented.Software module can be placed in random access memory (RAM), memory, read-only deposit Reservoir (ROM), electrically programmable ROM, electrically erasable ROM, register, hard disk, moveable magnetic disc, CD-ROM or technology In any other form of storage medium well known in field.
The method and system checked above to regulation and controlling of information provided by the present invention are described in detail.It is used herein A specific example illustrates the principle and implementation of the invention, and the above embodiments are only used to help understand Method and its core concept of the invention.It should be pointed out that for those skilled in the art, not departing from this , can be with several improvements and modifications are made to the present invention under the premise of inventive principle, these improvement and modification also fall into the present invention In scope of protection of the claims.

Claims (10)

1. a kind of method that regulation and controlling of information is checked characterized by comprising
The SCD file of substation is imported into simulated program;
The simulated program according to the SCD file content, by everything information in the substation to schedule between Every be sent in sequence to telemechanical apparatus and monitoring backstage;Wherein, the movement of transmission has time identifier;
The monitoring records the everything information received from the background, the root generated according to monitoring backstage misjudgment information;
The everything information for the telemechanical apparatus forwarding that simulation main website record receives;
By the everything information of the everything information of monitoring backstage record and simulation main website record, using described The scheduling information table of substation compares.
2. the method as described in claim 1, which is characterized in that further include:
Count it is described simulation main website record everything information number, and with the action message in the scheduling information table Number is compared;
Judge the telemechanical apparatus with the presence or absence of leakage heat condition according to comparison result.
3. the method as described in claim 1, which is characterized in that by it is described monitoring backstage record everything information with it is described The everything information for simulating main website record, is compared using the scheduling information table of the substation, comprising:
It successively transfers under the same SOE time, the action message of simulation main website record and the movement of monitoring backstage record Information;
Using the scheduling information table, substation corresponding to the information dot address in the action message of simulation main website record is determined Interior information description;
Information description and the information description in the action message of monitoring backstage record are compared;
If the same, the telemechanical apparatus forwarding behavior information is correct;
If different, the telemechanical apparatus forwarding behavior information errors.
4. method as claimed in claim 3, which is characterized in that before the SCD file of substation is imported into simulated program, Include:
Setting simulation main website, communicates the simulation main website by 104 specifications with telemechanical apparatus in the substation.
5. such as the described in any item methods of Claims 1-4, which is characterized in that further include:
According to comparing result, determine whether the telemechanical apparatus forwards mistake;
If so, issuing prompt information.
6. the system that a kind of regulation and controlling of information is checked characterized by comprising
Simulated program module, for the SCD file of substation to be imported into simulated program;It, will according to the SCD file content Everything information is spaced to schedule in the substation is sent in sequence to telemechanical apparatus and monitoring backstage;Wherein, it sends out The movement sent has time identifier;
Monitoring backstage, for recording the everything information received, according to the monitoring root that misjudgment information generates from the background;
Telemechanical apparatus, for forwarding the everything information received to simulation main website;
Main website is simulated, for recording the everything information of the telemechanical apparatus received forwarding;
Contrast module, the everything of everything information and simulation main website record for recording the monitoring backstage Information is compared using the scheduling information table of the substation.
7. system as claimed in claim 6, which is characterized in that further include:
Comparison module, for count it is described simulation main website record everything information number, and with the scheduling information table In the number of action message be compared;
Judgment module, for judging the telemechanical apparatus with the presence or absence of leakage heat condition according to comparison result.
8. system as claimed in claim 6, which is characterized in that the contrast module includes:
Acquiring unit, for successively transferring under the same SOE time, after the action message and the monitoring of simulation main website record The action message of platform record;
Determination unit determines the information dot address in the action message of simulation main website record for utilizing the scheduling information table Information description in corresponding substation;
Comparison unit, for carrying out pair information description and the information description in the action message of monitoring backstage record Than;If the same, the telemechanical apparatus forwarding behavior information is correct;If different, the telemechanical apparatus forwarding behavior information Mistake.
9. system as claimed in claim 8 characterized by comprising
Setup module makes the simulation main website and telemechanical apparatus pass through 104 rule for the setting simulation main website in the substation About communicated.
10. such as the described in any item systems of claim 6 to 9, which is characterized in that further include:
Cue module, for determining whether the telemechanical apparatus forwards mistake according to comparing result;If so, issuing prompt letter Breath.
CN201510821788.7A 2015-11-24 2015-11-24 A kind of method and system that regulation and controlling of information is checked Active CN105447247B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510821788.7A CN105447247B (en) 2015-11-24 2015-11-24 A kind of method and system that regulation and controlling of information is checked

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510821788.7A CN105447247B (en) 2015-11-24 2015-11-24 A kind of method and system that regulation and controlling of information is checked

Publications (2)

Publication Number Publication Date
CN105447247A CN105447247A (en) 2016-03-30
CN105447247B true CN105447247B (en) 2018-12-18

Family

ID=55557418

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510821788.7A Active CN105447247B (en) 2015-11-24 2015-11-24 A kind of method and system that regulation and controlling of information is checked

Country Status (1)

Country Link
CN (1) CN105447247B (en)

Families Citing this family (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106909615B (en) * 2017-01-13 2022-09-23 中国电力科学研究院 Method and device for verifying data information consistency between master station and substation
CN107067161B (en) * 2017-03-20 2021-05-14 国网福建省电力有限公司 Automatic checking implementation system and method for information point table in smart power grid
CN106971351B (en) * 2017-03-27 2018-05-22 国网江苏省电力公司电力科学研究院 The automatic Acceptance Test System of intelligent substation regulation and controlling of information integration and method
CN106941281B (en) * 2017-04-12 2019-04-26 国网福建省电力有限公司 A method of telemechanical apparatus and regulation main website telemetering automated closed-loop joint debugging based on supervisory control of substation backstage
CN107861000A (en) * 2017-11-01 2018-03-30 南京国电南自电网自动化有限公司 A kind of method of automatic test substation intelligent alarm function
CN109698554A (en) * 2019-01-03 2019-04-30 国网山东省电力公司平邑县供电公司 Substation equipment Dispatching monitor and control system and method
CN109802490A (en) * 2019-02-21 2019-05-24 国网山东省电力公司临沂供电公司 A kind of intelligent platform of substation's electrification fortune inspection
CN109885025A (en) * 2019-03-07 2019-06-14 国网冀北电力有限公司检修分公司 A kind of test macro and method of monitoring system of electric substation
CN110705246A (en) * 2019-08-28 2020-01-17 国网四川省电力公司成都供电公司 Method for intelligently comparing and checking information of master station and transformer substation
CN110659822A (en) * 2019-09-20 2020-01-07 云南恒协科技有限公司 Intelligent information monitoring and management system for transformer substation
CN111291546A (en) * 2020-03-27 2020-06-16 广西电网有限责任公司河池供电局 Transformer substation equipment monitoring information table carding method based on version difference checking
CN111478818B (en) * 2020-05-11 2024-11-05 广西电网有限责任公司钦州供电局 Remote verification method based on SCD file and RCD file
CN113422820B (en) * 2021-06-21 2023-05-30 贵州电网有限责任公司 Automatic joint debugging device and method for remote information of main station
CN115914023B (en) * 2022-11-23 2024-05-07 国网四川省电力公司电力科学研究院 Method and device for monitoring full period information of security control system function test command

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103311829A (en) * 2012-03-08 2013-09-18 国家电网公司 Transformer substation monitoring system
CN204291050U (en) * 2014-12-16 2015-04-22 江苏省电力公司检修分公司 A kind of dispatching and monitoring information check system

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103311829A (en) * 2012-03-08 2013-09-18 国家电网公司 Transformer substation monitoring system
CN204291050U (en) * 2014-12-16 2015-04-22 江苏省电力公司检修分公司 A kind of dispatching and monitoring information check system

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
智能变电站远动信息快速校核方法;陆承宇;《电力系统保护与控制》;20150601;第43卷(第11期);第128-133页 *

Also Published As

Publication number Publication date
CN105447247A (en) 2016-03-30

Similar Documents

Publication Publication Date Title
CN105447247B (en) A kind of method and system that regulation and controlling of information is checked
CN103412208B (en) The method of intelligent substation electric power telemechanical device closed loop test
CN110231957B (en) System and method for automatically generating telecontrol configuration description file (RCD)
CN105511294B (en) Simulation telemechanical Virtual Debugging method based on emulation IED devices
WO2015106605A1 (en) Method for testing station level of intelligent substation
CN109150636B (en) Intelligent substation auxiliary point-to-point test method and system for full-link information flow
CN106505731B (en) A kind of intelligent substation and scheduling are to test case intelligent generating system and a method
CN106787199A (en) A kind of portable substation simulated testing system and method
CN102724006A (en) Rapid self-checking system and method of satellite comprehensive testing system
CN105958642B (en) A kind of electric substation automation system real-time simulation apparatus and test system
CN107317399A (en) Intelligent substation visualization is automatic to dot system and method
CN112737115A (en) Remote signaling joint debugging decoupling method for main station and plant station of transformer substation
CN110784020A (en) Automatic checking and accepting equipment, system and method for monitoring information
CN204291050U (en) A kind of dispatching and monitoring information check system
CN110766263B (en) Automatic acceptance method for secondary equipment of transformer substation and terminal equipment
CN108958216A (en) The automatic checkout system and method for new energy AGC or AVC control system
CN110401692A (en) A kind of automatic Acceptance Test System of supervisory control of substation information integral and method
CN106532958A (en) Substation IED (Intelligent Electronic Device) simulation method based on IEC61850 protocol
CN104574204B (en) Intelligent measuring and control device ICD models automatic identification system and method
CN108833392A (en) A kind of substation based on packet parsing information is automatically to point methods
CN106909615B (en) Method and device for verifying data information consistency between master station and substation
CN107257304A (en) Telemechanical is exempted to a configuration testing system
CN110838946A (en) Automatic acceptance system and method based on simulation substation
CN105680441A (en) Simulated replacement technique-based simulated point-alignment device
CN103676669A (en) Method and system for checking motion information

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant