Title Status and Plans for the Upgrade of the CERN PS Booster
Author(s) Hanke, Klaus (CERN) ; Aguglia, Davide (CERN) ; Angoletta, Maria Elena (CERN) ; Bartmann, Wolfgang (CERN) ; Bedel, Cyrille (CERN) ; Benedetto, Elena (CERN) ; Bertolasi, Stefano (CERN) ; Bertone, Caterina (CERN) ; Betz, Jochen (CERN) ; Birtwistle, Thomas (CERN) ; Blas, Alfred (CERN) ; Borburgh, Jan (CERN) ; Bracco, Chiara (CERN) ; Butterworth, Andrew (CERN) ; Carlier, Etienne (CERN) ; Chemli, Samy (CERN) ; Dahlen, Pierre (CERN) ; Dallocchio, Alessandro (CERN) ; Di Giovanni, Gian Piero (CERN) ; Dobers, Tobias (CERN) ; Findlay, Alan (CERN) ; Froeschl, Robert (CERN) ; Funken, Anne (CERN) ; Gabourin, Stéphane (CERN) ; Grenard, Jean-Louis (CERN) ; Grenier, Damien (CERN) ; Hansen, Jan (CERN) ; Hay, David (CERN) ; Lacroix, Jean-Michel (CERN) ; Le Roux, Pascal (CERN) ; Lopez Hernandez, Luz Anastasia (CERN) ; Martin, Christophe (CERN) ; Masi, Alessandro (CERN) ; Mikulec, Bettina (CERN) ; Muttoni, Yvon (CERN) ; Newborough, Antony (CERN) ; Nisbet, David (CERN) ; Obrecht, Michel (CERN) ; Paoluzzi, Mauro (CERN) ; Pittet, Serge (CERN) ; Puccio, Bruno (CERN) ; Tan, Jocelyn (CERN) ; Vollaire, Joachim (CERN) ; Weterings, Wim (CERN)
Publication 2015
Number of pages 3
In: 6th International Particle Accelerator Conference, Richmond, VA, USA, 3 - 8 May 2015, pp.THPF090
Subject category Accelerators and Storage Rings
Accelerator/Facility, Experiment CERN PSB
Abstract CERN’s Proton Synchrotron Booster (PSB) is undergoing a major upgrade program in the frame of the LHC Injectors Upgrade (LIU) project. During the first long LHC shutdown (LS1) some parts of the upgrade have already been implemented, and the machine has been successfully re-commissioned. More work is planned for the upcoming end-of-year technical stops, notably in 2016/17, while most of the upgrade is planned to take place during the second long LHC shutdown (LS2). We report on the upgrade items already completed and commissioned, the first Run 2 beam performance and give a status of the ongoing design and integration work.
Copyright/License publication: © 2015-2024 The Author(s) (License: CC-BY-3.0)

Corresponding record in: Inspire


 Record created 2016-03-27, last modified 2024-02-23


Published version from JACoW: