DEVELOPING A METHODOLOGY FOR FINDING NETWORK WATER
LOSSES USING INFORMATION TECHNOLOGIES: A CASE STUDY
A THESIS SUBMITTED TO
THE GRADUATE SCHOOL OF NATURAL AND APPLIED SCIENCES
OF
MIDDLE EAST TECHNICAL UNIVERSITY
BY
HAYRETTĐN ONUR BEKTA
IN PARTIAL FULFILLMENT OF THE REQUIREMENTS
FOR
THE DEGREE OF MASTER OF SCIENCE
IN
GEODETIC AND GEOGRAPHIC INFORMATION TECHNOLOGIES
DECEMBER 2010
Approval of the thesis:
DEVELOPING A METHODOLOGY FOR FINDING NETWORK WATER
LOSSES USING INFORMATION TECHNOLOGIES: A CASE STUDY
submitted by HAYRETTĐN ONUR BEKTA in partial fulfilment of the
requirements for the degree of Master of Science in Geodetic and Geographic
Information Technologies Department, Middle East Technical University by,
Prof. Dr. Canan Özgen
_____________________
Dean, Graduate School of Natural and Applied Sciences
Assoc. Prof. Dr. Mahmut Onur Karslıoğlu
_____________________
Head of Department, Geodetic and Geographic Inf. Tech.
Assoc. Prof. Dr. Nuri Merzi
Supervisor, Civil Engineering Dept., METU
_____________________
Assoc. Prof. Dr. Zuhal Akyürek
Co-Supervisor, Civil Engineering Dept., METU
_____________________
Examining Committee Members:
Prof. Dr. Melih Yanmaz
Civil Engineering Dept., METU
_____________________
Assoc. Prof. Dr. Nuri Merzi
Civil Engineering Dept., METU
_____________________
Assoc. Prof. Dr. Zuhal Akyürek
Civil Engineering Dept., METU
_____________________
Prof. Dr. Uygur endil
Civil Engineering Dept., METU
_____________________
Gökhan Bağcı
Env. Eng., ASKĐ
_____________________
Date: 17/12/2010
I hereby declare that all information in this document has been obtained and
presented in accordance with academic rules and ethical conduct. I also declare
that, as required by these rules and conduct, I have fully cited and referenced
all material and results that are not original to this work.
Name, Last name: Hayrettin Onur Bekta
Signature:
iii
ABSTRACT
DEVELOPING A METHODOLOGY FOR FINDING NETWORK WATER
LOSSES USING INFORMATION TECHNOLOGIES: A CASE STUDY
Bekta , Hayrettin Onur
M.Sc., Department of Geodetic and Geographic Information Technologies
Supervisor: Assoc. Prof. Dr. Nuri Merzi
Co-Supervisor: Assoc. Prof. Dr. Zuhal Akyürek
December 2010, 175 pages
This study aims to develop an integrated methodology for finding water leaks in a
water distribution network. The integrated methodology is formed from SCADA
System, Customer Information System (CIS), and Geographic Information System.
The methodology is based on forming district-metered areas (DMA) and sub-DMAs
in pressure zones by isolation of the network. Leaking spots in the network are
localised by step testing within the DMA. With leak noise loggers leaking spots are
localized with an increased accuracy and finally pinpointed by ground microphones.
Minimum night flows are observed from the SCADA system before and after the
repairs of the leaks to calculate physical water loss percentage in the DMA. Monthly
non-revenue water percentage is calculated using the data obtained from SCADA
and CIS. With a buffer analysis on the water distribution network data, the benefit of
iv
the leak noise loggers is maximized and the working time with the ground
microphones are minimized. The methodology is applied in two different DMAs in
Antalya water distribution network with different characteristics. In the first DMA,
only the developed methodology is applied and a decrease of 19.2% is achieved in
physical water losses. In the second DMA, pressure reduction is added to the
methodology and a decrease of 4.9% is achieved.
Keywords: Geographic Information System, Customer Information System,
SCADA, water leakage, minimum night flow, district metered area, leak noise
logger, ground microphone, pressure management, Antalya.
v
ÖZ
BĐLGĐ TEKNOLOJĐLERĐ KULLANILARAK SU EBEKESĐNDEKĐ
KAYIPLARIN BULUNMASINA YÖNELĐK METODOLOJĐ
GELĐ TĐRĐLMESĐ: BĐR UYGULAMA
Bekta , Hayrettin Onur
Yüksek Lisans, Jeodezi ve Coğrafi Bilgi Teknolojileri Bölümü
Tez Yöneticisi: Doç. Dr. Nuri Merzi
Ortak Tez Yöneticisi: Doç. Dr. Zuhal Akyürek
Aralık 2010, 175 sayfa
Bu çalı ma, bir içme suyu dağıtım ebekesindeki fiziksel kayıpları bulmak üzere bir
yöntem geli tirilmesini hedeflemektedir. Söz konusu çalı ma üç ayrı bilgi
teknolojisinin bütünle mi bir ekilde kullanımını içermektedir. Bu teknolojiler,
SCADA, Abone Bilgi Sistemi (ABS) ve Coğrafi Bilgi Sistemidir (CBS). Yöntem
temel olarak, içme suyu ebekelerindeki basınç bölgelerinde izole ölçüm bölgeleri ve
bu ölçüm bölgelerinin içinde daha küçük, geçici alt bölgelerin olu turulmasına
dayanmaktadır. Olası fiziksel kaçak noktaları önce alt bölgelerde yapılacak adım
deneyleri ile belli alanlara sıkı tırılmakta, daha sonra gürültü kaydedici cihazlar
yardımıyla bu alanlar iyice daraltılmaktadır. Son olarak yer mikrofonları ile
kaçakların noktasal yerlerinin saptanması yapılıp, arızalar onarılmaktadır. SCADA
sisteminden günlük en dü ük gece debisindeki dü ü ler gözlenmekte ve onarılan
vi
arızaların debileri ölçülmü olmaktadır. Minimum gece debileri yardımıyla fiziksel
kayıp oranları bulunmakta, SCADA ve ABS sistemlerinin aylık olarak çakı tırılması
ile de tahakkuk oranları takip edilmektedir. Ayrıca gürültü kaydedicilerin daha etkili
kullanımı ve yer mikrofonu ile dinlemenin en aza indirilmesi için CBS verileri
üzerinde tampon bölgeler olu turulmaktadır. Önerilen yöntem, Antalya içme suyu
dağıtım ebekesindeki deği ik özellikteki iki ölçüm bölgesinde saha çalı ması ile
uygulanmı tır. Đlk uygulamada yalnızca önerilen yöntem ile fiziksel su kayıp
oranında %19.2’lik bir dü ü gözlenmi tir. Đkinci uygulamada önerilen yöntem
basınç dü ürme yöntemiyle desteklenmi ve bu çalı mada da fiziksel su kayıp
oranlarında %4.9’luk bir dü ü elde edilmi tir.
Anahtar Sözcükler: Coğrafi Bilgi Sistemleri, Abone Bilgi Sistemleri, SCADA, su
kayıpları, minimum gece akımı, ölçüm bölgesi, gürültü kaydedici, yer mikrofonu,
basınç yönetimi, Antalya.
vii
To the beautiful and sunny days ahead,
viii
ACKNOWLEDGEMENTS
I would hereby like to express my deepest gratitude to my advisors Assoc. Prof. Dr.
Nuri Merzi and Assoc. Prof. Dr. Zuhal Akyürek for their major contributions,
unlimited patience and the valuable guidance. But for their help and support, this
thesis would neither start in the first place nor would it finish successfully.
I am also thankful to field and office staff on ASAT for their valuable works.
Without the precise and persistent efforts of Abdurrahman Usta, Abdullah Usta and
Nusret Usta, I would definitely get lost in the middle of Konyaaltı. Special thanks go
to the office staff, Đsmail Demirel, Erkan Demirba and Tuğba Özden who provided
the needed data used in the analysis.
I would sincerely thank to my colleagues in ASKĐ, Volkan Engin and Halil endil
for their support in seeking the correct answers in technical issues. Also, my dear
comrades working on the field as nameless heroes, Mustafa Ayten, Davut Çağığan,
Cemal Çökelek, Đsmail Gökdeniz, Gökhan Topçu and Tevfik Yaman receive my
greatest gratitude. I learned a lot from them during the field works.
My extended family gets one of the biggest thanks. Without the strong
encouragement of my mother Hepnur Bekta and my father Hüseyin Bekta , this
study would not come to an end. I also owe many thanks to my brother Deniz Bekta
and my grandmother Kadriye Sun, for their genuine enthusiasm to see the
completion of this study. They all encouraged me to go on.
The last but not the least, I am thankful from all my heart to my dear love Melike
Demir who emotionally supported the thesis studies all the time. I am sure she is as
happy as I am now.
ix
TABLE OF CONTENTS
ABSTRACT ........................................................................................................... iv
ÖZ .......................................................................................................................... vi
ACKNOWLEDGEMENTS .................................................................................... ix
TABLE OF CONTENTS ..........................................................................................x
LIST OF TABLES .................................................................................................xiv
LIST OF FIGURES ...............................................................................................xvi
LIST OF SYMBOLS .............................................................................................xxi
CHAPTERS
1.
2.
INTRODUCTION ............................................................................................1
1.1.
General......................................................................................................1
1.2.
Objective and Scope ..................................................................................2
THEORETICAL CONSIDERATIONS .............................................................3
2.1.
Elements of Water Distribution Networks .................................................3
2.1.1.
Pipes ..................................................................................................3
2.1.2.
Pumps ................................................................................................4
2.1.3.
Valves ...............................................................................................4
2.1.3.1.
Isolating Valves .........................................................................4
2.1.3.2.
Control Valves ...........................................................................5
2.1.3.3.
Check Valves .............................................................................5
2.1.3.4.
Air Release Valves .....................................................................5
2.1.3.5.
Drain Valves ..............................................................................5
2.1.3.6.
Pressure Reducing Valves (PRV) ...............................................5
2.1.4.
Distribution Reservoirs ......................................................................6
2.1.5.
Storage Tanks ....................................................................................6
2.1.6.
Fire Hydrants .....................................................................................6
x
3.
MODELLING THE NETWORK ......................................................................7
3.1.
3.1.1.
Modelling of Pipes.............................................................................8
3.1.2.
Modelling of Consumers....................................................................9
3.1.3.
Modelling of Nodal Elevations ........................................................10
3.1.4.
Modelling of Pumps, Tanks and Reservoirs .....................................11
3.2.
4.
Use of GIS in Modelling..........................................................................12
3.2.1.
Digital Elevation Models .................................................................12
3.2.2.
Digitized Network Maps ..................................................................12
3.2.3.
Geodetic GPS Instruments ...............................................................13
3.3.
Use of SCADA System ...........................................................................14
3.4.
Use of Customer Information System ......................................................14
WATER LOSS CONCEPT BASICS...............................................................16
4.1.
Definitions ..............................................................................................18
4.2.
Sources of Leakage .................................................................................24
4.2.1.
Leaks Occurring at the Sources ........................................................24
4.2.2.
Leaks Occurring in the Network Elements .......................................25
4.3.
Factors Affecting Leakage .......................................................................26
4.3.1.
Pressure ...........................................................................................26
4.3.2.
Hole Size .........................................................................................27
4.3.3.
Leak Duration ..................................................................................27
4.3.4.
Pipe Material ...................................................................................27
4.3.5.
Aging of Pipes .................................................................................28
4.3.6.
Workmanship ..................................................................................29
4.3.7.
Network Design ...............................................................................29
4.3.8.
Soil Types........................................................................................30
4.3.9.
Water Quality ..................................................................................30
4.4.
5.
Water Distribution Network Modelling Principles .....................................8
Controlling Water Leakages ....................................................................30
4.4.1.
Passive Leak Control (PLC).............................................................31
4.4.2.
Active Leak Control (ALC) .............................................................32
DEVELOPING THE METHODOLOGY ........................................................34
5.1.
Formation and Evaluation of District Metered Areas (DMA) ...................37
5.2.
Measuring Daily Demand Curves of the DMA ........................................42
xi
5.3.
Sub-DMA Formation...............................................................................45
5.4.
Calculating Water Loss Percentages ........................................................47
5.4.1.
Monthly Revenue Aspect .................................................................49
5.4.2.
Minimum Night Flow Aspect ..........................................................53
5.5.
Prioritizing the Sub-DMAs ......................................................................53
5.6.
Search for Leaks with Leak Noise Loggers ..............................................55
5.7.
Pinpointing the Leak with Ground Microphones ......................................58
5.8.
Measuring Daily Demand Curves of the DMA to See the Effects of Leaks
59
5.9.
6.
Equipments Used In the Field Studies......................................................60
5.9.1.
Noise Data Loggers .........................................................................61
5.9.2.
Ground Microphones .......................................................................62
CASE STUDIES IN ANTALYA WATER DISTRIBUTION NETWORK......65
6.1.
General Information about Antalya Water Distribution Network .............65
6.1.1.
GIS Layers ......................................................................................69
6.1.1.1.
Pipes ........................................................................................69
6.1.1.2.
Fittings .....................................................................................69
6.1.1.3.
House Connections ..................................................................70
6.1.1.4.
Buildings .................................................................................70
6.1.1.5.
Roads .......................................................................................71
6.1.1.6.
Cadastral Layers ......................................................................71
6.1.2.
SCADA Data ...................................................................................71
6.1.3.
Customer Information System (CIS) ................................................72
6.2.
Zone 6 Studies .........................................................................................76
6.2.1.
Data Sources ....................................................................................78
6.2.1.1.
Geographic Information Systems .............................................78
6.2.1.1.1.
Pipes .....................................................................................78
6.2.1.1.2.
Fittings ..................................................................................79
6.2.1.2.
6.2.2.
Customer Information Systems ................................................82
Calculating Water Loss Percentages ................................................82
6.2.2.1.
Monthly Revenue Aspect .........................................................83
6.2.2.2.
Minimum Night Flow Aspect ...................................................83
6.2.3.
Forming Sub-DMAs ........................................................................85
xii
6.2.3.1.
6.2.4.
Locating Physical Water Losses.......................................................89
6.2.4.1.
Forming Buffer Areas for Leak Noise Loggers.........................89
6.2.4.2.
Ground Microphoning in Logger Ineffective Areas ................ 100
6.2.5.
6.3.
Prioritizing sub-DMAs by Step Tests .......................................85
Results ........................................................................................... 106
Zone 2 Studies ....................................................................................... 122
6.3.1.
Data Sources .................................................................................. 123
6.3.1.1.
Geographic Information Systems ........................................... 123
6.3.1.1.1.
Pipes ................................................................................... 123
6.3.1.1.2.
Fittings ................................................................................ 124
6.3.1.1.3.
Buildings............................................................................. 125
6.3.1.2.
6.3.2.
Customer Information Systems .............................................. 127
Calculating Water Loss Percentages .............................................. 128
6.3.2.1.
Monthly Revenue Aspect ....................................................... 128
6.3.2.2.
Minimum Night Flow Aspect ................................................. 128
6.3.3.
Forming and Prioritizing Sub-DMAs ............................................. 132
6.3.4.
Locating Physical Water Losses..................................................... 133
6.3.4.1.
Forming Buffer Areas for Leak Noise Loggers....................... 133
6.3.4.2.
Ground Microphoning in Logger Ineffective Areas ................ 143
6.3.5.
Results ........................................................................................... 148
7.
DISCUSSION OF RESULTS ....................................................................... 169
8.
CONCLUSIONS AND SUGGESTIONS FOR FUTURE STUDIES ............. 171
REFERENCES ..................................................................................................... 173
xiii
LIST OF TABLES
TABLES
Table 4.1 IWA Standard Water Balance (Web 5) ....................................................17
Table 5.1 Typical Structure of a Customer Information System Database ...............51
Table 5.2 Sample Summary Table for Examining Daily Minimum Night Flow and
Water Loss Percentages ..........................................................................................59
Table 6.1 Percentages of pipe materials in Antalya WDN .......................................66
Table 6.2 A Sample Record from the CIS of ASAT ................................................75
Table 6.3 Pipe Diameters and Pipe Lengths in Zone 6 .............................................78
Table 6.4 Pipe Materials and Pipe Lengths in Zone 6. .............................................79
Table 6.5 Pipe Diameters, Pipe Materials and Pipe Lengths in Zone 6 ....................79
Table 6.6 Tabular Results of Flowmeter Values during Valve Closing Steps...........87
Table 6.7 Tabular Results of Flowmeter Values during Valve Closing Steps...........88
Table 6.8 Number of Valves in Sub-DMAs.............................................................89
Table 6.9 Leaks, Their sub-Zones and Repair Dates .............................................. 107
Table 6.10 SCADA Summary Table for Zone 6 .................................................... 115
Table 6.11 Monthly Revenue Percentages ............................................................. 120
Table 6.12 Pipe Diameters and Pipe Lengths in Zone 2 ......................................... 123
Table 6.13 Pipe Materials and Pipe Lengths in Zone 6. ......................................... 123
Table 6.14 Pipe Diameters, Pipe Materials and Pipe Lengths in Zone 6................. 124
Table 6.15 Number of Floors and Buildings in Zone 2 .......................................... 125
Table 6.16 Corrected Number of Floors and Buildings in Zone 2 .......................... 126
Table 6.17 Number of Valves and Loggers Placed in Zone 2 ................................ 133
Table 6.18 Applied Pressure Regulations on Zone 2 with Their Dates and Times.. 148
Table 6.19 Leaks, Their Regions, Discovery Methods and Repair Dates ............... 148
Table 6.20 SCADA Summary Table for Zone 2 .................................................... 161
Table 6.21 Monthly Revenue Percentages ............................................................. 167
xiv
Table 7.1 Overall Summary Table for the Case Studies......................................... 170
xv
LIST OF FIGURES
FIGURES
Figure 3.1: Different elevation choices for a hydrant (Walski et.al 2003) ................11
Figure 4.1 Typical Daily Demand Curve and Its Components (Web 7) ...................22
Figure 4.2 Typical Minimum Night Flow Changes with Time (Web 7) ...................23
Figure 5.1 Defining Pressure Zone Boundaries .......................................................35
Figure 5.2 Controlling Pumps, Tanks, Transmission and Distribution Pipes ............36
Figure 5.3 Assigning Each Customer a Pressure Zone .............................................37
Figure 5.4 Forming DMA in a Branching Network .................................................40
Figure 5.5 Forming DMA in a Branching Network in a Grid Network ....................41
Figure 5.6 Sample Daily Demand Curve Showing Minimum Night Flow in a
Residential Area .....................................................................................................43
Figure 5.7 Sample Daily Demand Curve Showing Zero Minimum Night Flow .......44
Figure 5.8 Conceptual Curves Showing Real and Idealized Water Loss Amounts ...45
Figure 5.9 Example Formation of a sub-DMA ........................................................46
Figure 5.10 Conceptual Drawing of a DMA with Water Movements ......................48
Figure 5.11 Conceptual Daily Demand Curve with Its Components ........................49
Figure 5.12 All Possible Irregularities in Monthly Meter Readings .........................50
Figure 5.13 Sample Valve Closing Data in a Step Test ............................................54
Figure 5.14 Sample Valve Opening Data in a Step Test ..........................................55
Figure 5.15 Data Logger Result Graph Showing a Possible Leak Noise Recording .56
Figure 5.16 Data Logger Result Graph showing a non-Leak Noise Recording ........56
Figure 5.17 Sample DMA Showing Leaks and Possible Detection Points ...............57
Figure 5.18 Timeline Showing Leakage Detection Technology Developments (Web
6) ............................................................................................................................60
Figure 5.19 Sample SePem 01 Result Graph ........................................................62
xvi
Figure 5.20: Pinpointing Leak Spot with Ground Microphone from Surface (Web10)
...............................................................................................................................63
Figure 5.21: Pinpointing Leak Spot with Listening Stick from Fittings (Web10) .....64
Figure 6.1 18 District Metered Areas formed in Antalya Water Distribution Network
...............................................................................................................................67
Figure 6.2 Coordinating the pipeline (Web 4) .........................................................68
Figure 6.3 Explanation of Coordinated and Schematic Valve Drawings ..................70
Figure 6.4 SCADA Measurements and Corresponding Customer Readings for one
Month .....................................................................................................................73
Figure 6.5 SCADA Measurements and Corresponding Customer Readings for one
Year........................................................................................................................74
Figure 6.6 Simplified Schematic Drawing of Konyaaltı Water Transmission System
and Zone 6 Entrance ...............................................................................................77
Figure 6.7 Distribution Main of Konyaaltı and Branching Pipes of 18 DMAs .........77
Figure 6.8 Recommended Valve Places and Their Effective Areas..........................81
Figure 6.9 Valves and Their Effective Areas Before and After Constructions..........82
Figure 6.10 Sample Daily Demand Curve of Zone 6 Showing Minimum Night Flow
before the Study ......................................................................................................84
Figure 6.11 Sub-DMAs in Zone 6 of Konyaaltı Network ........................................85
Figure 6.12 Manually Recording Discharge Values from Flowmeter’s Panel during
Step Test .................................................................................................................86
Figure 6.13 Water Losses in sub-DMAs Determined by Closing Valves .................87
Figure 6.14 Water Losses in sub-DMAs Determined by Closing Valves .................88
Figure 6.15 Noise Data Logger with Serial Number 3603 Placed On Valve #27066
and Its Corresponding Effective Areas ....................................................................91
Figure 6.16 Details of Logger with Serial Number 3603 Placed On Valve #27066 ..92
Figure 6.17 Noise Data Logger with Serial Number 3605 Placed On Valve #27169
and Its Corresponding Effective Areas ....................................................................93
Figure 6.18 Details of Logger with Serial Number 3605 Placed On Valve #27169 ..93
Figure 6.19 Noise Data Logger with Serial Number 3605 Placed On Valve #39681
and Its Corresponding Effective Areas ....................................................................94
Figure 6.20 Details of Logger with Serial Number 3596 Placed On Valve #39681 ..95
xvii
Figure 6.21 Noise Data Loggers with Serial Numbers 3606 and 3622 Placed On
Valves #27102 and #27104 and Their Corresponding Effective Areas ....................96
Figure 6.22 Details of Logger with Serial Number 3606 Placed On Valve #27102 ..96
Figure 6.23 Details of Logger with Serial Number 3622 Placed On Valve #27104 ..97
Figure 6.24 Noise Data Logger with Serial Number 3612 Placed On Valve #31903
and Its Corresponding Effective Areas ....................................................................98
Figure 6.25 Details of Logger with Serial Number 3612 Placed On Valve #31903 ..98
Figure 6.26 Noise Data Logger with Serial Number 3641 Placed On Valve #39582
and Its Corresponding Effective Areas ....................................................................99
Figure 6.27 Details of Logger with Serial Number 3641 Placed On Valve #39582 100
Figure 6.28 Position of leak spot and nearby logger effective areas. ...................... 102
Figure 6.29 Position of leak 1 and the nearest valve location with effective areas. . 103
Figure 6.30 Position of leak 3 and the nearby valve with its effective area ............ 104
Figure 6.31 Leak spots 4 and 5 and the nearby data logger’s effective area. .......... 105
Figure 6.32 Collar Repair Clamp .......................................................................... 106
Figure 6.33 Daily Demand Curve of Zone 6 on 04.04.2010................................... 108
Figure 6.34 Daily Demand Curve of Zone 6 on 05.04.2010................................... 109
Figure 6.35 Daily Demand Curve of Zone 6 on 06.04.2010................................... 110
Figure 6.36 Daily Demand Curve of Zone 6 on 07.04.2010................................... 111
Figure 6.37 Daily Demand Curve of Zone 6 on 08.04.2010................................... 112
Figure 6.38 Daily Demand Curve of Zone 6 on 12.04.2010................................... 113
Figure 6.39 Total Water Entering and Minimum Night Flow Values vs. Days....... 117
Figure 6.40 Water Loss Percentages vs. Days ....................................................... 118
Figure 6.41 Revenue Percentages over Periods ..................................................... 121
Figure 6.42 Zone 2 and 6 with Their Neighbouring Zones..................................... 122
Figure 6.43 Zone 2 Divided Into Three Pieces ...................................................... 127
Figure 6.44 Sample Daily Demand Curve of Zone 2 Showing Minimum Night Flow
on 31 July 2009 .................................................................................................... 129
Figure 6.45 Sample Daily Demand Curve of Zone 2 Showing Minimum Night Flow
on 21 August 2009 ................................................................................................ 130
Figure 6.46 Sample Daily Demand Curve of Zone 2 Showing Minimum Night Flow
on 2 October 2009 ................................................................................................ 131
Figure 6.47 Minimum Night Flows vs. Pressure Under PRV Effect ...................... 132
xviii
Figure 6.48 Decrease of Minimum Night Flows with the PRV .............................. 132
Figure 6.49 Noise Data Loggers with Serial Numbers 3605, 3608 and 3645 Placed
On Valves #20814, #20854 and #20815 with Their Corresponding Effective Areas
............................................................................................................................. 134
Figure 6.50 Details of Logger with Serial Number 3605 Placed On Valve #20814 135
Figure 6.51 Details of Logger with Serial Number 3645 Placed On Valve #20854 135
Figure 6.52 Noise Data Logger with Serial Number 3612 Placed On Valve #31910
and Its Corresponding Effective Areas .................................................................. 136
Figure 6.53 Details of Logger with Serial Number 3612 Placed On Valve #31910 137
Figure 6.54 Noise Data Logger with Serial Number 3652 Placed On Valve #27070
and Its Corresponding Effective Areas .................................................................. 138
Figure 6.55 Details of Logger with Serial Number 3652 Placed On Valve #27070 138
Figure 6.56 Noise Data Logger with Serial Number 3641 Placed On Valve #27259
and Its Corresponding Effective Areas .................................................................. 139
Figure 6.57 Details of Logger with Serial Number 3641 Placed On Valve #27259 140
Figure 6.58 Noise Data Logger with Serial Number 3625 Placed On Valve #20716
and Its Corresponding Effective Areas .................................................................. 141
Figure 6.59 Details of Logger with Serial Number 3625 Placed On Valve #20716 141
Figure 6.60 Noise Data Logger with Serial Number 3622 Placed On Valve #21037
and Its Corresponding Effective Areas .................................................................. 142
Figure 6.61 Details of Logger with Serial Number 3622 Placed On Valve #21037 143
Figure 6.62 Position of leak spot 6 and nearby logger effective areas. ................... 144
Figure 6.63 Position of leak 7 and the nearby valves with effective areas. ............. 145
Figure 6.64 Position of leak 8 and the nearby valve with its effective area ............ 146
Figure 6.65 Leak spot 9 and the nearby data logger’s effective area. ..................... 146
Figure 6.66 Leak spot 10 and the nearby data logger’s effective area. ................... 147
Figure 6.67 Leak spot 11 and the nearby data loggers’ effective areas. .................. 147
Figure 6.68 Daily Demand Curve of Zone 2 on 11.04.2010................................... 150
Figure 6.69 Daily Demand Curve of Zone 2 on 12.04.2010................................... 151
Figure 6.70 Daily Demand Curve of Zone 2 on 13.04.2010................................... 152
Figure 6.71 Daily Demand Curve of Zone 2 on 14.04.2010................................... 153
Figure 6.72 Daily Demand Curve of Zone 2 on 15.04.2010................................... 154
Figure 6.73 Daily Demand Curve of Zone 2 on 16.04.2010................................... 155
xix
Figure 6.74 Daily Demand Curve of Zone 2 on 17.04.2010................................... 156
Figure 6.75 Daily Demand Curve of Zone 2 on 18.04.2010................................... 157
Figure 6.76 Daily Demand Curve of Zone 2 on 19.04.2010................................... 158
Figure 6.77 Daily Demand Curve of Zone 2 on 20.04.2010................................... 159
Figure 6.78 Minimum Night Flows vs. Pressures in Zone 2 before and after the Field
Studies .................................................................................................................. 160
Figure 6.79 Total Water Entering and Minimum Night Flow Values vs. Days....... 164
Figure 6.80 Water Loss Percentages vs. Days ....................................................... 165
Figure 6.81 Revenue Percentages over Periods ..................................................... 168
xx
LIST OF SYMBOLS
C: Hazen Williams Roughness Coefficient
V: System Input Volume
C1: Authorized Consumption
C2: Billed Authorized Consumption
C3: Unbilled Authorized Consumption
C4: Billed Metered Consumption
C5: Billed Unmetered Consumption
C6: Unbilled Metered Consumption
C7: Unbilled Unmetered Consumption
C8: Unauthorized Consumption
L1: Water Losses
L2: Apparent Losses (Commercial Losses)
L3: Real Losses (Physical Losses)
L4: Leakage on Transmission and/or Distribution Mains
L5: Leakage and Overflows at Utility’s Storage Tanks
L6: Leakage on Service Connections up to Point of Customer Metering
I: Customer Metering Inaccuracies
RW: Revenue Water Volume
NRW: Non-Revenue Water Volume
QS: Total Monthly Inflow to the DMA Measured from SCADA.
qS1: SCADA Index at the Beginning of the Month
qS2: SCADA Index at the End of the Month
TS: Duration of the Month in Terms of Days
tS2: Last Day of the Month
tS1: First Day of the Month
IT: Daily Average Inflow to the DMA
xxi
tCn1: First Meter Reading Day of the nth Customer
tCn2: Second Meter Reading Day of the nth Customer
qCn: Consumption of the nth Customer Between Two Meter Reading Days
TCn: Water Usage Period of the nth Customer
DCn: Daily Average Consumption of the nth Customer
DT: Total Average Daily Consumption in the DMA
WL: Water Loss Percentage
dB: Sound Level of the Noise Data Loggers in Decibels
IL: Unitless Intensity Value of the Noise Data Loggers
Ø: Pipe Diameter Prefix
A0: Reference Amplitude of the Noise Data Loggers
A1: Field Measured Amplitude of the Noise Data Loggers
xxii
CHAPTER 1
1. INTRODUCTION
1.1.
General
World population increased considerably in the last century. According to the United Nations
Population Fund, world population will reach 7 billion people in the year 2012. According to present
estimate, 6.8 billion people are living on the earth (Web 8). With the increasing population, demand to
sound infrastructure services increased enormously. Domestic and industrial demand for electricity,
natural gas, telecommunication (including high-speed internet) and potable water are the most widely
used infrastructure services.
Potable water resources all around the world became extra important with the increasing
usage. Having limited supplies of this valuable resource, the water authorities are forced to focus on
the physical water losses.
Although water loss detection studies go back up to 150 years from now, in the last years
detection studies became much more effective with the improved acoustic and electronic devices. In
spite of that, cities grew and became more complicated with all kinds of infrastructure including water
distribution networks.
Jones (2006) draws attention to highly developed leak detection technology. Jones also states
the importance of easily monitoring and detecting leaks before they come above the surface. By early
recognition of leaks, pumping additional water to compensate for leaks is prevented. In addition,
damages caused by undetected leaks (paving, sidewalk costs, etc.) are minimized.
From the information technologies (IT) point of view, Geographic Information Systems
(GIS) combined with various IT elements broadens the horizons of leak detection studies. Summers
(2001) emphasizes the importance of automated meter reading combined with GIS and says;
“Automated meter-reading (AMR) using GIS technology enables real-time monitoring of water use
1
and a degree of trouble management were not before possible”.
Another subject Summers (2001) states is quickly pinpointing leaks on water mains with GIS
based water readings. Also according to him, locating leaks quickly will instantaneously save time,
labor, resource and money.
Another aspect on importance of leak detection is water quality aspect. Hunaidi et.al. (2000)
emphasizes the risk of leaky pipes in public health risk point of view, as contaminants can enter the
pressurized system in any case of water shortage or pressure drop.
1.2.
Objective and Scope
The objective of this thesis is to develop a methodology for finding water leakages in water
distribution networks using information technologies. The methodology is developed by integrating
the data obtained from geographic information systems (GIS), supervisory control and data
acquisition systems (SCADA) and customer information systems (CIS). In order to find the leaks
district metered areas (DMA) are formed on GIS system and they are verified on the field. In addition,
several acoustic and electronic leak detection devices are used on the field to locate and pinpoint water
leakages.
Novelty of this study is using CIS data for the calculation of physical water loss and revenue
loss amounts. Collecting and integrating customer information data with GIS is a very recent
development in Turkey in some pilot areas only.
The study consists of eight chapters. In the second chapter, some basic concepts about water
distribution network elements and theoretical equations of hydraulic solutions are given. In the third
chapter, concepts about modelling of the water distribution networks are explained. In the fourth
chapter basic knowledge about the water loss concepts are explained. In the fifth chapter,
methodology that is developed in the thesis is explained. As applications of the methodology, chapter
six contains two case studies that were conducted in Antalya water distribution network that have
different characteristics in most aspects. In chapter seven, discussions of the results are given. Finally,
in chapter eight, some conclusions and suggestions for future studies are stated.
2
CHAPTER 2
2. THEORETICAL CONSIDERATIONS
2.1.
Elements of Water Distribution Networks
2.1.1. Pipes
The major elements of all water distribution networks are pipes. They are major carrier
elements in the network in which water is transmitted from one place to another. Pipes are produced
by using different materials and in different sizes.
Various materials are used in the production stages of pipes. Prestressed concrete, asbestos
cement, cast iron, ductile iron, steel, high-density polyethylene (HDPE) and polyvinyl chloride (PVC)
can be given as major pipe materials. Some materials like asbestos cement and cast iron are not used
widely nowadays, on the other hand ductile iron and HDPE pipes are often used in many places
especially in water distribution networks.
Pipes of diameters varying from 19mm to 2200mm are produced by using different types of
materials. Larger diameters can also be produced upon special requests.
Pipes are mainly used for three distribution purposes:
•
Transmission Lines
•
Distribution Lines
•
Customer Service Connections
Transmission lines are the major carrier pipes between the source and the distribution
network. Usually they are the pipes between source (pump stations) and storage tanks. At various
points, connections to the distribution networks are placed in order to feed the network properly.
Larger diameter pipes are used in transmission lines compared to distribution lines, and their materials
3
are usually prestressed concrete, steel, HDPE and ductile iron.
Distribution lines are the pipes that distribute the water coming from transmission lines to the
streets of the network. These pipes are used to transmit water to the consumers with the help of
customer service pipes. Mostly steel, ductile iron, HDPE or PVC is preferred in distribution pipes.
Service connections are the pipes delivering water from the street pipes to the customer.
After the service connection pipes, interior pipes in the building distribute water to different customers
and deliver water to the taps. Mainly HDPE is used in service connection pipes.
2.1.2. Pumps
Pumps are devices converting electrical energy into mechanical energy for moving water
volumes by increasing their potential energy. This energy is used to overcome friction losses in the
pipes and raise the water to topographically higher points.
Pumps are selected carefully depending on various factors in the network, such as
topography, water demand of the consumers, efficiency requirements, etc.
2.1.3. Valves
Valves are the elements used to control water flow in the distribution network. Controlling
water flow can be done by blocking flow, directing flow from one path to another path in the network,
increasing or decreasing the amount of flow in the pipes, etc.
There are many types of valves used for many different purposes. The exact locations of the
valves on the network are extremely important for operation purposes. The types and places of the
valves should be known precisely in order to make correct operational decisions.
2.1.3.1.
Isolating Valves
As the name implies, isolation valves are used to separate a part of the network from the rest.
This action interrupts water flow in the line and creates a dry part in the network for repair and
maintenance purposes. Generally, gate valves are used for isolation actions. Gate valves are not
intended to control the flow amount in the network by partial closure. They are intended to permit
flow or stop flow by complete opening and closing.
Another usage area of isolation valves is to separate water distribution networks into separate
pieces without creating water shortages. It is especially useful while forming district-metered areas
4
(DMA) explained in Chapter 5.
2.1.3.2.
Control Valves
Control valves are used to control the amount of flow in the water distribution network. They
are usually butterfly type valves. By adjusting the butterfly valve’s interior mechanism, diameter of
the pipe section can be reduced. This will enable adjustment of amount of flow in the pipe.
2.1.3.3.
Check Valves
Check valves are the type of valves that permits water flow in one direction only and blocks
water flow if an opposite directional flow occurs. The flow inside the pipe controls this type of valves.
Unlike other valves, it works without any operator. It is used widely after pumps in order to prevent
backflow towards the pump.
2.1.3.4.
Air Release Valves
Air is to be avoided in a water distribution network. It enters to the water distribution
network generally while installation or during repair works. Air Release valves are the fittings that
remove air from the pipes. They are especially placed at the highest points in the transmission lines
and distribution pipes as air bubbles accumulate at the top sections of the pipes. Like check valves, air
valves do not require any operator to work.
2.1.3.5.
Drain Valves
Drain valves are gate valves one end open to atmosphere (often connected to the sewerage
lines) placed at the lowest points of transmission lines and distribution networks, for emptying the
pipeline whenever necessary. At the low points of the pipe, it is possible to empty the pipes that are at
higher elevations. Emptying pipes are useful during repair works, rehabilitation studies, etc.
2.1.3.6.
Pressure Reducing Valves (PRV)
PRVs are used to decrease high inlet pressures in the network. Water passing through the
valve is forced to create friction losses in the valve mechanism. Therefore, pressure is reduced at
5
the desired level. Preventing high pressures decreases water leakages in the network, as the amount of
water flowing through the leaks are directly proportional with the pressure in the system. PRVs have
many types. They may only reduce pressure at constant amounts, or adjust the pressure reduction
amount by considering some other parameters like hours of the day or demand of the consumers in the
network.
2.1.4. Distribution Reservoirs
Distribution reservoirs are the major water sources of a water distribution network. They are
usually dams or water treatment plants storing large volumes of water.
2.1.5. Storage Tanks
Storage tanks are water-storing structures to provide extra water to the network when needed.
The needed periods are usually when pumps do not work. At those times, storage tanks work as the
only water sources of the system. Similarly, storage tanks help pump flows at peak demand hours. In
addition, storage tanks are useful to overcome pressure fluctuations in the system and provide an even
pressure distribution. Having a storage tank also provides excess water for fire demands and
emergency cases.
2.1.6. Fire Hydrants
Fire hydrants are useful fittings placed in the water distribution networks mainly for fire
extinguishing purposes. The important property of these fittings is that they are connected to the
network with relatively large diameters when compared to a house connection. This allows the user to
draw large amounts of water from the hydrant.
Street washing, network flushing, sewer cleaning are some more usage areas of fire hydrants.
In addition, while modelling the network, calibration studies can be performed by using fire hydrants.
6
CHAPTER 3
3. MODELLING THE NETWORK
Modelling water distribution systems with the help of computer software products became
indispensable in the last years. Modelling study is done for many purposes like designing the network
before construction, and operating the network after the construction is completed. For all kinds of
modelling purposes, basic data about the network is needed. Needed data consists of pipe layout data
(including pipe characteristics) with all elements (valves, pumps, tanks, reservoirs, etc.) of the water
distribution system, consumption data, and topographic elevations of the network elements.
The reason to create a water distribution model can be stated as having a copy of the reality
that lies under the ground, inside computerized applications. Using the stated data, modelling of a
water distribution system can be done. The important thing about modelling data is the quality of the
data. Every piece of data should be representing the reality in the field accurately. Otherwise, every
error in the source data will introduce bits of uncertainties into the model. With a model having too
much uncertainties, means a model that does not represent the reality at all. That kind of a model can
be useful for theoretical studies, but will not be appropriate for designing a system or operating an
existing network.
Geographic information systems are one of the most useful tools in water distribution system
modelling. They are useful because in a comprehensive GIS used by the designer or by the water
authority, usually all the needed data are included. With some data transfers or with the help of some
developed modules, it is easy to generate a working model. Shamsi (2002) defines three methods to
link GIS data with computer models. They are:
1.
Interchange Method
2.
Interface Method
3.
Integration Method
7
In interchange method, GIS and the model are not linked together. Input parameters are
transferred from GIS to the model, they are processed in the model independently and the output
values are transferred back into the GIS as a new layer for presentation purposes.
In interface method, model is still executed independently elsewhere from the GIS, but a preprocessor for extracting input values and a post processor for displaying the results are available in the
GIS environment. Helping menus or buttons can be added into the GIS environment. It is simply
automation for manual actions stated in interchange method. Some knowledge of computer
programming is necessary for this automation.
Integration method is the combination of GIS and the model. The combination is provided
both GIS functions and model capabilities. In this method, either model is integrated into GIS or vice
versa. However, it is a better choice to integrate water distribution capabilities into the GIS software,
as geographic information systems are systems that are more inclusive.
3.1.
Water Distribution Network Modelling Principles
Shamsi (2005) summarizes hydraulic modelling process into three major steps:
1.
Development of spatial database
2.
Extraction of model layers
3.
Linkage to computer models
Development of spatial database is one of the main works done in GIS. Extraction of model
input parameters are done mainly with the data exporting features of the GIS software solutions.
Computer model links can be developed using one of the three methods stated in Chapter 3. This
summarization again shows the importance of GIS in modelling issues.
Shamsi (2005) emphasizes three input parameters used in hydraulic models. These are
skeletonized pipe layouts, nodal demands (consumers) and nodal elevations.
3.1.1. Modelling of Pipes
Pipes in a water distribution network are drawn on paper as linear features in the past years.
Those drawings are stored on plain paper or tracing paper in archives. Some very old pipes are not
even drawn on paper, staying as mysterious infrastructure elements that nobody knows enough or
correct information. At these times, modelling studies relied on existing projects of the pipes and
8
verbal knowledge (if there are any) of the personnel.
With the improved technology, paper sourced data are transferred into CAD or GIS
environment. Additionally, newer projects are prepared as CAD drawings mostly. Therefore accessing
the needed pipe data became easier.
Assuming properly scaled pipe layouts, lengths and interrelations with other pipes can be
obtained. With schematic pipe layouts, either assumptions about the length should be done or field
measurements should be done preferably with pipe locator devices.
Additional pipe characteristics are also needed. These characteristics are diameter and
roughness coefficient. Diameter data is usually available on the layout plans with some margin of
error. However, pipe roughness coefficient is one of the most difficult parameters to determine. As
roughness of a pipe is determined by a dozen of factors, including pipe material, age, water quality,
etc., some predetermined values for Hazen-Williams C coefficient are used for newly installed pipes.
According to the performance of the pipes, several calibration studies for the roughness coefficient
can be done to determine a realistic value for C.
As GIS layers may contain unnecessary details of the pipes (like tees, corners, valves, fire
hydrants, service connections, etc.), simplification is essential before modelling the network. This
process is called skeletonization. By getting rid of the unneeded details in the pipe layout, modelprocessing speed is increased incredibly. In addition, model results are not affected significantly.
Considering the type of model usage, level of skeletonization can be determined. For analysis
requiring only storage tank elevations, modellers do not need any house connection pipes and
distribution networks. Transmission lines are enough for modelling. On the other hand, if pressure
changes at every house connection during the day are a matter of concern, then every consumer pipe is
needed for a healthy model.
3.1.2. Modelling of Consumers
Nodal demands indicate the consumption rates in volume per unit time; mostly, litres per
second (l/sec) and meter cubes per hour (m3/hr) are used for consumption rates.
Consumers and their consumption values used to be kept in databases or spreadsheets. This
situation did not allow the modeller to use consumers one by one in a complicated model. Instead,
modeller used individual users’ consumption values accumulated at one point. As a result,
consumption variations in different customers were not clearly seen in the analysis.
However today, some of the municipalities and water administrations have attempts on
collecting houses as point features using GPS. With these data collected and combined with the
formerly used consumption databases in GIS environment, every customer and corresponding
9
consumptions can be used as precise modelling data. In addition, customer types can be used to
determine demand patterns and time-based analyses can be possible.
As data collecting is a cumbersome issue, positioning the customers with GPS and matching
them with correct address information should be done carefully. One of the most important issues
about consumption modelling is to determine the exact point of service pipe and network pipe
connection. This knowledge will help modeller to determine the pressure zone of the consumer, which
in some cases modeller may not be able to determine this knowledge by positions of consumers and
pipe layouts. It is a common situation at pressure zone borders to have two different network pipes
under different pressure zones.
Water losses can be modelled by distributing them to the customer nodes, as their exact spots
are not known. Alternatively, leak spots can be clustered to some part of the network if it is known
that it is a weak part of the network.
3.1.3. Modelling of Nodal Elevations
Determining exact topographic nodal elevations of an existing water distribution network can
be a difficult job. If pipes are installed at a constant depth from the ground surface, then determining
ground elevations, then subtracting the depth from ground elevations will yield the elevations of the
nodes. However, in practice installing the entire network at a constant depth is not possible at every
location. Existing infrastructure elements or difficulties faced due to stiff soils, depth of the pipeline
does not stand constant. If elevation data at every node are not collected, then it is a difficult task to
determine the nodal elevations after the installation. Therefore, usually ground elevations are assumed
as nodal elevations of the network (Shamsi 2005). Additionally ground elevations are the easiest data
that can be obtained.
10
Figure 3.1: Different elevation choices for a hydrant (Walski et.al 2003)
Figure 3.1 shows different choices (A, B and C) for modelling a hydrant’s elevation. Pipe
depth (Point A) can be considered for modelling nodes but it may be a difficult job to determine the
true depth of the pipe. Ground elevation (Point B) is the easiest measurable elevation for modelling
node elevation; however, it will not represent the true elevation of the physical reality. Hydrant
elevation (Point C) can be easily determined on the other hand it will not be so easy to gather
elevations of points on other nodes like corporation cocks, or pipe branching points.
Ground elevations can be determined from classical geodetic methods, air photography or
with GPS instruments. With the new established Cors-TR system, it became easy to determine
elevations of any ground point very accurately by using a real time kinematic (RTK) compatible GPS
device. At the end, collected elevations of the points are used to generate digital elevation models
(DEM) to interpolate the elevation values of nodes. Most modelling and GIS software products are
capable of assigning elevation values from the set of elevation data.
Topographic elevations of a water distribution network are important to determine the
hydraulic grade at each node. Hydraulic analysis results will not be meaningful unless all nodes in the
network are determined.
3.1.4. Modelling of Pumps, Tanks and Reservoirs
Pumps are usually essential elements in a water distribution network. They are modelled as
11
point objects. Minimal needed data about pumps are their elevations, pump characteristics and inlet
pressures. Without these data, pumps cannot be used in hydraulic analysis.
Tanks are point elements in the model. Base and water elevations should be known in order
to include a tank into the model. Additionally, base area and shape of the base area are important
issues for the investigation of oscillations in water levels in a dynamic analysis.
Reservoirs are modelled as point elements. Dams or water treatment plants providing water
to a network can be modelled as reservoirs. Water elevation (and the oscillations in that level) in a
reservoir should be known for modelling purposes. Groundwater sources can be considered as
distribution reservoirs too.
3.2.
Use of GIS in Modelling
3.2.1. Digital Elevation Models
Digital elevation models are the major sources of nodal elevations when a water distribution
system is being modelled. Usually they are produced by various methods of interpolation. Geoid
height data obtained by geodetic techniques or ellipsoidal heights obtained from GPS measurements
are converted to geoid elevations with appropriate transformation parameters. After obtaining DEMs,
contour maps are also produced. Contour maps and DEMs of the service area are important for a
water administration for both planning and operating applications.
3.2.2. Digitized Network Maps
Most water distribution networks that are in use now are installed before accurate mapping
applications were present. As a result, the as-built projects (if there are any) were mostly schematic
drawings showing the routes pf pipes and schematically representing places of network fittings.
Geodetic measurements of pipe elevations are necessary if a transmission line between a
pump and a storage tank is being constructed; however, in the distribution network elevation values
are not collected in most old projects. Pipe elevations were assumed as a constant value below the
ground elevations. However, due to changes in land use, some roads were filled and some of them
were lowered. As a result, depths of network pipes became inconsistent with ground elevations.
As pipe elevations were not given enough importance in networks, only inaccurately
coordinated or fully schematic x-y layout plans are the only data source while analyzing the network
for modelling purposes. Digitizing these network maps becomes an important task at this stage. This
task should be done either by scanning maps into computerized environment and coordinating by the
12
help of softwares or by using digitizing tables. Regardless of the method preferred, pipelines should
be digitized as polylines or lines, and fittings should be digitized as point features.
One last point to consider is very important for this task to be completely achieved. That is
the updating the digitized network. An update is strictly needed because; the digitized network maps
will be representing the networks first installment situations. Within time, various changes may have
been applied on the network. These changes may be newly installed pipes and valves, cancelled out
pipes and valves, displaced pipes and so on. Updating such changes on the digitized data will help the
administration to have an up-to-date network data. As a result modelling an up-to-date network will
represent more realistic values with the field observations.
3.2.3. Geodetic GPS Instruments
Nowadays, with the use of Cors-TR system, both x-y and z measurements having centimetre
accuracies can be done with geodetic GPS devices. Most newly installed pipelines and are coordinated
using geodetic GPS instruments. When coordinating pipelines, points on straight sections are not
usually considered. Only points at nodes that an angle occurring between pipes are coordinated.
Finally, when these points are combined with line or polylines, a linear feature representing the
pipeline is obtained.
Coordinating pipe fittings is easier as only point data is collected from the field. The
important thing is to collect point data always from the same place on every type of fittings (i.e. from
the top point of the valve shaft) in order to calculate the elevation of pipe’s internal elevation when
necessary.
Coordinating pipelines and fittings is very helpful for exploring an old portion of networks.
Pipelines are digitized as explained in Section 3.2.2, then by coordinating pipe fittings will help to
transform the schematic drawings into better coordinated network layouts. Also, when pipe fittings are
coordinated using geodetic GPS devices, they are easily found in case they are lost under asphalt some
day. As geodetic GPS devices give centimetre accuracy, minimum excavation and searching will be
done on the field, and fittings will be easily found.
As a result, a network having very realistic coordinates will be obtained. It will be very
useful, when accurate network layouts are overlaid on a digital elevation model. Pipe elevations will
then be available to the designer and analyzer with maximum accuracy. Therefore, modelling results
will be more realistic and nearer to the field observations. High accuracies in x-y are useful in
overlaying applications and high accuracies in z values may be very useful when calibrating the water
distribution network, which considers head loss values as little as a few decimetres.
13
3.3.
Use of SCADA System
Supervisory control and data acquisition (SCADA) systems are very useful tools for every
kind of analysis in a water distribution network. In special, SCADA systems can be used to gather
input parameters in a hydraulic analysis. SCADA systems in water distribution networks are used
mainly in:
•
Pump stations; measuring discharges, inlet and outlet pressures.
•
Storage tanks measuring water levels.
•
Any critical point defined by the authority measuring discharge and pressure.
Pump station and storage tank measurements can be used to determine daily demand curves
of a region. Additionally, if measuring points are placed at the entrances of district-metered areas
(DMA), instantaneous consumption in the area is measured directly. With the obtained consumption
values of the region, demands at the nodes can be estimated.
Having a SCADA system has numerous advantages. One of them is having continuous
measurements and recording them. Accessing the historical data enables the operator to see changes in
the network and take actions according to them.
In addition, as measurements are continuously recorded, monthly (or yearly) water budgets
can be derived. Combining SCADA data with the customer information system (CIS), opens the way
of calculating revenue water, non-revenue water and water losses. These topics are studied with more
detail in Chapter 4.
3.4.
Use of Customer Information System
Customer Information Systems (CIS) can be a very useful data source in water distribution
system modelling. The major data that will be obtained from CIS is the (generally monthly)
consumptions of the customers. Besides keeping the record of consumptions, in CIS various
information about the customers can be kept too. Some examples for these records can be address
information, identification information about the customer (name, surname, telephone number, e-mail
address, etc.), customer id number, pressure zone of the customer, information about the water meter,
etc.
Monthly consumption values can be jointly used with SCADA measurement records to
calculate water losses as stated above. The significant thing to consider for each customer in the CIS is
14
to clearly determine which customer is connected to which pressure zone. If this knowledge is
obtained exactly, water loss amounts in the interested region can be determined for sure. Chapter 4
gives detailed information about these topics.
15
CHAPTER 4
4. WATER LOSS CONCEPT BASICS
Water loss concept is a sophisticated concept and contains many components. These
components should be clearly understood in order to take action on the major title. Before getting into
the components, it is a necessity to see the full picture. International Water Association (IWA)
prepared an international standard approach for standard water balance calculations. This standard
approach can be seen in Table 4.1.
Table 4.1 explains the total input volume of water entering into the network and by dividing
it into smaller components and placing the components into different categories. Each component and
category has individual physical meanings. They are explained with examples in Section 4.1.
Usually in water administrations, different departments deal with the basic components of the
water audit. For example, all consumption values (C4 to C8) can be collected by the customers
department, while leakage terms (L4 to L6) are calculated by the water loss department. Unauthorized
consumption issues can be solved with the help of a specialized department, while input volumes can
be measured by the SCADA department. With such an administrative structure, it may be hard to
collect the whole data together and complete the water audit table. Therefore, a shared database can be
made available to all the departments in the administration to make the data transmission easier.
16
Table 4.1 IWA Standard Water Balance (Web 5)
Billed Authorized Consumption
Authorized
Consumption
[C1]
[C2]
Billed Metered Consumption [C4]
Billed Unmetered Consumption [C5]
Unbilled Authorized
Consumption
Unbilled Metered Consumption [C6]
[C3]
Unbilled Unmetered Consumption [C7]
(corrected for
known errors)
Apparent Losses
(Commercial Losses)
Unauthorized Consumption [C8]
[V]
[L2]
Customer Metering Inaccuracies [I]
System Input
Volume
Revenue Water
[RW]
Non-Revenue Water
[NRW]
Water Losses
Leakage on Transmission and/or Distribution Mains [L4]
[L1]
Real Losses
Leakage and Overflows at Utility's Storage Tanks [L5]
[L3]
Leakage on Service Connections up to Point of Customer
Metering [L6]
17
4.1.
Definitions
System Input Volume: This is the total volume of treated water introduced to the system.
Here, system is part of the network, which the water balance in Table 4.1 is being calculated. Input
volume should contain imported volume of water if there is any. The amount should be corrected for
known errors. The volume at this stage is the sum of all components of the water audit. When
calculated or measured precisely the components should add up to System Input Volume. It is denoted
by “V” and is composed of the terms Authorized Consumption (C1) and Water Losses (L1).
V = C1 + L1
(4.1)
Authorized Consumption: It is the total volume of billed and unbilled water taken by
registered customers. Billed and unbilled water may be either metered or unmetered. If there is any
water exported, it should be included in this term. In addition, leaks after the customer meters are
added to this term. It is denoted by C1 and composed of the terms Billed Authorized Consumption
(C2) and Unbilled Authorized Consumption (C3).
C1 = C2 + C3
(4.2)
Water Losses: These are the total amount of Apparent (L2) and Real Losses (L3). They sum
up a large part of Non Revenue Water volume.
L1 = L2 + L3
(4.3)
Billed Authorized Consumption: It is the sum of both metered (C4) and unmetered (C5)
consumptions. These two components are the only terms included in revenue water. Therefore, Billed
Authorized Consumption is the only term that the water administrations can generate income.
C 2 = C 4 + C5
(4.4)
Unbilled Authorized Consumption: It is the authorized consumption of customers, to whom a
privilege is given by the water administration. They are included in Non Revenue Water amount as no
billing is made for their consumptions. This type of consumption may be metered (C6) or unmetered
18
(C7).
C3 = C6 + C7
(4.5)
Apparent Losses: They consist of unauthorized consumptions (C8) and water meter
inaccuracies (I). They are referred as water losses but they are not actual water losses that leave out
the system. They are also called as commercial losses, which indicate that the actual lost thing is
money. Apparent losses are impossible to avoid completely, but with convenient methods, they can be
minimized.
L2 = C8 + I
(4.6)
Real Losses: These are the major topics of interest in this study. They are the amount of
water that somehow leaves out the system by leaks and overflows before the points of customer
meters. This term can be separated into three terms of Leakage on Transmission and/or Distribution
Mains (L4), Leakage and Overflows at Utility’s Storage Tanks (L5) and Leakage on Service
Connections up to Customer Meters (L6). This term cannot be avoided completely but with
appropriate methods, it can be decreased in high amounts.
L3 = L4 + L5 + L6
(4.7)
Billed Metered Consumption (C4): It is the major term in revenue water. It consists of mainly
customers whose consumptions are being metered and billed. Residential users, commercial users,
factories can be given as examples to this category.
Billed Unmetered Consumption (C5): It is the term, in which a billing action is done to the
consumers but that action is not done depending on metering values. It means customers are not billed
by volume, instead an approximation is done to the consumptions they are making and billing is done
according to that approximation. An example may be a billing to a customer, whose water meter is not
functioning for a short time. Then an estimate can be done for this period’s consumption.
Unbilled Metered Consumption (C6): This type of consumption is metered but not billed.
Examples may be given to the water usage of water administration itself or water supplied to some
institutions without any billing (schools, religious facilities etc.). To be able to keep a record these
19
amounts are metered.
Unbilled Unmetered Consumption (C7): Neither metered nor billed consumptions are in this
category. Examples are usually water drawn from fire hydrants by the fire authority, public garden
watering, water used in street cleaning, water used in network flushing and discharging water from the
network in a repair work. These sub terms can be transferred to unbilled metered consumption by
using appropriate water meters while using water.
Unauthorized Consumption (C8): It is the illegal usage of water in anywhere by any means
from the distribution pipes or by deactivating the water meter by any methods to decrease the metered
usages. As this action is illegal, water administrations apply fines to people doing unauthorized
consumption. The amount of this consumption is naturally not metered. It is approximately
determined.
Customer Metering Inaccuracies (I): They are defined as both meter reading errors and errors
due to the type of the water meters. Water meter reading errors can be explained by rounding a
decimal metered value to the nearest integer value in order to bill the customer (i.e. rounding 3.4 m3 to
3 m3). Water meters of type B are widely being used. However, this type (and its similar types) does
not meter very low amounts of use. As a result, very little usages (like water dribbling from the taps)
will not be metered with low accuracy meters. Type C and better accuracy water meters should be
used to decrease the amount of water included in this term.
Leakage on Transmission and/or Distribution Mains (L4): Any type of leakage that occurs on
transmission mains or distribution mains is this kind. Either they are repaired, or they keep on leaking
until they are discovered.
Leakage and Overflows at Utility's Storage Tanks (L5): Leakage occurring at storage tanks
can be avoided by water insulation methods used on structural elements. Overflows are possible
outcomes of a bad management of storage tanks. They can be avoided using by automated systems
like SCADA.
Leakage on Service Connections up to Point of Customer Metering (L6): Leakages occurring
on service connections are one of the major sources of water leaks. As they occur before the customer
meter, water leaving the system is wasted without getting any revenue.
20
Revenue Water (RW): Revenue water is the total consumptions of water that produce
revenue to the water administration. Naturally, administrations would be pleased to increase the
revenue water amounts. It can be made possible by reducing the terms that are listed in non-revenue
water in any amount. As the total supplied water amount is the sum of revenue and non-revenue water
amounts, decreasing one term increases the other. To achieve an increase in revenue water:
•
All types of unbilled consumptions should be billed
•
Illegal usages should be prevented
•
Precise water meters should be used
•
Water losses should be prevented.
RW = C2 = V − NRW
(4.8)
Non-Revenue Water (NRW): Non-revenue water is the sum of all terms except C4 and C5.
This sum may constitute a large part of the total water supplied. Non-revenue water should be
decreased as much as possible. It may be achieved by decreasing all the terms it includes one by one.
Its main disadvantages are:
•
Providing no revenue to the administration
•
Wasting valuable amounts of water in some terms
NRW = C3 + L1
(4.9)
Before beginning a study on the field, some measurements should be collected to have an
idea about the properties of water usage of the interested region. Flow and pressure measurements are
the basic parameters of the water loss studies. Measuring flows at the entrance of an isolated region
provides daily demand curves of the region.
Daily demand curves are very basic and useful graphs that are drawn with the data obtained
from isolated areas in field. Briefly, the daily demand curves are graphs showing the variations in flow
with respect to time. Examining these graphs covering at least one day, reveals the water usage of the
interested area. In Figure 4.1, a sample daily demand curve is given with its components. The
components are described below. Apart from water usage characteristics, minimum nightly flows are
21
observed in daily demand curves. This parameter is one of the basic parameters that indicate the
amount of water leaks.
Time (Hr)
Figure 4.1 Typical Daily Demand Curve and Its Components (Web 7)
Minimum flow is the amount of discharge that enters to an isolated water distribution
network (i.e. a DMA), at night hours (usually between 02:00 and 04:00). This value is an important
value as it is the closest value to the physical loss amount of that network. As minimum night flow is
the closest value to the physical water loss amount, usually these two values are assumed the same.
When bursts or increases in background leakage occur in the network, minimum night flow level
increases too. An ultimate minimum level should be reached at any region, and this level should be
conserved by checking if there is an increase. If there is a big increment in the minimum night flow
level, leak detection studies should be performed to reduce the level to its original value. In Figure
4.2 a sample for minimum night flows and burst effects are given.
Background Leakage: Background leakages can be defined as unavoidable small losses that
are impossible to detect with today’s technology of active leakage detection techniques. Today’s
technology mostly depends on acoustic detection, so flow rates of a very small leakage makes very
little sound. Background leaks are very little seepages through any part of the network. They are
discovered either by chance or after some time when they are big enough to be detected.
The amount of background leakages is directly proportional with the pressure. Therefore, to
22
minimize the background leakages, pressure reduction techniques may be useful.
Bursts: Bursts are leakages that are bigger than background leakages, which can be detected
with active leakage detection techniques. Bursts should be effectively detected and fixed as quickly as
possible as the discharge that is lost through these events are greater than background leakages.
Bursts are usually reported by the customers if a harmful situation occurs, but bursts that is
not harmful to any customer is not reported, as its existence is not known yet. Active leakage
detection techniques are aimed to find and fix the bursts that nobody is aware of.
Figure 4.2 Typical Minimum Night Flow Changes with Time (Web 7)
Leak Duration: Leak duration is the time that passes between the occurrence of a leak and
repairing of it. The duration can be divided into three components. They are; awareness duration,
locating duration and repair duration. Any leak keeps on flowing throughout these three durations
until it is fixed. These are awareness duration, locating duration and repair duration. To minimize the
losses, minimum time should be spent on these three durations.
Awareness duration starts from the occurrence of the leak and lasts until the leak’s existence
is understood. If Active Leak Control (ALC) is being applied, this duration also includes locating
duration. IF Passive Leak Control (PLC) is being applied, then awareness duration is the duration
starting from leak occurrence and ending with the reporting of it to the water administration.
Awareness duration may differ from a few hours to a few years. If the leak is big, visible above the
ground and effects the customers directly, its existence will quickly be known. However, if the leak is
23
small, hidden underground and does not affect any customers directly, its existence can be unknown
for a long time.
Locating duration is the duration of pinpointing the leak spot using the leak detection tools.
The duration is usually short in PLC type of approach. It does not exceed a few days usually. In ALC
type of approach the locating duration is included in awareness duration as mentioned. This is because
when a leak’s existence is known with ALC, it is also located in the field.
Repair duration is the duration that passes while the leak is being fixed. With enough repair
teams, this duration rarely exceeds one day.
4.2.
Sources of Leakage
Leaks in a water distribution system can be categorized under many headings. At the end,
every classification defines a part of the physically wasted water amount.
Here, leak sources are classified under two main headings. First one can be named as losses
at the water sources, and second one can be named as losses at the distribution elements. All of the
categorized elements have a different share on the total amount of leakage. Regardless of the share of
leak amounts, every leakage should be investigated and minimized as quickly as possible. However,
the shares of different leak sources should be known in order to determine which source has a bigger
percentage and which source should be treated primarily.
4.2.1. Leaks Occurring at the Sources
Untreated water obtained from any kind of source is delivered to the treatment plant by
means of trunk mains. These big diameter pipes carry water on long pipelines without branching.
Trunk mains are usually made of prestressed concrete or steel pipes. Leaks occurring in these pipes
constitute a small amount of the total leaks when compared to the total amount in the water
distribution system. Whenever big leaks occur in the trunk mains, their effects may be observed in
measuring points or SCADA stations as sudden decreases in discharge and pressure. Also big leaks
can be observed as flooding of the pipeline route with the help of surveillance camera systems.
Concrete pipes can be affected from aggressive water and aggressive soils, which cause internal and
external corrosion resulting in cracks. Additionally cathodic protection for steel pipes is necessary to
prevent corrosion.
Another type of water loss is the loss occurring at the water treatment plants. Some amount
of water is inevitably lost during the treatment process however; it may be reduced by using more
developed treatment actions. Butler (2000) states 2 – 3 % to 7 % water can be lost during the
24
treatment process.
Water storage tanks in the water distribution system can be considered as sources. Losses that
occur in storage tanks can be water leaks through the walls or spilling of water due to overflows.
Leaks in the walls of storage tanks can be eliminated by constructing strong structures having water
isolation. Also during regular cleaning studies, impermeability of the walls should be checked by
standard tests. Spilling of water can be prevented by monitoring water levels from SCADA systems.
Number of working pumps can be decreased or shut down completely according to the water levels in
the storage tanks.
4.2.2. Leaks Occurring in the Network Elements
Leaks inside a water distribution system occurs more on different elements of the system. As
there are many different types of materials and much longer pipes in total are connected to each other,
a greater risk of making errors is valid inside the distribution system. Every singular pipe, every joint
between pipes, every service lines connected to the network and every fitting in the network is a
potential point for water leaks.
Pipes in the distribution network can be examined as transmission mains, distribution lines
and service pipes. These pipes serving each a different purpose are connected to each other according
to a predefined project. In general, in transmission lines prestressed concrete, ductile iron, steel or PE
pipes are used. When distribution networks are considered, generally ductile iron, steel, asbestos
cement, PE or PVC pipes are preferred. For service connections to the customers, usually galvanized
iron or PE pipes are used. With such a variety of materials, high quality joint pieces should be used for
making connections between them. Workmanship is another important issue. Good workmanship has
to be combined with good quality of materials in order to obtain a leak-free water distribution system.
Rubber gaskets are inevitable pieces between every pipe and fittings. When installed
properly, they guarantee a non-leaking connection between the pieces. Also during construction of
any type of pipe, bedding and backfilling materials should meet the required standards in order not to
harm the pipes as they are going to stay buried under heavy loads for many years.
Pipe joint elements such as tees and elbows are again elements similar to pipes. Only their
job in the system is different. They should be installed with good quality material and good
workmanship. Concrete thrust blocks are effective and cheap solutions for joint pieces to keep their
positions with pressurized water in them.
Fittings in the water distribution networks are other sources for leaks. These fittings include
mainly stop taps, fire hydrants and valves. Regular maintenance should be performed on every fitting,
and they have to be renewed whenever they are found leaking.
Stop taps are pieces mounted at the end of dead end pipes. They should be installed tightly
25
always using rubber gaskets. If a flanged pipe is considered, bolts and nuts have to be tightly installed,
if a pipe with sockets (such as ductile iron pipes) is used, then concrete thrust blocks should be used to
ensure the plugs are connected to the system and stay fluid-tight.
Fire hydrants can be a source for leaks as they are the most suitable pieces that are open to
external interferences. They have to be protected from unauthorized people, traffic accidents etc. To
prevent unauthorized use, hydrants should be kept tightly shut and a valve should be present on the
pipe connecting the hydrant to the network. By this way, without opening two consecutive valves, fire
hydrants will not work.
Valves are important fittings in a water distribution system, enabling control over the pipes.
They have to be regularly checked and kept ready for usage at all times. Every installation standards
mentioned above are valid for valves. Valves should not only be leaking water outside the system but
also they should not be working against the operators actions. When a valve is completely closed, it
should not let any water passing through itself. Similarly, when a valve is completely open, it should
work as a section of regular pipe, without having any effect on the flow. Therefore, valve status has to
be known for each valve (whether they are fully open, fully closed or partially open). Periodic valve
operations (opening and closing) may be helpful on determining faulty valves, but it may not be an
economic decision to replace every faulty valve. However, critical valves, such as valves at pressure
zone borders and district metered area (DMA) borders, should be kept in perfectly working
conditions.
4.3.
Factors Affecting Leakage
Leaks occurring in a water distribution system may be caused by internal factors from the
network itself or external factors from the environment. Under this section various factors will be
studied such as pressure, hole size, leak duration, pipe material, aging of pipes, workmanship, network
design, soil types and water quality.
4.3.1. Pressure
Pressure is one of the most important factors that affect leakage. It is the governing factor
affecting rate of leaks with hole size. If pressure in the system is high, then leaks are flowing more.
Therefore, to decrease leak rates, the first thing most water administrations think is to decrease system
pressures. However, decreasing pressures heavily depend on the topography of the water supply area.
Then, pressure reduction will be restricted up to a particular value. Critical points in the network such
as points at the highest elevations or places that use high amount of water with some minimum inlet
pressure will define the restriction of pressure decrease. However, in places that do not have steep
26
topographic differences, big decreases in pressure can be made. By only that way amount of water lost
through leaks will decrease significantly. Case studies in Chapter 6 gives detailed information and
examples about effects of pressure reduction on water leaks.
Sudden increases in pressure can also be considered as a factor affecting leakage. Most
sudden increases in pressures are caused from transient events. Sudden opening or closing of valves,
quick filling of the empty network after repair works can be harmful to the system and can increase
leaks in the network.
4.3.2. Hole Size
Naturally, bigger holes cause higher leak amounts. Big hole sizes combined with high
pressure cause the most leaks. However, smaller hole sized leaks cause more frictional loss while
water is flowing out, so they are better recognized by acoustic devices and located easier.
Hole sizes occurring in the pipes get bigger through time depending on parameters like
pressure and pipe material. So when a very small hole is generated in the system, it gets bigger with
time causing more amount of water to be wasted.
Another thing in the hole sizes is that they are not necessarily regular shaped holes.
Discovering irregular shaped holes in the pipes makes estimation of loss amounts harder. Using
approximate values for loss amount estimation can be made.
4.3.3. Leak Duration
Leak duration covering all the time that the leak is flowing is an important factor. Leaks
discovered early causes small harms, but leaks discovered after many months or years from its
occurrence cause water loss and increases whole size in time, which will cause more loss.
4.3.4. Pipe Material
Every pipe material has its own advantages and disadvantages. Their leak-effecting factor is
also different from one material to another.
Asbestos cement pipes can be considered as old pipes and they have been or being replaced
with modern materials nowadays. However, in some water distribution systems, they are still present
in some networks. As asbestos cement is a very brittle material, pipes made from it are open to cracks.
Cracks in asbestos cement can be repaired with collar repair clamps quickly. However, usage of such
27
hardware fixes the problem temporarily. That fixed point remains as a weak spot on the network. For
a permanent solution, the entire asbestos cement pipeline should be replaced with a better material.
Prestressed concrete pipes carry similar material properties; however, they are stronger to
cracks than asbestos cement as they include reinforcement bars inside. These kinds of pipes may
suffer from sulfate attack caused due to sulfate amount in the water. Within time, these pipes will be
corroded from inside and outside it they are not protected enough from outer effects.
Steel pipes have a very wide range from the tiniest diameter to the largest diameter. Their
main weak point for leaks is the absence of cathodic protection. If appropriate cathodic protection is
not applied to the steel pipes, as they are being installed, they are going to be corroded quickly and
formation of holes will be inevitable. Additionally welding workmanship can create weak spots and
affect leaks in the future.
Galvanized iron pipes can also be considered as old pipes and they are very open to
formation of holes. The galvanized protection does protect the pipe from external corrosion to some
degree. Moreover, after the protection is over, any hole or crack formed on the pipe will quickly get
worse with time.
PVC pipes are cheap pipes for water distribution and they are very easy to install. In addition,
they are durable to corrosion. However, they are weak against any external force. So they are easily
damaged with excavation machinery. Cracks are easily formed in PVC pipes causing leakage.
PE pipes are used in a very wide range of diameters for a very wide range of purposes. These
pipes are again durable to corrosion but they may have weak spots on “push fit” connections to other
pipes. With cheap material and workmanship, it is certain to have leaking spots in PE pipes.
Ductile iron pipes are very popular pipeline materials in varying diameters. When installed
correctly, they are durable to internal corrosion with cement lining inside and external corrosion with
the coating. They are easy to install but become expensive on very large diameters. Whenever they are
not installed according to the standards defined, they become weak and can leak from pipe
connections or fitting spots. Therefore, as valid for every type of pipe, high quality workmanship and
material should be essential.
4.3.5. Aging of Pipes
As water distribution systems are designed according to projected population’s usages for
tens of years from the construction date, installed pipes are going to get older and deteriorate.
Therefore, it can be generalized that older pipes may cause more leaks than new pipes.
Stronger pipe materials can be preferred for durability against time. PE pipes and ductile iron
pipes are being preferred for high durability to time effects as long as they are installed with proper
28
workmanship.
To decrease the effects of aging, renewing of the old pipes, broken valves and other elements
should be scheduled. Every year a percentage of network renewal should be programmed.
4.3.6. Workmanship
As stated before, workmanship and material quality play complementary roles when leaks are
considered. Good workmanship and high quality materials should be combined to prevent leakages.
At the absence of any of the two, weak spots in the network are probably generated. For good
workmanship, skilled workers and apprentices should be employed. Apart from skills, workers should
have a good technical knowledge about the repair works.
Workmanship is also crucial when new pipes are being installed. If good workmanship is
applied, problems at the beginning of the installment are minimized, leaving less problems to future.
Additionally, pipe transporting to site, stacking, laying the pipes, bedding with appropriate material
and backfilling all depend on good workers. As a result, water administrations should not employ
cheap and inexperienced workers at any stage of water works.
4.3.7. Network Design
Water distribution networks are designed before construction and construction drawings are
generated generally in 1/1000 scale. During construction, these drawings usually cannot be applied on
the field completely. According to construction difficulties faced in the field, some changes in the
original drawings are made and as built drawings are drawn which represents the actual constructions
made. During this process, original network design is changed, and in the constructed system, there
might be critical points in terms of leakage, which are not present in the original design. For example,
if looping network is changed into branching network, some high pressure points can be generated
resulting in more leaks.
Another thing concerning the network design is that during construction stage, all different
infrastructure elements (telecommunication, electricity, natural gas, fiber optics, drinking water,
wastewater, rainwater, etc.) should be installed leaving a distance (in both horizontal and vertical)
between them. By this way when excavating for any purpose water pipes are less damaged. However,
if different infrastructure elements are installed at very close distances to each other, it will be
inevitable to harm the lines during excavation. Unfortunately, it is a fact that relatively new
infrastructure elements can be laid just on top of the previously laid infrastructure systems. For
example, natural gas pipelines can be just on top of wastewater lines or drinking water lines. This is
because, during very first installments in such an area, ground is excavated and backfilled with soft
29
material. Other firms working at the same route prefer to excavate the exact same location with the
previous pipeline in order not to excavate hard soil and lay down the pipes quicker. This can be
considered as a cheap workmanship example as well.
Plastic marker tapes laid along the pipe are widely used in the field that warns the excavator
before reaching to the pipe. Additionally Butler (2000) suggests using metallic strips inside these
markers for locating plastic pipes using utility locators. When water pipes are located with good
accuracy (both position and depth), less leaks will occur during excavation for pipelines.
4.3.8. Soil Types
Soil types are also important factors when leaks in pipes are considered. Aggressive soil
types can cause external corrosion to pipes. As a result, holes, cracks and various other types of
damages can occur. During planning phase, detailed soil surveys should be conducted to have the
knowledge about the soil types in the region. Then appropriate pipe materials and backfill materials
can be defined to satisfy a strong water distribution system having minimum amount of leaks caused
by soil effects.
4.3.9. Water Quality
Quality of water inside the distribution network can be a pipe-weakening factor. Various
materials in the water can cause internal corrosion to metallic pipes. In addition, on dead end pipelines
water can remain still due to low consumption. In such cases, water quality drops considerably, and
rusting of metallic pipes can be accelerated. To prevent these kinds of water quality issues, periodic
flushing activities should be performed in the network.
4.4.
Controlling Water Leakages
Leak management is considered as a long-term study worldwide. It is not a process done a
few times throughout the lifetime of a water distribution network. Leak management is a process that
has to be run simultaneously with the operating of network from the beginning without waiting the
network to weaken.
Forming and evaluating manageable district metered areas and measuring inflow water is
crucial for leak management studies. While DMA is being formed, missing fittings are discovered,
unknown connections are found, missing projects are found and an up to date overall project is
generated. During these operations already, possibly water losses will be found at a certain extent
30
(such as leaks, missing and unknown connections between DMAs and pressure zones, etc.).
Water leaks can be controlled by means of separate or combined strategies that use two
approaches. These two approaches are named as “Passive Leak Control” and “Active Leak Control”.
Either of the two can be applied according to the water administration’s needs; however, for an
effective leak control strategy, the two approaches should be applied to the field in different ratios,
which meet the administration’s demands.
4.4.1. Passive Leak Control (PLC)
Leaks occurring in the network not visible and their effects are not easily recognized as long
as they do not reach to the surface and harm people in some way. As soon as a leak grows big enough
to show itself on the ground, or flood somebody’s property, the necessity of locating and fixing the
burst comes up. Leaks do not necessarily harm some place by flooding. They might show their effect
as low-pressure problems or having no water above some floors in an apartment. These “big enough”
bursts are reported either by the customers, or by the administrative staff to the leak detection crew.
Passive leak control comes into picture at this stage. It can be defined as detecting leakages
depending on the reported burst events. Action taken contains only repair of observed bursts and
elimination of low-pressure problems of related customers. Only customer reports of house flooding
events, inadequate pressure problems and similar reports are focused on.
Smaller leaks that do not harm any customer remain below the ground until they are big
enough to start giving damage. Small leaks can remain hidden for months or even years. As
undetected leaks, water lost through them constitutes a huge amount when awareness time is extended
to years.
In simple words, PLC is chasing big leaks after they have given enough harm and made
themselves visible. Its main disadvantage is, leaks are detected after big amounts of water are lost.
However, it may be a cheap solution if there is a plenty of water sources that are enough for customer
demands and water losses. Apart from water sources, if water production cost is very cheap, if bursts
are found out easily and quickly, searching for leaks in an active manner may not be feasible.
However, it should be noted that, by applying passive leak control, it would be a difficult task to
decrease the overall water loss amounts. Conversely, overall water loss amounts will possibly tend to
increase with the growing city, increasing population and water demands.
31
4.4.2. Active Leak Control (ALC)
Unlike PLC, active leak control is a collection of methods applied on a formed and evaluated
DMA. In general, flows in the DMAs are monitored and sudden, unexpected increases in flow are
searched for. Whenever these kinds of changes occur, leak detection surveys are done inside the
borders of the DMA. This activity of continual searching for water leakages (mostly bursts) is done
using acoustic and electronic devices. These devices are listening rods, ground microphones, digital
correlators, leak noise loggers and so on.
With the help of active leak control methods, big bursts that do not reach above the ground
surface can be easily detected depending on the instrumentation. Additionally, even small background
leaks are detected and pinpointed with this method. As a result, all the “detectable leaks” are found
and fixed in the DMA. However, there are limits that a leak could be found with these methods. Butler
(2000) states; in the UK, 55 l/property/day is the acceptable level of leakage. Trying to find leaks
beyond this point is not considered as economic solutions. He also defines an undetectable leakage
level as 30 l/property/day. It is the ultimate level that leaks can be decreased in a water distribution
network using today’s technical equipment (unavoidable night flow).
ALC is effective up to some extent when applied alone. When bursts are found and fixed in a
system, pressures will increase in the system. This increase will generate new bursts or background
leaks at various parts of the network. Therefore, ALC should not be applied only once to the network.
It should be applied to the network within a schedule. Weekly, monthly or yearly repetitions of ALC
studies may be a good idea depending on the properties of the network.
To decrease the happening of new background leaks, pressure management studies should be
run with ALC cooperatively. With pressure management (mostly reducing excess pressure in the
system where possible), generation of background leaks can be slowed down or totally avoided.
Pressure reduction in a network decreases the volume of wasted water as well as the rate of leak
growth. With lower pressure, fewer leaks will be generated with time in the network.
ALC requires the administration to spend money on possible constructions for DMA
formation, leak detection instruments and to make effort to locate and fix the leaks. The effort
includes training staff and giving the staff up to date information of new technology. As the process is
an expensive investment at the beginning, some DMAs should have higher priority than the others
should. For instance, DMAs that are fed by pumping should be investigated before DMAs that are fed
by gravity pipelines. That means water lost at higher elevations are more valuable than lower
elevations considering electricity costs.
After applying ALC, less water is supplied to the DMA so resources and energy costs are
saved. Applying ALC is reasonable when resources are limited, water production costs are high and
bursts cannot be detected by visual inspection only.
For both PLC and ALC, a water administration should form a specially trained team. This
32
team should have the knowledge of using various equipments like water meters, data loggers and
ground microphones. However forming a leak detection team would be insufficient, as the job
requires different sources of data from different departments of the administration. Various
departments therefore should work cooperatively letting their data to be used by anyone. These
departments in a typical water administration are GIS, SCADA, project developing, IT, customer
relations and operations’ departments.
33
CHAPTER 5
5. DEVELOPING THE METHODOLOGY
Before applying the methodology for locating water losses in a water distribution network,
some minimal requirements should be satisfied. These requirements involve detailed studies on
projects, investigations on field, construction works, training staff and many more subjects.
Formation of a water distribution system goes through some essential phases like master
planning, feasibility studies, rehabilitation studies, final design and construction. The resulting system
is usually handed on to operations department. The work from now on is to operate the existing
system, dealing with new consumers, repairing the failures and performing any kind of maintenance
work including leak detection.
In these general phases of events, a perfect system in every aspect is impossible to create. In
any phase, due to any reason a change in the ideal system can be made. However, for an effective
study against water leakages, all kinds of uncertainties have to be minimized. In simpler words, every
detail in the water distribution system should be known precisely from master planning phase to
operating phase. The ultimate objective is to trace any water drop from the source at the very
beginning of the system to the taps of customers where it is consumed. It is possible only by having a
water distribution system that is totally under control. To achieve this goal, simple but important steps
should be followed. These steps are briefly discussed below.
•
Pressure zone borders have to be defined clearly (Figure 5.1). If any change in the pressure
zone borders is to be made, it should not be made by combining zones having two different
pressures but extending one zone up to the needed point. Defining pressure zone borders is
crucial because they are the most suitable parts of the water distribution system that are open
to exploits. In any case of low pressure problems, constructing new connections from an
34
upper pressure zone is used as the most practical solution. Changing pressure zone borders is
one of the most harmful actions against a controlled water distribution network.
•
The modern requirement of having SCADA, GIS and CIS is essential for a controlled water
distribution system. SCADA is a must for measuring pressures and discharges at various
points, GIS is necessary for having an up to date knowledge of the system elements (pipes,
fittings, pumps, tanks, etc.) and CIS is needed for keeping the customer records regularly.
With these three elements integrated together, a totally controlled water distribution system
can be easily achieved.
Figure 5.1 Defining Pressure Zone Boundaries
•
To have a controlled water distribution system, it is necessary to know every element in
detail. By analogy, this goal is similar to a tree, from the roots and the body, then to the
branches and lastly the leaves of the tree. For the water distribution system elements, firstly
pumps, main transmission lines (with every fitting on them) and water storage tanks should
be precisely known. As a second step, distribution network should be known in detail with
every fitting on them (Figure 5.2). Lastly, service pipes and customer locations should be
known. These records are preferably kept in GIS environment. Keeping these data up to date
is crucial for a controlled network. Every change in the field has to be quickly reflected to the
35
related GIS layers with enough accuracy.
•
Unknown connections (connections physically existing in the network, but not drawn on asbuilt projects) should never exist in the system. Unknown connections between networks
(whether in the same zone or not) should be discovered and recorded. Having unknown
connections at any point in the network means studying a theoretical network depending on
official records, which behaves completely different from the actual state on the streets. As a
result, observations and measurements obtained from field would not meet theoretical studies
done at the office.
Figure 5.2 Controlling Pumps, Tanks, Transmission and Distribution Pipes
•
After detecting the routes of transmission lines, distribution network pipes with their fittings
and service connection pipes, pressure zone borders should be defined with precision. The
required precision is at building level (Figure 5.3). Every building (covering the customers
inside) must be known with their pressure zones. Customers inside the borders of a pressure
zone may be easy to determine but customers near the borders of the zone is harder to
investigate. With this step, every building is assigned a pressure zone, therefore the reflection
of any action done on the pressure zones is known in building level.
36
Figure 5.3 Assigning Each Customer a Pressure Zone
Upon completing the most necessary actions stated above, district metered areas can be
•
formed for the purpose of water leak detection. The procedure is explained in Section 5.1.
The major purpose of completing the tasks for a controlled water distribution network is to
clarify the mysteries that lie under the ground. When the infrastructure is known well enough, the
working system is known in detail. Knowing the system in detail lets the water administration act
consciously. Only conscious actions done on a working system leads the administration to its goals.
If the administration does not make its choices consciously, in any stage of water leak
detection studies surprises may occur. These surprises usually slow down the studies, make all
planned actions invalid and force them to be planned from scratch. The surprise events can be
exemplified by unknown pipes in use, unknown cancelled pipes, old pipes that are not known either
they are in use, unknown valves that are left closed, incomplete or wrong customer databases,
measuring devices working improperly and so on.
5.1.
Formation and Evaluation of District Metered Areas (DMA)
Every leak occurring in a water distribution network can be defined as a unique case. Type of
the network, material of the pipes, workmanship, soil type of the region and operating pressures are
just some of the uncertainties that can make the case unique. In order to take action against these kinds
37
of unique cases, proper, standardized, methodological steps must be followed. When designed and
applied properly, these steps will certainly be helpful for preventing water losses.
As a simple fact, precise and routine metering at predefined points (preferably at the
entrances of isolated regions) should be the first step for water utilities to start dealing with water loss.
Flows must be accurately measured in the distribution network for the grand purpose of tracing the
input water from the source to the consumer. Most of the time, metering is only done in two stages of
the water distribution cycle. First metering is done at the water treatment plant, where the treated
water is supplied to the system and last metering is done at the consumers at the billing stage. It seems
that there are no middle stages, but there should be. Without having any middle metering stages, any
calculated lost water will be the representative amount for the whole distribution network area. To
decide where to focus on the network, considering the losses, middle metering points should be
established between the source and the consumers.
Forming district-metered areas (DMA) will guide the water utilities to decide to focus on
smaller segments of their distribution networks. By these establishments, water utilities will have the
opportunity to watch over their networks not just as a big one-piece mechanism but also as a big
mechanism that consists of several smaller living parts. Metering of the DMAs, continuously with
SCADA systems or by routine metering with portable equipment helps the water utility to take control
over the metered area.
DMA realizations should have some limitations in size. DMAs that are small in size but large
in quantity may have a high initial cost to the water utility, but controlling smaller DMAs may be
easier. On the other hand, large sized DMAs will have low initial cost. However, as the area gets
larger in size to take control over the area will be harder. There is not a single valid limitation for
DMAs. The necessary DMA formation rules should define lower and upper boundaries. These
boundaries may be in terms of area, pipe length or number of consumers. In some cases, natural
topographic limitations may force the utility for a DMA design.
Butler (2000) gives typical DMA sizes in UK in terms of property counts. The given
limitation is areas having properties between 1000 and 5000. This can be used as a guideline for
limiting the size of the DMAs. Assuming every property having 5 people living, the limits become
5000 to 25000 people. DMAs containing properties less than 1000 mean too small areas. When the
area gets smaller, it will be easier to manage the water losses, and every detail in the network could be
better investigated. On the other hand possibly too many dead ends will be created in the network.
Water quality will be adversely affected due to still water in the dead ends. Also the initial investment
cost will increase if permanent measuring stations are established for each DMA. When DMAs
contain more than 5000 properties, the area becomes too big to manage. It will take too much time to
scan the area for water losses. In addition, it will be easy to miss the unknowns in the network
(unknown connections, forgotten valves left closed, etc.). However, less dead end points will be
created and less initial investments will be done. The basic thing is, when the DMA gets larger, it will
be harder to find and locate singular, small water leak spots.
38
At the absence of population and building number data, DMA sizes can be defined
considering the lengths of distribution network pipes. However, if the region is a developing region
where settlements are still taking place, considering lengths of pipes for the definition of the size of
the DMA can mislead the designer. If an example in terms of pipe lengths is to be given; DMA’s total
pipe lengths should not be less than 5000 meters and should not exceed 25000 meters.
DMA formation can be studied in two points of view. One is forming the DMA before the
construction of the water distribution network. The other is to divide and isolate the divisions in an
existing water distribution network to form DMA.
The first one includes classical design procedures of a distribution network. In the design
process of a water distribution network, a branching type of network is suitable for DMA formation
purposes. However, due to quality aspects in dead end pipes, branching type of networks are
disadvantageous choices. Grid types of networks are better choices instead of branching type of
networks. Circulating water in this type of networks removes the drawbacks of the water quality, but
as the network is designed in a loop type, DMA formation has to be done with valve closing
operations in order to divide the area into smaller areas. This may have some disadvantages while the
operations are applied to the field like, not properly working isolation valves or unknown connections
(pipes and/or valves) within the network.
Second point of view deals with DMA formation in existing networks. As stated above the
existing network will be either in the form of a branching system, a grid system or a combination of
these two.
The solution for purely branching systems may be to make each and every branch a DMA
(measuring at points A and B), which may be an expensive solution, or place metering points at some
predefined points on the water distribution mains and use differences between these metered values
for the branches between metering points (at points C, D and E). An example for this case can be seen
in Figure 5.4. As a rule of thumb, forming a DMA can be stated as drawing a closed border around the
network without crossing any of the pipes; except the pipe that is both the starting and ending point.
39
Figure 5.4 Forming DMA in a Branching Network
When it comes to form DMA regions in a grid or a grid and branch combined system, valves
and their locations on the network becomes extra important. In this case valve places are important
because they are used (by closing or opening) to isolate smaller pieces from the big area. In this case,
the rule of thumb stated above is still valid with the inclusion of rule to allow crossing the network
only at valve points meaning that the crossed valves will stay closed to form the DMA. A sample
DMA formation for grid systems can be seen in Figure 5.5. Measuring points are located at A and B.
The advantage is ability to define different DMA areas by a few valve operations. The disadvantage
may rise in a hydraulics problem in which the defined and applied DMA may suffer from low water
pressures in peak consumption hours. The main reason for this is that while applying the DMA, the
designer chooses a one-pipe-fed system, so that the metering location would be on that only pipe that
feeds the DMA. If the diameter of the main feeding pipe is not large enough to feed the DMA after
itself or if water is forced to follow a path with a high-energy loss; some customers will face lowpressure issues. The solution to this problem can be found in defining the DMAs only for short terms.
Here, short term is defined as applying the DMA and necessary valve operations only for the hours of
minimum usage (mainly night hours until early morning) while actively working on the field for leak
detection. DMAs that are not suffering this kind of problems can be left as permanent areas, so need
for valve operations becomes unnecessary.
40
Figure 5.5 Forming DMA in a Branching Network in a Grid Network
A procedure to be followed for DMA formation can be given like this:
•
Clearly identify the transmission mains and their branching points to the secondary pipes.
•
Obtain maximum knowledge about paths of the secondary pipes and the valves placed on
them.
•
Keep all valves in operating condition.
•
Define the desired limits for DMA size.
•
Use the largest diameter branching pipe as the entrance for the aimed DMA.
•
Draw the borders of the DMA around the area within the desired size by crossing pipes only
on the points of isolation valves.
•
Place the discharge-metering device (water meter) on the entrance branch pipe.
•
Keep the isolation valves closed whenever DMA is in use.
A valve at the entrance of the area can be useful for testing the validity of the DMA. After
isolating the area from the rest of the network, the entrance valve can be closed and the area can be
observed if there is an unknown source entering the system. Normally with this operation all the
consumers should have a shortage of water within some time. This means that the border drawn in
office is valid on the field too. If there are some consumers still not affected from closing of the
entrance valve, it shows either an isolation problem or an unknown connection from neighbouring
zones.
Another useful method for testing isolated DMAs can be taking pressure readings along the
41
borders of two neighbouring areas. To see a difference between neighbouring zones, they have to be
in different pressure zones. At the end, it will be seen that at one side of the border a set of similar
pressure readings are read (maybe high values), on the other side of the border another set of similar
pressure readings are read (conversely low values).
5.2.
Measuring Daily Demand Curves of the DMA
The major aim to form district-metered areas in water distribution networks is to measure the
flow entering to that area. Only measuring night flows can be useful for leak detection but at least
measurement of a whole day gives a daily consumption data about the isolated area. From the daily
consumption data, graph of the consumption, commonly referred as a daily demand curve can be
drawn. This curve clearly indicates the amount of water that is given to the DMA with respect to time.
From the shape of the graph, consumption pattern of the region can be seen. By analyzing the pattern,
water usage characteristics of the area can be seen. These characteristics differ from one DMA to
other, as the people living in different DMAs have different habits of water usage. Many different
aspects can be listed for different usage habits, like socioeconomic status of residents, whether the
area is a residential area, a commercial area, or a hospital region etc.
For a typical residential DMA, it may expected to have a two peaked daily demand curve,
one peak in the morning when the residents wake up and go to work and one peak in the afternoon
when the residents return to their houses from work. Of course, these patterns do not have to be exact
copies of one another for different days, but for a correct measurement of a daily demand curve, the
pattern of the graph is not expected to show a big change unless an event affecting the water usage
habits occurs.
In water loss studies daily demand curves are used extensively but especially late night
measurements of the curve is searched for. For a typical residential district, night flow values entering
to the district decreases to a minimal level, between mostly 02:00 and 04:00 a.m. In Figure 5.6 a
conceptual drawing for a minimum night flow is given. This conceptual minimum level is usually
taken into consideration to have an idea about the water leaks (Area B).
42
Figure 5.6 Sample Daily Demand Curve Showing Minimum Night Flow in a Residential Area
Above explained minimal level can be called as minimum night flow and in an ideal, leak
free zone it is zero (Figure 5.7). This ideal situation is believed to be reached when nobody consumes
any drop of water for a time period at night. An ideal situation told above is never reached in reality.
Water flowing into the isolated and metered area does not drop below a level. Mostly this minimum
night flow is considered as the sum of leaks in the area if there are not any significant night users.
43
Figure 5.7 Sample Daily Demand Curve Showing Zero Minimum Night Flow
By obtaining the daily demand curves of different DMAs, their minimum night flow amount
can be divided to the average daily consumption value to define a leakage percentage. Among these
values, greater ones should have higher priorities for leak detection studies compared to DMAs having
small leakage percentages.
Different approaches for defining a leakage percentage may be normalizing the minimum
night flow with number of people living in the DMA or sum of lengths of the pipe network of the
interested area.
After fixing the leaks in a DMA, a decrease in the daily demand curve will be observed.
Normally minimum night flow values will be decreased. These decreased values should be observed
routinely to see when there will be new leaks occurring in the area. Every DMA should have its own
characteristic minimum night flow value to be observed carefully.
As stated above, the minimum night flow values are decreased to zero only in theoretical
ideal conditions. In reality very little leaks (i.e. dripping water within the system) will be in the system
all of the time. These very little leaks will be too hard and costly to find and fix so they are left to flow
freely out from the system. Their cumulative amount will form the minimum unavoidable night flow
(See Section 4.4.2).
Another fact is that the minimum night flow line is not a constant line throughout the day.
Theoretically, it must rise a bit at night hours due to decreasing consumption and increasing overall
system pressure. Similarly, it must decrease a little at peak consumption hours as the overall system
44
pressure decreases. Therefore, this parameter is directly related with network’s pressure (Figure 5.8).
The curve shown as “Real Water Loss Curve” indicates the representative curve of water losses
changing due to pressure variation during the day. “Idealized Water Loss Level” is on the other hand,
is the simplified level of water losses. Pressure changes effecting losses during the day is not taken
into account for this line. However, by taking 24-hour pressure measurement samples in the network,
it may be possible to generate a model for real water loss changes during the day. Among this study,
the variation of leaks will not be taken into account and assumed constant during the day.
Figure 5.8 Conceptual Curves Showing Real and Idealized Water Loss Amounts
5.3.
Sub-DMA Formation
Dividing DMAs into smaller regions using valves can be used to determine the starting point
for water leak detection. In practice, the DMA is divided into smaller sub-DMAs, which consist of
only a few streets. Therefore, with operations like step testing, it might be possible to choose the
weakest places of the DMA. This step can be preferred for quick analysis of large DMA areas where
maximum benefit is aimed within limited time.
Sub-DMAs are formed just like forming DMAs. In an arbitrary DMA, a looping pipe with
preferably a larger diameter from the rest of the pipes can be seen as a transmission line. Next, the
necessary areas are defined by drawing the border over the isolation valves that are going to stay
45
closed at least on metering times. It should be carefully checked that unknown connections should not
exist between isolated sub-DMAs. In such a case, it is not possible to form the needed isolated area.
An example for a sub-DMA can be seen in Figure 5.9. Sub-DMA borders, isolation valves to be
closed in order to isolate A07 from A02, A03, A08 and controlling valve at the entrance of sub-DMA
are seen in the Figure 5.9.
Figure 5.9 Example Formation of a sub-DMA
Purpose of forming sub-DMAs is to perform some tests to define which part of the DMA is
weaker in terms of water loss. This method can be useful when the metered area is too large and
equipment and workforce is limited. So instead of losing precious time examining parts of the
network that the operator is not sure whether there is leakage or not, certainly leaking parts of the
network is focused on.
Forming sub-DMAs inside a DMA may have advantages in terms of taking control over the
network. Keeping a valve just behind the sub-DMA entrance enables the field operator to control a
few street pipes by using only one valve.
To use one valve to control a whole DMA requires little investment and maintenance as there
is only one valve to keep an eye on. This provides a superficial control over the network of the DMA.
This means that only rough experimental actions can be applied to the network (shutting the whole
DMA). When sub-DMAs are formed, all the necessary valves behind sub-DMA entrances should be
kept usable. This step requires more investment and maintenance. However, a better level of control
46
over the network is provided. As a result, much more flexible operations over the network may
become available (shutting any combinations of sub areas inside the DMA). If an ultimate degree of
control is required over the network, all of the valves at each street intersection should be kept usable.
It requires much more time, money and human resources to keep the valves ready for action. As a
result, an in depth control over the network is guaranteed, meaning very precise operational actions
over the network can be made (shutting any street level pipe combinations). The three different
situations can be explained with fictitious valve numbers.
Low Control (1/50 valve): If a DMA is known to have 50 valves installed, but only the main
valve at the entrance is kept ready for usage it is an example for the first situation. In this case only
shutting the whole DMA can be performed. Step tests and sub-DMA formation is impossible.
Medium Control (20/50 valve): This is the situation when only the boundary valves between
sub-DMAs are kept working. It may be any number between 1 and 50 but to be similar with the case
study it is given as 20 of the 50 valves are being used. In this case, a few sub-DMA regions can be
defined, and step tests can be performed. Sub-DMAs can be shut down without disturbing other parts
of the DMA.
High Control (50/50 valve): Each water distribution network should reach this ideal situation.
In this case, all of the installed valves are being used. It enables the operator to generate numerous
different sub-DMA combinations. Step tests are still valid. Moreover, one of the most useful aspects is
to shut down only pipes at street level even without disturbing the neighboring street.
Sub-DMA formation concept can be ignored by some water loss operators that do not prefer
to prioritize the area instead prefer to search for leaks covering the whole area.
5.4. Calculating Water Loss Percentages
Water loss percentages can be calculated from two different points of view. One of them is to
integrate SCADA and CIS data to calculate the monthly revenue amounts. It is a monthly based
calculation considering several assumptions. The second point of view is to calculate the water loss
percentage by using only daily demand curves obtained from SCADA systems or other devices. This
second method can be applied daily. Theoretically, the percentages that are going to be explained in
Sections 5.4.1 and 5.4.2 have to be equal. However due to errors in the data and assumptions made in
calculations, these two values show a variation. Table 4.1 formed by International Water Association
(IWA) can provide the schema for organization of the consumption records and water loss percentage
calculations.
Considering Figure 5.10, the parallelism between the two approaches may be clearly
explained. In the figure, Q represents the monthly volume of water flowing into the DMA, q1, q2 and
q3 represent the monthly volumes of consumptions of the customers in the DMA and q4 represents
47
the monthly total volume of water loss due to leakages. For simplicity, water meter errors and reading
inaccuracies can be ignored; therefore, those errors are all added to q4. If they are not ignored then, all
errors should be considered in the meter readings of the customers. Considering the given figure,
following equation can be written:
Q = q1 + q 2 + q3 + q 4
(5.1)
The above equation is based on monthly revenue aspect explained in Section 5.4.1.
Figure 5.10 Conceptual Drawing of a DMA with Water Movements
From the other approach, minimum night flow aspect, again Figure 5.10 is considered but for
simplicity, this time not in a monthly manner but in a daily manner. Of course, same procedure can be
applied in monthly manner. This time Q will represent the total volume of inflow through the day, q1,
q2 and q3 will represent the volumes of consumptions and q4 will represent the total volume of water
loss due to leakages. To show these values on the daily demand curve Figure 5.11 is given below. In
the figure, “q1+q2+q3” summation is the area between minimum night flow and the daily demand
curve. Due to changes in the usage through the day, different values are reached at different hours.
However, a constant level of water leakage keeps on flowing in the day. This leakage volume is
represented by “q4” and it can be investigated as the area under the minimum night flow. To sum up,
the addition of q1+q2+q3+q4 gives the total inflow into the DMA and still equation 5.1 is valid. The
value q4 represents the same physical quantity as a result.
In the next two sections calculation of water loss amounts from two different perspectives is
given.
48
35
Consumption (m³/hour)
30
25
20
15
10
5
Time
08:16:00
06:58:00
05:40:00
04:22:00
03:04:00
01:46:00
00:28:00
23:10:00
21:52:00
20:34:00
19:16:00
17:58:00
16:40:00
0
Figure 5.11 Conceptual Daily Demand Curve with Its Components
5.4.1. Monthly Revenue Aspect
While calculating water loss amounts considering monthly revenues, two sources of data
should be present. One of them is monthly consumption values for each customer in the DMA, the
other one is monthly continuous discharge measurements obtained usually from SCADA
measurements. It is the best to have a continuous SCADA discharge measurements for the month, to
see detailed changes in the consumption. However, to make the calculations, only cumulative
discharge values at the beginning and end of the month is sufficient. So, at the absence of SCADA
measurements, needed data (discharge index) can be collected with other types of devices such as a
turbine water meter (usually referred as Woltman type meters). With the turbine meter installed at the
entrance of the DMA, two readings must be taken from the indexes of the meter; one reading at the
beginning of the month and one at the end.
In order to make the calculations, data obtained from SCADA (or manual measurements) and
CIS have to be integrated. This integration is needed due to the limitation of CIS data. As
consumption readings are collected in monthly basis, continuous SCADA data has to be divided into
monthly slices.
In Figure 5.12 all possible irregularities that may occur during superimposing of SCADA
measurements and CIS readings. If monthly regular readings are taken from the customer meter, that
is the case that will generate minimum amount of error. For irregular monthly readings type I and II,
49
some amount of error will be introduced, as only one end does not overlap with SCADA measurement
period. In types III to VI, more amount of error is introduced because, two ends of the meter reading
period do not coincide with SCADA measurement periods.
Beginning of Month
End of Month
SCADA MEASUREMENT
Regular Monthly Reading
Irregular Monthly Reading Type I
Irregular Monthly Reading Type II
Irregular Monthly Reading Type III
Irregular Monthly Reading Type IV
Irregular Monthly Reading Type V
Irregular Monthly Reading Type VI
Error Generating Periods
Figure 5.12 All Possible Irregularities in Monthly Meter Readings
In the below formulations, qS1 and qS2 are denoted for cumulative SCADA measurement
indexes at beginning and ending points of the month (i.e. 5000 m3 and 10000 m3), tS1 and tS2 are
denoted for the beginning and ending points of the month determined from SCADA settings (i.e. 1
March 2010 at 00:00 a.m. and 31 March 2010 at 23:59p.m.). QS is then the difference between the
indexes, indicating the total inflow and TS is the duration of the month in terms of days.
QS = qS 2 − qS 1
(5.2)
TS = tS 2 − t S1
(5.3)
According to the given example values, QS becomes 5000 m3 and TS becomes 31 days. That
indicates that a total inflow of 5000 m3 has occurred in 31 days into the DMA.
50
Additionally, an IT parameter is defined to calculate daily average inflow to the DMA,
assuming that the inflow entering the DMA is same everyday throughout the month. Unit of IT is
m3/day.
IT = QS / TS
(5.4)
In Table 5.1 a sample for a CIS database is given. In the sample table, minimal required
fields are given as “Building ID”, “Customer ID” to identify the consumers, “DMA ID” to identify the
customers in a DMA from other DMAs, the beginning and ending days of the interested meter reading
periods and the consumption value of the interested period in meter cubes. As optional fields, any
kind of information for the customers can be added to the database. These fields are simply given as
“Various Information” in the table. These fields can include any kind of contact information of the
customer (address, telephone, etc.), water meter related data (ID, type, installation date, etc.), type of
the consumer (residential, school, hospital, public garden, etc.). After each reading period, newcollected consumption data is added to the database under three new columns. These columns will be
next periods first meter reading date (which will be the same date with previous periods last reading
date), last reading date and the consumption value.
Table 5.1 Typical Structure of a Customer Information System Database
Building
ID
Customer
ID
DMA
ID
Various
Information
500010
500010
500010
500011
500011
500012
500012
…
800001
800015
800020
800002
800255
800003
800365
…
5
5
5
5
5
5
5
…
…
…
…
…
…
…
…
…
March
Period
First Date
[tC11 … tCn1]
27.02.2010
27.02.2010
27.02.2010
05.03.2010
05.03.2010
01.03.2010
01.03.2010
…
March
Period
Last Date
[tC12 … tCn2]
28.03.2010
28.03.2010
28.03.2010
03.04.2010
03.04.2010
31.03.2010
31.03.2010
…
March
Consumption
(m3)
[qC1 … qCn]
30
12
23
40
8
50
19
…
…
…
…
…
…
…
…
…
…
To explain the consumers, qC1, qC2, qC3 … qCn are defined as the monthly meter readings for
each customer indicating their consumption in terms of m3 (i.e. 30 m3, 40 m3, 50 m3 …). Total number
of metered customers is denoted by n. tC11, tC12, tC21, tC22, tC31, tC32 … tCn1, tCn2 are the dates that
customer meters are being read by the administration staff. First index defines the customer and
second index defines whether the reading is done at the beginning of the month (corresponding to
previous month’s measurement) or at the end of the month. If the second index is 1 then it is the meter
reading date of previous month. If the index is 2 then the value is the meter reading date of the related
month (i.e. for 1st customer 27 February 2010 – 28 March 2010, for 2nd customer 5 March 2010 – 3
April 2010, for 3rd customer 1 March 2010 – 31 March 2010 …).
51
To calculate the monthly periods of each customer the below equations are used:
(5.5)
TC 2 = tC 22 − tC 21
(5.6)
TC 3 = tC 32 − tC 31
(5.7)
…
TC1 = tC12 − tC11
TCn = tCn 2 − tCn1
(5.8)
Then, the values given in the example lead to the results of; TC1 = 33 days, TC1 = 30 days and
TC1 = 31 days. Then parameters DC1, DC2, DC3 … DCn are defined. These D parameters will define the
daily average consumption of each customer depending on the assumption that everyday same volume
of water is consumed.
(5.9)
DC 2 = qC 2 / TC 2
(5.10)
DC 3 = qC 3 / TC 3
(5.11)
…
DC1 = qC1 / TC1
DCn = qCn / TCn
(5.12)
As a last step, the D parameters are added up to find the total average daily consumption of
the DMA. The resulting parameter is defined as DT. Similarly, the units of DC and DT parameters are
m3/day.
n
DT = ∑ DCi = DC1 + DC 2 + DC 3 + ... + DCn
(5.13)
i =1
At the final stage, the DT value is subtracted from IT to find the rate of water loss in terms of
m3/day.
WL = IT − DT
(5.14)
A percentage can be derived from the calculated value by:
52
WL (%) =
WL
× 100
IT
(5.15)
5.4.2. Minimum Night Flow Aspect
Considering Figure 5.11 as a sample daily demand curve, a water loss percentage for the
DMA can be calculated. On the graph minimum night flow line can be drawn horizontally ignoring
the effects of pressure changes. Another important thing to consider is to detect the DMA’s minimum
night flow hours. This is a period of time in which none of the consumers are using water. When that
time is reached the measured inflow value to the DMA will be the minimum night flow. The area
below minimum night flow line (q4) is the water loss amount during the day. To make a comparison
with the total water entering to the DMA (q1+q2+q3+q4), following formula is used:
WL(%) =
q4
× 100
q1 + q2 + q3 + q4
(5.16)
With this percentage, a realistic idea about the amount of water loss can be obtained. The
needed data can be obtained from SCADA records or manual daily flow measurements (with mobile
flowmeters, etc.). After obtaining water loss percentages for different DMAs, it is possible to see the
weakest DMA in terms of leaks.
The values found in 5.15 and 5.16 should be the same. However, due to various errors and
assumptions made before calculations, “WL” values differ from each other.
5.5.
Prioritizing the Sub-DMAs
After forming sub-DMAs, the number of areas to be controlled against water leaks increase.
The increased number of areas can make things complicated if an order of some kind is not given to
the areas. An order can be given to the sub-DMAs by a method called step test.
In step testing method, it is required to have an isolated DMA with its measuring point ready
to use at the entrance. In addition, DMA should be split into smaller sub-DMAs in order to prioritize
them. The test is applied usually at night hours (or whenever minimum daily usage occurs in that
particular DMA) while measuring the flow entering to the DMA. At the time when it is believed that
no water usage is occurring (that is when minimum night flow occurs), one of the sub-DMAs is shut
down with the help of its valve at the entrance pipe. By doing so, the water loss occurring in that sub-
53
DMA is precluded from the minimum night flow. By checking the measurement that is being
recorded at the DMA entrance, it is possible to determine the water loss amount in the area that has
just shut down. The discharge amount measured at the entrance will decrease to some level and that
decrease will be the amount of water that is being lost at the closed down sub-DMA. Keeping the first
sub-DMA closed, another sub-DMA is shut down and its effect will be seen in the measuring point
immediately. Without opening any of the previously closed valves, all the sub-DMAs are shut down
and their effects are recorded by checking the flowmeter at the DMA entrance. After closing all the
sub-DMAs, the flowmeter should read zero flow and this result will be compatible to the result that is
applied to the field. This result is; by closing all the necessary valves, all the users and the leaking
points are restrained from the source. At the end of the closing steps, a flow versus time data is
generated and it should look like Figure 5.13. The graph explains the amount of water loss occurring
in each of the sub-DMA like steps of a stair. In the sample graph, minimum night flow is 50 m³/hr. It
can be considered as the total loss of the DMA. By closing the first sub-DMAs, loss of the remaining
sections reduces to 40m³/hr. It indicates that water loss occurring in the first sub-DMA is 10m³/hr.
Each reduction in the graph will reflect the loss occurring in the related sub-DMA. A prioritization
among the sub-DMAs can be done by the data obtained in the closing steps. Highest water loss
detected sub-DMAs should have a higher priority when searching for leaks.
Step Test - Closing Process
3
60
Discharge (m /hr)
50
40
30
20
10
01:00
01:10
01:20
01:30
01:40
01:50
02:00
02:10
02:20
02:30
02:40
02:50
03:00
03:10
03:20
03:30
03:40
03:50
04:00
04:10
04:20
04:30
04:40
04:50
05:00
05:10
05:20
05:30
05:40
05:50
06:00
0
Time
Figure 5.13 Sample Valve Closing Data in a Step Test
After reaching zero flow at the end of closing steps, the reverse procedure should be done in
order to check if same prioritization could be done or not. In a similar manner, it is performed by
opening the valves of the sub-DMAs one by one and getting a step-by-step increasing flow versus
time data indicating the water losses of the sub regions (Figure 5.14).
54
Step Test - Opening Process
60
Discharge (m³/hr)
50
40
30
20
10
01:00
01:10
01:20
01:30
01:40
01:50
02:00
02:10
02:20
02:30
02:40
02:50
03:00
03:10
03:20
03:30
03:40
03:50
04:00
04:10
04:20
04:30
04:40
04:50
05:00
05:10
05:20
05:30
05:40
05:50
06:00
0
Time
Figure 5.14 Sample Valve Opening Data in a Step Test
There are some important points to be considered while doing step tests. First, step tests
should be done at minimum night flow hours. This is usually some time between 02:00 a.m. and 04:00
a.m. (which may extend to 01:00 – 05:00 depending on the water usage characteristics of the region).
Opening or closing a valve should be done very slowly to prevent transient effects that might occur in
the network. Next, after shutting an area, the effect should be seen at the flowmeter clearly and if an
inconsistency occurs in the discharge values (i.e. an increase instead of a decrease when a valve is
closed), a waiting period should be left before shutting another area. Within this waiting period, the
transient effects minimize and the network comes to equilibrium.
5.6.
Search for Leaks with Leak Noise Loggers
Leak noise logging devices are being used in water leak detection for more than 20 years
(Thornton, 2002). Simply they are mobile microphones with recording capability. They are usually
placed on the fittings of the network such as valves, fire hydrants etc. Their job is to record the noises
of the pipeline it is placed on for leak sounds. Testing is preferably conducted between 02:00 a.m. –
04:00 a.m. to make sure environmental noises are minimal. A potential leak is found by getting a
noise amplitude data that never drops to zero indicating that a constant noise is present in the network
(Figure 5.15). That constant noise should be checked whether it is a constant leak sound or another
noise such as a machine, working non-stop. This check can be done by looking at the dominant
frequency value of the recording, or from frequency histograms of the recording if supported by the
device. A non-leak noise is determined from a data logger result that hits zero noise level at night
(Figure 5.16). It states that ultimate silence is reached at the measurement location indicating no leak
on the nearby water distribution network. The success is greatly dependent on the technical
55
specifications on the device as well as the material of the pipe. The spatial location of the location in
the network is also important as the farther the leak point to the logger, the lower chance it is to be
detected. Units in sample figures (Figure 5.15 and Figure 5.16) may differ from one brand to another.
However, the general approach is to provide unitless sound levels, which gives rough information
about the leaking spot.
Figure 5.15 Data Logger Result Graph Showing a Possible Leak Noise Recording
Figure 5.16 Data Logger Result Graph showing a non-Leak Noise Recording
56
Figure 5.17 Sample DMA Showing Leaks and Possible Detection Points
For a sample network shown in Figure 5.17, it is assumed there are two leak spots A and B. If
leak noise loggers are to be placed on every valve from 1 to 9 in this network, most probably leak A’s
noise will be generated on valves 2 and 3. Similarly leak B’s noise will be heard by the loggers on
valves 6 and 7. Of course, loggers placed on other nearby valves may be affected from leak noises
depending on the intensity of leak noise and depth of the leak. However, the above named valves are
expected to have higher noise levels, as they are the nearest valves to the leaks. In addition, logger on
valve 3 will gather more noise from logger placed on valve 2. Valves 6 and 7 will give similar results
which will provide the important knowledge of which valve is nearer to leak B. Intensity of the logger
measurements will determine the nearness amount.
Noise loggers can be used in “measure and move on” manner or as permanent devices. Many
brands develop different models for these two purposes. In the first manner, devices are used to
measure for leak noises on a set of fittings for one or two days, then collected to be placed elsewhere.
By this way with a limited number of loggers, a large number of DMAs can be searched for leaks. In
the second manner, suitable loggers are placed on fittings for long time use. They are programmed in
such a way that, measurements are taken every day, or every week, or every month. Then on
predefined dates and times, the operator sweeps the area to collect the data to check whether a leak
exists or not. As the water distribution network can be considered like a living organism, there may be
no leak signal on a fitting one day, but an opposite signal can be received the other day. Therefore, the
network should be kept under investigation all the times.
It is a well-known fact that sound is transmitted better in particular materials. Materials such
as cast iron or steel have a better transmission of sound than plastic materials like high-density
polyethylene (HDPE) or polyvinylchloride (PVC). Loggers placed on metallic pipes receive leak
noises from a greater distance compared to loggers placed on plastic pipes.
57
In the last few years, these devices are improved greatly. Primitive versions of noise loggers
only recorded environment noises wherever they are placed. Nowadays loggers can be programmed to
stand by on daytime and start recording noises on night hours to eliminate ambient noises. Also a
considerable amount of energy saving is insured. In addition, they are capable of detecting the
frequency of the recorded noises and with the help of preinstalled frequency libraries; loggers are able
to compare the recorded noises with real leak noises. By this comparison, leaks can be detected with a
better accuracy. Another useful property is provided with the help of GIS tools. Sound amplitude data
collected with two consecutive loggers can be correlated with the distance calculated from the water
distribution network layer to point a leak point if it is between these loggers. With this property, leak
noise correlating devices, which are used to perform this same correlation work, can be eliminated
from leak detection studies.
5.7.
Pinpointing the Leak with Ground Microphones
Pinpointing leak spots with ground microphones is one of the most preferred techniques in
water leak detection. With the improved technology, numerous brands produce numerous models of
acoustic leak detectors. Generally called ground microphones, are the devices that are used outdoors
for listening possible leak noises on asphalt, concrete or earth surfaces. Their working mechanism
depends on amplifying the noise that the device detects from ground and delivers that noise to the
operator. With some improvements on the device, they are able to filter unnecessary noises and
interferences making the operator easily focus on the leak noise.
Preferably, after making necessary detections with noise data loggers, operator starts
searching the most probable areas (near valves that generate the highest leak signals on loggers)
moving back and forth. Operators with enough experience usually pinpoint the leak within one hour’s
time.
Similar to leak noise loggers, sound generated by the water leak first vibrates the faulty pipe.
Then the pipe spreads the noise and vibration to nearby locations. At this step pipe material parameter
becomes more of an issue. Noises will be spread to a wide area or to a narrow area depending on the
material. As a general fact, metallic pipes spread the noise to much wider areas than plastic pipes. This
fact effects ground microphoning study deeply. Listening on plastic pipes require more attention in
order not to miss the leak spot whereas on metallic pipes less attention may be paid. The importance
of this aspect can be explained by assuming two similar networks, one composed of metallic pipes
whereas the other one composed of plastic pipes. For example, in the first case a water leak will be
detected by ground microphoning the pipeline with 100-meter intervals, whereas same leak spot will
be detected by ground microphoning with 10-meter intervals. This will yield the fact that sound
spreads more on metallic pipes.
Usually, pinpointing is done by spotting the point that most noise is gathered. After
excavating the pointed spot, whether the correct position of the leak is spotted is understood.
58
Errors of a few meters are acceptable as in some cases leaking water sprays and hit a hard surface
away (like a rock) and most of the noise is taken at the water hitting point. However to be able to find
even that spot without being able to see what is going on underground can be stated as a success.
5.8.
Measuring Daily Demand Curves of the DMA to See the Effects of
Leaks
After locating and fixing the water leakages, daily demand curves and consumption data
should be obtained again for the new period to see the effects of leaks. Water loss percentages should
be calculated for the new conditions and those percentages should be investigated closely while on the
other hand leak detection studies should go on. Probably for every DMA, a level will be reached
where the leaks cannot be decreased anymore. That level should be recorded as in future
investigations if that ultimate value is exceeded, then it means that new leaks are generated in the
network and as soon as possible some action should be taken.
A continuous discharge measuring system like SCADA may have great advantages when
located at the DMA entrance. With the help of such kind of a system discharges, pressures and daily
consumptions of the DMA can be investigated continuously. A summary table like Table 5.2 can be a
useful tool for examining daily water loss values. The values from SCADA records can be manually
picked for this table or some kind of software can be developed to scan SCADA records every night
and pick the minimum values recording them on a separate environment.
Table 5.2 Sample Summary Table for Examining Daily Minimum Night Flow and Water Loss
Percentages
Date
Days
Water
Entering (m3)
Minimum
Night Flow
(m3/h)
Minimum
Flow Time
Total Lost
Water (m3)
Water Loss /
Total Flow
(%)
[A]
[B]
[C]
[D]
[E]
[F] = 24 x [D]
[G] = 100 x [F] / [C]
01.03.10
02.03.10
03.03.10
04.03.10
05.03.10
06.03.10
Mon
Tue
Wed
Thu
Fri
Sat
1160
1130
1096
1156
1167
1247
30.2
28,7
31,0
36,1
29,2
29,3
01:50
04:10
02:00
04:30
04:35
04:30
724.13
688,88
744,38
866,25
701,63
702,00
62.425
60,962
67,917
74,935
60,122
56,295
.
.
.
59
It should be noted that, having a leak free network is not realistic. Then, instead of dealing
with little leakages after fixing the big ones in a DMA, some other unstudied DMA should be
investigated for leaks that are bigger (leaking more) and easier to find. By this way, in a shorter time,
larger quantity of leaks can be detected and their cumulative effect would be greater in every aspect.
With the help of a table similar to Table 5.2 used during the case studies, the effects of
repairs on the network and possible occurrence of new leaks are observed. In Section 6.2.5 and in
Table 6.10, effects of repairs are seen as the decreasing values of “Total Lost Water” column. The
repairs are done beginning from 6th of April and the “F” column of Table 6.10, decreased from 834.75
m³ down to 500-m³ level when the repairs are completed. In this aspect, tables similar to Table 5.2
prepared by the administration are very useful for leak monitoring purposes.
5.9.
Equipments Used In the Field Studies
The history of leak detection devices goes back more than 150 years (Figure 5.18).
According to the historical records, leaks are tried to be localized by using wooden sticks. Those
sticks were used to listen and pinpoint the leak spot in a very primitive manner (Web6). However,
today’s high-end technological devices use the same principle of leak sounds to pinpoint them.
Throughout this study, acoustic loggers and advanced ground microphones are used for leak detection.
According to the timeline in Figure 5.18, these devices are all developed after 1990s, so the
technology they are being used is a new technology.
Figure 5.18 Timeline Showing Leakage Detection Technology Developments (Web 6)
The two major equipments (noise data loggers and ground microphones) used during field
studies are products of Hermann Sewerin GmbH. Sewerin is a German company dealing with water
losses for many years. In general these two devices are easy to learn and practical to use in the field.
60
There are more complicated and more functional devices on the market, but used Sewerin products
satisfy minimum requirements for a basic scanning of a distribution network.
The two devices work with similar principles. Acoustic leak detection is the basis of these
devices. A leaking pipe generates a sound with some characteristics. Noise data loggers are capable of
detecting these characteristics and give alerts indicating water leakage nearby. In addition, their output
results can be manually examined for detailed analysis and detecting leaks that could not be
automatically alerted. Ground microphones work with simpler principles. They raise the sound level
where the listening stick is touching. With the raised sound level, operators can trace and pinpoint the
leak spot very efficiently. Interfering noises can be filtered by these devices, to have a clearer sound of
the leak spot.
5.9.1. Noise Data Loggers
Sewerin’s SePem 01 is used as data loggers in the field. A pack of 20 loggers was available
during the study. Loggers were distributed over the water distribution network during daytime, and
collected from the field the next day. Before distributing, programming of the loggers was performed.
They were programmed to take listening measurements at night between 02:00 and 05:00. Having a
total of 20 loggers had a limitation in terms of working time. Total working time in the field could be
shorter if more loggers were equipped.
SePem 01 devices are actually meant to be permanent loggers that will stay in the field for
years. With the help of their radio connection property, they can be programmed and their results can
be transferred easily and quickly within a distance. This distance is usually enough to make remote
connection from a slowly moving car. As a result, loggers can be permanently recording
measurements. From time to time, operators can drive through the area to check whether any leak is
detected by the loggers. However, in this study these devices were distributed and collected within
two days not to face the risk of getting the devices stolen.
61
Figure 5.19 Sample SePem
01 Result Graph
Figure 5.19 shows a sample result graphic obtained from a SePem 01 recording. In this
graph, x-axis shows the time in hours, which covers the duration of measurement. Y-axis is a unitless
axis showing the intensity of the sound level. According to the information obtained from the
manufacturer, the intensity values in y-axis can be converted to values in terms of decibel (dB) by
using Formula 6.1. In this formula, “IL” represents the intensity value obtained from the graph (sound
level); “dB” represents the sound level in decibel.
dB = 20 x log10 ( I )
(5.17)
The intensity value IL is a unitless quantity, which is the proportion of the field-measured
amplitude A1 over a reference amplitude A0. This reference amplitude could not be obtained from the
manufacturer, so throughout this study the output graphs are given with unitless sound levels.
5.9.2. Ground Microphones
During the field studies, Sewerin’s Aquaphon A 100 was the most used equipment. It is an
electronic ground microphone having the ability to recognize noises of frequency between 1 Hz and
10 KHz. With such a wide range, it is also equipped with the frequency-filtering feature. It can filter
out the selected frequencies, helping the operator to focus on the leak noise only. The device can be
used with two major hardware. One ground microphone headpiece for listening ground noises (on
asphalt, pavement or earth surfaces) (Figure 5.20) and one listening stick for listening noises from
fittings (valves, hydrants or customer water meters) (Figure 5.21). One from the two hardware is
selected depending on the listening spot. The units of the values read in the device’s screen are again
62
unitless values as described in Section 5.9.1.
Working mechanism of Aquaphon A100 is easy. Volume of the noise that is being listened is
elevated at the device and transferred to the operator from the headphones. When the leak spot is near,
operator hears a higher volume of the leak sound also observing the amplitude of the noise from the
device’s screen. Search for leakage is done near the suspected spots, trying to detect the highest leak
sound. Leak spot is often located where the maximum leak noise is obtained.
Figure 5.20: Pinpointing Leak Spot with Ground Microphone from Surface (Web10)
63
Figure 5.21: Pinpointing Leak Spot with Listening Stick from Fittings (Web10)
As seen from Figure 5.20 and Figure 5.21, the device’s screen shows higher values when
listening point is nearer to the leak spot. As another helper, the real, amplified sound of the leak heard
from the headphones are considered. In Figure 5.21, conceptually two corporation cocks and one
underground hydrant is shown. Corporation cocks are usually buried and not kept ready for regular
usage in Turkey. Valves in the network are used more than corporation cocks.
64
CHAPTER 6
6. CASE STUDIES IN ANTALYA WATER DISTRIBUTION NETWORK
As applications of the methodology explained in Section 5, two district metering areas,
namely “Zone 6” and “Zone 2” are selected in Antalya’s Konyaaltı County. The procedure is clearly
applied on field. At the end, a decrease in minimum night flow and an increase in monthly revenue
ratios are achieved in both zones.
6.1. General Information about Antalya Water Distribution Network
Antalya is Turkey’s seventh biggest city in terms of population. The total population of the
city is nearly 2 million and about half of them are living in central counties (Aksu, Dö emealtı, Kepez,
Konyaaltı, and Muratpa a) (Web1). As the city is one of the major tourism cities of Turkey, its
population increases considerably in summer.
Antalya’s major water sources are deep-wells distributed over city’s different places. As a
treatment process, only chlorine is injected to the water and it is pumped to the city. Distribution
concept is drawing the water out of the wells, and then pumping it to storage tanks located at the far
end of the network mains. While pumping water to the tanks; distribution to the secondary network is
done.
Water consumption of Antalya’s central counties stated above, is around 180000 m3 per day
according to the records at the SCADA centre. Moreover, according to the previous records,
consumption becomes slightly more than 200000 m3 per day during the tourism season.
The city has nearly 3000 km of water distribution mains and secondary pipes. Pipe materials
show a great variation throughout the city network. Major materials can be stated as; PVC, HDPE,
asbestos cement, steel, ductile iron and cast iron (Table 6.1). The whole city network goes through a
65
rehabilitation process in which the old pipes (mainly steel and asbestos cement) are being replaced by
PVC pipes. Most of the house connections are HDPE pipes, while there are still some primary and
secondary distribution pipes, which are HDPE too.
Table 6.1 Percentages of pipe materials in Antalya WDN
Pipe Material
Percentage (%)
PVC
HDPE
Asbestos Cement
Steel
Ductile Iron
Cast Iron
Galvanized
Glass Reinforced Plastic
Unknown
58.18
24.90
7.29
3.78
2.37
2.30
0.56
0.36
0.25
Total
100
Topography of the city varies considerably as the city lies between Western Taurus
Mountains (Bey Dağları) and Mediterranean Sea. Neighbourhoods in Konyaaltı have a very flat
elevation distribution, whereas neighbourhoods near the sea cliffs and the Castle may have very steep
sloped streets.
Antalya Water and Wastewater Administration (Antalya Su ve Atıksu Đdaresi, ASAT) is the
organization, which is responsible for all of the water and wastewater issues in the central counties.
For more than a year, the administration runs a pilot project aiming to deal with water losses,
controlling the network, forming a SCADA system with district metering areas (DMA), obtaining
reliable GIS layers of the city, forming an up to date database of the customers.
As a starting location Konyaaltı county is chosen. The whole network in the county is
investigated carefully with the administration’s office and field personnel and as a result, the network
is divided into 18 DMAs (Figure 6.1). To achieve a big success almost all of the valves on the
network were located in the field, excavated and made ready for use. This makes thousands of valves
that have been treated all around Konyaaltı. To overcome the risk of these valves to be covered by
asphalt, all of them have been coordinated precisely with Cors-TR compatible GPS receivers.
Forming the DMAs in the field was achieved by determining the borders and closing the valves that
intersect with the borders. Similarly, detection of valves under asphalt surface and making them ready
for use is done in the rest of the city.
66
Figure 6.1 18 District Metered Areas formed in Antalya Water Distribution Network
At the entrance pipes of each DMA, electromagnetic flowmeters were placed and connected
to the SCADA system. By the help of this system, administrative staff can see the flow, pressure and
water quality values of the interested DMA instantaneously. In addition, all of these data are stored in
the SCADA’s database for future access to the historical values.
To obtain reliable GIS layers of the city GPS surveys have been done. Field collected data is
entered to a system built on ArcGIS. As stated above, all of the isolation valves are coordinated using
GPS. Additionally all of the fire hydrants, air valves and related fittings of the network are
coordinated. Also, all of the pipes and dead end points in the network are coordinated some by just
tracking the pipes between valves on the asphalt surface, and some by excavating and taking the real
coordinates (Figure 6.2). Another GIS layer is formed from the house connections. Again, some of
them are coordinated by excavating the asphalt and touching the connection, some of them were
coordinated either by the help of utility locator devices (pipe and cable detectors) or by knowledge of
highly experienced field personnel.
67
Figure 6.2 Coordinating the pipeline (Web 4)
As another task, all of the buildings in the county are given a unique id and they are
connected to the customer database (see section 6.1.3). With this step, a customer information system
that can be integrated to GIS is almost established. By the help of this study, it became easy to
calculate the total consumption in a DMA in a monthly basis. On the other hand, it is possible to
measure the flow entering to the DMA in any time period. So the water loss amount and non-revenue
water percentage of each DMA in Konyaaltı can be calculated to a certain extent. These topics are
discussed in detail in sections 6.2.2 and 6.3.2. Other useful layers like cadastral layers and street
centreline layers are obtained from Greater Municipality of Antalya and Municipality of Konyaaltı.
Konyaaltı has approximately 310 km of water distribution network mains and secondaries.
Just like the other parts of Antalya water distribution network, pipe materials in Konyaaltı is mainly
PVC with small amounts of HDPE, steel, ductile iron and asbestos cement.
Konyaaltı lies along the Mediterranean Sea and has very little elevation changes. Mainly all
of the elevations near the seaside can be assumed as a constant value. So this makes very little
pressure changes at the entrance of the consumers due to topography. This is not valid in other regions
of the city. For example, neighbourhoods near the mountainous regions or old city centre located in
the Castle (Kaleiçi) show great elevation changes. Assuming constant elevation values can only be
accepted in some parts of Konyaaltı.
The county has 42104 consumers according to the records of ASAT. The 2009 population for
the county is given as 106748 by TÜĐK (Web2).
68
6.1.1.
GIS Layers
6.1.1.1.Pipes
Pipe layer is drawn in polyline and contains the following attribute fields: Unique ID for each
pipe segment, diameter of the pipe in millimetres, material of the pipe, depth of the pipe (if known),
calculated length of the pipe, pressure zone of the pipe, address information and information about the
installation of the pipe. These attribute fields are filled from project values and field staff’s knowledge
but they may contain important mistakes (mostly wrong diameter and wrong material) that conflict
with the reality on the field.
6.1.1.2.Fittings
Fittings layer is composed of point objects. These objects’ coordinates are collected using
GPS. However, this realistic drawings of the fittings are not suitable for a map layout especially
fittings that are located within centimetres to each other. To overcome this problem, the GIS
department places new point objects that represent the position of the object schematically. In Figure
6.3 below, “Kvana” represents the real coordinated valve; on the other hand, “Vana” represents the
schematic drawing of the corresponding valve. These schematic points are identified in their attribute
tables. They are not placed for each valve. Placement is within operator’s responsibility. If operator
thinks that too much overlapping of the objects will occur when a layout is plotted, he or she places a
schematic twin of the fitting.
69
Figure 6.3 Explanation of Coordinated and Schematic Valve Drawings
Fittings layer contains the following attribute fields: Unique ID for each fitting, diameter of
the fitting in millimetres, material of the fitting, type of the fitting, address information and
information about the installation of the pipe. Whether the fitting is coordinated or schematic is
identified in “type of the fitting” column.
6.1.1.3.House Connections
House connections layer contain exactly the same attributes with the pipe layer, but they
represent the service connection pipes not the distribution network pipes. Therefore, they have smaller
diameters and shorter lengths. This useful layer determines which building is connected to which pipe.
In addition, it becomes more important on the borders of different pressure zones. If the buildings
seem to be connected to a different pressure zone’s pipe, the leakage computations of the zones are
deeply affected.
6.1.1.4.Buildings
Buildings layer is the layer that represents every building in the city. They are drawn in
polygon shapes. They are digitized using satellite images by using the corners of the roofs mostly. The
70
attributes can be listed as: Unique ID for each building, name and number of the building, type of the
building (residential, office etc.), number of floors, subscription ID of one of the consumers in the
building, number of customers in the building, number of the zone that the building is in and address
information. Subscription ID of one of the consumers is aimed to build a connection with the
customer information system in order to assign monthly consumptions to the buildings. By this way,
very precise hydraulic modelling works can be done. Also this knowledge can be used to make a
connection with the SCADA records to calculate the amount of physical water loss. This topic is
studied in sections 6.2.2 and 6.3.2.
6.1.1.5.Roads
Road layer is a polyline layer that represents the centreline of the roads. They are given a
unique id and the road name as the most important attribute values. This layer is a layer obtained from
Municipality of Konyaaltı.
6.1.1.6.Cadastral Layers
Cadastral layer is obtained again from Municipality of Konyaaltı and drawn in polygons.
Usually these layers are produced in NetCAD environment and transformed into GIS layers through a
series of operations. They represent the cadastre areas and have the following attributes: Unique ID,
Area of Usage (residential, green field, hotels etc) and cadastre number. This layer is useful in field
studies as the street spaces are clearly seen between cadastre areas helping to determine the addresses.
In addition, it is useful to check whether a pipeline falls inside a cadastre area or not indicating a
possible cancelled out pipe that is not removed from the pipe layer.
6.1.2.
SCADA Data
Data obtained from SCADA is very useful for the determination of water losses. From
SCADA measurements, the total water flow entering to the DMA can be obtained for a particular time
period. This is obtained by subtracting the first index from the second index. With ideal conditions
where there is no water loss in the system in any type, the same amount of water should be obtained
by summing up all the index changes at the customer meters within the same time period. Unlike ideal
conditions, there are water losses all around the network, water meters are not perfectly measuring the
flow that is used and meter readings are being read by people that can make rounding errors.
The metering data is explained in section 6.1.3 in some aspects. Strict monthly readings are
71
not done so, each user’s water usage is metered for a different time period. With the data available, it
is impossible to superpose the SCADA data and the customer readings because of different time
periods (Figure 6.4). To overcome this difficulty, customer readings can be normalized by the time
period they have used water, so monthly usages can be converted to daily usages assuming a 24 hour
constant flow everyday throughout the metering period. By summing all of the average daily
consumptions of all users, average daily consumption of zone 6 is obtained. Average daily
consumption of the total zone can be compared to the monthly water flow entering to the DMA
divided by the time period. In Section 5.4.2 extensive information is provided for water loss
percentages and SCADA – CIS integration.
6.1.3.
Customer Information System (CIS)
Having examined the structure of the customer information system, it is difficult to say an
organized connection between the consumptions and the GIS data is present. The integration is made
by the interested staff’s effort. This is because the customer relations department and GIS department
were not designed to work cooperatively at the stage of establishment of ASAT. GIS department has
done most of the work by digitizing the all of buildings in the pilot study area, giving a unique ID to
each building, and collecting all of the customer information in the buildings (pressure zone name,
customer IDs, address related data, telephone numbers, e-mail addresses, water meter IDs, water
meter types and brands). In the meantime, customer relations department keeps on collecting monthly
consumption data from water meters with a different crew. As the water meter reading crew works
directly on field, GIS crew also worked on field to check if the buildings still exist, or if new buildings
are being built. Data collected from these two sources are integrated manually. On the other hand, a
study for the automation of this integration was going on when this thesis study has been done. The
integration is made simply by bringing together the unique customer IDs and unique building IDs with
the consumption data of each customer.
As explained theoretically in Section 5.4.1, consumption records being kept in terms of
periods. Each period roughly defines 30 days consumption. As the record collecting crew is working
independently from the GIS crew, the data collected in the same period represents different days’
consumptions for different users. With the help of Figure 6.4 below an example can be given for this
situation. For example; a user’s (Customer 2) consumption data is collected between 02.03.2010 and
07.04.2010 (37 days) on the other hand another user’s (Customer 1) consumption data is collected
between 11.02.2010 and 23.03.2010 (41 days) and these two consumption data have been recorded
under 2010 – 3rd period consumptions column. Almost every customer has different monthly reading
periods. This is done probably because of people in the meter reading crew is collecting data
considering different borders (probably neighbourhood borders) but not pressure zone borders. It is
best to collect the data within the pressure zone completely in one day to detect monthly water loss
amounts. However, due to administrative reasons this stated action seems very difficult to apply with
72
1 Apr 2010
31 Mar 2010
1 Mar 2010
31 Feb 2010
meter reading crew. It may be possible if data logging water meters were used throughout the zone.
SCADA Measurement (1 Month)
Customer 1 - Meter Reading 2010/3
Customer 2 - Meter Reading 2010/3
Customer 3 - Meter Reading 2010/3
…
Customer 4 - Meter Reading 2010/3
Figure 6.4 SCADA Measurements and Corresponding Customer Readings for one Month
As stated, the errors are introduced from beginning and ending of the monthly periods. To
reduce this effect, a long period of time can be considered. By this way there still will be errors
coming from the edge of months, but their share in the total will decrease. When considered monthly,
every customer’s reading will be out of SCADA bounds. When a longer period is considered, only
January and December readings will be out of yearly SCADA measurement’s bounds. All the other
consumption readings from February to November will be reflected in SCADA measurements (Figure
6.5). This helps to determine the revenue percentage in a better way with the available data.
73
1 Jan 2011
31 Dec 2010
1 Jan 2010
31 Dec 2009
SCADA Measurement (1 Year)
Customer 1 - Meter
Reading 2010/1
Customer 2 - Meter
Reading 2010/12
Customer 3 - Meter Reading
2010/1
…
Customer 4 - Meter Reading
2010/12
Figure 6.5 SCADA Measurements and Corresponding Customer Readings for one Year
The records for consumptions have been integrated (as stated above) beginning from 1st
period of 2008. The consumptions for each customer are kept under three columns for each period.
Two of these columns are the beginning and ending days of reading periods, and the third column is
reserved for the collected metering data in terms of meter cubes. The precision of the readings are in
meter cube level. Unfortunately, an inevitable piece of error is introduced to the collected data at this
stage, by rounding up or down the water meter reading.
The data obtained shows that a proper record keeping has been done from 2009 until now.
The improper records in the first 12 months are due to some absences in beginning and ending dates
for periods. After 2009 1st period, there are not any missing data in the beginning and ending date
columns. In Table 6.2 a sample record from the CIS of Antalya Water and Wastewater Administration
is given. The original database is reordered and grouped into five categories defined by the author for
visual simplicity (PART A to PART E).
In PART A, key values about the identity of the customer is given. ABONE NO defines the
unique ID for the customer and it never changes with consumers moving in or out to the address. In
other words, this unique ID is tied to the address where the consumption is being done. Typical
address and contact information are being recorded in the related fields. Type of the customer is given
in two fields, one in ABONE TURU (as predefined codes for quick fetching from the database) and
the other one in ABONE TURU ACIKLAMASI (for print out purposes). Lastly DURUM field
defines the status of the customer whether water is actively being used or account is suspended due to
some reason.
74
PART B contains fields about the water meter. Its identification number, brand and type of
the meter and the meter’s installation dates are being recorded in these fields.
PART C is the only part that is being updated regularly in monthly intervals due to
consumptions. Every month three new columns are added to the database, which keeps the record of
the consumption period’s beginning date, ending date and consumed water volume. Additionally, in a
separate field, the average of all consumptions are being calculated and updated every month.
PART D contains all the GIS related data. Most of the address data recorded in this part is
also kept in predefined codes for possible GIS integrations. The most valuable field in PART D is
CBS ABONE NO. In this field, unique IDs for the buildings are being kept. By using these unique
IDs, a quick integration between the monthly consumption values and the building layer in GIS (or
node layer in the water distribution models) is possible to make. Also pressure zone’s (or DMA’s) IDs
are being recorded in this part.
Lastly, in PART E, necessary administrative data for each customer is recorded. These data
contain tax information, sewerage details and data required by customer relations department’s water
meter reading crew.
Table 6.2 A Sample Record from the CIS of ASAT
PART A – IDENTIFICATION
ABONE NO
195755
ABONE ALT NO
1
ABONE ISMI
SEVKET YARIMBAS
ABONE TURU
1
ABONE TURU ACIKLAMASI
EV ABONESI
ADRESI
ARAPSUYU MAH 646 SOK NO:37 D:7
EV TELEFONU
2299999
IS TELEFONU
CEP TELEFONU
5324777777
E-MAIL ADRESI
KOMSU ABONE NO
20020354
DURUM
A
PART B – WATER METER DATA
SAYAC NO
16532
SAYAC MARKA
CBAY-B
BINA IC SIRA
1
ĐLK ABONELĐK VERĐLĐ TARĐHĐ
01.03.2005
ABONE BA LANGIÇ TARĐHĐ
01.03.2005
KAPANI TARĐHĐ
PART C – CONSUMPTION DATA
ABONE TUKETIM ORTALAMASI
10,42
2010-4 ILK TRH
10.03.2010
2010-4 SON TRH.
12.04.2010
2010-4 M3
11
2010-5 ILK TRH
12.04.2010
2010-5 SON TRH.
12.05.2010
2010-5 M3
9
75
Table 6.2 Continued
PART D – GIS DATA
195755
2
3747
7
3
KONYAALTI BELEDIYESI
1
MERKEZ
7
ARAPSUYU MAH.
38
646 SOK.
CBS ABONE NO
CBS ZON NO
ADA
PARSEL
ILCE KODU
ILCE ADI
BELDE NO
BELDE ACIKLAMASI
MAHALLE KODU
MAHALLE ADI
SOKAK KODU
SOKAK ADI
SITE
BLOK
APARTMAN
MANOLYA APT.
DIS KAPI
37
DAIRE NO
7
EV SAYISI
1
ISYERI SAYISI
0
PART E – OTHER ADMINISTRATIVE ISSUES
DEFTER
368
DEFTER ACIKLAMASI
ARAPSUYU-3
SAYFA
104
SIRA
102
CTV VAR MI? 1-Var 0-Yok
1
KANAL VAR MI? 0-Yok 1-2-3-4 Var
1
KANAL ORANI
0,30
KANAL TARIHI
01.05.2006
ZON NO
368
BINA TAKIP NO
119
6.2. Zone 6 Studies
Zone 6 of Konyaaltı network is one of the 18 district metering areas explained above. Zone 6
has 344 buildings registered in the customer information system (CIS) at the time of this study. The
total number of customers is given as 1800 in the CIS.
The DMA is fed by a pump station located in Boğaçayı and a storage tank located in Hurma
(Figure 6.6).
76
Figure 6.6 Simplified Schematic Drawing of Konyaaltı Water Transmission System and Zone 6
Entrance
The diameter of the transmission line between this pump station and storage tank varies from
Ø400mm to Ø800mm. Zone 6 and most of the other 18 DMA’s take one branching pipe from this
transmission line and serves to a district area (Figure 6.7).
Figure 6.7 Distribution Main of Konyaaltı and Branching Pipes of 18 DMAs
77
6.2.1.
Data Sources
6.2.1.1.Geographic Information Systems
6.2.1.1.1.
Pipes
The name of DMA has two alternatives that are being used by the ASAT staff. It is named as
zone 6 by the GIS crew, as metering point 70 by the SCADA crew.
The main transmission line within the DMA is an Ø200mm HDPE pipe, and it serves to an
approximately 8800m of secondary pipes. The distribution of lengths of the pipes is given in the table
below (Table 6.3). It can be seen from the table that transmission mains are mainly Ø200mm and a
small amount of Ø225mm pipes. In addition, a majority of the street network consists of pipes
between Ø90mm and Ø150mm pipes.
Table 6.3 Pipe Diameters and Pipe Lengths in Zone 6
Pipe Diameter (mm)
Pipe Length (m)
50
63
75
90
100
110
150
200
225
156.0
233.7
361.3
1842.9
907.6
4380.3
962.6
1851.1
39.3
Total
10734.8
It is stated previously that pipe materials in Antalya water distribution network consist of
various types. Similar situation is present in this DMA, namely zone 6. The material distribution is
given in the table below (Table 6.4). It is seen that because of the rehabilitation studies done in the
study area, most of the old pipes are renewed with PVC pipes. A relatively small amount of asbestos
cement pipes (AÇB) are planned to be cancelled out due to low durability to pressure and due to water
quality risks.
78
Table 6.4 Pipe Materials and Pipe Lengths in Zone 6.
Pipe Material
Pipe Length (m)
Steel
Galvanized
Unknown
PE
Asbestos Cement
HDPE
PVC
27.9
46.9
149.0
161.7
385.8
1884.2
8079.4
Total
10734.8
The result of a more detailed tabular analysis is given below indicating the diameters,
materials and their lengths in this network (Table 6.5).
Table 6.5 Pipe Diameters, Pipe Materials and Pipe Lengths in Zone 6
Diameter (mm)
Pipe Material
Pipe Length (m)
50
63
63
75
90
90
100
100
110
110
150
150
150
200
225
225
PE
Galvanized
PVC
PVC
PVC
Asbestos Cement
PVC
Unknown
PVC
PE
PVC
Asbestos Cement
Steel
HDPE
HDPE
Steel
156.0
46.9
186.8
361.3
1692.6
150.3
758.6
149.0
4374.6
5.7
705.3
235.5
21.8
1851.1
33.2
6.1
Total
6.2.1.1.2.
10734.8
Fittings
On the fittings layer there are 58 valves and 5 fire hydrants all of which are suitable to use.
These isolation valves are examined one by one on the field. Some old valves were seen to bleed very
little amounts of water out of the system. In long-term studies, these leaks can sum up to big amounts.
However, as these valves are working properly, meaning they can be completely closed or opened
79
without affecting the flow; the Administration is not willing to spend money and time to renew them.
After all, these small leaks remained unrepaired.
Another important aspect for the isolation valves was the existence of three isolation valves
that were isolating zone 6 from two neighbouring zones, Zone 2 and Zone 8. It is necessary to keep
these three isolation valves closed at all times because the neighbouring zones are under different
pressure values. If any of these isolation valves remain partially or fully open, then unaccounted water
may enter to or exit from the system. In more complex and rough topographies, borders of pressure
zones are mostly determined by elevation, but in Konyaaltı, the topography is very flat. Consequently,
pressure zone borders are determined by isolation valves that remain closed at all times.
Before the study, it was noted that the DMA had some deficiency in terms of valve numbers
and placements. In the technical brochures of the equipment used on the field, Sepem 01 leak noise
loggers, it is given under the “recommended distance between loggers” title as 300 – 500 meters for
metallic pipe material, and 50 – 100 meters for plastic pipe material (Web 3). To be on the safe side,
and by considering the major pipe material, which is PVC, it is assumed that the devices will work
within a limit of 50-meter range on the field. By making a buffer analysis to draw 50-meter diameter
circles around valves, it was seen that most of the network remained outside of the effective range of
the noise loggers. In conclusion, at ten different places of the network the administration was advised
to place valves and connect some of the dead end pipes to the nearest pipe available to ensure the
sound of the leaks will travel to a wider distance. Administration was convinced and constructed eight
of the ten connections in a short time period. Two of the advised connections were not made because
of the complexity of the electricity and telecommunication network at the construction points.
The administration was also advised to place 35 valves at different places of the network. 11
of them were placed while constructing the nine connections stated above. However, the other 24
valves were not placed because they were mostly not at street intersections but in the mid point of
street lines. These kinds of valves remain ineffective in terms of isolation of pipes at street level. The
ineffectiveness is due to the existence of valves at street intersections. The situation is explained better
in Figure 6.8. In the figure, dots indicating present valve locations and possible recommended valve
places are seen. The buffer circles around valves are 50 meter in diameter. Valve at the street
intersection controls the whole street. New valves will remain ineffective as their job of isolating the
street is done better with the present valve. In addition, placing valves at regular distances on the
network may be an expensive job.
80
Figure 6.8 Recommended Valve Places and Their Effective Areas
The figures below show the situation of the network before and after the maintenance works
(Figure 6.9). Before the maintenance, network had 47 valves, after the suggested construction works
number of valves increased to 58.
81
Figure 6.9 Valves and Their Effective Areas Before and After Constructions
6.2.1.2.Customer Information Systems
Upon investigating the CIS database, it is found out that there are totally 1782 customers in
zone 6 of Konyaaltı. These customers are being residents in 344 buildings according to the customer
relations department’s data. However, in the building layer generated by GIS department, there are
392 buildings. Remaining 48 buildings are either buildings that use water mutually with some
neighbouring building (commonly seen in shacks), or using wells instead of city’s water distribution
network. Therefore, these kinds of customers do not have a separate customer IDs. Consumptions
generated by mutual users are reflected to the owner’s meter, and consumptions of private well users
are out of interest for this study.
6.2.2. Calculating Water Loss Percentages
Water loss percentage calculation is studied in two aspects throughout this study. First aspect
is calculating monthly revenue ratios with the help of SCADA and CIS data. Second aspect is
comparing minimum night flow of the region to the total consumption. Extensive explanations are
given in Section 5.4 theoretically. During field studies, the procedures given in Section 5.4 are applied
82
in both aspects. They are explained in Sections 6.2.2.1 and 6.2.2.2. Results obtained after the field
studies are also summarized in Section 6.2.5.
6.2.2.1.Monthly Revenue Aspect
This calculation can be done in monthly periods if water meters are being read in monthly
periods, which is the usual situation. In addition, as explained in previous sections, it contains some
amount of error if the SCADA system and CIS are not meant to work cooperatively. In addition, this
calculation cannot determine whether the lost water is revenue loss (illegal water usage) or a physical
water loss. Resulting calculation gives the result as the sum of all losses.
Procedure explained in Section 5.4.1 is applied to Zone 6 and for 2010 3rd period (before the
field works). The water flow index on 1 March 2010 00:00 is 23560 m³ and on 31 March, 23:59 is
59970 m³. The difference is 36410 m³, which is the volume of water entering to zone 6 during the
dates mentioned. The time period is 31 days. Averaged daily supplied flow is 1174,52 m³/day. The
sum of all 1782 customers’ averaged daily usage is 436,87 m³/day. This means that with all the errors
considered, about 63% of the supplied water is lost, only 37% of the supplied water can reach to end
users. This percentage is called as monthly revenue.
After the field works applied in zone 6, the same calculation is done. This time the volume of
water entering to the zone is 30980 m3 between 1 April and 30 April. Its daily averaged value is
1032,67 m³/day. On the other hand, during 2010 4th period, the sum of customers’ averaged daily
usage is 457,84 m³/day. Applying the same procedure, the monthly revenue is found out to be 44%,
increasing by an amount of 7%. As explained, this procedure involves a considerable amount of error.
Therefore with the help of previous consumption and SCADA records, monthly revenue ratios are
calculated from 2009 6th period (roughly between 1 June 2009 – 31 May 2010). The tabulated results
and their graph are discussed in Results section.
6.2.2.2.Minimum Night Flow Aspect
As explained in detail in Section 5.4.2, minimum night flow value theoretically represents the
amount of physical water loss of the network. Comparing the minimum night flow value to the daily
usage of the region gives a water loss ratio. As the only data source is SCADA, this percentage can be
calculated for any time period. However, daily loss calculations should be considered for consistent
results.
SCADA records are investigated day by day and for each day, total water volume entering to
zone 6 is determined. It is then compared to total lost water volume that is the minimum night flow
occurring at that day, which is leaking for 24 hours. Graphical meaning of this is the ratio of the area
83
below minimum night flow level over the daily demand curve area.
As an example, the daily demand curve in Figure 6.10 can be considered. It is the actual daily
demand curve of zone 6 on 23 March 2010. The area under the minimum night flow line is the
amount of water lost throughout the day and can be denoted by letter “B”. On the other hand, the total
area is the total volume of water entering to a DMA for a day, denoted by “A+B”. Water loss
percentage (L%) is formulated in Equation 6.1 below. In this example, minimum level is at 32.5 m³/h
but this is a value changing from day to day in small amounts. As the study area is a tourist area,
theoretical minimum night flow may not be observed at all. There is a consistent night usage everyday
by some consumers. Consumptions occurring at late night hours tend to decrease towards morning
hours but most probably, their usage hours overlap with those who wake up early and generate usage
at early morning hours.
As mentioned in Chapter 5, minimum night flow shows little variations during the day due to
changes in pressure. However, in the case studies, this variation is ignored and minimum night flow is
assumed as constant.
L(%) =
B
× 100
A+ B
(6.1)
Daily Demand Curve of Zone 6 – 23 March 2010
90.0
80.0
Discharge (m³/hr)
70.0
60.0
50.0
40.0
30.0
Minimum Night Flow = 32.5 m3/h
20.0
10.0
23:00
22:00
21:00
20:00
19:00
18:00
17:00
16:00
15:00
14:00
13:00
12:00
11:00
10:00
09:00
08:00
07:00
06:00
05:00
04:00
03:00
02:00
01:00
00:00
0.0
Time
Figure 6.10 Sample Daily Demand Curve of Zone 6 Showing Minimum Night Flow before the
Study
Calculations for zone 6 are done before and after the field works. Before the field works,
minimum night flow in the system was at 30 m3/h level. Corresponding water loss ratio was around
65%. After detecting the leaks and repairing them, the minimum night flow decreased to 20 m3/h level
and water loss ratio decreased down to an average of 55%. However, a short time after the repairs,
84
both minimum night flow and water loss percentage showed an increase. This is an indication of new
leaks at either new repaired points or other weak points in the water distribution network. This topic is
discussed in detail in Results section.
6.2.3.
Forming Sub-DMAs
In zone 6 network of Konyaaltı, with the help of new connections and new placed valves, the
DMA was divided into 8 sub-DMAs (Figure 6.11) on the plans first. Then the theoretical borders were
verified by closing boundary valves on the field. As a transmission line, the Ø200mm PE pipe is used.
Seven out of 8 sub-DMAs consisted of branches of pipes, which are fed by this main pipe. The eighth
sub-DMA covered an area of houses that are directly connected to the main transmission line. First
seven sub-DMAs are controlled with their entrance valves. Whenever one of the valves is closed, the
associated sub-DMA is left without water. The valve controlling last sub-DMA is on the main
transmission line. Therefore, if it is closed, the whole DMA is shut down.
Figure 6.11 Sub-DMAs in Zone 6 of Konyaaltı Network
6.2.3.1.Prioritizing sub-DMAs by Step Tests
Although the flow data is recorded by the SCADA system, the measurements were recorded
manually by checking the flowmeter instrument’s panel located at the DMA entrance (Figure 6.12).
At this panel, real time flow, pressure and water quality values can be observed. The SCADA
85
system in Antalya is configured in such a way that, changes in flow or pressure at measuring points
are not transmitted to the central SCADA unit up to some tolerance limits. If flow or pressure values
change more than that limit, then the new value is transmitted to centre. By this limitation, it is aimed
to minimize the transmission traffic and therefore minimizing the possible scrambles that may occur
in the transmitted data. However, setting such a limit prevents the operator to see small changes
occurring in the system. Therefore, the only way was to use flowmeter’s panel to see and record the
changes occurring for a reliable study.
Figure 6.12 Manually Recording Discharge Values from Flowmeter’s Panel during Step Test
The step test is performed on 1 April 2010 between 02:00 – 05:00. The main reason for
testing between these hours is that the neighbourhoods Arapsuyu and Ku kavağı are mainly
residential areas. There are some touristic facilities but as the date of measurements were in April,
very limited tourist activity was present in the region. As a result, minimum nightly usage occurs
between these hours. Sub-DMAs are shut down in the order 2 – 7 – 3 – 4 – 1 – 5 – 6. Valve at the
main entrance that controls the eighth sub-DMA is not shut down because after shutting seventh subDMA, zero flow value is reached at the flowmeter. According to the valve closing steps following
tabulated results are obtained (Table 6.6). In addition, the corresponding graph is given in Figure 6.13.
As seen from the graphical results, most of the water leakage is measured at sub-DMAs 4, 5 and 6
with leakage amounts 8m³/hr, 14m³/hr and 12m³/hr respectively. Therefore, they are the weakest
regions of zone 6 according to the closing step results.
86
Step Test - Closing Process
Discharge (m³/hr)
50
45
40
35
30
25
20
15
10
5
0
#2
Loss:
5 m³/hr
#7
Loss:
1 m³/hr
#3
Loss:
0 m³/hr
#4
Loss:
8 m³/hr
#1
Loss:
4 m³/hr
#5
Loss:
14 m³/hr
03:25:00
#8
Loss:
0 m³/hr
03:20:00
03:15:00
03:10:00
03:05:00
03:00:00
02:55:00
02:50:00
02:45:00
02:40:00
02:35:00
02:30:00
02:25:00
02:20:00
02:15:00
02:10:00
02:05:00
02:00:00
#6
Loss:
12 m³/hr
Time
Figure 6.13 Water Losses in sub-DMAs Determined by Closing Valves
Table 6.6 Tabular Results of Flowmeter Values during Valve Closing Steps
Closed Sub-DMA
Discharge Read From
Flowmeter (m³/hr)
All Open
2
7
3
4
1
5
6
44
39
38
38
30
26
12
0
Valve-closing actions ended around 03:30 and zero flow values are reached as expected. To
check the results, valve-opening actions started. Valves were opened slowly to minimize possible
transient effects. Opening order of the valves was 6 – 5 – 1 – 4 – 3 – 7 – 2. At around 05:00 all the
sub-DMA entrance valves were opened, and the network was returned to the state before the step test.
Obtained results are given in Table 6.7 and Figure 6.14 below. If the results are examined, it would be
seen that the priorities of the sub-DMAs are in accordance with the results of valve closing actions.
The weakest zones are 5 and 6 as they are in the both test results. Sub-DMA 4 seems one of the weak
87
sub-DMA in valve-opening test but the opposite in the valve-closing test. Rest of the sub-DMAs are
relatively stronger sub-zones when compared to 5 and 6.
Step Test - Opening Process
Discharge (m³/hr)
45
40
35
30
25
20
15
10
5
0
#1
Loss:
2 m³/hr
#5
Loss:
12 m³/hr
#4
Loss:
12 m³/hr
#3
Loss:
0 m³/hr
#2
Loss:
3 m³/hr
#7
Loss:
0 m³/hr
#6
Loss:
13 m³/hr
05:00:00
04:55:00
04:50:00
04:45:00
04:40:00
04:35:00
04:30:00
04:25:00
04:20:00
04:15:00
04:10:00
04:05:00
04:00:00
03:55:00
03:50:00
03:45:00
03:40:00
03:35:00
03:30:00
03:25:00
03:20:00
#8
Loss:
0 m³/hr
Time
Figure 6.14 Water Losses in sub-DMAs Determined by Closing Valves
Table 6.7 Tabular Results of Flowmeter Values during Valve Closing Steps
Opened SubDMA
Discharge Read From
Flowmeter (m³/hr)
All Closed
6
5
1
4
3
7
2
0
13
25
27
39
39
39
42
As a result, sub-DMAs 4, 5 and 6 are grouped as weak, and the other sub-DMAs are grouped
as relatively strong DMAs. Looking at the number of valves at each sub-DMA it was concluded that
in two days, it would be possible to sweep the whole zone 6 by using leak noise loggers. As there
were a limited number of loggers first day should be spent on scanning sub-DMAs 4, 5 and 6. Rest of
88
the sub-DMAs can be scanned the other day.
6.2.4.
Locating Physical Water Losses
6.2.4.1.Forming Buffer Areas for Leak Noise Loggers
After prioritizing the sub-DMAs, zone 6 is divided into two regions that are going to be
swept one after other with leak noise loggers. Sub-DMAs 4, 5 and 6 are given first priority for leak
detection study, sub-DMAs 1, 2, 3, 4, 7 and 8 are given second priority. Number of valves in each
sub-DMA are given in Table 6.8 below.
Table 6.8 Number of Valves in Sub-DMAs
Sub-DMA
Number of Valves
1
9
2
2
3
6
4
10
5
8
6
7
7
4
8
8
With the equipped 20 loggers, sweeping study was first done in sub-DMAs 4, 5 and 6 on
01.04.2010. The loggers were programmed to record possible leak noises between 02:00 and 05:00 in
10-second intervals. They are programmed to send the recorded data to the master unit, the day after
between 10:00 and 12:00. While collecting the data from the loggers one by one, master unit gave
warnings at valves where possible water leakage is detected. According to the technical details of the
data loggers, minimum sound level must be much greater than zero. Additionally, frequencies
between 50 Hz and 100 Hz are treated as possible background noises and it is said that they do not
come out to be leaks usually. The Operation Instructions booklet also states that low frequency values
indicate leaks far away, high frequency levels indicate nearer leaks. Lastly, third parameter, width of
the measurements should be low to indicate a good measurement with a low interference noise. Noises
that satisfy these three conditions are reported as possible leakage and a warning is transmitted to the
operator. At the same manual, it is written in bold that “A leak alert is not a guarantee that a leak is
89
actually present” (Web 3). Therefore, other studies should be done in order to pinpoint the leak spot.
Forming buffer areas around logger placed valves, depends on the idea of determining
effective leak detection areas of loggers. According to the technical details of the equipped loggers,
their effective leak detection distance is between 50 and 100 meters as diameter, on plastic pipes. This
is stated as “recommended distance between loggers”. According to Thornton (2002), this distance
can be as low as 10 – 15 meters for plastic pipes. For metallic pipes, he states effective distances can
be as high as 1000 meters, but recommends a conservative value of 250 meters for an upper limit.
Additionally, he recommends a value for asbestos cement and cement pipes between plastic pipes and
metallic pipes. These values recommended by Thornton are direct distances from leak to listening
point so they should not be treated as a diameter distance. Taking into account these recommendations
given by Sewerin and Thornton, two buffer layers are built around logger placed valves, with
diameters 20 meters and 50 meters taking into consideration the worst cases. With these buffer layers,
logger effective pipes and logger ineffective pipes in the network are easily determined. The results
can be seen in Figure 6.15, Figure 6.17, Figure 6.19, Figure 6.21, Figure 6.24 and Figure 6.26.
Considering 20-meter buffer areas, it is hard to say leak noise loggers are useful for the
network of zone 6. That is because; loggers can scan a very little portion of the network. As expected,
in sub-DMA 6 loggers do not scan for leaks at all, due to very long distanced pipes without any valves
on them. In rest of the sub-DMAs, the picture is not much different. Only little portions of the network
on street intersections are believed to be scanned. The total length of pipes that are logger ineffective
is 7847 meters. It corresponds to 73% of total pipe length in the network. According to these data,
suggested study is to sweep the logger ineffective areas with ground microphones. However, it seems
better to use only ground microphones and sweep the entire network without spending money and
time on leak noise loggers.
According to 50-meter buffer areas, a larger portion of the network is believed to be scanned.
However, sub-DMA 6 is still suffering from lack of valves. Sub-DMAs excluding 6 are in better
condition when compared to 20-meter buffer areas, as logger ineffective areas are much less. Total
length of logger ineffective pipes is 7229 meters. It corresponds to 67% of the total network length.
When these percentages are compared, it seems sensible to use leak noise loggers with ground
microphones together.
As a result first day at 2 points water leak noise were detected at valves 27066, and 27169
with the logger serial numbers 3603 and 3605 (alert #1 and alert #2). Same study done on 01.04.2010
is repeated on 05.04.2010 with the remaining valves. Second day results were 5 leak noise alerts with
logger serial numbers 3596, 3606, 3612, 3622, and 3641 (alert #3 to alert #7). Detected points are
shown in figures below. As a next step for leak pinpointing, ground microphoning is applied.
Alert #1: Noise Data logger with serial number 3603 is placed to the valve at the intersection
th
of 6 Avenue and 551st street. According to the GIS layer pipes are steel and PVC with diameters
90
Ø150mm and Ø90mm. The valve that is used during the data logging process is given a unique ID
number of 27066 (Figure 6.15). In the figure, the position of the valve is seen with the 10m radius and
25m radius buffer areas. Pipes inside the buffer circles show the maximum possible effective distance
of the logger according to the criteria discussed above.
Figure 6.15 Noise Data Logger with Serial Number 3603 Placed On Valve #27066 and Its
Corresponding Effective Areas
As it can be seen from the Figure 6.16, there is a constant noise on this logger between 02:00
and 05:00 that never drops below 163. This noise is generated with a frequency value 634. The value
for width indicates the quality of the measurement, and it is relatively small compared to the other
loggers distributed the same day. It indicates a good measurement with a small margin for errors. The
only drawback in this measurement is that the “Minimum level” value is rather small. It may indicate
a leak that is not very close to the valve. For a detailed investigation, scanning with the ground
microphone along east and west in 6th Avenue and towards north in 551st street was scheduled.
91
Figure 6.16 Details of Logger with Serial Number 3603 Placed On Valve #27066
Alert #2: The logger having a serial number of 3605 is placed on the valve with ID 27169 on
the intersection of 555th and 553rd streets. Below in Figure 6.17 the position of the valve is seen. In
addition, the corresponding buffer areas with 10 meter and 25 meter radius can be seen too. Pipes at
this corner are coded as Ø110mm PVC pipes.
92
Figure 6.17 Noise Data Logger with Serial Number 3605 Placed On Valve #27169 and Its
Corresponding Effective Areas
Figure 6.18 Details of Logger with Serial Number 3605 Placed On Valve #27169
Above, it is given the output figure for the logger with serial number 3605 (Figure 6.18). It
gives the minimum level as 258, which is a little higher than the previous logger but still a low noise.
93
Frequency is reported as 888 Hz. Width is given as 164, which is a low value indeed. It indicates that
the measurement is done with low interference. To find probable leaks, a ground microphoning study
was scheduled on these two streets.
Alert #3: Leak noise logger with serial number 3605 was placed on the valve with ID 39681
at the intersection of 6th avenue and 659th street. The pipes are PVC and HDPE with diameters
differing from Ø110 mm to Ø200mm. In Figure 6.19, three logger placed valves are seen. Only logger
on valve #39681 reported probable leak alert (Figure 6.20). At the same time, that valve is the one,
which is used while making one of the advised connections.
Figure 6.19 Noise Data Logger with Serial Number 3605 Placed On Valve #39681 and Its
Corresponding Effective Areas
94
Figure 6.20 Details of Logger with Serial Number 3596 Placed On Valve #39681
Alert #4 and Alert #6: At the intersection of 526th and 555th street there are three valves given
in Figure 6.21. Around each valve corresponding buffer areas are seen. Three loggers were placed at
these valves. Two of them reported a leak alert. These two loggers (3606 and 3622) were placed on
valves #27102 and #27104. Logger resulting graphs are given below in Figure 6.22 and Figure 6.23.
Logger 3606 resulted with a minimum level 697 whereas logger 3622 resulted with 423. With a quick
judgement, if the signal is coming from the same source it has to be nearer to logger 3606 than 423 as
its minimum noise level is higher. The frequency values are 269 and 333 respectively so this result
strengthens the conclusion that is reached by assuming the source is same for these loggers. The
measurements are done with little interference if width values 146 and 104 are considered.
95
Figure 6.21 Noise Data Loggers with Serial Numbers 3606 and 3622 Placed On Valves #27102
and #27104 and Their Corresponding Effective Areas
Figure 6.22 Details of Logger with Serial Number 3606 Placed On Valve #27102
96
Figure 6.23 Details of Logger with Serial Number 3622 Placed On Valve #27104
Alert #5: Alert 5 is reported by logger #3612 on valve #31903. Alerting point is inside the
borders of sub-DMA 2. The valve is located on Atatürk Boulevard, which is a highly crowded road at
daytime and night hours. The Ø75mm PVC pipe that is connected to the Ø110mm PVC pipe on the
boulevard passes through parcels as seen in Figure 6.24. This pipe is probably going to be cancelled
out later on. In Figure 6.25 the reported graph by the software is presented. Minimum level is seen as
886, which is a high value compared to other alerts. It may be interpreted as a leak that is not so far
away. Frequency of this measurement is reported as 666Hz and width is reported as 260 which is a
little higher than the other measurements. Having a width higher than others can be explained with a
higher interference noise as the valve is located on a busy street. Ground microphoning study is
specially scheduled for a night listening to overcome the daytime traffic noise. Other alert points do
not need to be listened at night because absolute silent moments can be reached during daytime.
97
Figure 6.24 Noise Data Logger with Serial Number 3612 Placed On Valve #31903 and Its
Corresponding Effective Areas
Figure 6.25 Details of Logger with Serial Number 3612 Placed On Valve #31903
Alert #7: 7th alert was reported on the intersection of 555th and 530th streets. At this
intersection, there are two valves one on Ø110mm asbestos cement pipe to the west, other one on
98
Ø110mm PVC pipe to east. Alerting logger having the ID 3641 was placed on the valve having ID
39582, which is on the asbestos cement pipe (Figure 6.26). Despite being valves next to each other,
the alerting sound was not detected by the other logger placed on valve 39579. Reported measurement
results are minimum level of 613, frequency of 492 Hz and width of 107. These values can be
interpreted as a leak that is within a fairly near distance. With a width value of 107, low interference
noises are the case again (Figure 6.27).
Figure 6.26 Noise Data Logger with Serial Number 3641 Placed On Valve #39582 and Its
Corresponding Effective Areas
99
Figure 6.27 Details of Logger with Serial Number 3641 Placed On Valve #39582
6.2.4.2.Ground Microphoning in Logger Ineffective Areas
Ground microphoning is applied to zone 6 just after the logger study. Listening is done
around leak sounding valves first. Listeners used either their field experiences or aligned themselves
by looking at the valve positions on the asphalt surface in order to locate the network. All listening
study is done by moving just on top of the pipes. Detailed investigation results for the seven data
logger alerts are given below.
After having realized ground microphoning at the alert points, remaining listening schedules
first focused on sub-DMAs 4, 5 and 6, because the result of the step test pointed these sub-DMAs as
the weakest regions. If correlation study could have been done, that would be a guide way for the
listening study. As that study is skipped, listening study focused directly on alerting valves. After
listening the valves, nearby network may have been skipped based on the idea that loggers already
listen the nearby network to some extent. However to be absolutely sure about the leaks in the
network of zone 6, the entire network was scanned with ground microphones focusing first on the subDMAs stated above. Listening study of the whole zone lasted for three days.
With the careful examination of the listening staff, alert 1 turned out to be the noise coming
from the zone isolation valve with ID 27069 that is separating zones 6 and 2. The point is on the
border of sub-DMAs 4 and 8. It can be attributed to both of the areas. After ground microphoning the
isolation valve, the staff made a judgement that the valve does not fully close itself and therefore it
lets water passage from zone 6 to zone 2. Movement is in this way because zone 2 is a different
100
system working under a constant reduced pressure of 2.9 bars. However, zone 6 is under an average
pressure of 5 bars. These two systems are separated by this valve and it should be left closed at all
times. A construction was scheduled related with this valve to be changed with a new one.
For the case of alert 2, the point is inside sub-DMA 5. When the ground microphoning crew
listened the related valve, they detected a leak sound. However, a more careful visual examination
revealed that the valve was bleeding out water from the sealing part of the valve (salmastra in
Turkish). The amount of water that is leaking out from the system is very small indeed but the noise it
generates is not negligible. So within the help of noise data loggers, a broken valve was found.
Nevertheless, as stated in sections above, the administration was not willing to replace these kinds of
working valves. Indeed, these kinds of leaking valves will affect the reliability of water loss studies in
the future. The leaking noise may mislead the operators while searching for bigger leaks.
Alert 3 was on 6th avenue, on one of the new connected valves. The point is inside sub-DMA
1. Despite having a leak alert from the noise data loggers, ground microphoning crew did not detect
any leak noise with their equipment. As a result nowhere was excavated because a recent excavation
was done for the connection, and it is concluded by the administrative staff that if there were a leak, it
would have been seen when the excavation was taking place.
Alerts 4 and 6 took place at the same location. The placing of the three valves was very close
to each other. They were just in front of a public garden inside the borders of sub-DMA 2. One of the
pipes is passing through the garden towards north-west. Listening crew scanned the area surrounding
these valves, but did not catch a leak sound again. As no pinpointing of any leakage was possible, no
place for excavation could be determined.
Fifth alert was on the logger with the highest minimum noise level and highest interference.
This point is in sub-DMA 2. Listening study was done at night during 24:00 and 00:01. The
boulevard’s traffic reduces to a sensible level in terms of noise after 24:00. Despite listening entire
road over the network, listening crew was unable to pinpoint a leak at this location.
Leak 2: For the case of seventh alert, by careful listening with the ground microphones, a
leak was pinpointed in front of Diker Apartment. It is an apartment located in the sub-DMA 3. This
time, pinpointed leak spot stays in the presumed 25m radius effective area of the leak noise logger.
This leak was detected on an Ø110mm asbestos cement pipe at two pipes’ connection point. This
failure is said to be seen at almost every asbestos cement pipe connection. The failure is fixed with a
piece called “collar repair clamp” (hazır tamir parçası in Turkish). The whole pipeline was not
renewed with PVC pipes, so this remaining asbestos cement pipe remains as potential water leakage
point (Figure 6.28). This resulting leak is named as “Leak 2” in this study.
101
Sub-DMA 3
Figure 6.28 Position of leak spot and nearby logger effective areas.
Ground microphoning the logger ineffective areas resulted in four more water leak
detections. Resulting leaks 1, 3, 4 and 5 are explained in detail below.
Leak 1: Water leak is detected by the ground microphoning crew on 521st street, in front of
Elif Apartment that is inside the borders of sub-DMA 5. The failure occurred on the PE house
connection with a diameter of Ø40mm (Figure 6.29). As the sewerage network was constructed after
the water distribution network in Antalya, some water lines were displaced in the field. While making
displacements, most of the house connections were improperly renewed and made potential water
leakage spots. This leakage case was interpreted with this explanation. House connection pipe was
used to be directly connected from the street to the house, but while sewerage network was being
installed, a manhole was placed on top of the house connection pipe. So the house connection was
improperly renewed with spare parts turning around the manhole to the house entrance. The points
where spare parts exist became weak points and turned into water leakage points with time.
102
Sub-DMA 5
Figure 6.29 Position of leak 1 and the nearest valve location with effective areas.
Leak 3: This leak was detected on the intersection of 659th and 660th streets on an Ø90mm
PVC pipe. It has no nearby valves so it cannot be detected by noise data loggers (Figure 6.30). The
leak spot is located in sub-DMA 4. While making the ground microphoning study, on 660th street,
near the leakage, some water bleeding through the asphalt surface was seen. It indicated a probable
leak point but it looked like the water that may have been spilled from the sprinklers in the public
garden just beside the leakage point. After making the ground microphone survey, the leak is
pinpointed and excavation is done. After the excavation, the reason of the failure is seen at the
connection point of the PVC pipe with the nearby PE pipe. The heads of the pipes were improperly
connected and through time, this weak spot became the leak spot.
103
Sub-DMA 4
Figure 6.30 Position of leak 3 and the nearby valve with its effective area
Leak 4: Despite being in the logger effective areas, this leak was not detected by the noise
data loggers. It is pinpointed by the ground microphoning crew at the intersection of 6th avenue and
657th street (Figure 6.31) in front of Aile Apartment. It is a failure occurred on the house connection,
which is a galvanized Ø32mm pipe. The reason why the loggers did not detect the nearby leakage can
be explained by a set of mistakes that are made during the digitizing operations. As explained at the
beginning of this chapter, digitizing of all the house connections are done either by field crew’s
knowledge or by pipe detectors if the pipes are metallic. In this case, the door of the apartment is on
6th avenue but on 657th street. So by mistake, it is assumed that the house connection was connected to
the Ø110mm PVC pipe on 657th street. Nevertheless, as the connection is known to be galvanized
iron, the utility locator device is used to check the correct place of the house connection. The
connection is traced with the pipe detector and found out to be connected to the Ø200mm HDPE pipe
that is on 6th avenue. Also during the excavation, it is seen that the pipe is not buried but passes
through a cement pipe. This is probably done to prolong the service life of the galvanized iron pipe.
However, according to the picture it was not so successful at all. The wrong position and correct
position of the galvanized pipe is seen in Figure 6.34. Another thing seen in the figure is that the two
pipes on the 6th avenue and the pipe on 657th street are connected to each other with a series of
connections. Therefore, a data logger placed on valve #27137 should be able to detect the leak
occurring on the HDPE pipe (namely leak 4). However, as there are too many connecting pieces
between the pipes and valves, the noise generated at the leak spot weakens as it travels to the data
logger vanishing at some place between. With this correction made on the house connection, Aile
104
Apartment was understood to be in sub-DMA 8 not in sub-DMA 4. The whole house connection is
renewed with a PE pipe as the galvanized iron pipe rusted at several point and was not a usable pipe
anymore.
Sub-DMA 8
Figure 6.31 Leak spots 4 and 5 and the nearby data logger’s effective area.
Leak 5: This final leak pinpointed by the ground microphones was only 50m west of the 4th
detected leak spot on 6th avenue which is a leak spot in sub-DMA 1 (Figure 6.31). The pipe is given in
the GIS layer as Ø150mm PVC but after the excavation of the pinpointed spot, the pipe was found out
to be asbestos cement. The noise that the listening crew got was so weak that they were not so sure if
there is a leak or not. During the excavation, the pipe was found at around 2 meter deep. This explains
the weakness of the noise generated at the leak spot. The failure is just the same as the one faced in
leak 2. The two asbestos cement pipes were improperly connected to each other. They were not in a
straight line but making an angle of approximately 10˚ with each other. This made the connection a
weak spot, and it turned into a leaking point within time. The failure is fixed with a collar repair clamp
(Figure 6.32).
105
Figure 6.32 Collar Repair Clamp
6.2.5.
Results
To overcome the water losses in zone 6 of Konyaaltı water distribution network, step testing,
noise logger placements and ground microphoning studies are applied on the field. The total duration
of the study was 2 weeks (10 working days). The same study could be made possible in a shorter
period with more noise data loggers, more ground microphones and more operators. However,
spending less than a week on a DMA may lead to superficial results.
As most of the pipes are plastic in the network, noise data loggers are effective only to a
small extent. Accordingly, most of the study should be made with ground microphones. This means a
lot more ground microphones should be purchased and more operators should be trained. The GIS
layers have many mistakes in them that affect the water loss study deeply. This should be overcome
by training experienced personnel that are responsible only for a well-defined area (a pressure zone, a
few pressure zones or maybe a complete district). With this method, the responsible personnel will be
in charge of all the events in the area and will keep the GIS layers up to date. In the case of Antalya,
the responsible personnel are the people that have the valve and network knowledge and that are in
charge of shutting the water of any region. Unfortunately, they do not have an engineering
background so they may have difficulty working both on field and on projects. They prefer to use their
106
own knowledge that depends on past experiences not on GIS system or printed projects.
The daily demand curves obtained from SCADA gave information about a minimum night
flow of 28 – 30 m³/hour before the study ( Figure 6.33 and
Figure 6.34). It was detected in step
tests that most of this flow was occurring in sub-DMAs 4, 5 and 6. Unfortunately, with almost no
valves on sub-DMA 6, no water leakage points could be detected. In total, 5 leak points and an out of
order valve was detected. This zone border valve was shut down, and the five leak spots were fixed
neatly. As a summary, a table is given for leaks and their corresponding sub-DMAs (Table 6.9).
Table 6.9 Leaks, Their sub-Zones and Repair Dates
Leaks
Sub-DMAs
Out Of Order Valve Between 4 and 8
Repair Date
05.04.2010
1
5
06.04.2010
2
3
07.04.2010
3
4
07.04.2010
4
8
09.04.2010
5
8
09.04.2010
To see the effect of each leak, daily demand curve obtained from SCADA between
04.04.2010 and 09.04.2010 should be examined ( Figure 6.33 through
Figure 6.38).
107
Daily Demand Curve of Zone 6 - 04.04.2010
80
70
Discharge (m³/hr)
60
50
40
30
20
Minimum Night Flow: 32.8 m3/hr
10
Time
Figure 6.33 Daily Demand Curve of Zone 6 on 04.04.2010
23:00
22:00
21:00
20:00
19:00
18:00
17:00
16:00
15:00
14:00
13:00
12:00
11:00
10:00
09:00
08:00
07:00
06:00
05:00
04:00
03:00
02:00
01:00
00:00
0
10
Daily Demand Curve of Zone 6 - 05.04.2010
80
70
Discharge (m³/hr)
60
50
40
30
20
Minimum Night Flow: 32.6 m 3/hr
10
Time
Figure 6.34 Daily Demand Curve of Zone 6 on 05.04.2010
23:00
22:00
21:00
20:00
19:00
18:00
17:00
16:00
15:00
14:00
13:00
12:00
11:00
10:00
09:00
08:00
07:00
06:00
05:00
04:00
03:00
02:00
01:00
00:00
0
10
Daily Demand Curve of Zone 6 - 06.04.2010
80
70
Discharge (m³/hr)
60
50
40
30
20
10
Minimum Night Flow: 34.8 m 3/hr
Time
Figure 6.35 Daily Demand Curve of Zone 6 on 06.04.2010
23:00
22:00
21:00
20:00
19:00
18:00
17:00
16:00
15:00
14:00
13:00
12:00
11:00
10:00
09:00
08:00
07:00
06:00
05:00
04:00
03:00
02:00
01:00
00:00
0
11
Daily Demand Curve of Zone 6 - 07.04.2010
80
70
Discharge (m³/hr)
60
50
40
30
20
10
Minimum Night Flow: 31.9 m 3/hr
Time
Figure 6.36 Daily Demand Curve of Zone 6 on 07.04.2010
23:00
22:00
21:00
20:00
19:00
18:00
17:00
16:00
15:00
14:00
13:00
12:00
11:00
10:00
09:00
08:00
07:00
06:00
05:00
04:00
03:00
02:00
01:00
00:00
0
11
Daily Demand Curve of Zone 6 - 08.04.2010
80
70
Discharge (m³/hr)
60
50
40
30
20
10
Minimum Night Flow: 23.0 m 3/hr
Time
Figure 6.37 Daily Demand Curve of Zone 6 on 08.04.2010
23:00
22:00
21:00
20:00
19:00
18:00
17:00
16:00
15:00
14:00
13:00
12:00
11:00
10:00
09:00
08:00
07:00
06:00
05:00
04:00
03:00
02:00
01:00
00:00
0
11
Daily Demand Curve of Zone 6 - 12.04.2010
80
70
Discharge (m³/hr)
60
50
40
30
20
Minimum Night Flow: 21.0 m 3/hr
10
Time
Figure 6.38 Daily Demand Curve of Zone 6 on 12.04.2010
23:00
22:00
21:00
20:00
19:00
18:00
17:00
16:00
15:00
14:00
13:00
12:00
11:00
10:00
09:00
08:00
07:00
06:00
05:00
04:00
03:00
02:00
01:00
00:00
0
11
It is seen from the daily demand curves that on 5th of April (
Figure 6.34), the effect of
renewing the isolation valve made an increase on the consumption that should not occur. This is an
unexpected result because as this faulty valve is renewed, the neighbouring pressure zone with lower
pressures would not be fed from this point anymore. The only reasonable explanation for this case is
that after renewing, the valve was accidentally left slightly open. Therefore, a rise in the minimum
night flows occurred from 32.6m³/hr on 05.04.2010 at 05:00 a.m. to 34.8m³/hr on 06.04.2010 at 03:30
a.m.
On 6th of April, leak #1 was fixed on sub-DMA 5. Moreover, the minimum night flow is
decreased from 34.8 m³/hr to 31.9m³/hr at the very first night on 07.04.2010 at 02:35 a.m. Therefore,
this leak corresponded to an approximate water loss of 2.9 m³/hr.
On 7th of April, two leaks were fixed, namely leak #2 and #3 on sub-DMAs 3 and 4
respectively. With these leaks fixed a huge amount of decrease occurred in minimum night flow of
zone 6. It decreased from 31.9 m³/hr to 23 m³/hr on 08.04.2010 at 05:15 a.m. This means that these
two leaks corresponded to an approximate water loss of 8.9 m³/hr.
On 8th of April, two more leaks were fixed, namely leak #4 and #5 on sub-DMAs 8. With
these leaks fixed, some more decrease is observed in minimum night flow of zone 6. It decreased from
23 m³/hr to 21 m³/hr on 12.04.2010 at 05:20 a.m. This means that these two leaks corresponded to an
approximate water loss of 2 m³/hr.
Totally, the five leaks and one faulty valve summed up to an 13.8m³/hr decrease in minimum
night flow meaning a decrease in water loss of zone 6. Within two week’s time, major water leaks
were found and fixed in the zone. Most of the remaining leaks are believed to be in sub-DMA 6. It is
one of the largest sub-DMAs in the zone and it is a much-uncontrolled area as it has too few valves
and too long pipelines.
Some of the remaining leaks are very little dribbles of water that cannot be heard with any
instrument (background leakage). The administration plans to build a pressure reducing valve at the
entrance of DMA in order to minimize these very little water losses by pressure management. A
similar study is being applied at the neighbouring pressure zone named Zone 2. In this zone, pressure
is reduced at the entrance of the DMA from an average of 5.5 bars down to a stable level of 2.9 bars.
By doing so, minimum night flows of the area decrease from around 55 m³/hr level down to 40 m³/hr
level. This operation can be applied easily to the zone because there is not a topographic limitation in
the zone meaning almost every customer is at the same topographic elevation. So reducing pressure to
a minimum level does not affect the consumers. Buildings higher than 4 floors are forced to use their
own pumping system (with small booster pumps) in the apartment regulated by law.
Minimum Night flows in the DMA showed a significant decrease after the completion of
repairs. Parallel to this decrease, daily total volume of water entering to the zone decreased too. This
indicates prevention of physical water losses is achieved. From 1 March 2010 to 1 June 2010 below is
a table (Table 6.10) summarizing the effects of field works on water losses. Minimum night flow
114
values on 27 March, 1 April and 13 April are not realistic values because at those nights step tests
were performed (these values are given in italic). On the field, zero flow values were reached but
SCADA system did not record those values maybe because of waiting for short periods when the
whole DMA was waterless.
Table 6.10 SCADA Summary Table for Zone 6
Date
Days
Water
Entering to
Zone 6 (m3)
15.Mar.10
16.Mar.10
17.Mar.10
18.Mar.10
19.Mar.10
20.Mar.10
21.Mar.10
22.Mar.10
23.Mar.10
24.Mar.10
25.Mar.10
26.Mar.10
27.Mar.10
28.Mar.10
29.Mar.10
30.Mar.10
31.Mar.10
01.Nis.10
02.Nis.10
03.Nis.10
04.Nis.10
05.Nis.10
06.Nis.10
07.Nis.10
08.Nis.10
09.Nis.10
10.Nis.10
11.Nis.10
12.Nis.10
13.Nis.10
14.Nis.10
15.Nis.10
16.Nis.10
17.Nis.10
18.Nis.10
19.Nis.10
20.Nis.10
Mon
Tue
Wed
Thu
Fri
Sat
Sun
Mon
Tue
Wed
Thu
Fri
Sat
Sun
Mon
Tue
Wed
Thu
Fri
Sat
Sun
Mon
Tue
Wed
Thu
Fri
Sat
Sun
Mon
Tue
Wed
Thu
Fri
Sat
Sun
Mon
Tue
1150
1106
1194
1150
1150
1200
1200
1160
1146
1244
1200
1191
1159
1150
1300
1163
1257
1190
1290
1250
1300
1294
1216
1084
1016
1040
982
968
1020
980
950
950
1000
1048
1002
1000
926
Minimum
Night Flow
(m3/h)
Minimum
Flow
Time
Total
Lost
Water
(m3)
Water
Loss /
Total Flow
(%)
32.3
30.2
29.6
30.7
33.5
27.8
35.5
28.2
32.5
34.2
30.4
30.0
7.6
30.3
37.3
31.4
37.4
20.3
34.6
34.7
32.8
32.6
34.8
31.9
23.0
24.8
22.5
22.7
21.0
15.3
20.1
30.2
20.5
23.5
20.9
21.5
24.1
06:25
04:25
04:10
02:05
03:10
04:35
07:05
03:30
02:45
05:00
03:05
03:50
04:05
05:25
04:45
04:15
05:25
03:10
01:50
05:05
05:15
04:55
03:30
02:15
05:15
02:15
02:45
07:05
05:20
02:35
02:15
05:50
04:00
01:50
05:15
05:00
02:25
774.00
724.95
710.25
736.88
804.00
667.88
851.25
676.50
780.00
820.88
730.50
721.13
183.38
726.75
894.75
752.63
897.75
486.75
830.85
833.63
787.50
783.00
834.75
764.63
552.38
594.38
539.25
544.13
504.38
367.50
481.50
724.50
492.38
564.38
501.00
516.75
579.38
67.304
65.547
59.485
64.076
69.913
55.656
70.938
58.319
68.063
65.987
60.875
60.548
15.822
63.196
68.827
64.714
71.420
40.903
64.407
66.690
60.577
60.510
68.647
70.537
54.368
57.151
54.913
56.211
49.449
37.500
50.684
76.263
49.238
53.853
50.000
51.675
62.568
115
In Figure 6.39 below daily total water entering to zone 6 is shown in continuous lines. It
shows a change between 1100 m3/h and 1300 m3/h from day to day before the study. After fixing the
leaks, this value drops down to 900 m3/h - 1000 m3/h level. Dashed line indicates the daily minimum
night flow values. They are oscillating between 30 m3/h and 35 m3/h before the study; however, they
drop down to 20 m³/h after the study.
Within two weeks time the water entering to the DMA shows an increase an amount of 50 m3
to 100 m3. Also minimum night flow values show an increase of about 5 m3/h. These increments may
be an indication of new leaks on either recently repaired-spots or totally different weak spots. From
another aspect, it may be explained as no minimum night flow occurs in some days in this DMA.
Minimum night flow amounts changing every night by large values point an explanation of no
minimum night flow occurrence.
To look at Figure 6.40, the decrease in water loss percentages can be seen too. On the graph
there are three sharp drops on dates when step test are performed. They should not be taken into
account. For other points, it is seen that the water loss percentage is between 60% and 70% before the
study. It shows a drop of 10 points for two weeks after the study. Towards the end of May, the loss
value climbs up a 5% becoming values between 55% and 65%. These results again show indications
of new leaks.
116
11
1400
1300
1200
1100
1000
900
800
Total Volume (m )
04.03.10
07.03.10
10.03.10
3
Figure 6.39 Total Water Entering and Minimum Night Flow Values vs. Days
01.03.10
13.03.10
16.03.10
19.03.10
22.03.10
25.03.10
28.03.10
31.03.10
03.04.10
06.04.10
09.04.10
12.04.10
15.04.10
18.04.10
21.04.10
24.04.10
27.04.10
30.04.10
03.05.10
09.05.10
12.05.10
Minimum Discharge (m /hour)
Total Volume
06.05.10
15.05.10
18.05.10
24.05.10
27.05.10
30.05.10
3
Min. Discharge
21.05.10
40.0
35.0
30.0
25.0
20.0
15.0
10.0
5.0
0.0
11
25.03.10
28.03.10
31.03.10
03.04.10
06.04.10
09.04.10
12.04.10
15.04.10
18.04.10
21.04.10
24.04.10
27.04.10
30.04.10
03.05.10
06.05.10
09.05.10
12.05.10
15.05.10
18.05.10
21.05.10
24.05.10
27.05.10
30.05.10
Water Loss Percentages (% )
22.03.10
80
19.03.10
70
16.03.10
60
13.03.10
50
10.03.10
40
07.03.10
30
04.03.10
20
10
Figure 6.40 Water Loss Percentages vs. Days
01.03.10
To compare the revenue ratios before and after the study, SCADA and CIS data are used
cooperatively. A resulting table (Table 6.11) and a figure (Figure 6.41) are provided below for
historical inspection of revenue percentages over different revenue periods. The calculation formulas
are given at the top row for each column.
It is seen that in summer period, the daily average water entering to zone 6 is around 1200 3
1300 m /day. With the decreasing population to winter months, water consumption decreases and
daily average water entering to zone 6 decreases to 900 – 1000 m3/day. The effect of repairing leaks is
seen on April and May periods with a consistently decreasing water entrance to the zone. On March,
36000 m³ water was pumped into the zone whereas on April and May this value dropped down to
30000 m³. So a water loss of approximately 6000 m³ was prevented per month.
In the CIS part, it is seen that in each period total revenue shows seasonal variations. Higher
revenues in summer periods and lower revenues in winter periods are observed. With these CIS
provided values compared to SCADA data, monthly revenue percentages are obtained. Comparing
values of March, April and May, it is seen that there is an increase of 7% in April and 3% in May.
Some of this increase is due to the repairs of leaks. In addition, some of the increase is due to
increasing revenues due to summer season.
Similar comments can be made from Figure 6.41. The graph indicates increasing revenues in
summer months and decreasing revenues toward winter. The only exception is in December period.
The reason for this exception may be the shortages in SCADA data. SCADA data is reset 6 times at
different days in December. There are similar shortages in other months but at this data shortage, there
are long periods of time which there are no SCADA data available. With the best approximation done,
the total water entering to zone 6 in December is calculated as 27820 m3, which shows a significant
difference from November and January. Therefore, this point in December stays a possible outlier in
the whole dataset.
119
Table 6.11 Monthly Revenue Percentages
SCADA DATA
CIS DATA
Water Entering to
Average Daily Water Entering
Period's Total Daily Average
Monthly Revenue
Dates
Days
Zone 6 (m³)
to Zone 6 (m³)
Period
Revenue (m³)
Revenue (m³)
Percentages (%)
A
B
C
D=C/B
E
F
G
H = 100xG/D
01.06.09 - 30.06.09
30
36700
1223.33
2009/6
15942
530.57
43.37
01.07.09 - 31.07.09
31
41000
1322.58
2009/7
18495
609.10
46.05
01.08.09 - 31.08.09
31
40430
1304.19
2009/8
23068
645.23
49.47
01.09.09 - 30.09.09
30
32690
1089.67
2009/9
14135
584.96
53.68
01.10.09 - 31.10.09
31
35489
1144.81
2009/10
16228
537.14
46.92
01.11.09 - 30.11.09
30
37971
1265.70
2009/11
14008
484.51
38.28
01.12.09 - 31.12.09
31
27820
897.42
2009/12
14135
445.15
49.60
01.01.10 - 31.01.10
31
32300
1041.94
2010/1
13459
421.62
40.46
01.02.10 - 28.02.10
28
31430
1122.50
2010/2
11163
407.88
36.34
01.03.10 - 31.03.10
31
36410
1174.52
2010/3
12051
436.87
37.20
01.04.10 - 30.04.10
30
30980
1032.67
2010/4
14981
457.84
44.34
01.05.10 - 31.05.10
31
30650
988.71
2010/5
14364
473.15
47.85
(01.06.09 - 31.05.10)
365
413870
1133.89
182029
-
43.98
2009/6 2010/5
12
12
2009/12
2010/1
2010/2
2010/3
2010/4
2010/5
Revenue %
60
2009/11
50
2009/10
40
2009/9
30
2009/8
20
2009/7
10
0
Figure 6.41 Revenue Percentages over Periods
2009/6
6.3. Zone 2 Studies
After completing the studies on zone 6, to see the effects of pressure management over water
leakages, a similar zone is picked for further studies. Second case study is performed on this DMA
namely zone 2. The most important property of this DMA is the pressure management regulation that
is being applied since 2009 August. With the SCADA and CIS data available, it is possible to
investigate the water leakages in this zone:
•
Without any pressure reduction
•
With pressure reduction only
•
Pressure reduction combined with locating and fixing water leakages
Zone 2 is another member of the Boğaçay Pump Station – Hurma Water Storage Tank
system. It is located northeast of zone 6 still staying next to Mediterranean shores (Figure 6.42).
Figure 6.42 Zone 2 and 6 with Their Neighbouring Zones
122
6.3.1.
Data Sources
6.3.1.1.Geographic Information Systems
6.3.1.1.1.
Pipes
Just like zone 6, the name of DMA has two alternatives. It is named as zone 2 by the GIS
crew and as metering point 68 by the SCADA crew. Zone 2 will be used throughout the text.
The main transmission line within the DMA is an Ø150 mm PVC pipe, and it serves to an
approximately 12000 m of secondary pipes. Although there are Ø200 mm pipes in the network, they
were not used as the main feeder pipe because their material is asbestos cement and they are being
cancelled out whenever possible. The lengths of the pipes are given in the table below (Table 6.12).
Table 6.12 Pipe Diameters and Pipe Lengths in Zone 2
Pipe Diameter (mm)
Pipe Length (m)
63
90
99
100
110
150
200
369,8
1019,4
98,4
1770,7
5512,2
2081,3
1072,0
Total
11923,8
Pipes in this DMA consist of four different materials. The material distribution is given in the
table below (Table 6.13). As the rehabilitation study is still going on in this area, most of the pipes
were renewed with PVC pipes, and asbestos cement pipes are being planned to be converted to PVC
as soon as possible.
Table 6.13 Pipe Materials and Pipe Lengths in Zone 6.
Pipe Material
Pipe Length (m)
PE
Asbestos Cement
HDPE
PVC
365,1
907,5
1731,5
8919,7
Total
11923,8
123
A more detailed table is provided for this DMA showing diameters and materials of pipes
(Table 6.14). The most remarkable thing in this table and Table 6.12 is the 99 mm diameter pipes.
This shows a typical example of an incorrect data entering go the GIS layers. As there is not a
standard pipe diameter of 99 mm, those pipes may either be 100 mm diameter pipes or belong to a
group whose diameters are not exactly known. In that case, “99” is the arbitrary entered value, maybe
to be corrected in the future.
Table 6.14 Pipe Diameters, Pipe Materials and Pipe Lengths in Zone 6
Diameter (mm)
Pipe Material
Pipe Length (m)
63
90
99
100
100
100
100
110
110
110
150
150
200
200
200
PVC
PVC
PVC
PVC
HDPE
PE
Asbestos Cement
PVC
HDPE
PE
PVC
Asbestos Cement
Asbestos Cement
HDPE
PVC
369,8
1019,4
98,4
1473,5
88,3
134,5
74,4
4143,1
1138,6
230,6
1815,4
265,9
567,2
504,6
0,2
Total
6.3.1.1.2.
11923,8
Fittings
According to the GIS data, there are 65 valves and 5 fire hydrants in zone 2. Due to time
limitations, these valves were not examined one by one on the field. They were only examined shortly
while noise data loggers were being placed on them. According to those examinations, most of them
were in good shape and serves to the administration’s needs. They might have small leakages like in
zone 6 but they are not separately considered as water leaks in this study. Possible small leaks
contribute to the overall leakage sum.
As stated before, zones 2 and 6 are connected to each other with an isolation valve that is
kept closed at all times. The reason for this is applying different pressure regulations in these DMAs.
While working in zone 6, this isolation valve was discovered to be faulty and it was renewed.
Therefore, with this action it can be said that maximum isolation is obtained between these two zones
working under different pressures. By this result, two zones can be separately examined by their
124
SCADA and GIS records in terms of water loss percentages.
6.3.1.1.3.
Buildings
For the topography of zone 2, same things can be said with zone 6. They are almost similar in
terms of topographic elevations showing almost no change. The most important difference between
zone 2 and zone 6 is that they work under different pressures. The two DMAs are being fed from the
same system, but at the entrance of zone 2, with the help of a pressure-reducing valve (PRV) pressures
are reduced from an average value of 5.5 bars to a constant level of 3.0 bars. Minimum pressure that
has to be supplied by the water administrations show large variations due to lots of factors like
topographic elevations, number of floors of the buildings in that area etc. As the topographic elevation
differences can be ignored in this DMA, the consideration of number of floors gains importance. With
the available GIS data an analysis on floor numbers of the buildings is done. The first results are given
in Table 6.15.
Table 6.15 Number of Floors and Buildings in Zone 2
Number of Floors
Number of Buildings
1
2
3
4
5
6
7
8
9
10
11
12
13
16
50
—9999
15
19
133
77
19
18
15
18
12
7
3
1
1
1
5
130
Total
474
The first things to be noted in this table are having a 50-floor building, which is not a correct
thing, and having a sum of 130 buildings with -9999 floors, which mean their values were not entered
to the system. Buildings having floors up to 16 are observed at the DMA so the rest of the data seems
correct. To overcome these data inconsistencies the following assumptions are made. 50-floor
buildings are ignored as they consist only around 1% of the total data. “-9999-floor buildings”
125
were distributed to the other buildings proportional to their percentages in the total data. The resulting
distribution is given in Table 6.16.
Table 6.16 Corrected Number of Floors and Buildings in Zone 2
Number of Floors
Number of Buildings
Percentages (%)
1
2
3
4
5
6
7
8
9
10
11
12
13
16
21
26
184
107
26
25
21
25
17
10
4
1
1
1
4,42
5,6
39,23
22,71
5,6
5,31
4,42
5,31
3,54
2,06
0,88
0,29
0,29
0,29
Total
469
100
As seen in the table, more than 70% of the buildings have number of floors between 1 and 4.
With the majority of the buildings being like this, a pressure of 3.0 bars is considered adequate by the
administration. Buildings having higher number of floors will face low-pressure problems, and some
of them will not even have water in the top floors. For this situation, the administration applied a
procedure explained step by step below:
•
Without any warning, the pressure is reduced from 5.5 bars to 3 bars in the DMA.
•
Low pressure and water shortage complaints are reported by the customers to the telephone
support lines of ASAT.
•
Those complaining customers are warned to install booster pumps at the entrance of their
apartments to solve their pressure problems. These warnings were done according to the
related rules of ASAT and Greater Municipality of Antalya.
•
The pressures in the DMA were released to 5.5 bars for 1 month to let the complaining
customers install their booster pumps.
•
At the end of one month, the pressures were permanently reduced to 3.0 bars.
With this procedure, the administration meets the minimum pressure requirements, which
may exist as a legal written document or a practical rule, and decreases the water leakages in the
DMA considerably. Also regulating pressure to constant values provides the users constant quality
126
water at all times of the day. The disadvantage of reducing pressures is, hiding some of the water leaks
from detection as the leaks are directly related to system’s pressure. However, the problem is solved
by releasing pressure while working in the zone for leak detection purposes and reducing the pressures
after locating and fixing the leaks. The studies about this concept are explained in the next chapters.
Unlike zone 6, the administration was not advised to construct any new connections or install
new valves in zone 2. The studies are performed in the DMA without any step test applications.
The DMA has two big streets crossing each other. They divide the DMA into three nearly
equal pieces (A, B and C), which are seen in Figure 6.43. These regions are taken as the basis of the
field works. It is planned to work on parts A, B and C for one day each. Total studying time is planned
as five days, so for the remaining two days all the excavation and water leak repair studies are
scheduled.
Figure 6.43 Zone 2 Divided Into Three Pieces
6.3.1.2.Customer Information Systems
Zone 2 of Konyaaltı network is one of the two neighbouring zones of zone 6. Zone 2 is larger
than zone 6 in terms of both area and population. CIS records state 3025 customers located in 474
buildings. In zone 6 the corresponding values were 1800 customers in 344 buildings.
The structure of CIS is exactly the same with zone 6 as they are both a part of the same
127
database.
6.3.2.
Calculating Water Loss Percentages
Water loss percentages are computed through two aspects for zone 2. Compared to the case
for zone 6 the SCADA records are carefully investigated to catch the pressure reduction date and time.
According to the records, after warning the customers about the new regulations, pressure is reduced
from 5.5 bars to 3.0 bars in two stages. On 12 August 2009 at 11:30, pressures were reduced to 3.5
bars. After some time on 28 September 2009 at 10:00, pressures were finally reduced down to 3.0
bars. These actions deeply affected water loss percentages in both monthly revenue aspect and
minimum night flow aspect.
6.3.2.1.Monthly Revenue Aspect
Procedure already explained for zone 6 is applied to zone 2 gathering the necessary SCADA
and CIS data. Before the pressure reduction, revenue percentage in the zone was around 55%
(meaning a revenue loss of 45%) while after the pressure regulation revenue percentage increased to
70% level (meaning a revenue loss of 30%)
Similar comments can be made by looking at the monthly water meter indexes. Before the
regulation, monthly water entering to the zone was at 60000 m3 level on the other hand after the
regulation this value reduced down to 45000 m3 level. It clearly states that water leaks are reduced just
by getting rid of the excess pressure at the zone entrance.
After the field works there has been some further improvements in the water leak
percentages. They are discussed in more detail in the Results section.
6.3.2.2.Minimum Night Flow Aspect
Similar to zone 6, daily demand curves are investigated. This time, they are investigated in
more detail, especially considering July, August, September and October of 2009 to see the effect of
pressure reduction alone. Three daily demand curves are picked to see the stages of water loss. Three
of the curves were picked from Fridays. The dates are, 31 July 2009, 21 August 2009 and 2 October
2009.
31 July 2009 curve (Figure 6.44) represents a sample day (Friday) without any pressure
regulation. Pressure oscillates between 5 bars and 5.7 bars. The minimum night flow value is 65.1
m3/h in this sample day with unreduced pressure. Maximum flow values reach up to 120 m3/h
128
maximum consumption hours. With the proposed procedure, calculation of water loss percentage
yields up to 69.5%. That calculation was done by proportioning the area under minimum night flow
line to the total area under the daily demand curve (B/ (A+B)). On this day, a total volume of 2250 m3
water passed through the water meter at the entrance of DMA according to SCADA records.
Deily Demand Curve of Zone 2 – 31 July 2009
6.0
120
5.5
80
5.0
60
Pressure (bar)
Discharge (m³/hr)
100
40
4.5
3
20
Minimum Night Flow = 65.1 m /h
Discharge
Pressure
23:00
22:00
21:00
20:00
19:00
18:00
17:00
16:00
15:00
14:00
13:00
12:00
11:00
10:00
09:00
08:00
07:00
06:00
05:00
04:00
03:00
02:00
01:00
4.0
00:00
0
Time
Figure 6.44 Sample Daily Demand Curve of Zone 2 Showing Minimum Night Flow on 31 July
2009
For a comparison, another Friday just after the first stage pressure regulation is picked. That
day is 21 August 2009. As seen in that curve (Figure 6.45) pressure is reduced down to 3.6 bars with
little oscillations through the day. With the reduction of pressures, minimum night flow value
decreased down to 47.7 m3/h immediately. When compared to 31 July 2009, which means a loss of
17.4 m3/h is prevented. Calculation of water loss percentage for this day results in a loss percentage of
64.2%. That is a prevention of 5.3% water loss. Looking at the peak hours, it is seen that peak hour
discharges reduced to 90 m3/h level. For comparison, a total volume of 1785 m3 water passed through
the water meter on this day. From this value, it can be seen that a reduction of 465 m3 occurred in the
water indexes.
In the Figure 6.45, one thing draws attention too. That is the interruption of both discharge
and pressure values at around 02:00. This probably means an energy shortage or a data transmission
failure. In 30 – 45 minutes time the data comes back again and reports the values as before. In fact,
SCADA records obtained from ASAT are full of shortages and missing data values like this. Most of
the small shortages are corrected through this study by considering the nearest values before and after
the missing values. However, in this case the shortages are left uncorrected to illustrate an example
about the problem.
129
Deily Demand Curve of Zone 2 – 21 August 2009
4.0
120
3.8
3.6
3.4
80
3.2
3.0
60
2.8
40
2.6
3
20
Pressure (bar)
Discharge (m³/hr)
100
2.4
Minimum Night Flow = 47.7 m /h
2.2
Discharge
Pressure
23:00
22:00
21:00
20:00
19:00
18:00
17:00
16:00
15:00
14:00
13:00
12:00
11:00
10:00
09:00
08:00
07:00
06:00
05:00
04:00
03:00
02:00
01:00
2.0
00:00
0
Time
Figure 6.45 Sample Daily Demand Curve of Zone 2 Showing Minimum Night Flow on 21
August 2009
Taking a step further and reducing the pressure of the DMA down to 3.0 bars, had an effect
on the SCADA values as expected. The selected sample day is again a Tuesday, 2 October 2009. The
curve shows again a decrease in minimum night flows (Figure 6.46). The reduction is not as much as
the previous action but it is still valuable. Minimum night flow this time is 38.7 m3/h. That means a 9
m3/h more decrease in the losses. This final decrease makes the water loss percentages 58.1%. 1600
m3 is the total volume of water entering to the DMA on 2 October 2009.
As seen from the Figure 6.46, pressure values are stabilized to 3 bars with very little
oscillations which may be ignored when compared to previous situations.
130
Deily Demand Curve of Zone 2 – 2 October 2009
3.10
120
3.05
3.00
80
2.95
60
2.90
40
Pressure (bar)
Discharge (m³/hr)
100
2.85
20
3
Minimum Night Flow = 38.7 m /h
Discharge
Pressure
23:00
22:00
21:00
20:00
19:00
18:00
17:00
16:00
15:00
14:00
13:00
12:00
11:00
10:00
09:00
08:00
07:00
06:00
05:00
04:00
03:00
02:00
01:00
2.80
00:00
0
Time
Figure 6.46 Sample Daily Demand Curve of Zone 2 Showing Minimum Night Flow on 2 October
2009
Considering these three days alone, 26.4 m3/h decrease in minimum night flow is obtained.
650 m3/day decrease in volume of water entering to DMA is achieved. Overall, a decrease of 11.4% is
obtained in water loss percentages. All these achievements are done without fixing any leaks in the
system but only reducing the pressure with the help of a PRV.
To summarize all of these operations, following graphs in Figure 6.47 and Figure 6.48 can be
considered. Figure 6.47 illustrates the three different day’s values in the same graph. In the other
figure, with the historical values, the drop of minimum night flows with the reducing pressure is
clearly seen.
131
Minimum Night Flows vs Pressures
70.00
31.07.2009; P=5,50 bar;
Qnightmin= 65,10m³/h
3
Min. Night Flow (m /h)
60.00
50.00
21.08.2009; P=3,60 bar;
Qnightm in= 47,70m³/h
40.00
02.10.2009; P=3,00 bar;
Qnightm in=38,70m³/h
30.00
20.00
2.00
2.50
3.00
3.50
4.00
4.50
5.00
5.50
6.00
Pressure (bar)
Figure 6.47 Minimum Night Flows vs. Pressure Under PRV Effect
Minimum Night Flows and Pressures vs Time
3
Pressure (bar)
Discharge (m /h)
70
7.00
65
6.00
60
5.00
55
4.00
50
3.00
45
2.00
40
1.00
29.10.09
24.10.09
19.10.09
14.10.09
09.10.09
04.10.09
29.09.09
0.00
24.09.09
19.09.09
14.09.09
04.09.09
Pressure
30.08.09
25.08.09
20.08.09
10.08.09
05.08.09
31.07.09
26.07.09
21.07.09
16.07.09
11.07.09
06.07.09
01.07.09
30
15.08.09
Discharge
09.09.09
35
Figure 6.48 Decrease of Minimum Night Flows with the PRV
6.3.3.
Forming and Prioritizing Sub-DMAs
Unlike zone 6, no sub-DMA formation is done in the network of zone 2. Instead, the DMA is
virtually divided into three parts with the two avenues; 5th avenue and 7th avenue while studying
(Figure 6.43). Virtually dividing means no valve isolation actions done to divide the DMA. This
division is only for practical purposes. At each divided region, one day’s of working is done with the
noise data loggers. This lead to a quicker sweeping of the DMA when compared to zone 6. Of course,
this choice brought its disadvantages with it. Most important disadvantage is that no step test could be
132
performed which in the other zone. Therefore, without having an idea about which part of the network
is the weakest part, water leak detection studies are performed.
6.3.4.
Locating Physical Water Losses
6.3.4.1.Forming Buffer Areas for Leak Noise Loggers
As no sub-DMA formation studies are done, buffer analysis is done on the whole valve layer
with again 20 m and 50 m diameter values. By paying attention to cover the maximum area using up
to 20 noise data loggers, candidate valves were chosen for logger placement. As the network suffers
from the same problems as zone 6 (having mostly plastic pipes, long dead end connections, etc.),
noise data loggers are effective up to a certain extent. At the point where data loggers become
ineffective, ground microphoning crew will step in. In Table 6.17 number of valves and number of
loggers placed in each artificially divided region are given.
Table 6.17 Number of Valves and Loggers Placed in Zone 2
Region
A
B
C
Number of Valves
28
17
20
Number of Loggers Placed
20
12
16
Total
65
48
Before starting field works in zone 2, SCADA centre is informed to deactivate the pressurereducing valve at the entrance of the zone. With this action done, a higher pressure will be present in
the system which will make the water leaks flow in higher amounts and generate higher sounds. When
the leaks generate higher sounds and vibrations, both leak noise logger devices and ground
microphone devices will be able to detect and pinpoint the leaks better.
According to the SCADA records, the pressure is released to its normal level on 12.04.2010
at 14:20. With this action, water entering to zone 2 and minimum night flows of the zone increased in
high amounts.
With the equipped 20 loggers, data logger study was first done in region “A” (east of 7th
avenue and north of 5th avenue) on 12.04.2010. The loggers were programmed to record possible leak
noises between 02:00 and 05:00 in 10-second intervals ensuring similar conditions done in zone 6.
They are programmed to send the recorded data to the master unit, the day after between 10:00 and
12:00. On 13.04.2010, 16 more loggers were placed on region “C” (west of 7th avenue and north of 5th
133
avenue). Finally, on 14.04.2010 12 loggers were placed on region “B” (south of 5th avenue).
In region A, three leak alerts were received from loggers #3605, #3645 and #3612. First two
of these pointed the same point. These alerts were named as alert 8, alert 9 and alert 10.
In region C, three more leak alerts were received from loggers #3652, #3641 and #3625.
These alerts are named as alert 11, alert 12 and alert 13.
Finally, in region B, one leak alert was received from logger #3622. This is named as alert
14. These 7 alerts are explained in detail below. After collecting these leak alerts, ground
microphoning studies are performed. Those studies are explained in the next section.
Alert #8 and Alert#9: Three data loggers were placed on three different valves located on
th
625 street, in front of “Hotel Starlight” as in Figure 6.49. Two of these data loggers reported leak
alert. These two loggers have the serial number 3605 and 3645. Their corresponding noise graphs are
given in figures below (Figure 6.50 and Figure 6.51).
Figure 6.49 Noise Data Loggers with Serial Numbers 3605, 3608 and 3645 Placed On Valves
#20814, #20854 and #20815 with Their Corresponding Effective Areas
In this measurement, the third data logger did not receive a leak sound. It can be interpreted
as the possible leak is either on Ø150mm PVC pipe or on Ø90mm PVC pipe, as they are not directly
connected to the valve that did not receive leak sound. The effective area of logger #3608 may not
include the leak spot either. Another interpretation can be the use of 90-degree elbow and reduction
fittings may have an effect on the fading out of the leak noise. As seen from the figure, there are four
different pipe diameters at the intersection point, and there has to be some diameter reduction fittings
134
in the connections. These fittings may have reduced the sound of a possible leak.
Figure 6.50 Details of Logger with Serial Number 3605 Placed On Valve #20814
Figure 6.51 Details of Logger with Serial Number 3645 Placed On Valve #20854
135
When looking at Figure 6.50 and Figure 6.51, it is easy to say that the possible leak point is
nearer to valve #20854 as its minimum sound level is 1794 whereas from valve #20814 only a
minimum sound level of 424 is recorded. In addition, there is a big difference in the frequency values.
Valve #20854 seems to point a leakage better than valve #20814 by having a frequency of 523 Hz.
Width values are better in $20814 therefore its recording has less interference and represents a better
recording quality.
The ground microphone studies cleared this spot and a leak was found. It is explained as
“Leak 7” in the next chapter.
Alert #10: The logger having the serial number of 3612 is placed on the valve with ID 31910
th
on 600 street, in front of Villa Park Apartment. Below in Figure 6.52 the position of the valve is
seen. In addition, the corresponding buffer areas with 10 meter and 25 meter radius can be seen too.
Pipes at this corner are coded as Ø110mm PVC and Ø200mm HDPE pipes.
Figure 6.52 Noise Data Logger with Serial Number 3612 Placed On Valve #31910 and Its
Corresponding Effective Areas
136
Figure 6.53 Details of Logger with Serial Number 3612 Placed On Valve #31910
Above, it is given the output figure for the logger with serial number 3612 (Figure 6.53). It
gives a minimum level as 159. Frequency is reported as 222 Hz. Width is given as 191. According to
the minimum level value, the possible leak is either a small leak or it is at a distance away from the
valve. To find and pinpoint the probable leak, a ground microphoning study was scheduled. While
studying at this place, it was also seen that a small water puddle in front of the next building (Đnci
Saray Otel). As the puddle was inside the garden, it was thought of an accumulation of water because
of watering the plants. Still it was noted as a possible leaking spot. After the ground microphoning
studies the leak was found. It is discussed in detail as “Leak 6” in the next chapter.
Alert #11: Leak noise logger with serial number 3652 was placed on the valve with ID 27070
th
on 6 avenue (Figure 6.54). This valve is the valve at the connection point between zone 6 and zone 2.
During the studies in zone 6, a nearby valve pointed out this valve to be faulty and the administration
decided to install a new valve assuming that it is faulty. After renewing the valve and shutting it, a
possible connection between these two pressure zones are assumed to be blocked. However, during
this last data logging study, the valve sounded like a leak sound. This time the minimum sound level
exceeded the noise data logger’s ranges and recorded a maximum level of 3000 with a frequency 761
Hz (Figure 6.55). This situation first lead to a thought that if the valve was left slightly open
unintentionally after the construction studies. To prove this, the isolation valve was checked and seen
that it was closed firmly. Then the field staff of ASAT warned the ground microphoning crew about
the pipeline located there is not buried to the ground due to the bridge over the creek at that point.
137
Finally the sound being recorded is interpreted as the environmental sound hitting the pipeline under
the bridge and being detected at the noise data logger.
Figure 6.54 Noise Data Logger with Serial Number 3652 Placed On Valve #27070 and Its
Corresponding Effective Areas
Figure 6.55 Details of Logger with Serial Number 3652 Placed On Valve #27070
Alert #12: At the intersection of 655th street and 5th avenue, noise data logger with serial
number #3641 is placed on the valve. There are Ø100mm, Ø110mm and Ø150mm PVC pipes and
138
Ø150mm asbestos cement pipes at this place (Figure 6.56). Placed logger reported a leak alert
depending on the measurements of minimum level of 1392, a high value and frequency level of 761
Hz. The width value showing the quality of measurement is 240, which can be considered as a
moderate value (Figure 6.57). According to these results, a water leakage seems almost certain in
nearby locations. However with the ground microphoning studies done carefully on this location,
operators were unable to pinpoint a leak spot. They were not able to hear a water leakage with their
devices. So nowhere at this intersection was excavated.
Figure 6.56 Noise Data Logger with Serial Number 3641 Placed On Valve #27259 and Its
Corresponding Effective Areas
139
Figure 6.57 Details of Logger with Serial Number 3641 Placed On Valve #27259
Alert #13: Alert 13 is reported by logger #3625 on the intersection of 5th avenue and 600th
street. At this intersection, there are totally three valves located on the pipes as seen in Figure 7.17.
Three noise data loggers were placed on these valves but only logger #3625 reported a leak sound
with a graph shown in Figure 6.58. This might be interpreted as the possible leak may be either on
Ø150mm PVC pipe to the west, as the sounding valve is the only valve on that pipe, or the leak may
be on the Ø200mm HDPE pipe towards north in a place that only #3625 can hear its sound not the
other two. This can be supported by having a possible leak at the other end of 600th street, which is a
case explained in alert #10. However a distance of around 100m between these two locations
invalidate this thought as sound of a leaking spot is not seen to travel this much of a distance in plastic
pipes as far as in this study. With a relatively low minimum sound level of 303 and a frequency level
of 365Hz the possible leak seems to be small or far away from the valve (Figure 6.59). After getting
these results, a ground microphoning study was performed. Even though listening the nearby streets
with more effort than usual listening, no sign of a water leakage was heard by the operators. No
operations were performed at this place.
140
Figure 6.58 Noise Data Logger with Serial Number 3625 Placed On Valve #20716 and Its
Corresponding Effective Areas
Figure 6.59 Details of Logger with Serial Number 3625 Placed On Valve #20716
Alert #14: Last alert was reported on the intersection of 603rd and 607th streets in front of a
mosque named “Deniz Kenarı Cami” (Figure 6.60). At this place, five different pipes intersect on two
different points. Similar to the previous situation, only one of the three placed loggers reported a leak
141
sound. This logger had the serial number of #3622. According to the theoretical buffer areas
generated, the leak may be present towards the 607th street (on Ø110mm HDPE pipe) or towards the
unnamed street which goes to the mosque entrance (Ø100mm PVC pipe).
Having a low minimum noise level of 315 may indicate that the leak is at some distance
away from the valve. The measurement had a very low width value of 62 (Figure 6.61). This states a
good quality measurement. Scheduled ground microphoning studies revealed this alert and a leak was
found on Ø100mm PVC pipe. This is explained as “Leak 11” in the next section.
Figure 6.60 Noise Data Logger with Serial Number 3622 Placed On Valve #21037 and Its
Corresponding Effective Areas
142
Figure 6.61 Details of Logger with Serial Number 3622 Placed On Valve #21037
6.3.4.2.Ground Microphoning in Logger Ineffective Areas
Ground microphoning is applied to zone 2 when the logger study was still running. This is
done due to time limitations. Applying logger first, and according to their results running ground
microphone studies requires more than a week’s time as the DMA is larger. To cover the whole area
in five working days, logger study and ground microphoning were applied as concurrent events. As a
matter of fact, logger effective areas were also scanned with ground microphones. The thing to note at
this point is that, ground microphoning study did not obviate data logger studies. Data logger studies
cleared the way for ground microphoning studies, and ground microphoning studies helped
pinpointing of the leaks as a supportive action. In general terms, the methodology was applied on the
field completely.
Although running both data logger and ground microphoning studies at the same time, only
two thirds of the zone could be listened with the microphones. These regions are A and B (Figure
6.43). For region C, an agreement was done with the water authorities of Antalya, to schedule the
ground microphoning crew as soon as possible before the pressures are reduced again. Unfortunately,
listening of region C was done about one month later and with reduced pressures. This is figured out
by exploring through the previous SCADA records. The pressure was released while working with the
143
noise data loggers. Moreover, this release lasted one week (7 days) only. After 7 days, the pressure is
reduced to 3.0 bars and it was not released during the days when region C is said to be listened. This
deeply affected the study as no leaks are found in region C. During the logger studies combined with
ground microphones in regions A and B a total of 6 water leaks are found and repaired. This event
also proved that under high pressures it is easier to find leaks. With 5.5 bars, both ground
microphones and data loggers are able to detect leak sounds. However when this pressure is reduced
to 3.0 bars, no leaks could be discovered by the microphones.
Ground listening staff examined the regions A and B as stated. They gave extra importance to
the alerting points. However, alerts 11, 12 and 13 did not result in a physical water loss. Alerts 8 and 9
turned out to be a leaking point explained below in “Leak 7”. Alert 10 was pointing “Leak 6”. And
alert 14 was an indication of “Leak 11”. In the logger ineffective areas, listening crew also was able to
pinpoint some leak points. These are named as leaks 8, 9 and 10. They are explained in detail below.
In the scanned two thirds of the zone, a total of six leaks were found and repaired.
Leak 6: The alerting spot in front of “Villa Park Apartment” is investigated by the ground
microphoning crew (Figure 6.62). Before their listening study, a water bleeding spot at the next
building was already seen. That suspicious point turned out to be a water leak at the house connection
of “Đnci Saray Otel”. The repair works were done on 14 April 2010.
Figure 6.62 Position of leak spot 6 and nearby logger effective areas.
Leak 7: This situation named as “Leak 7” is one of the most interesting situations faced
throughout the study in Konyaaltı. When the ground microphoning crew listened the suspicious
valves, they faced with a very high sound and pinpointed that most sounding spot. After the
excavation not a leaking point was discovered but a corporation cock (priz musluğu in Turkish) was
found. This fitting named corporation cock is a valve (mostly a spherical valve) at the connection
144
between a house connection and a street pipe. This valve was not leaking any water but making sound
like a leaking sound. It was checked and seen completely open meaning water was flowing through it.
With the careful investigations of the valve and the corresponding house connection after it, it was
discovered that none of the buildings were taking water from that pipe. Therefore that valve was
closed completely. Again, every nearby building is checked if there was any water shortage or not.
None of the customers complained about any water shortage problem. As a result, the valve was left
closed and buried. The reason for a ghost valve and a house connection was said to be an old house
connection, which is forgotten to be closed after the cancellation of the service pipe. For a long time
this house connection was letting water flow (Figure 6.63).
Figure 6.63 Position of leak 7 and the nearby valves with effective areas.
Leak 8: This leak was detected on 621st street on an Ø150mm PVC pipe by the ground
microphoning study. The nearest logger placed valve did not receive any leak sound because the leak
spot is approximately 70 meters away (Figure 6.64). Leak spot was in front of Baylav Apartment. The
failure occurred on the main PVC pipe. Failure reason is reported as the bad workmanship done
during the displacement of water pipes. The displacement is done because of the installation of
sewerage lines. Unlike most cities in Antalya, this is the common problem. Sewerage lines were
installed much later than water lines, and due to displacements of water pipes, failures occur. The
failure is repaired on 15 April 2010.
145
Figure 6.64 Position of leak 8 and the nearby valve with its effective area
Leak 9: This leak was detected on a nearby street as leak 8. It is very far away from the
nearest valve (approximately 90 meters). So its sound was not recognized by the data logger at that
valve (Figure 6.65). The leak was pinpointed by the ground microphoning crew. On the repair day of
16 April 2010, the failure is seen on the house connection of Yusuf Apartment. The house connection
was a low quality pipe, which is called by the workers as “black pipe” due to its colour. It is indeed a
black, plastic pipe but its main disadvantage is being a brittle material. Therefore, failure is inevitable
on these kinds of pipes. Luckily, they are not being used at all nowadays.
Figure 6.65 Leak spot 9 and the nearby data logger’s effective area.
Leak 10: This leak is pinpointed by the ground microphoning crew again. As seen in Figure
6.66, it is very far to the effective areas of data loggers. The failure was at the house connection of
146
“Ufuk Sitesi B Blok”. It is fixed by the ASAT workers on 16 April 2010.
Figure 6.66 Leak spot 10 and the nearby data logger’s effective area.
Leak 11: In this final pinpointed leak, the point was detected by the data loggers as alert #14.
According to that alert, the leak should be either on Ø110mm HDPE pipe or on Ø100mm PVC pipe.
With the careful examination of ground microphone crew, the leak was pinpointed on the house
connection of the mosque in 604th street (Figure 6.67). It is again repaired on 16 April 2010.
Figure 6.67 Leak spot 11 and the nearby data loggers’ effective areas.
147
6.3.5.
Results
In zone 2 of Konyaaltı water distribution network, two major actions have been done to avoid
physical water losses. First step was to reduce the pressure of the zone to a constant value. This action
was done in August 2009 and its effects are discussed in two aspects. They will be studied below with
more detail. As a second step, within the limited working time of one week, physical water loss
detection studies are performed. The studies are performed using noise data loggers and ground
microphones. To detect and pinpoint the leaks precisely, pressure of the network was released for one
week. After fixing the leaks, pressures are lowered again to the constant value.
With applying these two steps of pressure reduction and physical water loss detection studies,
a considerable amount of water loss is prevented. In the light of results obtained, it is concluded that
applying both pressure management and active leak detection techniques together are indispensible.
Two methods are highly effective on their own, however when they are combined, their effects
increase.
To examine the graphs and results below, it may be necessary to recall the actions done in the
DMA; that are summarized in Table 6.18 and Table 6.19.
Table 6.18 Applied Pressure Regulations on Zone 2 with Their Dates and Times
Applied Action
Pressure Reduction from 5.5 bars to 3.6 bars
Pressure Reduction from 3.6 bars to 3.0 bars
Pressure Release from 3.0 to 5.5 bars
Pressure Reduction from 5.5 bars to 3.0 bars
Date and Time
12.08.2009 – 11:30
28.09.2009 – 10:00
12.04.2010 – 14:10
19.04.2010 – 10:50
Table 6.19 Leaks, Their Regions, Discovery Methods and Repair Dates
Leaks
Region Discovery Method
6
A
7
A
8
Logger + G.
Microphone
Repair Date
14.04.2010
A
Logger + G.
Microphone
G. Microphone
15.04.2010
9
A
G. Microphone
16.04.2010
10
A
16.04.2010
11
B
G. Microphone
Logger + G.
Microphone
14.04.2010
16.04.2010
148
The effects of pressure reduction done in 2009 are studied in earlier chapters. To see the
effect of pressure release followed by the leak repairs, the daily demand curves of the DMA between
11 April and 20 April should be examined. They are given below in Figure 6.68 to Figure 6.77.
First thing that draws attention from the daily demand curves is the rise of discharge values
with the released pressure. On 11 and 12 April 2010, minimum night flow values are on 36 m3/h level
(Figure 6.68 and Figure 6.69). When the pressures are released, this value jumps up immediately to
49.3 m3/h (Figure 6.70). This means that an additional loss of 13 m3/h is created by releasing the
pressure from 3 bars to 5 – 5.5 bars.
With the detection of physical water losses and repairing them, minimum night flow values
decrease gradually day by day. They are clearly seen in each day’s daily demand curve. Total decrease
is from 49.3 m3/h to 38.6 m3/h avoiding a water loss of 10.7 m3/h (Figure 6.71 to Figure 6.77). The
only exceptional day to this gradual decrease is 18 April 2010. According to the SCADA records, a
higher minimum night flow is observed on 18 April when compared to 17 April. That can be
interpreted as a false minimum night flow value. At that night, the customers showed high night
usage, so the SCADA records were not able to capture the minimum night flow values.
Another thing that is worth mentioning is the short periods of discharge and pressure
recordings of zero values. These are seen on 14, 15 and 16 April 2010. These shortages are generated
by the workers of ASAT, in order to fix the leaks. Short periods of announced water shortages help
the workers to fix the leaks quicker.
Similarly, when the pressure is reduced down to 3.0 bars again, a drop of 9.3 m3/h is
observed. It is clearly seen when 19 April and 20 April graphs are examined. Therefore, both pressure
reduction and active water leak detection are actions worth doing to prevent water losses (Figure
6.77).
In Figure 6.78, the effects of overall actions on the DMA can be seen in a single graph.
Starting from 12 April, first the pressures are released. Then repairs are done in the network dropping
the minimum night flows. Lastly, pressures are again reduced and a drop in minimum night flows
occurred again.
149
Deily Demand Curve of Zone 2 – 11 April 2010
80
3.50
70
3.00
2.50
50
2.00
40
1.50
30
1.00
20
3
Minimum Night Flow = 36.1 m /h
10
0.50
Discharge
Pressure
Time
Figure 6.68 Daily Demand Curve of Zone 2 on 11.04.2010
23:15
22:30
21:45
21:00
20:15
19:30
18:45
18:00
17:15
16:30
15:45
15:00
14:15
13:30
12:45
12:00
11:15
10:30
09:45
09:00
08:15
07:30
06:45
06:00
05:15
04:30
03:45
03:00
02:15
01:30
00:45
0.00
00:00
0
Pressure (bar)
Discharge (m3/h)
60
15
Deily Demand Curve of Zone 2 – 12 April 2010
140
6.00
120
5.00
4.00
80
3.00
60
2.00
40
1.00
20
3
Minimum Night Flow = 36.4 m /h
Discharge
Pressure
Time
Figure 6.69 Daily Demand Curve of Zone 2 on 12.04.2010
23:15
22:30
21:45
21:00
20:15
19:30
18:45
18:00
17:15
16:30
15:45
15:00
14:15
13:30
12:45
12:00
11:15
10:30
09:45
09:00
08:15
07:30
06:45
06:00
05:15
04:30
03:45
03:00
02:15
01:30
00:45
0.00
00:00
0
Pressure (bar)
Discharge (m3/h)
100
15
120
6.00
100
5.00
80
4.00
60
3.00
40
2.00
3
Minimum Night Flow = 49.3 m /h
20
1.00
Discharge
Pressure
Time
Figure 6.70 Daily Demand Curve of Zone 2 on 13.04.2010
23:15
22:30
21:45
21:00
20:15
19:30
18:45
18:00
17:15
16:30
15:45
15:00
14:15
13:30
12:45
12:00
11:15
10:30
09:45
09:00
08:15
07:30
06:45
06:00
05:15
04:30
03:45
03:00
02:15
01:30
00:45
0.00
00:00
0
Pressure (bar)
Discharge (m3/h)
Deily Demand Curve of Zone 2 – 13 April 2010
15
6.00
250
5.00
200
4.00
150
3.00
100
2.00
50
1.00
3
Discharge
23:15
22:30
21:45
21:00
20:15
19:30
18:00
17:15
16:30
15:45
15:00
14:15
13:30
12:45
12:00
11:15
10:30
Time
Figure 6.71 Daily Demand Curve of Zone 2 on 14.04.2010
Pressure
0.00
09:45
09:00
08:15
07:30
06:45
06:00
05:15
04:30
03:45
03:00
02:15
01:30
00:45
00:00
0
Minimum Night Flow = 48.9 m /h
Pressure (bar)
300
18:45
Discharge (m3/h)
Deily Demand Curve of Zone 2 – 14 April 2010
15
Deily Demand Curve of Zone 2 – 15 April 2010
6.00
200
180
5.00
160
4.00
120
3.00
100
80
2.00
60
40
1.00
20
3
Discharge
23:15
22:30
21:45
21:00
20:15
19:30
18:45
18:00
17:15
16:30
15:45
15:00
14:15
13:30
12:45
12:00
11:15
10:30
Time
Figure 6.72 Daily Demand Curve of Zone 2 on 15.04.2010
Pressure
0.00
09:45
09:00
08:15
07:30
06:45
06:00
05:15
04:30
03:45
03:00
02:15
01:30
00:45
Minimum Night Flow = 47.6 m /h
00:00
0
Pressure (bar)
Discharge (m3/h)
140
15
Deily Demand Curve of Zone 2 – 16 April 2010
6.00
100
90
5.00
80
4.00
60
3.00
50
40
2.00
30
20
1.00
3
Minimum Night Flow = 41.5 m /h
10
Discharge
Pressure
Time
Figure 6.73 Daily Demand Curve of Zone 2 on 16.04.2010
23:15
22:30
21:45
21:00
20:15
19:30
18:45
18:00
17:15
16:30
15:45
15:00
14:15
13:30
12:45
12:00
11:15
10:30
09:45
09:00
08:15
07:30
06:45
06:00
05:15
04:30
03:45
03:00
02:15
01:30
00:45
0.00
00:00
0
Pressure (bar)
Discharge (m3/h)
70
15
120
6.00
100
5.00
80
4.00
60
3.00
40
2.00
20
3
Minimum Night Flow = 39.6 m /h
1.00
Discharge
Pressure
Time
Figure 6.74 Daily Demand Curve of Zone 2 on 17.04.2010
23:15
22:30
21:45
21:00
20:15
19:30
18:45
18:00
17:15
16:30
15:45
15:00
14:15
13:30
12:45
12:00
11:15
10:30
09:45
09:00
08:15
07:30
06:45
06:00
05:15
04:30
03:45
03:00
02:15
01:30
00:45
0.00
00:00
0
Pressure (bar)
Discharge (m3/h)
Deily Demand Curve of Zone 2 – 17 April 2010
15
120
6.00
100
5.00
80
4.00
60
3.00
40
2.00
3
Minimum Night Flow = 41.3 m /h
20
1.00
Discharge
Pressure
Time
Figure 6.75 Daily Demand Curve of Zone 2 on 18.04.2010
23:15
22:30
21:45
21:00
20:15
19:30
18:45
18:00
17:15
16:30
15:45
15:00
14:15
13:30
12:45
12:00
11:15
10:30
09:45
09:00
08:15
07:30
06:45
06:00
05:15
04:30
03:45
03:00
02:15
01:30
00:45
0.00
00:00
0
Pressure (bar)
Discharge (m3/h)
Deily Demand Curve of Zone 2 – 18 April 2010
15
Deily Demand Curve of Zone 2 – 19 April 2010
100
6.00
90
Discharge (m3/h)
70
4.00
60
50
3.00
40
2.00
30
3
Minimum Night Flow = 38.6 m /h
20
1.00
10
Discharge
Pressure
Time
Figure 6.76 Daily Demand Curve of Zone 2 on 19.04.2010
23:15
22:30
21:45
21:00
20:15
19:30
18:45
18:00
17:15
16:30
15:45
15:00
14:15
13:30
12:45
12:00
11:15
10:30
09:45
09:00
08:15
07:30
06:45
06:00
05:15
04:30
03:45
03:00
02:15
01:30
00:45
0.00
00:00
0
Pressure (bar)
5.00
80
15
Deily Demand Curve of Zone 2 – 20 April 2010
90
3.50
80
3.00
70
50
2.00
40
1.50
30
1.00
20
3
10
0.50
Minimum Night Flow = 29.3 m /h
Discharge
Pressure
Time
Figure 6.77 Daily Demand Curve of Zone 2 on 20.04.2010
23:15
22:30
21:45
21:00
20:15
19:30
18:45
18:00
17:15
16:30
15:45
15:00
14:15
13:30
12:45
12:00
11:15
10:30
09:45
09:00
08:15
07:30
06:45
06:00
05:15
04:30
03:45
03:00
02:15
01:30
00:45
0.00
00:00
0
Pressure (bar)
Discharge (m3/h)
2.50
60
15
Minimum Night Flows vs Pressures
60
50
3
Min. Night Flow (m /h)
13.04.2010; P=5,50 bar;
Qnightmin= 49,3m³/h
12.03.2010; P=3,00 bar;
Qnightm in= 36,4 m³/h
40
19.04.2010; P=5,50 bar;
Qnightmin=38,6m³/h
30
20.04.2010; P=3,00 bar;
Qnightmin= 29,3 m³/h
20
2
2,5
3
3,5
4
Pressure (bar)
Figure 6.78 Minimum Night Flows vs. Pressures in Zone 2 before and after the Field Studies
4,5
5
5,5
6
16
Considering the values in Figure 6.78, 12.9 m3/h loss is prevented just by reducing pressure.
That is a drop of 26%. With the leaks fixed only, a drop of 10.7 m3/h is achieved in minimum night
flows. That is a drop of 21.7%. With the actions done together, a drop of 7.1 m3/h is obtained from
36.4 m3/h value at the 3 bar level. That corresponds to a drop of 19.5%. To examine day-by-day
changes in minimum night flows and total water entering to the zone, Table 6.20 is given below.
Table 6.20 SCADA Summary Table for Zone 2
Date
Days
Water
Entering to
Zone 6 (m3)
01.03.10
02.03.10
03.03.10
04.03.10
05.03.10
06.03.10
07.03.10
08.03.10
09.03.10
10.03.10
11.03.10
12.03.10
13.03.10
14.03.10
15.03.10
16.03.10
17.03.10
18.03.10
19.03.10
20.03.10
21.03.10
22.03.10
23.03.10
24.03.10
25.03.10
26.03.10
27.03.10
28.03.10
29.03.10
30.03.10
31.03.10
01.04.10
02.04.10
03.04.10
04.04.10
05.04.10
Mon
Tue
Wed
Thu
Fri
Sat
Sun
Mon
Tue
Wed
Thu
Fri
Sat
Sun
Mon
Tue
Wed
Thu
Fri
Sat
Sun
Mon
Tue
Wed
Thu
Fri
Sat
Sun
Mon
Tue
Wed
Thu
Fri
Sat
Sun
Mon
1370
1330
1388
1362
1310
1410
1390
1340
1400
1400
1418
1482
1400
1360
1390
1400
1370
1380
1400
1420
1410
1370
1400
1400
1400
1455
1445
1330
1420
1400
1400
1427
1433
1460
1530
1510
Minimum
Night Flow
(m3/h)
Minimum
Flow
Time
32,9
31,8
32,1
34,7
32,6
31,9
34,9
33,3
32,1
32,1
33,7
33,7
31,4
29,5
30,9
34,9
32,2
31,8
31,9
31,1
32,4
32,8
32,7
34,2
31,9
34,7
32,4
34,7
31,6
30,3
32,3
33,3
33,4
31,9
34,6
33,9
03:05
05:20
05:05
02:25
05:25
05:05
05:35
04:50
04:30
05:05
04:45
05:20
04:50
04:50
04:30
04:20
05:20
05:05
04:50
04:35
04:35
04:45
02:40
02:30
04:15
03:10
03:45
06:35
04:10
05:25
04:45
05:45
04:20
05:40
04:35
04:15
Total
Lost
Water
(m3)
789,61
762,42
771,09
833,67
782,81
766,41
838,13
799,69
769,92
770,39
809,77
809,53
754,22
707,58
742,73
838,59
772,97
762,66
765,00
746,95
777,19
787,27
783,75
819,84
765,94
833,44
777,19
832,73
757,50
726,33
775,03
799,22
800,86
766,64
830,63
814,69
Water
Loss /
Total Flow
(%)
57,636
57,325
55,554
61,209
59,757
54,355
60,297
59,678
54,994
55,028
57,106
54,624
53,873
52,028
53,434
59,900
56,421
55,265
54,643
52,602
55,120
57,465
55,982
58,560
54,710
57,281
53,785
62,612
53,345
51,881
55,359
56,007
55,887
52,510
54,289
53,953
161
06.04.10
07.04.10
08.04.10
09.04.10
10.04.10
11.04.10
12.04.10
13.04.10
14.04.10
15.04.10
16.04.10
17.04.10
18.04.10
19.04.10
20.04.10
21.04.10
22.04.10
23.04.10
24.04.10
25.04.10
26.04.10
27.04.10
28.04.10
29.04.10
30.04.10
01.05.10
02.05.10
03.05.10
04.05.10
05.05.10
06.05.10
07.05.10
08.05.10
09.05.10
10.05.10
11.05.10
12.05.10
13.05.10
14.05.10
15.05.10
16.05.10
17.05.10
18.05.10
19.05.10
20.05.10
21.05.10
22.05.10
23.05.10
24.05.10
25.05.10
Tue
Wed
Thu
Fri
Sat
Sun
Mon
Tue
Wed
Thu
Fri
Sat
Sun
Mon
Tue
Wed
Thu
Fri
Sat
Sun
Mon
Tue
Wed
Thu
Fri
Sat
Sun
Mon
Tue
Wed
Thu
Fri
Sat
Sun
Mon
Tue
Wed
Thu
Fri
Sat
Sun
Mon
Tue
Wed
Thu
Fri
Sat
Sun
Mon
Tue
1440
1400
1480
1467
1463
1422
1644
1774
1660
1690
1630
1630
1640
1500
1350
1360
1400
1500
1490
1450
1388
1362
1400
1370
1322
1358
1450
1450
1430
1420
1400
1380
1390
1380
1464
1536
1570
1530
1550
1510
1494
1516
1380
1430
1420
1400
1360
1360
1450
1390
Table 6.20 Continued
32,2
04:50
31,9
05:15
33,3
05:15
33,2
04:45
34,2
04:20
36,1
03:55
36,4
05:20
49,3
05:00
49,0
05:00
47,6
03:55
41,5
04:55
39,6
03:35
41,3
06:20
38,6
04:45
29,3
05:00
28,3
05:45
30,9
05:00
30,7
05:40
35,4
03:55
31,6
05:40
29,7
04:10
29,7
05:05
26,9
04:50
31,8
05:05
31,1
05:15
28,0
04:40
32,1
05:10
30,9
05:10
30,3
04:45
29,7
04:50
30,9
04:50
31,6
04:15
28,5
04:40
28,9
04:40
29,6
04:35
33,7
04:50
32,3
04:55
34,7
04:50
32,5
04:40
33,1
05:30
33,1
04:40
33,2
05:00
32,5
04:40
30,5
04:35
30,7
03:15
31,1
05:30
29,5
05:35
31,2
04:25
30,2
05:35
30,8
06:05
772,73
766,41
800,39
797,34
820,31
865,31
872,81
1182,66
1176,47
1143,52
996,33
950,63
990,70
926,25
702,66
680,39
742,50
736,88
848,91
757,27
712,03
712,97
645,70
762,66
746,02
673,13
770,86
742,03
726,56
711,80
741,56
757,97
685,08
693,28
710,86
809,06
774,84
832,73
779,30
794,40
793,36
796,41
781,03
731,95
736,64
746,95
708,98
748,59
723,75
738,28
53,662
54,743
54,080
54,352
56,071
60,852
53,091
66,666
70,872
67,664
61,124
58,321
60,409
61,750
52,049
50,029
53,036
49,125
56,974
52,225
51,299
52,347
46,122
55,668
56,431
49,567
53,163
51,175
50,809
50,127
52,969
54,925
49,286
50,238
48,556
52,673
49,353
54,427
50,277
52,609
53,103
52,533
56,596
51,186
51,876
53,354
52,131
55,044
49,914
53,114
162
26.05.10
27.05.10
28.05.10
29.05.10
30.05.10
31.05.10
Wed
Thu
Fri
Sat
Sun
Mon
1408
1405
1477
1520
1480
1450
Table 6.20 Continued
29,3
04:45
29,4
04:40
26,1
04:30
30,5
06:05
31,4
05:35
32,8
03:30
703,36
704,53
625,55
732,19
754,22
787,27
49,955
50,145
42,353
48,170
50,961
54,294
In Figure 6.79 below daily total water entering to zone 2 and minimum night flows for each
day are plotted. It is seen that with the increasing pressure, the values show a great increase for one
week. The decrease in minimum night flows from 30 – 35 m3/h level to 25 – 30 m3/h level is seen in
the graph too.
Figure 6.80 describes better the decrease in water loss percentages. Before this study, the
water loss percentages were at a range of 55% – 60 %. During the study week, it is seen as high as
70%. After fixing the leaks and reducing the pressure, the leak percentages drop down to 50% – 55%.
That is a drop of 5% showing the effect of active studies.
163
16
55
50
45
40
35
30
25
20
Qmin (m /h)
04.03.2010
07.03.2010
3
10.03.2010
13.03.2010
16.03.2010
Minimum Night Flows and Total Water Entrance Amounts vs Time
19.03.2010
22.03.2010
25.03.2010
28.03.2010
31.03.2010
03.04.2010
06.04.2010
09.04.2010
Time (Days)
Figure 6.79 Total Water Entering and Minimum Night Flow Values vs. Days
01.03.2010
12.04.2010
15.04.2010
18.04.2010
21.04.2010
24.04.2010
27.04.2010
30.04.2010
03.05.2010
06.05.2010
09.05.2010
12.05.2010
15.05.2010
Qmin
18.05.2010
21.05.2010
Qtotal (m )
24.05.2010
30.05.2010
3
Qtotal
27.05.2010
1800
1700
1600
1500
1400
1300
1200
16
% Loss
75
70
65
60
55
50
45
40
Figure 6.80 Water Loss Percentages vs. Days
01.Mar.10
05.Mar.10
09.Mar.10
13.Mar.10
17.Mar.10
21.Mar.10
25.Mar.10
29.Mar.10
06.Nis.10
10.Nis.10
14.Nis.10
18.Nis.10
22.Nis.10
26.Nis.10
30.Nis.10
04.May.10
08.May.10
12.May.10
16.May.10
20.May.10
24.May.10
28.May.10
Percentage Water Losses over Time
02.Nis.10
To check the revenue ratios, Table 6.21 and Figure 6.81 are given below. When the table is
examined, the pressure regulation in 2009 can be seen clearly on August and September months.
Revenue percentages increased from 55% level up to 70% level by pressure reduction. Also daily
average water entering to the zone decreased from 2000 m3/day level down to 1500 m3/day level.
However, the effects of active leak detection studies are not so distinct in both the table and the graph.
An increase of 3.64% from 2010/4 period to 2010/5 period may indicate the leak detection studies.
But the previous period does show an opposite reaction which is a 3% decrease from 2010/3 period to
2010/4 period. This may be because; active leak detection studies are performed in mid April.
Therefore the effects of them can only be seen in the second half of April consumptions which may
not be visible in 2010/4 period.
166
Table 6.21 Monthly Revenue Percentages
SCADA DATA
CIS DATA
Water Entering to
Average Daily Water
Period's Total
Daily Average
Monthly Revenue
Dates
Days
Zone 6 (m³)
Entering to Zone 6 (m³)
Period
Revenue (m³)
Revenue (m³)
Percentages (%)
A
B
C
D=C/B
E
F
G
H = 100xG/D
01.06.09 - 30.06.09
30
57700
1923,33
2009/6
31865
1036,30
53,88
01.07.09 - 31.07.09
31
67750
2185,48
2009/7
36597
1206,64
55,21
01.08.09 - 31.08.09
31
59240
1910,97
2009/8
47333
1312,67
68,69
01.09.09 - 30.09.09
30
49360
1645,33
2009/9
29740
1168,73
71,03
01.10.09 - 31.10.09
31
47508
1532,52
2009/10
31947
1089,07
71,06
01.11.09 - 30.11.09
30
43172
1439,07
2009/11
29291
990,33
68,82
01.12.09 - 31.12.09
31
42770
1379,68
2009/12
25952
845,39
61,27
01.01.10 - 31.01.10
31
41900
1351,61
2010/1
27026
847,94
62,74
01.02.10 - 28.02.10
28
38150
1362,50
2010/2
22693
800,33
58,74
01.03.10 - 31.03.10
31
43150
1391,94
2010/3
24003
860,68
61,83
01.04.10 - 30.04.10
30
44600
1486,67
2010/4
28337
874,41
58,82
01.05.10 - 31.05.10
31
44750
1443,55
2010/5
27897
901,68
62,46
(01.06.09 - 31.05.10)
365
535300
1466,58
362681
-
67.75
2009/6 2010/5
16
Figure 6.81 Revenue Percentages over Periods
2010/5
2010/4
2010/3
2010/2
2010/1
2009/12
2009/11
2009/10
2009/9
2009/8
2009/7
2009/6
Revenue %
80
70
60
50
40
30
20
10
0
16
CHAPTER 7
7. DISCUSSION OF RESULTS
The importance of controlling water losses revealed itself before, during and after the field
studies. At the beginning, calculated physical water loss amounts of more than 50% showed the fact
that considerable losses (potable water loss, electricity loss, efforts spent for treating water, etc.) do
occur. After all, it does not seem reasonable to provide 100 units of water knowing that at least 50
units is being lost and not taking any action against this issue for years.
In order to fight against physical water losses, basically there are two methods. One is to
detect point losses using standard procedure(s) and then fixing the leaks. The second is based on
pressure management. In fact, these two methods are complementary.
During Antalya case studies, it was possible to make controlled experiments with two
networks (subzone 2 and subzone 6 of Konyaaltı pressure zone); the two study areas were similar. The
essential difference was that, pressure management was applied only to subzone 2. Certainly, in
subzone 2, concerning to reduce physical water losses, more satisfactory results were obtained with
respect to subzone 6 where pressure management was not applied.
Table 7.1 summarizes the overall effects of the water leak repairs in both physical water loss
aspect (considering minimum night flows obtained from SCADA) and monthly revenue loss
percentage aspect (considering both SCADA records and CIS records). According to Table 7.1 in both
zones, considerable amounts of reductions are obtained. The values for comparison are selected
during the high-pressure periods (which may be considered as the same in both zones). In addition,
considering 344 properties in zone 6 and 474 properties in zone 2, minimum night flow values are
computed to compare with the UK values supplied by Butler (2000) given in Section 4.4.2.
Considering the values before repairs and after repairs, it can be easily concluded that step
testing, forming sub-DMAs and similar preparations lead to a better performance in water leak
detection. In zone 6 by making step tests and prioritizing the sub-DMAs, a reduction of 963
l/property/day is achieved; on the other hand, in zone 2 without any step tests and preparations only a
reduction of 543 l/property/day is achieved.
169
In addition, to check the final leak levels obtained after the repairs it is seen that, leak levels
in Antalya are too much compared to the UK values. Butler (2000) gave 55 l/property/day as an
acceptable level of leakage; however, Antalya values are around 1500 l/property/day and 2000
l/property/day in zones 6 and 2 respectively.
Table 7.1 Overall Summary Table for the Case Studies
Physical Water Losses
Zone 6
Zone 2
Before Repairs
After Repairs
34.8 m³/h
21 m³/h
68.6%
49.4%
2428 l/prop/day
1465 l/prop/day
(06.04.2010)
(12.04.2010)
49.3 m³/h
38.6 m³/h
66.67%
61.75%
2496 l/prop/day
1954 l/prop/day
(13.04.2010)
(19.04.2010)
Monthly Revenue Loss Percentages
Before Repairs
After Repairs
63.66%
52.15%
(2010/02)
(2010/05)
38.17%
37.54%
(2010/03)
(2010/05)
170
CHAPTER 8
8. CONCLUSIONS AND SUGGESTIONS FOR FUTURE STUDIES
The importance of Information Technologies (GIS, SCADA and CIS) concerning the studies
for the reduction of physical water losses were brought to light in a detailed manner.
One of the compelling conditions faced during the case studies was the misleading GIS data.
Due to lack of attention while generating GIS data, leads field staff to make wrong decisions about the
case, and causes to lose considerable amount of time. In zone 6, careless operations of an office
personnel lead to digitizing double service connections for a single building. Also there were
numerous other mistakes in other layers. Very recent constructed connections and placed valves were
not digitized until a request from field staff was delivered. It also shows a miscommunication problem
between different units of the administration. To eliminate such problems, all the water loss related
departments should be combined under a different organization in the administration so that a good
and fast communication between units could be ensured. Especially, to be able to control better the
water distribution network and the actions done to it, there should be only one unit in the water
authority, which deals with monitoring, detection and repairing of the leaks.
The topic of water losses will gain more importance in the next years. The technological
developments allow production of more detailed and better water loss detection equipments. SCADA
systems are developing in a positive manner also. With better SCADA systems and computer
networks, it can be made possible a low data transmitting tolerance in the SCADA systems. It is
possible with today’s technology but higher data transmitting tolerances are being preferred in order to
save disk space in the computers and to avoid possible radio scrambles. If this issue is solved, then
obtaining more precise daily demand curves will be possible. In addition, storage tank elevations will
be obtained with better precisions.
Unfortunately, water administrations discover the importance of saving water only whenever
a drought season appears. However, saving the tiniest drop of water has a small but meaningful
contribution to the valuable water reserves. Administrations then should focus on their customer
171
information systems and keep a GIS integrated customer information database (CIS). Consumptions
should be monitored and recorded with the highest accuracy available. Transforming usual water
meters into more precise water meters can be a positive move towards gaining more revenue from the
customers. Moreover, using new generation water meters that have the ability to log consumption data
over time can lead the way of obtaining individual water usage behaviours (and daily demand curves)
of customers. With these water meters, it would be possible to eliminate the errors that are faced
through this study during the computation of revenue loss amounts.
By applying water distribution system master projects, big amounts of investments are laid
under the ground without having precise location information of the infrastructure. To have the
maximum benefit from the water distribution system elements, infrastructure knowledge should be
reliable. Starting from detection of fittings in the network and then detecting the pipeline routes are a
must to deal with water leaks. Geographical information systems provide exactly the needed solution
for infrastructure location determination. Water administrations should discover the importance of
generating reliable GIS data layers and should keep them up to date. Discovering the whole system at
once and keeping it up to date is the easiest solution when compared to having unreliable and out of
date GIS data layers.
Pressure management, in summary, seems to be as a very easy and effective solution for
water loss controlling. However, it hides the leaks at a certain extent. In zone 2 of Antalya water
distribution network, two thirds of it was scanned with ground microphones while pressure
management was suspended. This scanning helped pinpointing six leaks. In the remaining one thirds
of the network, ground microphoning was applied under reduced pressures. As a result, even one leak
point was not detected. It is almost impossible having no leak in that area, as all the conditions were
homogenous throughout the zone. Therefore, combined working of active leak detection studies and
pressure management is a very powerful method to choose. It should not be forgotten that both
methods (fixing point leaks) and pressure management are complementary methods.
172
REFERENCES
Aronoff, S. (1989) Modeling, Geographic information systems: a management
perspective, WDL Publications, Canada.
Bağcı, G., Integration of SCADA with GIS for Water Quality Modeling of
Distribution Network, M. Sc. Thesis, METU, Dept. of Env. Eng., 2001.
Bhave, P. R. (1991) Analysis of Flow in Water Distribution Networks, Technomic,
UK.
Butler, D. (2000) Leakage Detection and Management, Palmer Environmental, UK.
Cesario, L. (1995) Modeling, Analysis, and Design of Water Distribution Systems,
American Water Works Association, USA.
Eker, Đ., Analysis of Water Distribution Network Systems Using Information
Systems, M. Sc. Thesis, METU, Dept. of Civ. Eng., 1998.
Jones, M. (2006). “With Today’s Technology, What Percentage of unaccounted-for
water is OK?” American Water Works Association Journal, 98 (2), 32–33.
Hunaidi, O., Chu, W., Wang, A., Guan, W. (2000). “Detecting Leaks in Plastic
Pipes.” American Water Works Association Journal, 92 (2), 82–94.
Özkan, T., Determination of Leakages in a Water Distribution Network Using
SCADA Data, M. Sc. Thesis, METU, Dept. of Civ. Eng., 2001.
173
Özkan, T., Leakage Control by Optimal Valve Operation, Ph. D. Thesis, METU,
Dept. of Civ. Eng., 2008.
Shamsi, U. M. (2005) GIS Applications for Water, Wastewater, and Stormwater
Systems, CRC Pres, USA.
Shamsi, U. M. (2002) GIS Tools for Water, Wastewater, and Stormwater Systems,
American Society of Civil Engineers, USA.
Summers, P. (2001). “Finding Your Way” American Water Works Association
Journal, 93 (11), 58–61.
Thornton, J. (2002) Water Loss Control Manual, McGraw-Hill, USA.
Walski, T. M., Barnard, T. E., Durrans, S. R., Meadows, M. E., (2004) Computer
Applications in Hydraulic Engineering, Haestad Press, USA.
Walski, T. M., Chase, D. V., Savic, D. A., Grayman, W., Beckwith, S., Koelle, E.
(2003) Advanced Water Distribution Modeling and Management, Haestad Press,
USA.
Web
1,
Turkish
Statistical
Institute.
City
Populations
of
Year
2000.
<http://tuikrapor.tuik.gov.tr/reports/rwservlet?nufus2000db2=&ENVID=
nufus2000db2Env&report=il_koy_sehir_cinsiyet.RDF&p_kod=1&p_kod=1&desfor
mat=spreadsheet> (May 17, 2010).
Web 2, Turkish Statistical Institute. Konyaaltı Population of Year 2009.
<http://report.tuik.gov.tr/reports/rwservlet?adnksdb2=&report=turkiye_ilce_koy_seh
ir.RDF&p_il1=7&p_ilce1=2038&p_kod=2&p_yil=2009&p_dil=1&desformat=html
&ENVID=adnksdb2Env> (May 17, 2010).
174
Web
3,
Hermann
Sewerin
GmbH.
SePem
01
Operating
Instructions,
<http://www.sewerin.com/download/248.html> (March 20, 2010).
Web 4, Antalya Water and Wastewater Administration. Antalya Su ve Atıksu Bilgi
Sistemi. <http://www.asat.gov.tr/index.php?page=pages&PID=601> (May 20, 2010).
Web 5, International Water Association Efficient Operation and Management
Specialist Group. The IWA Water Loss Task Force Water 21 – Article No.2
Assessing Non-Revenue Water and its Components – a Practical Approach.
<http://www.iwaom.org/datosbda/Descargas/29.pdf> (July 31, 2010).
Web 6, International Water Association Efficient Operation and Management
Specialist Group. The IWA Water Loss Task Force Water 21 – Article No.4 Leak
Detection Practices & Techniques – A Practical Approach.
<http://www.iwaom.org/datosbda/Descargas/30.pdf> (July 31, 2010).
Web 7, International Water Association Efficient Operation and Management
Specialist Group. The IWA Water Loss Task Force Water 21 – Article No.5
Managing Leakage by District Metered Areas.
<http://www.iwaom.org/datosbda/Descargas/31.pdf> (July 31, 2010).
Web 8, United Nations Population Fund. State of World Population 2009 – Facing a
changing world: woman, population and climate.
<http://www.unfpa.org/swp/2009/en/pdf/EN_SOWP09.pdf> (August 14, 2010).
Web 9, Cors-TR System. Ulusal Cors Sisteminin Kurulması ve Datum Dönü ümü
Projesi.
<http://cors-tr.iku.edu.tr/> (May 1, 2010).
Web 10, Hermann Sewerin GmbH. Aquaph6on A 100 Operating Instructions,
<http://www.sewerin.com/download/211.html> (March 20, 2010).
175