References: {{Portal|Germany|Energy}}
cleanup
Line 9: Line 9:
| caption =
| caption =
| operator = SEL Süddeutsche Erdgasleitung
| operator = SEL Süddeutsche Erdgasleitung
| partners = [[E.ON]], [[Wingas]]
| partners = [[E.ON Ruhrgas]], [[Wingas]]
| length_km = 500
| length_km = 500
| discharge =
| discharge =
Line 33: Line 33:


{{Portal|Germany|Energy}}
{{Portal|Germany|Energy}}
{{E.ON}}


{{DEFAULTSORT:South German Natural Gas Pipeline}}
{{DEFAULTSORT:South German Natural Gas Pipeline}}
[[Category:Natural gas pipelines in Germany]]
[[Category:Natural gas pipelines in Germany]]
[[Category:E.ON]]

Revision as of 20:34, 28 March 2018

South German natural gas pipeline
Location
CountryGermany
General directioneast-west
FromBurghausen
ToLampertheim
General information
Typenatural gas
PartnersE.ON Ruhrgas, Wingas
OperatorSEL Süddeutsche Erdgasleitung
Commissionedcanceled
Technical information
Length500 km (310 mi)

South German natural gas pipeline (German: Süddeutsche Erdgasleitung (SEL)) was a natural gas pipeline project in Germany. It was planned to run from Burghausen on the German-Austrian border to Lampertheim, state of Hesse. The length of the pipeline was to be about 500 kilometres (310 mi) and the diameter was to be 1,200 millimetres (47 in). The pipeline was to be constructed jointly by E.ON Ruhrgas and Wingas, a joint venture of Wintershall and Russian Gazprom. The project was expected to cost €600 million ($759.2 million). Project was stopped in November 2008, mainly due to difficulties in financing. According to Wingas, the pipeline project was not economically sustainable; hence the halt of operations.[1]

References

  1. ^ "Germany's Wingas Nixes Natural Gas Pipeline". USA Today. Associated Press. 2008-11-19. Retrieved 2016-04-23.