                                                          Table of Contents
1   SAP PS MASTER DATA .............................................................................................................. 3
    1.1   BUILD PROJECT STRUCTURE ...............................................................................................................3
    1.1.1   Impact ...........................................................................................................................................4
    1.2   ACTIVATE ACCOUNT ASSIGNMENT ELEMENTS ......................................................................................5
    1.2.1   Impact ...........................................................................................................................................8
    1.3   RELEASE WBS FOR SPENDING ............................................................................................................9




                                                                                                                                                     Page 2
SAP PS Training Material




1 SAP PS MASTER DATA


1.1    Build Project Structure

                    To build lower WBS levels on a project once it has been activated by the
Purpose:            AR. Projects can be structured by asset, phase or responsibility. This is at
                    the discretion of the project manager.
Menu path:          Accounting  Project System  Project  CJ20N – Project Builder
Transaction
                    CJ20N
code:
Screen name:        Project Builder




                                                                                    Comment/
Step      Button/
                                      Value/Action                   Mandatory      Expected
 Nr        Field
                                                                                     Result

1       Proj def      Double click on
                      button in the Work list section.

      Note: This action will open the relevant project definition and add it to
      the work list section for quick editing in future. All frequently accessed
      projects should be added to this list for quick editing in the future.

Screen name:        Include in Worklist




                                                                                    Comment/
Step      Button/
                                      Value/Action                   Mandatory      Expected
 Nr        Field
                                                                                     Result




                                                                                                   Page 3
SAP PS Training Material




        Project                                                                     Number of
2       definition                                                                 the Project
                                                                                    definition.
3                     Click the Enter      button
Screen name:         Project Builder



1.1.1   Impact

This task is used to build the project. Projects can be structured according to phase, asset or
responsibility. In all cases projects are hierarchical in nature. SAP uses the following project
numbering logic:




                                                                                                   Page 4
SAP PS Training Material




1.2    Activate Account Assignment Elements

                     To determine which WBS elements will receive actual costs and which
                     WBS elements will be classified for WIP (AUC). For each account
Purpose:             assigned WBS an AUC is automatically created when the project is
                     released. Certain fields are activated for Account assigned WBS
                     elements.
Menu path:           Accounting  Project System  Project  CJ20N – Project Builder
Transaction
                     CJ20N
code:
Screen name:         Project Builder




                                                                               Comment/
Step      Button/
                                       Value/Action               Mandatory    Expected
 Nr        Field
                                                                                Result

1       Proj def       Double click on
                       button in the Work list section.

      Note: This action will open the relevant project definition and add it to
      the work list section for quick editing in future. All frequently accessed
      projects should be added to this list for quick editing in the future.

Screen name:         Include in Worklist




                                                                               Comment/
Step      Button/
                                       Value/Action               Mandatory     Expected
 Nr        Field
                                                                                 Result
        Project                                                               Number of
2       definition                                                           the Project
                                                                              definition.


                                                                                            Page 5
SAP PS Training Material




3                  Click the Enter      button
Screen name:      Project Builder




                                                                           Comment/
Step    Button/
                                    Value/Action               Mandatory   Expected
 Nr      Field
                                                                            Result

    Note: Notice that the Project definition is added to the work list
    section highlighted above.

                   To open this project, double click on it
4
                                                          .
Screen name:      Project Builder




                                                                                      Page 6
SAP PS Training Material




                                                                                     Comment/
Step      Button/
                                       Value/Action                      Mandatory   Expected
 Nr        Field
                                                                                      Result
5                      Expand the treeview node                                  
Activate all account assignment elements which are the lowest in the hierarchy


     Note: Activating account assignments makes the WIP classification
     field required. See TAB called Control for details.
Screen name:         Project Builder




                                                                                                Page 7
SAP PS Training Material




                                                                             Comment/
Step     Button/
                                      Value/Action               Mandatory   Expected
 Nr       Field
                                                                              Result
Double click on each item and enter the WIP classification
Screen name:       Project Builder




                                                                              Comment/
Step     Button/
                                      Value/Action               Mandatory     Expected
 Nr       Field
                                                                                Result
           WIP       10                                                      Enter the
                                                                             WIP
                                                                             classification
                                                                             which is
                                                                             used to
                                                                             classify
6                                                                   
                                                                             costs in the
                                                                             balance
                                                                             sheet for
                                                                             WIP / AUC
                                                                             for each
                                                                             asset.

    Note: Repeat the same steps for each account assignment WBS.

                                                                             Comment/
Step     Button/
                                      Value/Action               Mandatory   Expected
 Nr       Field
                                                                              Result
7                    Click the Save       button                    



1.2.1   Impact

Account assigned WBS elements when released automatically create an (AUC) asset under
construction. WIP classification is a Financial requirement.




                                                                                              Page 8
SAP PS Training Material




1.3   Release WBS for spending


                       This transaction is used to update the system and user status. A
Purpose:               project must be released (REL) to be able to post actual costs against
                       it. The user status ‘NCA’ must also be changed to ‘ACA’
                       Accounting  Project System  Project  CJ20N – Project
Menu path:
                       Builder
Transaction code:      CJ20N
Screen name:           Project Builder




  Step      Button/                                                          Comment/
                              Value/Action           Mandatory
   Nr         Field                                                       Expected Result
Double click on the relevant project in the work lists section or if your project is not here,
then double click on the project definition                       and search for it.
Screen name:            Project Builder




                                                                                                 Page 9
Preview Original paying document published on :
http://expertplug.com/materials/training/sap-ps-training-guide

You can find many more full SAP training material and SAP jobs on http://expertplug.com/.
ExpertPlug is an SAP marketplace for training materials and an online community of experts. We
offer a simple way for the global SAP workforce, consulting companies and industry to market their
skills and find quality information.
As an SAP Expert, you can also market your SAP skills and make extra revenue by publishing SAP
documents on http://expertplug.com/.

More Related Content

SAP PS Training Guide

  • 2. SAP PS Training Material Table of Contents 1 SAP PS MASTER DATA .............................................................................................................. 3 1.1 BUILD PROJECT STRUCTURE ...............................................................................................................3 1.1.1 Impact ...........................................................................................................................................4 1.2 ACTIVATE ACCOUNT ASSIGNMENT ELEMENTS ......................................................................................5 1.2.1 Impact ...........................................................................................................................................8 1.3 RELEASE WBS FOR SPENDING ............................................................................................................9 Page 2
  • 3. SAP PS Training Material 1 SAP PS MASTER DATA 1.1 Build Project Structure To build lower WBS levels on a project once it has been activated by the Purpose: AR. Projects can be structured by asset, phase or responsibility. This is at the discretion of the project manager. Menu path: Accounting  Project System  Project  CJ20N – Project Builder Transaction CJ20N code: Screen name: Project Builder Comment/ Step Button/ Value/Action Mandatory Expected Nr Field Result 1 Proj def Double click on button in the Work list section. Note: This action will open the relevant project definition and add it to the work list section for quick editing in future. All frequently accessed projects should be added to this list for quick editing in the future. Screen name: Include in Worklist Comment/ Step Button/ Value/Action Mandatory Expected Nr Field Result Page 3
  • 4. SAP PS Training Material Project Number of 2 definition  the Project definition. 3 Click the Enter button Screen name: Project Builder 1.1.1 Impact This task is used to build the project. Projects can be structured according to phase, asset or responsibility. In all cases projects are hierarchical in nature. SAP uses the following project numbering logic: Page 4
  • 5. SAP PS Training Material 1.2 Activate Account Assignment Elements To determine which WBS elements will receive actual costs and which WBS elements will be classified for WIP (AUC). For each account Purpose: assigned WBS an AUC is automatically created when the project is released. Certain fields are activated for Account assigned WBS elements. Menu path: Accounting  Project System  Project  CJ20N – Project Builder Transaction CJ20N code: Screen name: Project Builder Comment/ Step Button/ Value/Action Mandatory Expected Nr Field Result 1 Proj def Double click on button in the Work list section. Note: This action will open the relevant project definition and add it to the work list section for quick editing in future. All frequently accessed projects should be added to this list for quick editing in the future. Screen name: Include in Worklist Comment/ Step Button/ Value/Action Mandatory Expected Nr Field Result Project Number of 2 definition  the Project definition. Page 5
  • 6. SAP PS Training Material 3 Click the Enter button Screen name: Project Builder Comment/ Step Button/ Value/Action Mandatory Expected Nr Field Result Note: Notice that the Project definition is added to the work list section highlighted above. To open this project, double click on it 4 . Screen name: Project Builder Page 6
  • 7. SAP PS Training Material Comment/ Step Button/ Value/Action Mandatory Expected Nr Field Result 5 Expand the treeview node  Activate all account assignment elements which are the lowest in the hierarchy Note: Activating account assignments makes the WIP classification field required. See TAB called Control for details. Screen name: Project Builder Page 7
  • 8. SAP PS Training Material Comment/ Step Button/ Value/Action Mandatory Expected Nr Field Result Double click on each item and enter the WIP classification Screen name: Project Builder Comment/ Step Button/ Value/Action Mandatory Expected Nr Field Result WIP 10 Enter the WIP classification which is used to classify 6  costs in the balance sheet for WIP / AUC for each asset. Note: Repeat the same steps for each account assignment WBS. Comment/ Step Button/ Value/Action Mandatory Expected Nr Field Result 7 Click the Save button  1.2.1 Impact Account assigned WBS elements when released automatically create an (AUC) asset under construction. WIP classification is a Financial requirement. Page 8
  • 9. SAP PS Training Material 1.3 Release WBS for spending This transaction is used to update the system and user status. A Purpose: project must be released (REL) to be able to post actual costs against it. The user status ‘NCA’ must also be changed to ‘ACA’ Accounting  Project System  Project  CJ20N – Project Menu path: Builder Transaction code: CJ20N Screen name: Project Builder Step Button/ Comment/ Value/Action Mandatory Nr Field Expected Result Double click on the relevant project in the work lists section or if your project is not here, then double click on the project definition and search for it. Screen name: Project Builder Page 9
  • 10. Preview Original paying document published on : http://expertplug.com/materials/training/sap-ps-training-guide You can find many more full SAP training material and SAP jobs on http://expertplug.com/. ExpertPlug is an SAP marketplace for training materials and an online community of experts. We offer a simple way for the global SAP workforce, consulting companies and industry to market their skills and find quality information. As an SAP Expert, you can also market your SAP skills and make extra revenue by publishing SAP documents on http://expertplug.com/.