INTERNATIONAL JOURNAL OF
PROJECT
MANAGEMENT
International Journal of Project Management 24 (2006) 53–65
www.elsevier.com/locate/ijproman
Framing of project critical success factors by a systems model
Joyce Fortune *, Diana White
Department of Technology Management, Faculty of Technology, The Open University, Walton Hall, Milton Keynes MK7 6AA, United Kingdom
Received 11 June 2004; received in revised form 27 June 2005; accepted 14 July 2005
Abstract
Perhaps the best known approach for tackling the human and organisational aspects of projects is through the use of Ôcritical
success factorsÕ but although the approach has very many champions it is not without its critics. This paper sets out the findings
of a major review of the sets of factors that are available and outlines the main reservations that have been expressed about the
approach. It then shows how a systems model, the Formal Systems Model, can be used as a framing device to deliver the benefits
of taking account of Ôcritical success factorsÕ whilst at the same time avoiding the problems associated with Ôcritical success factorsÕ
that give rise to the criticisms.
Two IS projects are used to demonstrate use of this framing devise. When observation began at the start of the projects they
looked very similar and equally likely to succeed. In the event, one of the projects was largely successful across the whole of the
range of measures normally used to judge success whilst the other exhibited most of the characteristics of failure. Analysis using
the framing device is well able to demonstrate the marked differences in the ways the two projects were managed and to account
for stark contrast in the levels of success achieved. The paper concludes that the Formal System Model allows the underlying benefits of Ôcritical success factorsÕ to be secured whilst overcoming most of the problems associated with a checklist approach.
2005 Elsevier Ltd and IPMA. All rights reserved.
Keywords: Critical success factors; Formal system model; Human and organisational aspects of projects
1. Introduction
The concept of success factors is usually credited to
Daniel [1] who introduced it in relation to the Ômanagement information crisisÕ that was being brought about
Ôby too rapid organizational changeÕ. In his seminal paper on the topic Rockart [2] unpacked the term Ôcritical
success factorsÕ (CSFs) thus:
. . .the limited number of areas in which results, if they
are satisfactory, will ensure successful competitive performance for the organization . . .
. . . the few key areas where Ôthings must go rightÕ for the
business to flourish.
*
Corresponding author. Tel.: +44 01908 654896; fax: +44 01908
653718.
E-mail address: J.Fortune@open.ac.uk (J. Fortune).
0263-7863/$30.00 2005 Elsevier Ltd and IPMA. All rights reserved.
doi:10.1016/j.ijproman.2005.07.004
. . . areas of activity that should receive constant and
careful attention from management.
. . . the areas in which good performance is necessary to
ensure attainment of [organizational] goals.
Rockart gave his examples of critical success factors
at industry and organization level from the perspective
of the Chief Executive but sets of factors have now
been developed at very many different levels and across
a huge range of undertakings and activities. Where project management is concerned, the search for CSFs began in the 1960s. Since then very many authors have
published lists of factors, sometimes relating them to
specific problem domains and types of activity, sometimes stressing their applicability to all types of projects
and sometimes turning the notion on its head and referring instead to critical failure factors. There have also
been a significant number of studies comparing sets
54
J. Fortune, D. White / International Journal of Project Management 24 (2006) 53–65
of factors and either trying to identify the definitive list
or pointing out the need to match the list used to the
project being undertaken. In recent times, the flow of
research publications identifying new sets of factors
has slowed but reference to and use of the concept
has not diminished.
2. Comparison of sets of factors
This section is based upon a review of 63 publications
that focus on CSFs. Between them they draw on a variety of data sources and encompass theoretical studies
and empirical studies of successful and unsuccessful projects. The CSFs cited across the 63 publications are
listed in Table 1 in decreasing order of frequency of
occurrence. It should be noted that in a number of papers, factor definitions were unclear. For example the
factors Ôboard sponsorship supportÕ [3] and Ôupper management buy-inÕ [4] have been categorised here under the
heading Ôsupport from senior managementÕ but it is accepted that they could also have been categorised under
the heading of Ôproject sponsor/championÕ.
The table shows there is only limited agreement
among authors on the factors that influence project success. The three most cited factors are: the importance of
a project receiving support from senior management;
having clear and realistic objectives; and producing an
efficient plan. However, although 81% of the publications include at least one of these three factors, only
17% cite all three. This lack of concurrence has also been
identified by Wateridge [46] who states that Ôthere does
not appear to be a consensus of opinion among
researchers and authors on the factors that influence
project successÕ.
Another of the many interesting things that emerge
from the comparison between publications is that
although the importance of having a committed project
sponsor or an executive to support or ÔchampionÕ the
project was only cited in 19% of the publications examined, a study undertaken by Poon and Wagner [35]
ranked this factor as the most critical. Similarly the
studies undertaken by Cash and Fox [14], Martinez
[18] and Jang and Lee [29] rank this factor among the
three most critical and Larsen and Myers [66] in their
case study evaluating a package-driven process re-engineering project found that a number of the managers
they interviewed attributed initial project success to
the commitment of the projectÕs sponsor.
3. Criticisms of the critical success factor approach
In addition to the lack of agreement between authors
that has been demonstrated above, two criticisms of the
CSF approach emerge from the literature. The first is
that the inter-relationships between factors are at least
as important as the individual factors but the CSF approach does not provide a mechanism for taking account of these inter-relationships. As Nandhakumar
[67] points out, Ôa better understanding of the relationship between key success factors and the EIS development is required if success factors are to be of any
guidance to the practitioners to develop effective information systemsÕ. Belassi and Tukel [24] provide an
example of the problem.
For instance, top management support is a factor
related to an organization which can be affected by the
general state of the economy. Similarly, the uniqueness
of the project activities can affect the project managerÕs
competence on the job. Lack of top management support together with the project managerÕs lack of competence on the job might lead to project failure.
Larsen and Myers [66] draw attention to the second
criticism: Ôthe factor approach tends to view implementation as a static process instead of a dynamic phenomenon, and ignores the potential for a factor to have
varying levels of importance at different stages of the
implementation processÕ.
The next section of this paper will propose a way
of overcoming these difficulties whilst allowing almost
all CSFs that have been identified as a result of a substantial review of the literature to be taken into
account.
4. The Formal System Model
Fig. 1 shows a model of a robust system that is capable of purposeful activity without failure. This model,
known as the Formal System Model (FSM), was developed as part of their failures method by Bignell and Fortune [68]. It unites most core systems concepts and was
adapted from Checkland [69], who in turn drew on the
ideas of Churchman (particularly his concept of a teleological system) [70] and Jenkins [71].
The formal system at the heart of the model comprises a decision-making subsystem, a performancemonitoring subsystem and a set of subsystems and
elements which carry out the tasks of the system and
thus effect its transformations by converting inputs into
outputs. The decision-making subsystem manages the
system. It is responsible for decisions about how the
purposes of the system are to be achieved such as which
transformations are to be carried out and by what
means and for providing the resources to enable this
to happen. It makes known its expectations to the subsystems and components that carry out the systemÕs
transformations and to the performance monitoring
subsystem. It is therefore the decision-making subsystem
55
J. Fortune, D. White / International Journal of Project Management 24 (2006) 53–65
Table 1
Critical success factors identified across 63 publications
Critical factor
Literature
Count of
citations
Support from senior
management
Avots [5] ; Cleland and King [6] ; Morris [7] ; Pinto and Slevin [8] ; Morris and Hough [9] ;
Stoddart-Stones [10] ; Magal et al. [11] ; Pinto and Mantel [12] ; McComb and Smith [13] ; Cash
and Fox [14] ; Yap et al. [15] ; Pollalis and Frieze [16] ; Tennant [4] ; Selin and Selin [17] ;
Martinez [18] ; The Standish Group [19] ; Couillard [20] ; Wastell and Newman [21] ; Tan [22] ;
Munns and Bjeirmi [23] ; Belassi and Tukel [24] ; KPMG [25] ; McCormack [3] ; McGolpin and
Ward [26] ; Dvir et al. [27] ; Kasser and Williams [28] ; Jang and Lee [29] ; Whittaker [30] ;
Turner [31] ; Weir [32] ; Taylor [33] ; Thite [34] ; Poon and Wagner [35] ; Cooke-Davies [36] ;
Andersen et al. [37] ; Caldeira and Ward [38] ; Yeo [39] ; Westerveld [40] ; Turner [41]
Baker et al. [42] ; Morris [7] ; Hughes [43] ; Pinto and Slevin [8] ; Pinto and Mantel [12] ;
Tennant [4] ; Selin and Selin [17] ; Harding [44] ; Couillard [20] ; Yeo [45] ; Wateridge [46] ; The
Standish Group [19] ; Beare [47] ; Tan [22] ; Munns and Bjeirmi [23] ; Spinelli [48] ; Cicmil
[49] ; Dvir et al. [27] ; Glass [50] ; Kasser and Williams [28] ; Jang and Lee [29] ; Clarke [51] ;
Weir [32] ; Taylor [33] ; Thite [34] ; Poon and Wagner [35] ; Anderson et al. [37] ; Caldeira and
Ward [38] ; Yeo [39] ; Westerveld [40] ; Turner [41]
Avots [5] ; Baker et al. [42] ; Cleland and King [6] ; Morris [7] ; Morris and Hough [9] ; Pinto
and Mantel [12] ; Pollalis and Frieze [16] ; Martinez [18] ; The Standish Group [19] ; Wateridge
[46] ; Couillard [20] ; Smart [52] ; Williams [53] ; Belassi and Tukel [24] ; KPMG [25] ; Spinelli
[48] ; McCormack [3] ; McGolpin and Ward [26] ; Dvir et al. [27] ; Kasser and Williams [28] ;
Glass [50] ; Whittaker [30] ; Clarke [51] ; Turner [31] ; Taylor [33] ; Andersen et al. [37] ; Yeo
[39] ; Westerveld [40] ; Turner [41]
Avots [5] ; Cleland and King [6] ; Morris [7] ; Hughes [43] ; Pinto and Slevin [8] ; Curtis et al.
[54] ; Magal et al. [11] ; Pinto and Mantel [12] ; McComb and Smith [13] ; Cash and Fox [14] ;
Pollalis and Frieze [16] ; Wateridge [46] ; Couillard [20] ; Tan [22] ; Gowan and Mathieu [55] ;
Hilderbrand [56] ; Spinelli [48] ; Dvir et al. [27] ; Kasser and Williams [28] ; Clarke [51] ; Turner
[31] ; Thite [34] ; Cooke-Davies [36] ; Andersen et al. [37] ; Yeo [39] ; Westerveld [40] ; Turner
[41]
Morris [7] ; Pinto and Slevin [8] ; Curtis et al. [54] ; Magal et al. [11] ; Pinto and Mantel [12] ;
McComb and Smith [13] ; Yap et al. [15] ; Pollalis and Frieze [16] ; Wateridge [46] ; Smart [52] ;
Beare [47] ; Wastell and Newman [21] ; Belassi and Tukel [24] ; Munns and Bjeirmi [23] ; Cicmil
[49] ; Spinelli [48] ; McCormack [3] ; Dvir et al. [27] ; Jang and Lee [29] ; Turner [31] ; Caldeira
and Ward [38] ; Yeo [39] ; Westerveld [40] ; Turner [41]
Baker et al. [42] ; Morris [7] ; Pinto and Slevin [8] ; Curtis et al. [54] ; Magal et al. [11] ; Pinto
and Mantel [12] ; McComb and Smith [13] ; Cash and Fox [14] ; Pollalis and Frieze [16] ;
Tennant [4] ; Martinez [18] ; Willcocks and Griffiths [57] ; The Standish Group [19] ; Dvir et al.
[27] ; Glass [50] ; Jang and Lee [29] ; Weir [32] ; Poon and Wagner [35] ; Caldeira and Ward
[38] ; Westerveld [40]
Avots [5] ; Pinto and Mantel [12] ; McComb and Smith [13] ; Cash and Fox [14] ; Pollalis and
Frieze [16] ; Martinez [18] ; Willcocks and Griffiths [57] ; Smart [52] ; The Standish Group [19] ;
Hougham [58] ; Cicmil [49] ; McGolpin and Ward [26] ; Dvir et al. [27] ; Weir [32] ; Taylor
[33] ; Thite [34] ; Poon and Wagner [35] ; Cooke-Davies [36] ; Yeo [39]
Avots [5] ; Baker et al. [42] ; Morris [7] ; Pinto and Slevin [8] ; Pollalis and Frieze [16] ; Martinez
[18] ; Cannon [59] ; Couillard [20] ; Pinto and Kharbanda [60] ; Belassi and Tukel [24] ; Munns
and Bjeirmi [23] ; Spinelli [48] ; Dvir et al. [27] ; Glass [50] ; Weir [32] ; Taylor [33] ; Andersen
et al. [37] ; Westerveld [40] ; Turner [41]
Avots [5] ; Pollalis and Frieze [16] ; Smart [52] ; Pinto and Kharbanda [60] ; Munns and Bjeirmi
[23] ; KPMG [25] ; McGolpin and Ward [26] ; Dvir et al. [27] ; Whittaker [30] ; Poon and
Wagner [35] ; Cooke-Davies [36] ; Andersen et al. [37] ; Caldeira and Ward [38] ; Yeo [39] ;
Westerveld [40] ; Turner [41]
Morris [7] ; Pinto and Slevin [8] ; Morris and Hough [9] ; Yap et al. [15] ; Pollalis and Frieze
[16] ; Tennant [4] ; McCormack [3] ; The Standish Group [19] ; Belassi and Tukel [24] ; Gowan
and Mathieu [55] ; Dvir et al. [27] ; Kasser and Williams [28] ; Turner [31] ; Caldeira and Ward
[38] ; Westerveld [40] ; Turner [41]
Morris and Hough [9] ; Cash and Fox [14] ; Pollalis and Frieze [16] ; Tennant [4] ; Martinez
[18] ; Smart [52] ; Gowan and Mathieu [55] ; Pinto and Kharbanda [60] ; Dvir et al. [27] ; Turner
[31] ; Thite [34] ; Andersen et al. [37] ; Caldeira and Ward [38] ; Westerveld [40] ; Turner [41]
Morris [7] ; Pinto and Mantel [12] ; McComb and Smith [13] ; Pollalis and Frieze [16] ; Cannon
[59] ; Williams [53] ; Yeo [45] ; Tan [22] ; KPMG [25] ; Dvir et al. [27] ; Glass [50] ; Poon and
Wagner [35] ; Caldeira and Ward [38] ; Yeo [39]
Cleland and King [6] ; Morris [7] ; Morris and Hough [9] ; Pinto and Mantel [12] ; McComb and
Smith [13] ; Tennant [4] ; Selin and Selin [17] ; Dvir et al. [27] ; Glass [50] ; Kasser and Williams
[28] ; Weir [32] ; Yeo [39] ; Westerveld [40] ; Turner [41]
(continued on
39
Clear realistic objectives
Strong/detailed plan kept
up to date
Good communication/
feedback
User/client
involvement
Skilled/suitably qualified/
sufficient staff/team
Effective change
management
Competent project manager
Strong business case/
sound basis for project
Sufficient/well allocated
resources
Good leadership
Proven/familiar
technology
Realistic schedule
31
29
27
24
20
19
19
16
16
15
14
14
next page)
56
J. Fortune, D. White / International Journal of Project Management 24 (2006) 53–65
Table 1 (continued)
Critical factor
Literature
Count of
citations
Risks addressed/assessed/
managed
Morris and Hough [9] ; Selin and Selin [17] ; Smart [52] ; Beare [47] ; Williams [53] ; KPMG
[25] ; Baldry [61] ; Dvir et al. [27] ; Whittaker [30] ; Weir [32] ; Cooke-Davies [36] ; Yeo [39] ;
Westerveld [40]
Morris [7] ; Morris and Hough [9] ; Cash and Fox [14] ; Yap et al. [15] ; Martinez [18] ;
McGolpin and Ward [26] ; Jang and Lee [29] ; Baldry [61] ; Thite [34] ; Poon and Wagner [35] ;
Caldeira and Ward [38] ; Yeo [39]
McComb and Smith [13] ; Cash and Fox [14] ; Pollalis and Frieze [16] ; Selin and Selin [17] ;
Cicmil [49] ; Dvir et al. [27] ; Weir [32] ; Thite [34] ; Poon and Wagner [35] ; Cooke-Davies
[36] ; Westerveld [40] ; Turner [41]
Baker et al. [42] ; Cleland and King [6] ; Morris and Hough [9] ; Dvir et al. [27] ; McComb and
Smith [13] ; Pollalis and Frieze [16] ; Tennant [4] ; Glass [50] ; Caldeira and Ward, [38] ;
Westerveld [40] ; Turner [41]
Pollalis and Frieze [16] ; Cannon [59] ; Willcocks and Griffiths [57] ; Martinez [18] ; Couillard
[20] ; Hougham [58] ; Gowan and Mathieu [55] ; Taylor [33] ; Thite [34] ; Cooke-Davies [36]
Morris and Hough [9] ; Pollalis and Frieze [16] ; McCormack [3] ; KPMG [25] ; Glass [50] ;
Jang and Lee [29] ; Caldeira and Ward [38] ; Yeo [39] ; Westerveld [40] ; Turner [41]
Avots [5] ; Cleland and King [6] ; Sauer [62] ; Beare [47] ; Pinto and Kharbanda [60] ; Munns
and Bjeirmi [23] ; McCormack [3] McGolpin and Ward [26] ; Dvir et al. [27]
Magal et al. [11] ; Yap et al. [15] ; Pinto and Kharbanda [63] ; Pinto and Kharbanda [60] ;
McCormack [3] ; Dvir et al. [27] ; Caldeira and Ward [38]
Morris and Hough [9] ; Pollalis and Frieze [16] ; Tennant [4] ; Sauer [62] ; Yeo [45] ; Pinto and
Kharbanda [60]
Hughes [43] ; Munns and Bjeirmi [23] ; Dvir et al. [27] ; Glass [50] ; Jang and Lee [29] ; Turner
[41]
13
Morris [7] ; Cleland and King [6] ; Archibald [65] ; Pinto and Kharbanda [60] ; Caldeira and
Ward [38] ; Westerveld [40]
Yap et al. [15] ; Dvir et al. [27] ; Jordan et al. [64] ; Sauer [62] ; Cooke-Davies [36]
Hughes [43] ; Selin and Selin [17] ; Cannon [59] ; Cooke-Davies [36]
6
Curtis et al. [54] ; Pinto and Kharbanda [63] ; Turner [41]
3
Project sponsor/champion
Effective monitoring/control
Adequate budget
Organisational adaptation/
culture/structure
Good performance by suppliers/
contractors/consultants
Planned close down/review/
acceptance of possible failure
Training provision
Political stability
Correct choice/past experience
of project management
methodology/tools
Environmental influences
Past experience (learning from)
Project size (large)/level of
complexity (high)/number of
people involved (too many)/
duration (over 3 years)
Different viewpoints
(appreciating)
12
12
11
10
10
9
7
6
6
5
4
= Empirical-data mainly obtained from survey(s).
= Empirical-data mainly obtained from case studies(s).
= Theoretical – but data often based on work of others.
that allows the system to exhibit choice, and thus behave
as a purposeful system. The performance monitoring
subsystem is charged with observing the transformation
processes and reporting deviations from the expectations to the decision-making subsystem so that it can initiate corrective action where necessary.
The other features of the model include: a continuous
purpose or mission that gives rise to expectations; a degree of connectivity between the components; an environment with which the system interacts; boundaries
separating the system from its wider system and the
wider system from the environment; resources; and
some guarantee of continuity.
The FSM has been used successfully over a long period of time to investigate failures (see [72,73]). The way
it is used is to conceptualize a situation as a system and
then compare the resulting system with the FSM in order to determine the extent to which the components,
links and other features necessary for purposeful activity
without failure are present. Such comparisons across a
broad range of projects have revealed a number of common themes. These include:
1. Deficiencies in the apparent organizational structure
of the system, such as a lack of a performance-measuring subsystem or a control/decision-making
subsystem.
2. No clear statements of purpose supplied in a comprehensible form to the system from the wider system.
3. Lack of an effective means of communication
between the various subsystems.
4. Not enough consideration given to the influence of
the environment, and insufficient resources to cope
with those environmental disturbances that were
foreseen.
5. An imbalance between the resources applied to the
basic transformation processes and those allocated
to the related monitoring and control processes, perhaps leading at one extreme to quality problems and
at the other to cost increases or delays.
J. Fortune, D. White / International Journal of Project Management 24 (2006) 53–65
Table 2
Critical success factors mapped onto components of the Formal
System Model
Environment
attempts to
influence
disturbs
Wider system boundary
Wider system
formulates
initial
design of
provides
resources and
legitimates
area of
operation
makes known
expectations
supplies
performance
information
Component of FSM/
project attributes
Critical success factors from literature
Goals and objectives
Clear realistic objectives
Strong business case/sound basis for project
Performance
monitoring
Effective monitoring/control
Planned close down/review/acceptance of
possible failure
Decision-maker(s)
Support from senior management
Competent project manager
Strong/detailed plan kept up to date
Realistic schedule
Good leadership
Correct choice/past experience of project
management methodology/tools
System Boundary
System
Decision-making
subsystem
decides on
transformations
implemented
by designed
set of
provides
resources and
legitimates
operations
makes
known
expectations
Transformations
Skilled/suitably qualified/sufficient staff/team
Communication
Good communication/feedback
Environment
Political stability
Environmental influences
Past experience (learning from)
Organisational adaptation/culture/structure
Boundaries
Project size/level of complexity/number of
people involved/duration
Resources
Adequate budget
Sufficient/well allocated resources
Training provision
Proven/familiar technology
Good performance by suppliers/contractors/
consultants
Continuity
Risks addressed/assessed/managed
reports to
Subsystems and
components that carry
out transformations
57
Performance
monitoring
subsystem
provides performance
information
Fig. 1. The Formal System Model.
Table 2 shows that it is possible to map 23 of the
27 CSFs identified earlier in this paper with the features of the FSM directly and at least three of the
remaining four are implicit within the systemic nature
of the model. (These four are shown at the bottom of
the table. The possible exception is the Project Champion but it can be argued that that role is covered by
the legitimizing process.) The implication of the mapping shown in Table 2 is that the model contains
within it the factors identified in the literature as being
critical to success and can thus act as a framing device
for project critical success factors. Furthermore, because the FSM is as concerned with the relationships
between its components as it is with the components
themselves it should provide a way of making links
between factors and is thus be able to overcome the
first of the two main criticisms outlined above. The
FSM should also be able to deal with the second criticism of the CSF approach (that it is unable to cope
with the dynamic nature of IS projects) because it is
a dynamic model of a system that responds to decision making and interacts with its environment.
User/client involvement
Different viewpoints (appreciating)
Project sponsor/champion
Effective change management
5. Use of the FSM as a framing device
Accounts of two similar projects, one successful and
one not, will be used to investigate the proposal that
the FSM, which has value in its own right, allows a very
broad range of CSFs to be taken into account whilst
overcoming problems associated with their use. Information about the projects was gathered via series of
structured and semi-structured interviews whilst the projects were actually being carried out and therefore, by
definition, before their level of success could be known.
As Table 3 illustrates the two projects were very similar
in terms of size and scope and at the outset both looked
equally likely to succeed. In the event, however, the outcomes of the two projects were very, very different. Project A was largely successful across the whole of the
range of measures normally used to judge success. Project B, on the other hand, exhibited most of the characteristics of failure; it was over-budget, late and did not
58
J. Fortune, D. White / International Journal of Project Management 24 (2006) 53–65
Table 3
Project A and Project B – an initial comparison
Project type
Sector
Initial schedule
Budget
Success criteria
Number of stakeholders
Customers
IS software
Project management software used
Working environment
Project A
Project B
Information system
Public
10 months
Generous
On time, to quality, within budget, successful
installation of advice and enforcement infrastructure
112
General public
Bespoke
Microsoft Project
Extensive building work undertaken on main site
Information system
Public
14 months
Realistic
On time, within budget, successful installation
of web-based information system
120
General public
Off-the-shelf
Microsoft Project
Head office building completely refurbished
meet stakeholdersÕ expectations. The two projects will be
described briefly here. More detailed descriptions can be
found in Fortune and Peters [74].
5.1. Project A
Project A was carried out by a Government Agency
within a large Department of State. Its purpose was to
set up a UK-wide help line to communicate information
about a new, high-profile piece of legislation and to help
with the enforcement of the requirements of the legislation. The help line and enforcement system had to be in
place within eight months and the project as a whole
brought to a close a further two months after that.
A Project Board consisting of 30 people from senior
levels of the Agency and the two Departments of State
was put together to act as the decision makers for the
project. The Board members recognised that because
of their mix of cultures and lack of a shared geographical base they would need to establish robust line management reporting and decision making processes.
Their solution was to recognise two members based in
the north as project champions and arrange the remaining members into a functional matrix. An experienced
Project Manager was appointed from within the organization. He was placed in charge of the day-to-day management of the project and was supported by a core
team of 30 people who were also dispersed geographically. The size of the budget remains confidential, but
it is possible to say that the Project Manager regarded
it as generous.
An Ôin-houseÕ Project Management Method (similar
to PRINCE) with which most of the team were familiar
was used to manage the project. As prescribed by the
method, the project was divided into the following
stages:
initiation,
research,
investigation,
feasibility,
business case,
funding,
design,
development,
implementation,
closure.
During the course of the project it was felt that the method
was Ôtoo heavyÕ and required far too much documentation
so it was Ôcut downÕ. The software package ÔMicrosoft
ProjectÕ was used as a tracking tool to enable time taken
and costing information to be tracked weekly. It was also
used to identify dependencies and flag those regarded as
ÔcriticalÕ. The information it provided on project progress
was fed back to the Project Board.
Although there were some delays, unexpected events
and setbacks during the course of the project, the projectÕs owners, the Project Manager and his team all regarded it as a success. The objectives set for it were
met. By the appointed completion date a telephone help
line staffed by trained operatives able to offer information and advice was operational and 14 teams of Inspectors had been put in place in locations across the United
Kingdom and trained to carry out the necessary enforcement. The project was also within budget. The Closure
stage was reached on schedule and a Post Implementation Review was completed before the project was formally brought to a close by which time the help line
and the inspection teams were already embedded in
the organization and judged to be working well.
5.2. Project B
Project B was undertaken within a public sector organisation serving local government and was triggered by
concerns that much of the organisationsÕ ITC equipment
and software was out of date. A firm of outside consultants was called in to carry out an information and communication review and recommend a strategy which
would carry the organisation forward. The consultantsÕ
conclusion was that a completely new system was
needed with Internet as the Ôkey technologyÕ and a new
Windows-based client database at its heart.
J. Fortune, D. White / International Journal of Project Management 24 (2006) 53–65
59
Table 4
An evaluation of Projects A and B in relation to the CSFs identified in Table 1
Critical factor
Project A
Project B
Taken
account of
Comments
Taken
account of
Comments
Support from senior
management
X
The Project Board supported the Project
Manager. They met on a weekly basis
·
There was no evidence of the Project
Manager receiving support from the
Management Team. For example, he
was required to carry out all his
existing duties in addition to
managing the project
Clear realistic objectives
X
The project requirements were clearly
defined and perceived to be realistic. (This
perception was proved to be valid.)
X
The project requirements were clearly
defined and at senior levels, at least,
were regarded as realistic
Strong/detailed plan
kept up to date
X
A clear plan was formulated and an
efficient planning and control system was
operated to keep them up to date.
·
No detailed plan established.
Although the schedule was changed
on a number of occasions no measures
were taken to monitor performance
regularly
Good communication/
feedback
X
A robust line management reporting
system was established between the
Project Board and the Project Manager
and between the latter and his Team
·
Communication was poor and usually
took place by e-mail. Formal meetings
were rare. Little feedback was given
User/client
involvement
X
Those who would be using the system
became involved during the project and
though they did not participate directly
end usersÕ needs were considered
·
These were not considered. Indeed,
the opinions of the primary users were
ignored at the design stage
Skilled/suitably qualified/
sufficient staff/team
X
All 30 members of the had worked on
earlier projects run using the same ÔinhouseÕ Project Management Method and
most had worked with the Project
Manager before
·
Neither the Project Manager nor any
members of his Team had previous
project experience and only one
Project Team member had any IT/IS
qualifications
Effective change management
N/A
N/A
Competent project manager
X
Yes
·
No
Strong business case/sound
basis for project
X
Established as one of the stages of the ÔinhouseÕ Project Management Method
used.
X
Case signalled very clearly because
current ITC equipment and software
was recognised as out of date
Sufficient/well allocated
resources
X
All types of resource were sufficient and
well allocated.
X
Adequate resources (apart from
staffing) were available but were not
always allocated as well as they might
have been
Good leadership
X
The Project Manager proved to be a
charismatic leader
·
The Project Manager had inadequate
leadership skills
Proven/familiar technology
X
Yes
·
Those in organization not familiar
with the technology being introduced
Realistic schedule
X
Yes
X
Original schedule was realistic though
delays early on meant the project soon
fell behind schedule
Risks addressed/assessed/
managed
X
At the start of the project the Project
Manager tried to identify all the risks that
would need to be managed to ensure
project success. All risks that did arise
were managed successfully
·
The Project Manager identified the
project as a Ôrisky ventureÕ but he did
not undertake a risk analysis. No
contingency measures were put in
place
Project sponsor/champion
X
Two members of the Project Board acted
as project champions
·
No
Effective monitoring/control
X
Yes, assisted by use of Microsoft Project
·
No
(continued on next page)
60
J. Fortune, D. White / International Journal of Project Management 24 (2006) 53–65
Table 4 (continued)
Critical factor
Project A
Project B
Taken
account of
Comments
Taken
account of
Comments
Adequate budget
X
Budget described as ÔgenerousÕ
X
Budget described as ÔadequateÕ
Organisational adaptation/
culture/structure
X
Potential ÔclashÕ of cultures between
agencies involved in the project
identified as a risk and managed
accordingly
·
No effort made to take account of
problems caused by the organisationÕs
culture such as the communication
difficulties arising from excessive
reliance on e-mail.
Good performance by
suppliers/contractors/
consultants
X
Yes
·
Suppliers performed poorly; new
software was late, and essential
hardware was faulty or late
Planned close down/review/
acceptance of possible
failure
X
There was a planned closedown
and a post implementation review
was undertaken. Lessons learnt
were recorded
·
The scope of the project was reduced
towards the end and no planned
closedown took place. No formal
review was undertaken
Training provision
X
Although some training was late,
all staff were adequately trained
·
Training was inadequate and late. User
manuals did not progress beyond the
draft stage
Political stability
X
Yes
X
Yes
Correct choice/past experience
of project management
methodology/tools
X
A familiar Project Management
Method was chosen and adapted
to meet the projectÕs needs
·
No project management method was
used. Gantt Charts were produced for
scheduling purposes but the schedules
were not adhered to
Environmental influences
X
Taken account of successfully
·
Not considered and no effective action
taken when they did interfere with the
project
Past experience (learning from)
X
Every indication that Project
Manger had learnt from his
extensive past experience.
·
No
Project size (large)/level of
complexity (high)/number
of people involved (too
many)/duration (over 3
years)
Different viewpoints
(appreciating)
Counts of ÔyesÕ
N/A
X
N/A
Account taken of the viewpoints
of end users, Project Team and
the needs of the organisation
25/25 = 100%
The consultantsÕ proposal was accepted by the threestrong Management Team that ran the organization and
a Project Manager and four team members were appointed. The Management Team, rather than the Project Manager, took on the role of main decision maker
and co-opted further staff onto the project team as
and when necessary. In order to meet the various logistical considerations a 14 months schedule was drawn up
and a budget, described as ÔadequateÕ was agreed.
Use of the project management methodology
PRINCE2 was considered but in the end no formal
methodology was used. ÔMicrosoft ProjectÕ, of which
none of the project team had any previous experience,
·
Viewpoints of end users and the
Project Team not considered
6/25 = 24%
was used so that Gantt Charts could be produced for
scheduling purposes.
Although the project had been scheduled for a summer start the Project Manager and his team were so busy
with their routine duties that they did not hold their first
team meeting until nearly six months later. The main
item on the agenda was the rescheduling of the project
so as to meet the deadline that had been fixed. However,
it was not long before the project fell behind the revised
schedule as the first of a series of problems started to
emerge. The project was eventually drawn to a close
over six months later than originally envisaged and
although one of the primary aims was achieved – the
J. Fortune, D. White / International Journal of Project Management 24 (2006) 53–65
Environment
including national economy, Parliament, legislation
disturbs
Wider System Boundary
PROJECT BOARD
sets out requirements (help
line/enforcement system
to be completed on
time, to budget) formulates
business plan, schedule,
requirment for system to meet
quality standards,
projectto fit in with
organisation/other initiatives
defines
legislation,
defines final
rules and
regulations
provides funds for setting
up costs, identifies technology,
makes staff available, appoints
Independent Auditor, provides
late publicity
feeds back
information
on progress
System Boundary
IMPLEMENTATION SYSTEM
Project Manager
having considered end users,the
effectof travelling (time/stress) on team,
mix of cultures involved
sets out objectives,
business plan,
measures of
performance, defines
quality, suggests 'risk
diary', decides on
schedule, tracking
system,
communications plan,
sets up weekly
meetings
shares past
experience,
provides funds,
appoints team,
equipment,
technology,
training
suggests project
management method/tools,
expects effective
management of risk ,
loyalty, regular
communication, project
to fit in with other initiatives,
supports team decisions
no authority
to influence
feeds back
information
on progress
Performance
monitoring sub system
Project Team Members
undertaking
transformations
Change agent
flags critical dependencies,tracks
finance, issues papers on out standing
issues, monitors team performance,
risks, quality, change, close
down, lessons learnt
provide performance information
Unsuccessful attempt to influence
Fig. 2. Model of Project A.
Independent
Auditor
61
62
J. Fortune, D. White / International Journal of Project Management 24 (2006) 53–65
Environment
including Suppliers, Consultants, Contracts, other parts of Organisation, staff, outside contractors
very
limited
attempt
to influence
communication
culture
Wider System Boundary
MANAGEMENT TEAM
formulates
infrastructure,
sets out project
plan, use of
project management
tool (instructions
unclear)
provides adequate
budget, appoints
project manager
and team, appoints
co-opted team,
signs contracts
with suppliers
sets sc hedule,
requires users
to be trained
supplies limited
information
on progress
System Boundary
INFRASTRUCTURE
SETTING SYSTEM
Project Manager
having no previous project management
experience
sets out
limited
plan
provides
funds
Project Team carries
out normal duties and
implementation
activities
Distributes
Gantt Charts,
makes known
system
requirements
Co-opted
team
attempts to
train staff
Unsuccessful attempt to influence
Fig. 3. Model of Project B.
63
J. Fortune, D. White / International Journal of Project Management 24 (2006) 53–65
Table 5
Comparison between the features of the Formal System Model and Projects A and B
Feature of FSM/project attributes
Project A
Project B
Main decision-makers
(wider system)
Project Manager
(system)
Main decision-makers
(wider system)
Project Manager
(system)
Yes
Yes
Yes
Transformations
Yes
Yes
Yes – but on a number of
occasions expectations not clear
–
Yes
Yes
No
Yes – but expectations not
made clear
–
Communication
Environment
Boundaries
Resources
Continuity
Viewpoints
Project Champion
Change Agent
Counts of ÔyesÕ
Yes
No
Yes
Yes – but poor publicity
Yes
Yes – but not adequately
Yes
Yes
10/11
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
12/12
No
No
Yes
No
No
No
No
No
3/11
Yes
No
Yes – but expectations
not made clear
Yes – but normal duties
also carried out
No
No
No
No
No
No
No
No
3/12
Total counts
22/23 = 96%
Goals objectives
Performance monitoring
Decision-maker(s)
new Windows-based client database was put in place
successfully – many other objectives were not met. Furthermore, the project exceeded its budget by around
25%.
Unfortunately the completion of the project did not
mean an end to the problems associated with it. A number of technical limitations/inadequacies to the new
information system came to light soon after it went live.
The effect of these was to reduce the amount of activity
the organisation was able to undertake and this in turn
led to a reduction in the organizationÕs income. Many
members of staff were unhappy with the new system.
In part their dissatisfaction was due to their lack of
training but it was also triggered by their belief that their
opinions had been ignored when design decisions had
been made early in the projectÕs life cycle.
5.3. Critical success factors and the projects
Table 4 shows an evaluation of the two projects in
relation to the CSFs identified in Table 1.
5.4. Formal system model and the projects
Figs. 2 and 3 show Projects A and B, respectively,
presented in the format of the FSM. It is clear from
Fig. 2 that there is a very close match between Figs. 1
and 2. The presence of the components and interactions
needed for purposeful activity without failure is a reflection of the success of Project A. By contrast, comparison
of Fig. 3 with Fig. 1 reveals the many discrepancies that
are a strong reflection of the lack of success of Project B.
For example no evidence of performance monitoring,
unclear expectations, no communications plan, and a
very limited attempt to influence the environment.
6/23 = 26%
Table 5 shows the information used to prepare Figs. 2
and 3 in non-diagrammatic form. It is very noticeable
that there is a high degree of correspondence between
Tables 4 and 5 but the holistic impression of the two
projects that is painted in Figs. 2 and 3 is lost in the Tables. It can be argued that if action to remedy shortcomings was going to be taken during the life of Project B
Fig. 3 would give much greater guidance on where to
concentrate that action.
6. Conclusion
This paper has shown three things. Through a review
of sets of critical success factors from 63 publications it
has revealed that there is a lot of overlap between sets
but the factors selected for inclusion in individual lists
vary to a considerable extent. Second, it has shown that
the Formal System Model contains within it all of the
factors that are covered by sets of CSFs but has the
advantage of being able to consider the relationships between factors and, because it is dynamic, overcomes the
third criticism of the CSF approach. Thirdly, it has demonstrated that the Formal System Model is capable of
distinguishing between successful and unsuccessful projects and therefore if used in the planning and implementation phases can provide a way of tackling the human
and organisational aspects of systems development
projects.
References
[1] Daniel DR. Management information crisis. Harvard Bus Rev
1961(September–October):111–21.
64
J. Fortune, D. White / International Journal of Project Management 24 (2006) 53–65
[2] Rockart JF. Chief executives define their own data needs.
Harvard Bus Rev 1979(March–April):81–93.
[3] McCormack S. The lemon factor. The Engineer 1997(June):22–4.
[4] Tennant DV. Avoiding failure in project management. In:
Proceedings of the advances in instrumentation and control:
ISA conference and exhibition; 1993. p. 675–86.
[5] Avots I. Why does project management fail? California Manage
Rev 1969;12(1):77–82.
[6] Cleland DI, King WR. Systems analysis and project management. New York: McGraw-Hill; 1983.
[7] Morris PWG. Research at Oxford into the preconditions of
success and failure of major projects: In: Proceedings of the 18th
annual seminar/symposium of the Project Management Institute,
Montreal, Canada; 1986. p. 53–66.
[8] Pinto JK, Slevin DP. Critical factors in successful project
implementation. IEEE Trans Eng Manage 1987;EM-34(1):22–7.
[9] Morris PWG, Hough GH. The anatomy of major projects. Chichester: Wiley; 1987.
[10] Stoddart-Stones R. Development of project management systems
for major projects. Int J Project Manage 1988;6(1):34–8.
[11] Magal SR, Carr HH, Watson H. Critical success factors for
information centre managers. MIS Quart 1988;12:413–26.
[12] Pinto JK, Mantel SJ. The causes of project failure. IEEE Trans
Eng Manage 1990;37(4):269–76.
[13] McComb D, Smith JY. System project failure: the heuristics of
risk. J Inform Syst Manage 1991;8(1):25–34.
[14] Cash C, Fox R. Elements of successful project management. J
Syst Manage 1992;43(9):10–2.
[15] Yap CS, Soh CPP, Raman KS. Information systems success
factors in small business. OMEGA 1992;20(5/6):597–609.
[16] Pollalis YA, Frieze IH. A new look at critical success factors in
IT. Inform Strategy 1993(Fall):24–34.
[17] Selin G, Selin M. Reasons for project management success and
failure in multiproject environment: In: Proceedings of the
INTERNET world congress, Oslo, Norway; 1994. p. 513–9.
[18] Martinez EV. Avoiding large-scale information systems project
failure: the importance of fundamentals. Project Manage J
1994;25(2):17–25.
[19] The Standish Group. http://www.standishgroup.com/chaos.htm
[accessed April 2000].
[20] Couillard J. The role of project risk in determining project
management approach. Project Manage J 1995;26(4):3–15.
[21] Wastell D, Newman M. Information system design, stress and
organisational change in the ambulance service: a tale of two
cities. Acc Manage Inform Technol 1996;6(4):283–300.
[22] Tan RR. Success criteria and success factors for external
technology transfer projects. Project Manage J 1996;27(2):45–56.
[23] Munns AK, Bjeirmi BF. The role of project management in
achieving project success. Int J Project Manage 1996;14(2):81–7.
[24] Belassi W, Tukel OI. A new framework for determining critical
success/failure factors in projects. Int J Project Manage
1996;14(3):141–51.
[25] KPMG. What went wrong? Unsuccessful information technology
projects. KPMG Strategic and Technology Services; 1997.
[26] McGolpin P, Ward J. Factors influencing the success of strategic
information systems. In: Mingers J, Stowell F, editors. Information systems: an emerging discipline? London: McGraw-Hill;
1997. p. 287–327.
[27] Dvir D, Lipovetsky S, Shenhar A, Tishler A. In search of project
classification: a non-universal approach to project success factors.
Res Policy 1998;27:915–35.
[28] Kasser J, Williams VR. What do you mean you canÕt tell me if my
project is in trouble?: In: Proceedings of the FESMA98, Antwerp,
Belgium; 1998.
[29] Jang Y, Lee J. Factors influencing the success of managing
consulting projects. Int J Project Manage 1998;16(2):67–72.
[30] Whittaker B. What went wrong? Unsuccessful information
technology projects. Informat Manage Comput Security
1999;7(1):23–9.
[31] Turner JR. The handbook of project based management. second
ed. London: McGraw-Hill; 1999.
[32] Weir S. Designing and managing successful projects. http://
www.jws.net/weir/design.html [accessed December 1999].
[33] Taylor A. IT projects: sink or swim. Comput Bull 2000(January):
24–6.
[34] Thite M. Leadership styles in information technology projects. Int
J Project Manage 2000;18:235–41.
[35] Poon P, Wagner C. Critical success factors revisited: success and
failure cases of information systems for senior executives.
Decision Support Syst 2001;30(4):393–418.
[36] Cooke-Davies T. The ÔrealÕ success factors in projects. Int J
Project Manage 2002;20(3):185–90.
[37] Andersen ES, Dyrhaug QX, Jessen SA. Evaluation of Chinese
projects and comparison with Norwegian projects. Int J Project
Manage 2002;20(8):601–9.
[38] Caldeira MM, Ward JM. Understanding the successful adoption
and use of IS/IT in SMEs: an explanation from Portuguese
manufacturing industries. Inform Syst J 2002;12:121–52.
[39] Yeo KT. Critical failure factors in information system projects.
Int J Project Manage 2002;20(3):241–6.
[40] Westerveld E. The Project Excellence Model: linking success
criteria and critical success factors. Int J Project Manage
2003;21:411–8.
[41] Turner JR. Managing Web projects. Aldershot: Gower; 2004.
[42] Baker BN, Murphy DC, Fisher D. Factors affecting project
success. In: Cleland DI, King WR, editors. Project management
handbook. New York: Van Nostrand Reinhold; 1983. p. 669–85.
[43] Hughes MW. Why projects fail: the effect of ignoring the obvious.
Ind Eng 1986;18:14–8.
[44] Harding JS. A crash course in project engineering. Chem Eng
1995;102:118–26.
[45] Yeo KT. Planning and learning in major infrastructure development: systems perspectives. Int J Project Manage
1995;13(5):287–93.
[46] Wateridge J. IT projects: a basis for success. Int J Project Manage
1995;13(3):169–72.
[47] Beare D. Risk management in information systems development:
a case study. Eng Manage J 1995(April):63–5.
[48] Spinelli D. Keys to success in management projects. Network
World 1997;4(14).
[49] Cicmil SJK. Critical factors of effective project management. The
TQM Mag 1997;9(6):390–6.
[50] Glass RL. Software runaways: lessons learned from massive
software project failure. New Jersey: Prentice-Hall; 1998.
[51] Clarke A. A practical use of key success factors to improve the
effectiveness of project management. Int J Project Manage
1999;17(3):139–45.
[52] Smart G. DonÕt be a system victim. Internal Auditing
1995:18–21.
[53] Williams BR. Why do software projects fail? GEC J Res
1995;12(1):13–6.
[54] Curtis B, Krasner H, Iscoe N. A field study of the software design
process for large systems. Commun ACM 1988;31(11):1268–87.
[55] Gowan JA, Mathieu RG. Critical factors in information system
development for a flexible manufacturing system. Comput Ind
1996;28:173–83.
[56] Hilderbrand C. Loud and clear. CIO 1996;9(13):56–60.
[57] Willcocks L, Griffiths C. Predicting risk of failure in large-scale
information technology projects. Technol Forecast Social Change
1994;47:205–28.
[58] Hougham M. London Ambulance Service computer-aided despatch system. Int J Project Manage 1996;14(2):103–10.
J. Fortune, D. White / International Journal of Project Management 24 (2006) 53–65
[59] Cannon JA. Why IT applications succeed or fail. Ind Commer
Train 1994;26(1):10–5.
[60] Pinto JK, Kharbanda OP. How to fail in project management
(without really trying. Bus Horizons 1996;35(4):45–53.
[61] Baldry D. The evaluation of risk management in public sector
capital projects. Int J Project Manage 1998;16(1):35–41.
[62] Sauer C. Why information systems fail: a case study
approach. Henley on Thames: Alfred Waller; 1993.
[63] Pinto JK, Kharbanda OP. Lessons from an accidental profession.
IEEE Eng Manage Rev 1995;23(4):18–27.
[64] Jordan G, Lee I, Cawsey G. Learning from experience. London: H.M. Stationery Office; 1988.
[65] Archibald RD. Managing high-technology programs and projects. Second ed. Chichester: Wiley; 1992.
[66] Larsen M, Myers M. When success turns into failure: a packagedriven process re-engineering project in the financial services
industry. J Strategic Inform Syst 1999;8(4):395–417.
[67] Nandhakumar J. Design for success?: critical success factors in
executive information systems development. Eur J Inform Syst
1996;5(1):62–72.
[68] Bignell V, Fortune J. Understanding systems failures. Manchester: University of Manchester Press; 1984.
65
[69] Checkland PB. Systems thinking, systems practice. Chichester: Wiley; 1981.
[70] Churchman CW. The design of inquiring systems. New York: Basic Books; 1971.
[71] Jenkins GM. The systems approach. J Syst Eng 1969;1:3–49.
[72] Fortune J, Peters G. The formal system paradigm for studying
failures. Technol Anal Strategic Manag 1990;2(4):383–90.
[73] Fortune J, Peters G. Learning from failure. Chichester: Wiley; 1995.
[74] Fortune J, Peters G. Information systems: achieving success by
avoiding failure. Chichester: Wiley; 2005.
Joyce Fortune is Head of the Department of Technology Management
at the Open University. Her teaching and research interests include
systems failures, quality management and technology strategy. Her
most recent publications cover topics such as risk in project management, human rights and ethical policing, emergence and systems
approaches to failure.
Diana White is a Visiting Research Fellow in the Faculty of Technology at the Open University. In 2003, she was awarded a PhD by the
University for a thesis entitled A Systems View of Project Management
Risk and has published a number of papers in this area.